AD26-7-000 · 2026-08-21 · Buckeye Power, Inc.

Comments of Buckeye Power, Inc. in response to FERC's 07/30/2026 Notice re PJM Governance and Stakeholder Reforms

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder
Reforms
)
)

Docket No. AD26-7-000

COMMENTS OF BUCKEYE POWER, INC.

Buckeye Power, Inc. (“Buckeye”) submits these comments pursuant to the
Commission’s Notice Requesting Post-Conference Comment of July 30, 2026.1
Buckeye is an Ohio non-profit generation and transmission cooperative that
produces, procures, and provides at wholesale all the electric capacity, energy, and transmission required by its member electric distribution cooperatives. Buckeye operates as a cooperative and is owned by its 25 member distribution cooperatives, which are in turn each owned by their member-consumers.2  Those member cooperatives serve more than 400,000 residential, commercial, and industrial customers in service territories encompassing 77 of Ohio’s 88 counties. Buckeye operates not for the benefit of

shareholders, but for the benefit of its member-consumers.

1 Notice Requesting Post-Conference Comment (July 30, 2026), eLibrary No. 20260730-3067 (the “Notice”).

2 The 25 distribution cooperative members of Buckeye are: Adams Rural Electric Cooperative, Inc.; Buckeye Rural Electric Cooperative, Inc.; Butler Rural Electric Cooperative, Inc.; Carroll Electric Cooperative, Inc.; Consolidated Cooperative, Inc.; Darke Rural Electric Cooperative, Inc.; Firelands Electric Cooperative, Inc.; The Frontier Power Company; Guernsey-Muskingum Electric Cooperative, Inc.; Hancock-Wood Electric Cooperative, Inc.; Holmes-Wayne Electric Cooperative, Inc.; Licking Rural Electrification, Inc.; Logan County Cooperative Power and Light Association, Inc.; Lorain-Medina Rural Electric Cooperative, Inc.; Mid-Ohio Energy Cooperative, Inc.; Midwest Electric, Inc.; Midwest Energy & Communications; North Central Electric Cooperative, Inc.; North Western Electric Cooperative, Inc.; Paulding-Putnam Electric Cooperative, Inc.; Pioneer Rural Electric Cooperative, Inc.; South Central Power Company; Tricounty Rural Electric Cooperative, Inc.; Union Rural Electric Cooperative, Inc.; and Washington Electric Cooperative, Inc.

PDF page 2

- 2 -

Buckeye’s mission is to provide “to all member systems, stably and competitively priced, economical and highly reliable wholesale power, for the benefit of their members and their communities.”3 Buckeye provides this supply through wholesale power agreements under which it obtains generation resources and transmission service to meet the demand of its members, and its members pay a cost-based rate for these resources. Buckeye or its affiliates own or have the right to the output of approximately 2,445 megawatts of generating capacity located in or delivered into PJM Interconnection, L.L.C. (“PJM”). Buckeye is both a taker of transmission service under the PJM Open Access Transmission Tariff (“Tariff”) and a participant in the PJM market. Buckeye participates in the PJM market both as a market seller (as a generation owner) and as a buyer (as a Load-Serving Entity).

Buckeye has appended to these comments its responses to the questions posed in the appendix to the Notice.

Respectfully submitted,

/s/ Lija Kaleps-Clark___
Kurt P. Helfrich
General Counsel
Lija Kaleps-Clark
Deputy General Counsel
Buckeye Power, Inc.
6677 Busch Boulevard
Columbus, Ohio 43229
Telephone: (614) 681-5151
khelfrich@ohioec.org
lkaleps@ohioec.org

Counsel for Buckeye Power, Inc.

3 Buckeye’s mission statement can be found on its website at https://ohioec.org/buckeye-power.

PDF page 3

Questions/Comments
Yes
No
1) Should Board members’ terms be extended to five or more years?
Y

Comments:
2) Should there be a maximum number of years that a Board member may serve (e.g., 10 years)? Y

Comments:
3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?

Y

Comments: Buckeye is supportive of giving “preference” for Board members that reside in the PJM region.  However, residence within PJM should not be a requirement for Board member qualification as this would likely limit the number of qualified candidates.

4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?

Y

Comments:
5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?

N

PDF page 4

- 4 -

Comments:  Existing processes allow multiple opportunities for the Board and the stakeholders to communicate.  Relaxing restrictions is not necessary and may lead to unrestricted ex parte communications and undermine independent decision-making.

6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?

Y

Comments:
7) In order to increase transparency, should some Board meetings be open or available to the public?

Y

Comments: Buckeye supports allowing certain Board meetings to be open to the public, recognizing the value of transparency and stakeholder engagement. However, Buckeye does not support requiring all Board meetings to be open to the public, as non-public meetings can provide an important forum for candid, open discussion, deliberation, and the exchange of ideas that supports effective decision-making.

8) Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?

Y

Comments:
9) Should state representatives have at least one voting member on the Nominating Committee? Y

Comments:

PDF page 5

- 5 -

10) Should PJM adopt public performance metrics and tie management compensation to their achievement?

N

Comments:
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?

N

Comments: While Buckeye agrees with the ability for PJM to have Section 205 filing rights as indicated in response to questions 12 and 13 below, Buckeye believes the stakeholder process is important and valuable to identify the most effective solutions.  Buckeye thus supports PJM stakeholders having “jump ball” rights where PJM has Section 205 filing rights when a supermajority of stakeholders approve an alternative proposal as indicated in response to question 15.

12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee? Y

Comments:
13) Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?

Y

Comments:
14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?

N

Comments:

PDF page 6

- 6 -

15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?

Y

Comments:
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector- weighted voting?

N

Comments:
17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?

Y

Comments:

18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives?

Y

Comments: Buckeye supports the creation of an additional state representative group if states determine that such a group is needed.

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?

Y

Comments:

PDF page 7

- 7 -

20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?

Y

Comments: