Comments of Exelon Corporation in response to FERC's Notice re PJM Governance and Stakeholder Reforms
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder
Reforms
)
)
)
)
Docket No. AD26-7-000
COMMENTS OF EXELON CORPORATION
Exelon Corporation and its affiliates1 (collectively, “Exelon”) welcome the opportunity to comment in response to the Notice Requesting Post-Technical Conference Comments2 issued by the Federal Energy Regulatory Commission (“Commission”) in the above-captioned docket.
I. INTRODUCTION AND COMMENTS
Exelon appreciates the Commission’s attention to issues related to the governance structure of PJM Interconnection, L.L.C. (“PJM”) at this important time of change in the electricity industry. The efficacy of the PJM governance framework and stakeholder process has been a simmering issue for years but has come to a head over the looming resource adequacy crisis paired with the inability to move rapidly to interconnect new large loads while maintaining reliability and affordability. Forecasted resource adequacy concerns are especially acute in PJM, the region where Exelon’s utility operating companies provide electric service to over 10 million customers across five states and the District of Columbia. These circumstances present at a time when electricity has never been more important to
1 Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power and Light Company, PECO Energy Company, and Potomac Electric Power Company.2 Notice Requesting Post-Technical Conference Comments, Docket No. AD26-7-000 (July 30, 2026) (“Notice”).
PDF page 2
2
the US economy, to national security, and to the nation as it seeks to capitalize on strategic growth opportunities related to data center and artificial intelligence demands, expanded manufacturing capacity, and electrification of end-use energy applications that are increasingly becoming the practice and expectation of our customers. This is not a time for anyone to persist with a poorly performing governance structure.
The Commission, in initiating the instant docket, has properly identified pains stemming from PJM’s current governance framework. PJM’s rigid, hierarchical committee structure—which affords members binding affiliate voting rights at lower-level standing committees and binding sector- weighted voting rights at senior standing committees—is no longer fit for purpose. Time after time, the stakeholder process voting results reflect that efforts to reach a two-thirds supermajority required to pass solutions under this paradigm mostly result in gridlock, thereby derailing advancements needed to address today’s challenges. Perhaps equally important, gridlock leaves states feeling uncomfortable with outcomes, and investors tepid about the durability of the commercial environment in the region. It is also worth noting that the data consistently shows low voter turnout even when votes concern highly critical issues. For instance, most recently, only approximately 70 members—representing less than 15% of more than 500 qualified voting members—voted in the Reliability Backstop
Procurement/Connect and Manage critical issues fast path effort.3
To address the governance challenges facing PJM, Exelon’s view is informed by the guiding principle that it is critical to focus on development of solutions that are responsive to specific identified problems. Solutions that are reactive to general grievances about challenging processes, but that do not have ties to specific aims, will not meet the moment. Moreover, not all problems facing the region can
3 See MC Voting Results from the Special Members Committee – Reliability Backstop Procurement dated 6/30/26 -- https://www.pjm.com/committees-and-groups/committees/mc
PDF page 3
3
be addressed through governance reforms, especially important resource adequacy and affordability challenges depend on actions outside of the PJM market to resolve.
To this end, Exelon uses two primary objectives as a waypoint for potential reforms. First, the need to enhance independent decision-making by PJM. The PJM Board of Managers (“Board”) should be empowered to make decisions untethered from the need to obtain approval from the Members Committee, including being granted the filing rights to do so. This extends to the transmission planning protocols as well as the energy and ancillary services markets, as the Board has today for the capacity market. Furthermore, the terms of Board members should be extended and they should have more open lines of communication with the membership to enable receipt of a wider range of perspectives filtered through fewer intermediaries and overly structured meetings.
Exelon’s second objective is to modify the stakeholder process to more fully recognize the broader political context in which PJM operates. PJM has always included a diverse makeup of states, but today’s energy landscape is more political than it has ever been and pressing issues increasingly straddle the state-federal jurisdictional divide. States need a greater role in PJM, recognizing the inherently political nature of many decisions and the need to align PJM processes with state policies and, in turn, to make sure that states’ decisions (e.g., permitting) support PJM outcomes. There is a need for coordinated action between PJM and the states, and buy-in from the states to achieve PJM’s objectives. PJM cannot act without cognizance of, or in opposition to, the states if it hopes to be successful.
With this in mind, Exelon supports giving states a greater role in PJM. Exactly what form such a role takes should be a matter of discussion and could include representation of state interests on the PJM Nominating Committee, on the Board, and/or mandatory consultation processes between state representatives and the Board. We would be open to incorporating best practices from other Regional
PDF page 4
4
Transmission Organizations (“RTOs”)/Independent System Operators (“ISOs”) and how they integrate state policymakers into governance. However, any expanded role for the states in the PJM governance process should not impinge on efforts to enhance the independence of the Board. Said another way, any reform should not subordinate the Board to the states. An RTO must remain independent for its region to attract significant, needed, long-term capital investments. This can be achieved by ensuring that PJM’s policies are developed to be both considerate of and resilient to today’s fast-moving, short- duration political dynamic.
As PJM stakeholders chart a path forward for PJM’s governance framework, Exelon emphasizes that governance reforms cannot solve all problems. PJM faces challenges with its markets and with transmission planning that will require solutions beyond the reach of improved RTO governance, and in large part beyond any regional power market improvements that could flow from such changes. Rather, state and federal actions are likely required to address generation planning, siting, permitting, supply chain, and financing challenges. These comments do not offer prescriptions to address the need for increased entry of new supply; rather, we note that while improved governance is a worthy goal, seeking it should not become a distraction from other pressing threats to reliability and affordability in the footprint that will need to be addressed separately, and by a different set of stakeholders and using different tools.
Exelon remains committed to continuing to work with our states, federal policymakers, and PJM on governance reform for the region. We look forward to partnering with other stakeholders to retain existing structures that work, advance needed reforms, and drive compatibility of reforms with the diverse views of states in the PJM region. We recognize and appreciate that what takes place at the Commission and at PJM must also accommodate and, indeed, facilitate actions states may take to support their own policies and priorities. To date, Exelon has tried to focus external stakeholder
PDF page 5
5
engagement on governance by asking what problems need to be fixed and pushing towards reforms that
(1) enable independent decision making by PJM and (2) ensure PJM decisions are made with better awareness of political contexts. Exelon continues to pursue these objectives and urges the Commission to advance them through this proceeding.
PDF page 6
6
II. RESPONSES TO QUESTIONS IN NOTICE
A. Question 1 – Board Member Terms
Yes
No
Should Board members’ terms be extended to five or more years?
x
Exelon’s view is that Board members’ terms should be longer than the current three-year duration. The structure of PJM is extremely complex and the issues facing the region are multi-faceted. Thus, it takes time to come up to speed once a Board member is elected and installed. Then, when issues arise, it can take years to develop solutions through the stakeholder process, have them approved by the Commission, and then be implemented with time for stakeholders and market participants to respond and gain experience with new rules. Ideally, Board members would have terms of adequate duration to support both the education and initiation process and to serve for long enough to have a meaningful amount of continuity in oversight as PJM staff and the stakeholder process develop and implement improvements to markets, planning, and operational rules.
In addition to serving longer terms—and only if Board terms are extended—Exelon offers that Board members should only be able to serve at most three five year terms and must be younger than 75 years old to be eligible for election or re-election consistent with existing obligations. Maintaining these standards of conduct while extending individual term limits would enhance Board independence, recognizing that Board members would undertake votes with less concern about how those votes would impact their ability to be renominated. Especially as PJM faces increased political pressure and Board actions have been subject to unprecedented levels of scrutiny, not facing continual renomination will free Board members to act with the highest level of independence in line with what they think is the best course of action for the PJM region.
PDF page 7
7
B. Question 2 – Board Service Limits
Yes
No
Should there be a maximum number of years that a Board member
may serve (e.g., 10 years)?
x
Exelon’s view is that Board members should be limited in the maximum number of years they may serve. An appropriate maximum likely depends on whether Board members are eligible to be renominated for more than one term that is extended beyond the current three-year period (see answer to Question 1). If Board members are not eligible for renomination, an appropriate single term would be seven years. This duration balances the considerations of 1) allowing Board members to come up to speed on PJM and oversee a number of meaningful reform efforts with 2) the fact that there is risk with placing too much weight on the one-time decision of the Nominating Committee. As with any corporate hiring process, experience has shown that not every Board member ultimately proves to be the right fit. If Board members are eligible for renomination and terms are not extended, this balance may be struck by allowing one or two renominations (for a total of six or nine total years of service). If Board members are eligible for renomination and terms are extended, the balance will depend on the new length of the term. In any case, Exelon’s view is that fifteen years of service is a reasonable upper bound on total number of years of Board service, which would arithmetically limit allowed renominations to two so long as the term length is five years.
PDF page 8
8
C. Question 3 – Footprint Residence Preference
Yes
No
Should the Board member qualification rules be revised to provide
a preference for some Board members that reside in the PJM
region?
x
Exelon would support a residency preference for Board members. Residence in PJM may have several benefits for Board members, including that it may increase likelihood of prior experience with the RTO, may increase Board members skin-in-the game with respect to outcomes in the region, and may make it easier for stakeholders to engage actively with Board members. However, Exelon does not support a mandate of residence in the PJM region so as not to overly constrain the pool of Board candidates. There are already challenges identifying qualified and interested Board members (even without the preference or requirement); it would be ill advised to exacerbate such challenges. We would not wish to overly constrain PJM’s ability to recruit qualified candidates that can bring a diversity of valuable experience, including experience from other regions, to the Board.
PDF page 9
9
D. Question 4 – Cooling Off Period
Yes
No
Should the conflict-of-interest rules be revised to reduce the
cooling off period for Board members from two years to one year?
x
Exelon supports shortening the current two-year cooling off period to instead be one year. We understand the value of a cooling off period as a general matter, creating space between the time when a Board member may be affiliated with a PJM member and that member’s interest, and when she or he may serve on the Board and need to shift their perspective to the broader interests of the region. However, it is also important to, within reason, maximize the pool of quality, qualified candidates to serve on the Board. The current two-year cooling off period is unnecessarily restrictive and a one-year cooling off period may be a more appropriate duration to balance the interests. Note that this position is consistent with the implementation of a preference, but not requirement, for Board member residence in the PJM footprint—ultimately, the objective is to improve and expand the range of individuals that the Nominating Committee may consider to serve on the Board.
PDF page 10
10
E. Question 5 – Ex Parte Restrictions
Yes
No
Should restrictions on Board communications be relaxed to enable
more communication between the Board and stakeholders?
x
Exelon supports relaxation of restrictions to enable more communication between the Board and stakeholders. Especially if PJM’s governance structures are reformed in alignment with Exelon’s recommended reforms—including a shift to an advisory polling with enhanced section 205 rights for the Board—it will be more important than ever that the Board is able to effectively gather direct, candid, and unfiltered information from stakeholders. The Board may benefit from having more frequent and informal communication channels with stakeholders as it makes important forward- looking operational, strategic, and market-design decisions. It should not be required to rely only on communications through overly structured meetings with stakeholders (e.g., Liaison Committee meetings) and summaries filtered through PJM staff, however fair they may be. This would prevent situations where nuanced, non-conforming, or minority viewpoints are lost or reframed through the perspective of others. It may also allow for the Board to provide feedback to stakeholders earlier in the committee development process, allowing for Board guidance on paths forward that are aligned with the Board’s vision and most likely to garner the Board’s support. Of course, increased access needs to be balanced and cannot be unconstrained. Board members do not serve PJM on a full-time basis and cannot hear an unlimited number of stakeholder perspectives. There would need to be practical limits on the amount of time that each Board member should be available and mechanisms put in place to ensure that no one stakeholder or sector is able to monopolize Board bandwidth.
