AD26-7-000 · 2026-08-21 · Dominion Energy Services, Inc.
Post-Technical Conference Comments of Dominion Energy Services, Inc. re PJM Governance and Stakeholder Reforms
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
Post Technical Conference Comments
)
on PJM Governance and Stakeholder Reforms
)
Docket No. AD26-7-000
)
POST TECHNICAL CONFERENCE COMMENTS OF DOMINION ENERGY
SERVICES, INC.
Dominion Energy Services, Inc. (“DES”), on behalf of Virginia Electric and Power Company doing business as Dominion Energy Virginia (“Dominion Energy Virginia”), submits the following comments in response to the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Notice Inviting Post-Technical Conference Comments issued on the July 30, 2026 in this proceeding (“Notice”). Dominion Energy Virginia supports the Commission’s focus on PJM Interconnection, L.L.C.’s (“PJM”) governance reforms to strengthen PJM’s independence as well as explore ways to improve its stakeholder process so that PJM can quickly respond to emerging issues that require crucial reforms to maintain reliability of the bulk electric system.1
I. Introduction
DES is a wholly-owned subsidiary of Dominion Energy, Inc., and is a centralized services company providing administrative, management and support services to its associate companies. Dominion Energy Virginia, a subsidiary of Dominion Energy, Inc., is a public service corporation organized under the laws of the Commonwealth of Virginia and a public utility subject to regulation by the Commission and does business in the Commonwealth of Virginia and in the State of North Carolina. It is a regulated, vertically integrated public utility engaged in the generation,
1Dominion Energy Virginia submits these comments to help foster discussions but reserves the right to later challenge the legality of the ultimate proposed revisions to PJM’s governing documents.
PDF page 2
transmission, distribution, and sale of electric energy. Dominion Energy Virginia furnishes electric service to approximately 2.8 million retail customers in its approximately 30,000 square miles of certificated service territory covering parts of Virginia and North Carolina. To provide that service, Dominion Energy Virginia owns and operates a diverse fleet of nuclear, oil, biomass, pumped storage, hydro, coal, solar, wind and natural gas-fired electric generating capacity of approximately 21,000 megawatts. Dominion Energy Virginia owns 6,800 miles of electric transmission lines in Virginia, North Carolina and West Virginia, which is operated by PJM. Dominion Energy Virginia joined PJM effective May 1, 2005, after obtaining prior approval from the Commission, the Virginia State Corporation Commission, and the North Carolina Utilities Commission.2
II. Comments
1) Dominion Energy Virginia supports governance reforms that would reinforce PJM’s
independence as a core governance principle.
PJM’s independence is critical for operating a reliable regional grid across a diverse multi-state footprint and for executing its responsibilities as an Independent System Operator and Regional Transmission Organization. PJM must remain independent from any single market participant, sector, state or group of states, consumer group, industry, or governmental entity. Panelists that participated in the July 23 technical conference and other parties broadly agree that establishing greater PJM independence is a priority and one of the objectives should be to define the appropriate role for the
2 PJM Interconnection, L.L.C., 109 FERC ¶ 61,012 (2004), on reh’g in part, 110 FERC ¶ 61,234 (2005); Ex Parte: In the matter concerning the application of Virginia Electric and Power Company d/b/a Dominion Virginia Power for approval of a plan to transfer functional and operational control of certain transmission facilities to a regional transmission entity, V.S.C.C. Case No. PUE-2000-00551, Order Granting Approval (Nov. 10, 2004); In the Matter of Application of Virginia Electric and Power Company, d/b/a Dominion North Carolina Power, for Authority to Transfer Functional Control of Transmission Assets to PJM Interconnection, LLC, N.C.U.C. Docket No. E-22, Sub 418, Order Approving Transfer Subject to Conditions (Apr. 19, 2005).
