AD26-7-000 · 2026-08-21 · NRG Energy, Inc.

Post-Technical Conference Comments of NRG Energy, Inc. re PJM Governance and Stakeholder Reforms

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder Reforms

)

Docket No. AD26-7-000

Post-Technical Conference Comments of NRG Energy, Inc.
NRG Energy, Inc. respectfully submits these comments regarding potential reforms to the governance and stakeholder processes of PJM Interconnection, L.L.C. ("PJM"). Governance reform should be guided by several core principles: broad stakeholder participation, transparency, accountability, independence in decision-making, regulatory stability, and support for investment and innovation. The PJM region faces unprecedented reliability, affordability, and resource adequacy challenges. Meeting those challenges will require substantial investment in generation, demand response, advanced technologies, transmission infrastructure, and innovative market solutions. Governance reforms should therefore be evaluated not only on whether they improve decision-making processes, but also on whether they strengthen the region's ability to attract and retain capital necessary to maintain reliability and support economic growth.

I. Stakeholder Engagement Remains Paramount
A defining strength of PJM has long been its ability to bring together a diverse set of market participants, state officials, consumer advocates, suppliers, transmission owners, demand response providers, and emerging technology developers. These varied perspectives have improved PJM's outcomes and enhanced stakeholder acceptance of policy choices. Accordingly, any governance reforms should ensure that participation remains accessible and meaningful. Barriers to participation should remain reasonably low while reforms should preserve opportunities for stakeholders to identify concerns, develop alternatives, and contribute expertise. Stakeholder engagement should not be viewed as an obstacle to progress. Rather, it is an important mechanism for improving market design and identifying unintended consequences before they occur. The long-term success of PJM depends upon maintaining confidence that diverse viewpoints continue to receive fair consideration.

II. Governance Reform Must Not Impede Necessary Investment and Timely Action While stakeholder participation is essential, PJM's governance structure must also be capable of producing timely decisions. Investors evaluating opportunities in generation, demand response, storage, advanced technologies, large-load solutions, and other infrastructure require regulatory certainty and confidence that critical market and reliability issues will be resolved within reasonable timeframes. Governance structures that create persistent stalemates, indefinite delays, or fragmented decision-making undermine investment signals and can ultimately threaten reliability. To that end, further reforms should seek to improve efficiency without sacrificing inclusiveness. In particular, governance structures should encourage clear decision-making

PDF page 2

2

timelines, provide transparency regarding how stakeholder input informs final decisions, reduce unnecessary procedural complexity, and deliver sufficient certainty to support long-term capital investment. These improvements can largely be implemented without fundamental change to the PJM Operating Agreement.

III. Solutions Should Enhance Adoption of Innovations
The electricity sector is undergoing rapid transformation. New and emerging
technologies, novel business models, and large flexible loads are changing how electric systems operate. PJM's governance framework and the actions taken as part of that framework should welcome these developments rather than unintentionally discourage them. Governance reforms should be evaluated through the lens of whether they promote competitive outcomes, avoid barriers to entry, and allow new business models to compete on a level playing field. Competitive wholesale markets have succeeded because they enable innovation to emerge from market participants rather than from a central planner. Governance reforms should reinforce that principle.

IV. Board Independence Remains a Critical Element of PJM’s Success
Board independence has been a defining feature of PJM governance and should remain so. The PJM Board has the challenging task of balancing competing stakeholder interests while exercising sound judgment regarding reliability and market integrity to drive efficient outcomes that benefit the region’s stakeholders. An independent Board can and should remain accountable, transparent, and informed by stakeholder input. Reforms in this space should focus on improving communication and transparency. More significant changes to the nature of the Board would require a more deliberative exploration of the appropriate role of the Board relative to the role of PJM’s executives.

V. Reforms Should Avoid Unnecessary Disruption
The Commission should be cautious about reforms that fundamentally restructure PJM governance absent a compelling showing that such disruption is necessary. Major structural changes may create unintended consequences, increase uncertainty, and divert attention from the urgent reliability, market-design, and infrastructure challenges confronting the region. Incremental improvements that strengthen transparency, accountability, stakeholder engagement, and decision-making efficiency are often preferable to wholesale institutional redesign. In short, stakeholder efforts should seek targeted reforms that address identified shortcomings while preserving those aspects of PJM's governance framework that have contributed to decades of reliable system operations and competitive market development.

PDF page 3

3
VI. Conclusion
Effective governance must balance participation, independence, accountability, and timely action. As stakeholders consider further reforms, we encourage parties to consider the matters identified herein.

Respectfully submitted,
/s/ Cortney Madea Slager
Cortney Madea Slager
Vice President & Assistant General Counsel
Brianna Anderson
Regulatory Counsel
NRG Energy, Inc.
804 Carnegie Center
Princeton, NJ 08540
Neal A. Fitch
Sr. Director, Regulatory Affairs
NRG Energy, Inc.
804 Carnegie Center
Princeton, NJ 08540

PDF page 4

4

Appendix: Responses to Questionnaire
Question No.
Questions
Response
PJM Board Independence
1
Should Board members’ terms be extended to five or more years?
No
Comments
NRG does not object to consideration of alternative Board member terms, but further exploration of the benefits and detriments of alternative term lengths should be explored before determining the outcome.

2
Should there be a maximum number of years that a Board member may serve (e.g., 10 years)?

Yes
Comments
It is NRG's understanding that there are guidelines in practice today that limit any individual Board members' term of service today.

3
Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?

Yes
Comments
So long as this is a preference, and not a requirement, NRG can support this. The PJM Board, its Members, and its stakeholders should have a strong preference for the best qualified candidates regardless of residence.

4
Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?

Yes
Comments
NRG supports this revision as it will expand the pool of prospective Board candidates with relevant experience.

5
Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?

No
Comments
While NRG is open to different frameworks for Board communication, the existing framework provides significant transparency to all stakeholders regarding Board communications while avoiding issues regarding preferential or unduly discriminatory access.

6
In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?

Yes
Comments
NRG supports revisions that enhance transparency into the Board's reasoning for major decisions.  NRG also notes in recent matters of particular significance (e.g., the various CIFP decisions), the PJM Board has articulated its reasoning for the benefit of stakeholders.

7
In order to increase transparency, should some Board meetings be open or available to the public?

Yes
Comments
NRG supports this revision with the caveat that matters of litigation, personnel matters, and other confidential or sensitive matters should be addressed in executive session.

8
Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?

No
Comments

9
Should state representatives have at least one voting member on the Nominating Committee?

No
Comments
While NRG is open to considering a framework where a state representative has greater engagement with the Nominating Committee, more information is needed to appropriately consider this or other options.

10
Should PJM adopt public performance metrics and tie management compensation to their achievement?

Yes

PDF page 5

5

Comments
NRG supports this revision and is open to the most efficient manner by which such information could be shared. Several other ISOs and RTOs already have similar programs in place that identify organizational goals and/or priorities.

Section 205 Filing Rights
11
Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?

No
Comments
While NRG is open to considering a framework where the stakeholder process is advisory, more information is needed to consider this or other options.

12
Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?

No
Comments
While NRG is open to considering a framework where PJM has unencumbered section 205 rights over the energy market and ancillary services market, more information is needed to consider this or other alternatives.

13
Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?

No
Comments
While NRG is open to considering a framework where PJM has unencumbered section 205 rights over RTEP, more information is needed to consider this or other alternatives.

14
Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?

No
Comments
In the absence of a more precise description of what these rights would cover, NRG cannot support at this time.

15
Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?

No
Comments
While NRG is open to considering a framework where the PJM Members Committee has 'jump ball' rights over portions of the tariff where PJM has 205 rights, more information is needed to consider this or other alternatives.

Stakeholder Process
16
Should the approval threshold in the Members Committee be lowered from two- thirds sector-weighted voting?

No
Comments
NRG believes the two-thirds sector-weighted voting threshold has historically supported good faith negotiation among most stakeholders in the effort to reach consensus. It is not clear what good cause exists to change the threshold.

17
Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?

No
Comments
While NRG is open to considering a framework that alters the voting procedures, more information is needed to consider this or other alternatives.

State Participation
18
In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives? No

Comments
While NRG's preference would be that OPSI be broadly crafted in a manner to reflect the interests of the states, there is nothing stopping other state representative groups from forming and participating in PJM stakeholder processes as demonstrated by the recent CIFP and other events.

19
Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?

No

PDF page 6

6

Comments
In the absence of clarity with respect to which state representatives this refers to, and how such activity would be conducted, additional information is needed to consider this or other alternatives.

20
Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?

No
Comments
NRG observes that such consultation already happens today as OPSI and/or its representatives regularly participate in PJM stakeholder proceedings and other forae. If 'consult' is intended to mean a more formal process, NRG notes this is likely to result in a slower overall process for all stakeholders.