PDF page 11
11
F. Question 6 – Board Vote Transparency
Yes
No
In order to increase transparency, should Board votes be made
public or the Board be required to explain its reasoning?
x
Exelon does not support publication of Board votes or requirements for Board members to explain their votes. Thematically, Exelon supports PJM reforms to empower the Board and to increase independence, particularly in a period of heightened attention regarding developments in PJM. Requiring the Board to make public each of its votes would expose Board members to increased scrutiny and pressure at a time when they should be encouraged to take positions aligned with their best, unbiased judgement and insulated from blowback from market participants. The Board functions as a collective decision-making body and, as such, transparency is adequately served by disclosing the Board’s final action rather than the votes of individual members. The ability of the Board to act behind closed doors aligns with how most corporate boards function and allows appropriate levels of deliberative privilege and confidentiality. Moreover, it is Exelon’s view that governance changes should be focused on ensuring that the Board has more time to focus on the issues and engage meaningfully with stakeholders, a goal that is not advanced by requiring Board members to spend precious time documenting the reasoning for each vote that they take.
PDF page 12
12
G. Question 7 – Public Board Meetings
Yes
No
In order to increase transparency, should some Board meetings be
open or available to the public?
x
Exelon does not support making meetings of the Board available to the public. Similar to the reasoning for not supporting publication and explanation of voting, this would not advance the objective of Board independence. Instead, it would likely lead the Board to hold curated, selectively- scoped public meetings that, over concerns about optics and politics, would not involve meaningful, open dialogue or the taking of controversial votes. The Board would then do the bulk of its business in private executive sessions. Not only would these meetings be a drain on scarce Board time that is best spent on other activities, but they would also be unsatisfying to those who advocate for the value of public Board meetings to enhance transparency, thereby creating even more dissatisfaction with PJM governance. The Commission should seek reforms that provide more, not fewer, opportunities for the Board to engage in the deliberative process. In Exelon’s view, public Board meetings do not advance, and may undermine, that goal.
PDF page 13
13
H. Question 8 – Public Interest Principle
Yes
No
Should PJM’s governing documents be revised to explicitly state
that the responsibility of PJM and its Board is to serve the public
interest?
x
Exelon would support revisions to PJM’s governing documents to explicitly state that PJM and its Board are responsible to serve the public interest, as long as it is solely intended to memorialize, and not expand, requirements within the Federal Power Act (“FPA”). PJM is a public utility under the FPA, having received rights and obligations under that act from its public utility members. It already has appropriate legal and operational obligations for an entity regulated by the Commission to work in the public interest, primarily by ensuring grid reliability, providing non-discriminatory transmission access, and running markets and planning mechanisms that produce just and reasonable wholesale electricity rates. Thus, depending on how the language is worded, it could be acceptable to include a public interest principle in the operating agreement as embedded in the FPA.
PDF page 14
14
I. Question 9 – State Nominating Committee Representation
Yes
No
Should state representatives have at least one voting member on the
Nominating Committee?
x
Exelon supports a change to the Nominating Committee makeup that would give state representatives one vote. Providing states a vote would expand the perspectives represented on the Nominating Committee and ensure that perspective is included in the selection of Board members, in equal weight with the sectors currently represented on the Nominating Committee. Having this perspective and input from the states would serve to increase the confidence that the states have in how the Nominating Committee operates and makes its decisions, ultimately building trust in the Board on the part of the states and facilitating alignment between PJM processes and state action. Of course, the state representatives on the Nominating Committee would be expected to adhere to the same strict code of conduct and confidentiality rules as all other Nominating Committee members during and after their period of service. It would be up to the various relevant state entities to determine who to put forward as the Nominating Committee participant. Finally, Exelon does not support having more than one state representative voting member on the Nominating Committee, as that could create imbalance in how various interests are represented on the Nominating Committee and ultimately the Board.
PDF page 15
15
J.
Question 10 – Performance Metrics
Yes
No
Should PJM adopt public performance metrics and tie management
compensation to their achievement?