PDF page 3
states.3 The Organization of the PJM States, Inc. (“OPSI”) recommends that PJM “should have the authority to independently and unilaterally propose changes to the Operating Agreement under Section 205 of the FPA” and that the Commission should “provide PJM with the independence and agency it needs”.4 Chair Kelsey Bagot of the Virginia State Corporation Commission rightly asserts in her comments, the Section 205 filing authority “should rest firmly with the PJM Board” and that allowing it “to tailor reforms, considering guidance received from stakeholders” would “allow it to act comprehensively and independently”.5 Any governance reforms should be judged by whether they improve PJM’s ability to make timely, technically grounded decisions while maintaining transparency and stakeholder engagement. PJM correctly asserts that its ability to act hinges on its “legal authority to file proposed changes to the Commission” and that it should “possess unconditioned section 205 rights across all its operational, market and transmission planning responsibilities” to strengthen its independence.6 PJM can make a number of improvements to its current governance and stakeholder process that would enable it to perform its duties and responsibilities more effectively through a combination of 1) making member votes advisory by granting PJM sole Federal Power Act (“FPA”), Section 205 filing rights over its resource adequacy, electric transmission planning protocols and energy and ancillary service rules, 2) establishing a limited jump-ball mechanism for PJM Members only, and 3) implementing changes that would provide the states the means to more effectively engage in the PJM stakeholder process. Each of these recommendations will be discussed in more detail below.
2) Stakeholder votes should become advisory while preserving meaningful stakeholder rights.
3 See Pre-Conference Comments of Kelsey A. Bagot, Chair, Virginia State Corporation Commission, Docket No. AD26-7-000 (July 21,2026) (“Pre-conference comments of Chair Bagot”) at p.2. See also Comments from OPSI, Docket No. AD26-7-000 (July 21, 2026) (“Pre-Conference of Comments of the Organization of PJM States, Inc.”) at p. 3-4. 4 Pre-Conference of Comments of the Organization of PJM States, Inc.”) at p. 6. 5 Pre-conference comments of Chair Bagot, p.26 Comments from PJM Interconnection, L.L.C, Docket No. AD26-7-000 (July 14, 2026) (“PJM Pre Tech Conference Comments”). p.1,8
PDF page 4
PJM currently has FPA, Section 205 filing rights over its capacity market pursuant to the PJM Open Access Transmission Tariff (“PJM Tariff”) and Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (“RAA”). However, PJM does not have that same authority over other core responsibilities that include its electric transmission planning protocols because they reside in the Amended and Restated Operating Agreement of PJM Interconnection, L.L.C. (“PJM Operating Agreement”) and PJM Members have FPA, Section 205 rights under the PJM Operating Agreement. Since its transmission planning protocols reside in the PJM Operating Agreement, PJM is unable to ask the Commission to modify its transmission planning protocols under a Section 205 filing without receiving a 2/3 supermajority approval vote by its members. PJM also effectively lacks FPA, Section 205 filing rights for its energy and ancillary service markets. While these market rules reside in the PJM Tariff, the identical provisions are also in the PJM Operating Agreement. Therefore, if PJM Members do not authorize PJM to make changes to duplicative sections in the PJM Operating Agreement with a 2/3 supermajority vote in favor of the changes, PJM cannot submit changes under a single FPA, Section 205 filing. This division not only hinders PJM’s ability to timely present necessary reforms to the Commission, but it also creates a precarious situation in which, without the approval of the Members Committee, PJM would be “required to proceed under the more restrictive requirements of section 206.”7 This, in effect, can “limit the ability of important issues to reach the Commission for adjudication in a timely manner.”8
By making the PJM stakeholder votes advisory, stakeholder and member filibusters would no longer prevent PJM from cohesively bringing important market, planning, and reliability reforms to FERC under the FPA, Section 205 for timely consideration. Creating a process by which the Members Committee votes become advisory, which follows from the enhancement of PJM’s FPA, Section 205
7 PJM Pre Tech Conference Comments, p. 6
8 Id., p. 6
PDF page 5
rights, would still preserve transparency by showing PJM, stakeholders and the Commission where support and opposition exist without hindering PJM’s ability to act independently and swiftly. Under this paradigm, stakeholder input would remain robust, with clear written comment opportunities, technical review, and sufficient time for participants to assess proposed reforms to build consensus. Retaining the ability for consensus-building remains essential because consensus lowers litigation risk, improves implementation quality, and creates broader confidence in PJM rules.
3) The Commission should remove restrictions on PJM’s ability to exercise filing rights over its energy and ancillary service markets as well as its transmission planning protocols.
Electric planning protocols and reliability procedures in both the PJM Tariff and PJM Operating Agreement require PJM to file the proposed changes under FPA, section 206 if Members do not provide the 2/3 supermajority vote in favor of the changes. One way Members Committee votes can be made advisory is by removing all non-governance provisions from the PJM Operating Agreement and migrating those provisions to the PJM Tariff to the extent they are not already contained therein. The only requirements that should remain in the PJM Operating Agreement are those that pertain to the management and operation of PJM as is typical for most limited liability companies. Moving the transmission planning protocols or reliability provisions in the PJM Operating Agreement to the PJM Tariff, similar to how other Regional Transmission Organizations and Independent System Operators have such provisions in their open access transmission tariffs, will enable more efficient decision-making processes, while maintaining robust stakeholder engagement and transparency.9 This migration of the non-governance provisions would then provide PJM with unconditioned FPA, Section 205 filing rights over its energy and ancillary services markets, transmission planning protocols, and reliability provisions. Making this change will allow PJM to
9 PJM Pre Tech Conference Comments, p.7. PJM states that it “should be able to ask the Commission to review reforms in these areas consistent with the burden of proof that other RTOs and ISOs need to meet when filing reforms before the Commission on these same topics [resource performance, dispatch, operational flexibility, transmission expansion].”
PDF page 6
propose market rule changes under FPA, Section 205 whether or not PJM Members agree to the changes under the current supermajority vote construct. Expanding PJM’s FPA, Section 205 filing rights would allow PJM to adapt more quickly to emerging reliability, operational, market, and planning issues and place disputes before FERC more efficiently. The Commission remains the ultimate adjudicator and the use of a single PJM FPA, Section 205 filing would allow the Commission to timely review and act within the 60-day time clock that is not required for Section 206 actions. Expanded filing authority should be paired with robust advisory stakeholder input, strengthened state coordination through OPSI and transparent PJM Board of Managers oversight.
4) Stakeholder rights can be preserved by granting PJM members with limited “jump ball” rights for capacity, energy and ancillary service market reforms.
Once the Members Committee vote is made advisory, the stakeholders’ ability to develop alternative solutions can be retained using a “jump-ball” mechanism for reforms of the capacity, energy and ancillary services market rules.10 PJM members will retain the ability to approve alternative proposals that could ultimately be filed by PJM under its Section 205 rights with equal footing before the Commission under limited circumstances in which PJM and its members cannot achieve consensus on specific reforms. As part of the stakeholder process, the states, for example, through OPSI, may also bring forward alternatives for the Members Committee to consider, which if endorsed, could be submitted to the Commission on equal footing as the PJM proposal for consideration. A “jump-ball” option does several things. First, it creates an incentive for PJM to continue to work with stakeholders to reach a consensus on a reform of the PJM Tariff while still enabling it to submit changes to be timely adjudicated by the Commission. Second, it preserves members’ ability to develop competing proposals under the FPA, Section 205 standard of review in which the Commission would only have to deem the
10 See Participants Agreement among ISO New England, Inc. and the New England Power Pool, Section 11.1.5.
PDF page 7
preferred proposal just and reasonable. Third, a “jump ball” mechanism will provide a means for states to develop proposals for PJM members to consider, that could ultimately be filed under the mechanism if endorsed by PJM members. To be clear, Dominion Energy Virginia is not proposing that the states have Section 205 rights under a “jump ball” construct, but rather that the states have the ability to move alternative proposals through the Members Committee where the membership would have the ability to elevate them under its “jump ball” rights.
5) Granting states authority to direct FPA, Section 205 filings would undermine PJM’s independence.
Dominion Energy Virginia opposes granting states authority to direct FPA, Section 205 filings over PJM Tariff matters because it would undermine PJM’s ability to act independently. PJM should take into consideration input from the states and stakeholders regarding when tariff and market rule reforms are needed, but ultimately it is PJM that must prioritize where and when changes are most needed to meet its obligations as the Regional Transmission Organization and Independent System Operator. Unfettered ability of the states to direct PJM to make a Section 205 filing risks PJM’s independence and could result in PJM being sidetracked from its core responsibilities and may disrupt progress on important priority issues if it is forced devote resources to an issue given priority by a majority of PJM states. Additionally, state majorities may not reflect the interests or regulatory structures of all states in the PJM Region or benefit the “market” as a whole but rather may be self- interested. A central concern is that allowing a majority of states to direct a Section 205 filing to change the PJM Tariff could result in advancing proposals harmful to minority-state interests, including vertically integrated states such as Virginia that have different retail regulatory structures, planning obligations, and resource adequacy responsibilities than restructured states, or fail to align across all 14 jurisdictions in the PJM Region. The better approach is to strengthen OPSI’s ability to coordinate state views, provide technical input, and present majority and minority state positions to PJM and
PDF page 8
FERC. State input should inform PJM decision-making and FERC review but should not displace PJM’s independent regional role or create new procedural veto points.
6) OPSI can improve its efficacy within the PJM stakeholder process through greater coordination between state commissioners, legislators and governors.
The PJM states play an integral role in PJM’s stakeholders processes. OPSI is an organization consisting of state commissions, including the District of Columbia, that was established in 2005 and has played a crucial role as stakeholder advocates for solutions that it deems in the public interest.11 OPSI regularly meets with the PJM Board of Managers and also actively participates in the PJM stakeholder process to weigh in to share the perspective of its members with PJM and PJM members. The Commission accepted a PJM Member-funding mechanism in the same year to enable the organization’s ability to effectively share public policy perspectives. OPSI has the staff, technical expertise, legal support, and analytical capability to engage more effectively in PJM matters. Dominion Energy Virginia is open to discussing ways to support OPSI’s efforts and potentially expanded role. Additionally, OPSI should collect and reflect input from both state utility commissions, state governors and their designated energy policy representatives, while the states work to further coordinate and collaborate among their respective structures (e.g. governor, public utility commission, legislators) that will provide a more cohesive state perspective and reduce conflicting messages where possible. By doing so, OPSI can serve as the single authorized representative for providing the collective state perspectives, reducing the risk that PJM receives conflicting or duplicative direction from multiple state entities on behalf of each state. Where there is no unanimity, OPSI can present majority and minority state perspectives where consensus cannot be reached, so that stakeholders, PJM and FERC, can understand the range of state views. This would not prevent states from sharing their
11 Pre-conference comments of the Organization of the PJM States, Inc. p 3-4
PDF page 9
unique perspectives through direct communication with the PJM Board of Managers or taking up issues on their own either through their own stakeholder engagement or making a Section 206 filing. States are important stakeholders and Dominion Energy Virginia supports allowing one state representative appointed by OPSI, in coordination with the PJM governors and legislators, to participate on the PJM Nominating Committee, with one vote equivalent to the votes of other voting members of the Nominating Committee, while preserving PJM Board of Managers’ independence.
III. Conclusion
Dominion Energy Virginia supports the Commission’s attention to this important topic and asks that the Commission consider the issues raised in these comments during its evaluation of necessary future actions. Please see the attached appendix for responses to the survey provided in the post-conference supplemental notice.
Respectfully submitted,
/s/ Jacqulynn Hugee
Jacqulynn B. Hugee
Deputy General Counsel
Dominion Energy Services, Inc.
120 Tredegar Street
Richmond, VA 23219
(804) 819-2794
jacqulynn.b.hugee@dominionenergy.com
/s/ James G. Davis
James G. Davis
Regulatory and Market Policy Senior
Strategic Advisor
Dominion Energy Services, Inc.
120 Tredegar Street
Richmond, VA 23219
(804) 819-2718
james.g.davis@dominionenergy.com
/s/ Wesley Walker
Wesley Walker
Managing Counsel
Dominion Energy Services, Inc.
120 Tredegar Street
Richmond, VA 23219
(804) 819-2345
wesley.walker@dominionenergy.com
PDF page 10
Dated: August 21, 2026
APPENDIX
Dominion Energy Virginia provides the following answers to the following questions that were provided in the FERC supplemental notice for comments.
PJM Board Independence
1. Should Board members’ terms be extended to five or more years?: No, however we support modest term extensions if they enhance continuity and independence, provided there are reasonable total service limits and regular performance review.
2. Should there be a maximum number of years that a Board member may serve (e.g., 10 years)? Yes, a term limit should be established of no more than 10 years to balance institutional knowledge with fresh perspectives.
3. Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region? No, however we support considering regional knowledge as one factor, but avoid residency requirements that narrow the pool of independent, qualified candidates.
4. Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year? No, the cooling off period should not be reduced; independence should remain paramount.
5. Should restrictions on Board communications be relaxed to enable
more communication between the Board and stakeholders? Yes, we support more structured communication between the Board and stakeholders, with safeguards to preserve independence and avoid undue influence.
6. In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning? No, Board votes should not be made public, but we do support a greater explanation of Board reasoning with respect to their votes, particularly on major market, reliability, and governance reforms; publicizing individual votes may be less important than explaining the basis for decisions.
7. In order to increase transparency, should some Board meetings be open or available to the public? Yes, we support limited public or open sessions on broad policy issues, while preserving confidential executive sessions for commercially sensitive personnel, litigation, cybersecurity, or reliability-sensitive matters.
8. Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest? No, but we support clarifying that PJM and its Board serve the public interest through reliable,
PDF page 11
efficient, nondiscriminatory regional transmission service and wholesale markets consistent with the Federal Power Act.
9. Should state representatives have at least one voting member on the Nominating Committee? Yes, we support one OPSI-appointed state representative in a defined role, provided the process preserves Board independence and avoids control by any state or group of states.
10. Should PJM adopt public performance metrics and tie management compensation to their achievement? Yes, we support public performance metrics focused on reliability, market efficiency, project execution, and transparency, but compensation design should remain within the Board’s oversight.
Section 205 Filing Rights
11. Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board? Yes, we support making stakeholder votes advisory so PJM can bring timely proposals to FERC, while preserving transparent voting records and meaningful stakeholder input.
12. Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee? Yes, we support PJM having FPA, Section 205 filing rights over energy and ancillary service market rules without the need to obtain a 2/3 super majority vote of the Members Committee. PJM needs authority to respond quickly to changing operational conditions, market inefficiencies, and reliability risks.
13. Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two- thirds of the Members Committee?: Yes, we support PJM having FPA, Section 205 filing rights over RTEP without the need to obtain a 2/3 super majority vote of the Members Committee with appropriate transparency and consultation. PJM must be able to adapt planning rules and protocols quickly as load growth, generator retirements, interconnection needs, and regional infrastructure requirements evolve.
14. Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?: No, we do not support granting OPSI direct jump ball filing rights as a substitute for PJM independence. Instead, strengthen OPSI funding and consultation rights and allow OPSI to provide majority and minority state views to PJM and FERC.
15. Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal? Yes, we support a Members Committee with jump ball filing rights over defined resource adequacy and energy and ancillary services reforms when a supermajority supports an alternative. The possibility of a “jump-ball”
PDF page 12
filing on an issue will provide incentive for both PJM and stakeholders to strive for consensus on a single proposal to obviate the risk of the Commission choosing one proposal over the other.
Stakeholder Process
16. Should the approval threshold in the Members Committee be lowered from two- thirds sector-weighted voting?: No, if a “jump-ball” mechanism is adopted by PJM, a lower threshold could undermine PJM’s ability to present reforms and the Commission’s ability to act decisively on emergent issues by unnecessarily increasing the number of “jump-ball” filings
17. Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees? No, however we support consistent affiliate voting safeguards where votes have meaningful governance consequences, while preserving broad technical participation at lower-level committees.
Stakeholder Process
1. In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives? No, we do not support creating a separate state organization. Instead, we recommended that PJM and stakeholders encourage state governors to work with OPSI to include structured input from governors or their designated representatives. State governors should work with the existing OPSI entity that has been participating in the PJM stakeholder process for many years and is well versed in the issues that come before PJM and its membership for consideration.
2. Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? No, a formal state voting role in the stakeholder process could distort sector balance or enable a majority of states to override minority-state concerns. State views should be elevated through OPSI consultation, not through direct voting control.
3. Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation? Yes, we support requiring meaningful consultation with OPSI before PJM makes Section 205 filings related to resource adequacy and transmission cost allocation, while preserving PJM’s ability to file timely proposals and FERC’s authority to decide contested issues. This will not be a huge departure from what PJM has been doing since OPSI was created – taking OPSI’s input (when provided) into consideration prior to submitting filing with the Commission.