ER26-3380-000 · 2026-08-21 · Blue Ridge Power Agency
Comments of Blue Ridge Power Agency re PJM Interconnection, L.L.C.'s Reliability Backstop Procurement proposal
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. ER26-3380-000
COMMENTS OF BLUE RIDGE POWER AGENCY
Pursuant to Rules 211 and 212 of the Commission’s Rules of Practice and Procedure1 and the Commission’s notice of filing of August 3, 2026, Blue Ridge Power Agency (“Blue Ridge”) submits the following comments on the filing by PJM Interconnection, L.L.C. (“PJM”) of proposed revisions to the PJM Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish a Reliability Backstop Procurement (the “RBP Proposal”).2
As set forth below, Blue Ridge is concerned that the lack of specificity in the RBP Proposal as to cost allocation to load-serving entities may result in unjust and unreasonable rates to Blue Ridge’s members.
A. Blue Ridge
Blue Ridge is a non-profit corporation established in 1988 under the laws of the Commonwealth of Virginia. Blue Ridge is governed by its nine members, all of which are publicly- or consumer-owned electric distribution utilities. The Blue
1 18 C.F.R. § 385.211 & .212 (2025).2 Blue Ridge filed a separate (doc-less) motion to intervene in this proceeding on August 21, 2026.
PDF page 2
2
Ridge members collectively serve over 200,000 residents of the Commonwealth of Virginia. Blue Ridge assists its members in obtaining wholesale power and makes related transmission arrangements on their behalf. Blue Ridge is a member of PJM Interconnection, L.L.C., and a member of the Electric Distributor sector. Blue Ridge members serve load in the APS, AEP, and Dominion Energy Zones of the PJM region.
B. Comments
In its transmittal letter, PJM describes the RBP Proposal as “a one-time procurement of new capacity resources intended to address previously identified resource adequacy challenges in the PJM Region arising from insufficient commitments of capacity in the 2027/2028 and 2028/2029 Reliability Pricing Model (“RPM”) Auctions.”3 More specifically, PJM asserts that its RBP Proposal “is a just and reasonable means to address the influx of large loads while maintaining resource adequacy, reliability, and affordability in a manner that respects the divide between state and federal authorities and avoids disrupting existing commercial arrangements.”4
Blue Ridge shares PJM’s concerns and objectives and recognizes the need for interim measures to address them. But Blue Ridge is concerned that the cost- allocation methods described by PJM are not set forth with enough specificity in
3 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads at 1 (filed July 31, 2026) (“PJM RBP Transmittal”).4 Id. at 2.
PDF page 3
3
the Tariff and RAA to ensure that load-serving entities like Blue Ridge’s members are charged just and reasonable rates for PJM’s interim, supplementary procurement of capacity resources.
Blue Ridge agrees with PJM’s general proposal to allocate RBP costs within a zone/area in accordance with each load-serving entity’s “RBP Obligation” (or “RBO”) as determined by a state or Relevant Electric Retail Regulatory Authority (RERRA),5 provided that the legal authority of a municipal RERRA (e.g., a city council or utility board) over retail electric service in the municipal service area is fully respected by PJM. Moreover, given the unprecedented 15-year term of PJM’s proposed capacity procurements under the RBP Proposal, Blue Ridge is concerned that a one-time allocation of costs may become unjust and unreasonable over this 15-year period. Finally, Blue Ridge is concerned that the RBP Proposal does not have enough specificity to ensure that PJM allocates RBP costs to each area/zone in the PJM region in a manner roughly commensurate with cost causation. For example, PJM’s discretion to make load adjustments or “Qualifying RBP Offsets” is not adequately specified.6 The problem created by this lack of specificity is exacerbated by PJM’s “backup” cost- allocation method, applicable when an RBO is not determined, which socializes
5 See RBP Transmittal at 98.6 See id. at 100-102.
PDF page 4
4
RBP costs to all loads in an area/zone based on peak load contributions— irrespective of cost-causation due to a load-serving entity’s new large loads.7
C. Conclusion
PJM’s RBP Proposal does not adequately address the cost-allocation concerns set forth above. Blue Ridge suggests that the Commission demand more specificity from PJM, or, alternatively, set this filing for hearing and settlement procedures.
Respectfully submitted,
/s/ Randolph Elliott
Alice J. Wolfe
General Manager
Blue Ridge Power Agency
730 W Main St
P. O. Box 2310 (mailing)
Salem, VA 24153
(540) 378-0193
awolfe@brpa.org
F. Alvin Taylor
Randolph L. Elliott
McCarter & English, LLP
1301 K Street NW, Suite 1000 West
Washington, D.C. 20005
(202) 753-3400
ataylor@mccarter.com
relliott@mccarter.com
Attorneys for Blue Ridge Power Agency
August 21, 2026
7 See id. at 98-99.
PDF page 5
5
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C. this 21st day of August, 2026.
/s/ Randolph Elliott
Randolph L. Elliott