x
Exelon does not support establishment of public performance metrics that are tied to PJM management compensation. Such a change would create several problems. First, as a general matter, there is concern that, per Goodhart’s Law, any time a measure (here: metric) becomes a target, it ceases to be a good measure. It would be undesirable to reorient PJM management’s personal incentive structure towards narrow—even if well intentioned—objectives. The result could likely be that achieving those metrics could become the overriding priority, potentially 1) prioritizing short-term outcomes at the expense of balance and long-term perspective that is necessary to achieve the broader mission of PJM, and/or 2) giving precedence and attention only to those issues tied to performance metrics, leaving other important but unincentivized issues by the wayside. Second, the PJM process and, indeed, the overall electric utility industry structure, is likely not conducive to tying work product in one period to actual outcomes—whether they be regulatory, reliability, price/affordability, etc. — in the same period. Owing to the long timescales of the utility industry, outcomes are often a significant lagging indicator to actions, often by years. Judging the quality of management performance, especially at an RTO, is only something that can be done over time. Third, PJM management is already facing unprecedented levels of scrutiny in an environment where it can be hard to identify high-caliber personnel alternatives. Layering publicly-reported performance assessments on top of already significant pressure would not be constructive to management retention and, if it caused attrition of top staff, could actually reduce outcome quality.
PDF page 16
16
K.
Question 11 – Advisory Stakeholder Process
Yes
No
Should the stakeholder process be advisory, i.e., stakeholder votes
only inform the Board?
x
Exelon supports transitioning the PJM stakeholder process to be advisory. This would be a change from the current binding endorsements process, and would entail a move to advisory polling for operations, planning, and market rules as well as for tariff changes and other activities. Our view is that this—paired with the necessary shift in section 205 rights—is likely the most impactful available governance reform and would be a significant way to address the concern expressed by Commission Chair Swett that PJM’s governance structure is unacceptable and the region may be “too big to function.” This perspective is aligned with the view advanced by the PJM Transmission Owners that the “PJM’s stakeholder process, which culminates in PJM Members Committee votes, has been widely acknowledged as an often fractious, difficult and time-consuming exercise. Intended to promote collaboration and compromise, it has in practice instead led to stasis, with many self-interested parties effectively exercising veto power over critical issues.”4 Instead, advisory polling would maintain the benefits associated with the existing large, coordinated regional grid that provides backbone reliability to 67 million customers across a wide 13 states and the District of Columbia.
Binding member endorsement voting has limited PJM’s ability to act independently, nimbly, and effectively. The current binding structure has constrained PJM’s ability to modify its governing documents, either leading to inferior, compromised rule proposals or, in some cases, no ability to present proposals to the Commission at all. By its current process, PJM and its members are forced into
4 Duquesne Light Co., Amendments to the Consolidated Transmission Owners Agreement, Docket No. ER24-2336-000, at 8 (filed June 21, 2024).
PDF page 17
17
endless negotiations to secure majority consensus, leading to watered-down rules and stifled innovation.5 Furthermore, the binding stakeholder process has proven to be slow, creating occasions for individual opportunistic stakeholders to delay resolution, in some cases for years, and ultimately produces ineffectual outcomes. In the worst cases, the products of the existing binding process may be so compromised as to not achieve their objectives, potentially leading to the costs of running the stakeholder process—in time and other resources—without any benefits to customers or the market. Especially in an operating environment that demands decisive, timely action to maintain reliability and address affordability, the current structure is not tailored to the needs of a modern RTO. Advisory stakeholder polling is successfully used in MISO, CAISO, SPP, and ISO-NE. It serves as a tool for gathering information on the positions of the RTO membership on proposals being considered by RTO staff and the Board. Stakeholder polling can enhance transparency regarding the position of various stakeholders, while allowing a shift away from the sector-weighting structure that can lead to stilted results and inflexibility in the ability of decisionmakers to make judgements based on more than mechanistic vote-counting. Furthermore, an advisory stakeholder framework would preserve a stronger, formal voice for state regulators by allowing them to provide their perspective and have it considered, either by participating in polls or otherwise, in a manner that does not constrain the state perspective to being considered as just another vote.
In addition to bringing PJM into line with best practices across other RTO/ISOs, a shift to advisory polling would better align PJM’s governance with Commission policy. The Commission has historically prioritized the idea that RTOs/ISOs should be independent. Polling of members, that is strictly advisory, ensures the ultimate decision-making power rests with the RTO/ISO Board, with
5 See e.g., id. at Ex. C, Declaration of Pulin Shah, ¶¶ 11–14 (discussing the PJM stakeholder process impeding PJM from moving forward with storage as a transmission asset, preventing PJM from leveraging this potentially valuable, flexible, and cost-saving transmission option).
PDF page 18
18
support from expert staff. This would protect PJM from being deadlocked or dictated to by special interest groups or competing member companies. Leveraging advisory polling would allow the independent Board to gain the views of the members while properly empowering them to override biased stakeholder consensus when necessary to ensure fair market operations.
Advisory polling would particularly benefit PJM because it would strongly contribute to maintaining RTO independence and neutrality given PJM’s makeup and its range of stakeholders that is broader, more diverse in terms of represented interests and business structures, more politically heterogenous, and more topologically complex than other RTO/ISO regions. This reform would have the added benefit of addressing concerns, that have been expressed by the Commission and states regarding the need to prevent special interest groups, incumbent transmission and generation utilities, financial marketers, industrial customers and consumer advocates from capturing the regulatory process and vetoing market reforms that threaten their parochial business interests. An advisory framework would make it impossible for coalitions to vote down proposed reforms out of protective self-interest, resulting in rules that often protect the narrow interests of members at the expense of the regional grid as a whole. It would allow the Board to exercise its independence to bypass gridlock and make timely, objective, systematic, strategic decisions in the interest of broad grid reliability and market efficiency.
PDF page 19
19
L.
Question 12 – PJM 205 Rights Over Energy and Ancillary Service Markets
Yes
No
Should PJM have section 205 filing rights over the energy market
and ancillary services unencumbered by the requirement to obtain
approval of two-thirds of the Members Committee?
x
Exelon supports PJM having section 205 rights over the energy and ancillary services markets, unencumbered by the requirement to obtain any approval from the Members Committee. This would align with the section 205 rights that PJM currently has for the capacity market. This conclusion follows, in part, from similar reasoning that leads Exelon to support a change to an advisory stakeholder process: the current binding endorsement voting approach gives stakeholders outsized authority over section 205 filings to the Commission. Moreover, and beyond the practical challenges that have flowed from the current process that binds the Board to the actions of the Members Committee, the Members Committee should not have anything resembling 205 rights in the first instance. These rights appropriately lie with PJM as the Commission-jurisdictional public utility, unencumbered by the obligation to act in accordance with action of the Members Committee, a third party. Under the FPA, only a public utility has section 205 rights to file to change its tariff without showing that its existing provision is unlawful, and PJM is that public utility. The Members Committee is not.
This shifting of rights to the Board and away from the Members Committee restores the RTO’s proper rights and responsibilities. Under the current arrangement, in many instances PJM is prohibited from acting to modify its rules and processes without approval of the Members Committee; that is the definitional opposite of independence. It puts PJM in a position subservient to the Members Committee and in an inferior legal posture. PJM cannot act under section 205 to change its tariff without approval from the Members Committee, a body that may not act consistent with PJM’s interests, and may
PDF page 20
20
obstruct changes to maintain reliability and advance market efficiency. Instead, perversely, in many instances PJM may only change its own tariff by filing a complaint under section 206 against itself. Restoring section 205 rights to the proper party (i.e., PJM) and advancing the necessary and corresponding shift to an advisory stakeholder structure puts the ultimate accountability and responsibility for federal regulatory filings with PJM, rather than wrongly transferring them to private market participants. Then, the Commission is put in the proper role of adjudicating the merit of those filings and whether they are just and reasonable and not unduly discriminatory, rather than only having the chance to review those limited, delayed, watered-down filings that the PJM stakeholder process currently produces.
PDF page 21
21
M.
Question 13 - PJM 205 Rights Over Planning Protocols
Yes
No
Should PJM have section 205 filing rights over Regional
Transmission Expansion Planning (RTEP) unencumbered by the
requirement to obtain approval of two-thirds of the Members
Committee?
x
Exelon supports PJM having section 205 rights over the RTEP process unencumbered by the requirement to obtain any approval from the Members committee, as PJM has over the capacity market and as we support it having over the energy and ancillary service markets. Our reasoning in support of this position is consistent with that provided in response to Question 12. As the PJM Transmission Owners have stated, “PJM, as embodied in the PJM Board and staff, is the “public utility” under the FPA and is thus the only appropriate counterparty to the Transmission Owners in terms of transferred rights and commitments under the FPA.”6 We note that any enhancement of section 205 rights over the RTEP process would be subject to negotiation of appropriate corresponding amendments to the CTOA satisfactory to both PJM and the PJM Transmission Owners. Indeed, PJM and the PJM Transmission Owners attempted to implement just such a change in June 2024 in Docket Nos. ER24-2336, EL24- 119, and ER24-2338.
6 Id. at 21.
PDF page 22
22
N.
Question 14 – Jump Ball Rights for OPSI
Yes
No
Should the Organization of PJM States Inc (OPSI) have “jump
ball” rights over resource adequacy and transmission cost
allocation filings when a supermajority of OPSI agrees on an
alternative proposal?
x
Exelon does not support the creation of “jump ball” rights for OPSI or for any other party, including the Members Committee, for any issues, including resource adequacy and/or transmission cost allocation. Under the FPA, only a public utility like PJM may have section 205 rights.7 It would therefore be inappropriate to grant section 205 rights to any non-utility party, including OPSI or the Members Committee.
7 Commonwealth of Mass., Dep’t of Pub. Utils. v. United States, 729 F.2d 886, 888-89 (1st Cir. 1984) (Breyer, J.) and Atl. City Elec. Co. v. FERC, 295 F.3d 1, 9-10 (D.C. Cir. 2002) and Atlantic City Electric Co. v. FERC, 329 F.3d 856, 859 (D.C. Cir. 2003).
PDF page 23
23
O.
Question 15 – Members Committee Jump Ball Rights
Yes
No
Should the Members Committee have “jump ball” filing rights over
the portions of the tariff where PJM has 205 filing rights when a
supermajority of stakeholders approves an alternative proposal?
x
Exelon does not support the Members Committee having “jump ball” filing rights over any portions of the tariff, regardless of any stakeholder voting thresholds. For the same reason that Exelon does not support providing “jump ball” filing rights to OPSI, as described in the answer to Question 14, Exelon opposes providing a “jump ball” filing rights to the Members Committee. Only a public utility, not the Members Committee, may have section 205 rights.88 Id.
PDF page 24
24
P.
Question 16 – Sector Weighted Voting Threshold
Yes
No
Should the approval threshold in the Members Committee be
lowered from two-thirds sector-weighted voting?
x
Exelon does not support lowering the Members Committee sector-weighted voting threshold from two-thirds. This is not the solution to what ails the Members Committee process. While it is correct that the current sector-weighted voting thresholds have been a significant barrier to advancing reforms through the PJM stakeholder process, lowering the threshold could do as much to allow poorly conceived proposals to pass as much as it could reduce the likelihood that well-developed proposals are stymied. The right answer, consistent with Exelon’s position expressed elsewhere in these comments, is to focus on empowering PJM staff and the Board by granting the Board expanded section 205 rights and shifting the stakeholder process to be advisory. If that critical reform is implemented, then any weighting of votes or polls by the Members Committee would become unnecessary and voting reports could be used to analyze members’ positions through a more expansive and diverse set of filters rather than reducing everything to simply a member’s sector affiliation.
PDF page 25
25
Q.
Question 17 – Affiliate Voting in Lower-Level Committees
Yes
No
Should the voting rules barring affiliate votes, which apply to
senior standing committees, also apply to lower-level committees?
x
Exelon does not support extending the rules barring affiliate voting to the lower-level committees. The original motivation for the implementation of affiliate voting at lower-level committees was to foster innovation and ideation in discussions in those committees. We believe that affiliate voting still holds the potential to advance this objective, and to maintain the standing committees as open workshops for ideas as PJM stakeholders seek to address challenging issues. In this context, lower-level committees focus on highly technical operational and market mechanics. The affiliate structure allows companies that have more diverse business interests to express differentiated positions on behalf of those interests where there may be distinctions on technical issues. In the current context, it is also noteworthy that the affiliate voting bar at the senior committee level acts as a safeguard against affiliate abuse. Furthermore, should the stakeholder process shift to being advisory in nature, the importance of affiliate voting would diminish—allowed or not—as all votes would be informative to the ultimate decisions of the Board. Because the overall change to an advisory stakeholder structure is the more impactful change, changes to affiliate voting rules in the lower-level committees is of lesser consequence.
PDF page 26
26
R.
Question 18 – Governors and/or State Legislators’ Representative Group
Yes
No
In addition to OPSI, should there be a second state representative
group consisting of governors’ representatives and/or state
legislators’ representatives?
x
Exelon is supportive of creating an additional group, or groups, that allow for representation of state Governors and/or state legislators. This is consistent with Exelon’s overarching view that it is appropriate to enhance the role of the states in the PJM governance structure, owing to the fact that decisions have become more political and there are more critical issues that overlap federal and state jurisdiction, so there is a need to more closely align state perspectives and PJM action. While OPSI plays a valuable role, we recognize that OPSI may not represent the full range of perspectives of policymakers in the states, and therefore there may be room for an additional group, or groups, to ensure representation of those broader perspectives.
PDF page 27
27
S.
Question 19 – State Representative Voting
Yes
No
Should state representatives have a formal voting role in the
stakeholder process (limited to certain topics, such as resource
adequacy and regional transmission cost allocation) in addition to
the consumer advocate votes?
x
Should they want it, Exelon supports the option for representatives of state interests to have a formal voting role in the stakeholder process, which be cast in addition to consumer advocate votes. This position is consistent with our general view of the appropriateness of enhancing the role of the states in the PJM governance structure. Allowing for such voting, if this is a mechanism among others that state representatives view as appropriate and constructive, will allow them to formally express their position on issues of interest, along with the votes of other stakeholders. Granted, Exelon also supports shifting the PJM stakeholder process to be advisory (i.e., stakeholder votes only inform the Board), so in our view the process that the states would be voting in would inform but not bind the Board. This would have distinct advantages, however, when adding state representative voting, including 1) there would not be a need to determine how to integrate state representative votes into current binding sector-weighted structures and 2) by not constraining state representative votes to a specific treatment within a broader structure (e.g., sector-weighted voting), the Board would be free to consider state representative votes as they assess as appropriate and in a manner that may give such votes higher significance related to certain issues (e.g., resource adequacy).
PDF page 28
28
T.
Question 20 – OPSI Consultation on Resource Adequacy and Transmission Cost
Allocation Filings
Yes
No
Should PJM be required to consult with OPSI prior to making a
section 205 filing related to resource adequacy and transmission
cost allocation?
x
Exelon supports consultation between PJM and OPSI prior to PJM making section 205 filings on either resource adequacy or transmission cost allocation. Regarding the latter, it must be recognized that PJM does not have section 205 filing rights, as they were retained by the PJM Transmission Owners, so such consultation would be with the PJM Transmission Owners and not PJM. PJM makes transmission cost allocation 205 filings on behalf of the PJM Transmission Owners and the PJM Transmission Owners consult with the Members Committee pursuant to CTOA Section 7.3.2. Additionally, the PJM Transmission Owners typically consult with OPSI prior to making 205 filings. Although OPSI already has the ability and does participate in stakeholder processes as well as conducting consultation with PJM and the PJM Transmission Owners, Exelon supports greater engagement by OPSI as well as opportunities for both the state commissions and the executive branches of each state to be involved with mechanisms that allow each state to speak with one voice through OPSI.
PDF page 29
29
III. CONCLUSION
Exelon respectfully submits these comments for the Commission’s consideration as it continues to lead and drive towards solutions to deliver for American customers, including by improving governance structures in PJM. As the Commission considers these and other comments submitted in this record, Exelon will remain a partner in developing and maintaining infrastructure that supports affordability, reliability, resilience, national security, economic growth, and other public policy goals.
Respectfully submitted,
/s/ Bradley Perkins
Bradley Perkins
Vice President and Deputy General Counsel
Exelon Corporation
10 S. Dearborn
Chicago IL 60603
Phone: (312) 394-2632
Email: bradley.perkins@exeloncorp.com
/s/ William Sauer
William Sauer
Vice President, Regulatory Affairs
Exelon Corporation
701 9th Street, N.W.
Washington, DC 20068
Telephone: 202-868-7499
Email: William.Sauer@exeloncorp.com