Post-Technical Conference Comments of Geronimo Power, LLC urging PJM Interconnection, L.L.C. et al. to adopt reforms to the PJM Governance and Stakeholder…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder Reforms
)
)
)
Docket No. AD26-7-000
POST-TECHNICAL CONFERENCE COMMENTS OF
GERONIMO POWER, LLC
Pursuant to the Federal Energy Regulatory Commission’s (“FERC” or the “Commission”) July 30, 2026 Notice Requesting Post-Conference Comment,1 Geronimo Power, LLC (“Geronimo Power”) hereby submits these comments urging PJM Interconnection, L.L.C. (“PJM”) and the Commission to adopt reforms to the PJM stakeholder process and governance structure that ensure PJM’s independence and provide PJM with the tools necessary to administer its markets and effectively respond to regional challenges.
I. COMMENTS
The Commission has long recognized that “the success of [Regional Transmission
Organizations (“RTOs”)] will depend on both the perception and reality of [their] independence.”2 Indeed, FERC has explained that “the principle of independence is the bedrock upon which the [Independent System Operator (“ISO”)] must be built.”3 For an RTO or ISO to achieve independence consistent with this bedrock principle, FERC requires that they possess certain core characteristics. These characteristics include a “decisionmaking process that is independent of
1 PJM Governance and Stakeholder Reforms, Docket No. AD26-7-000, Notice Requesting Post-Conference Comment (July 30, 2026).2 Reg’l Transmission Orgs., Order No. 2000, FERC Stats. & Regs. ¶ 31,089, 65 Fed. Reg. 809 at 855, 89 FERC ¶ 61,285 (1999) (“Order No. 2000”), order on reh’g, Order No. 2000-A, FERC Stats. & Regs. ¶ 31,092, 90 FERC ¶ 61,201 (2000), aff’d sub nom. Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash. v. FERC, 272 F.3d 607 (D.C. Cir. 2001).3 Order No. 2000, 65 Fed. Reg. at 842. See also Atl. City Elec. Co. v. FERC, 295 F.3d 1, 4 (D.C. Cir. 2002) (“The Commission emphasized that an ISO’s independence with respect to governance and financial interests was fundamental to assuring that an ISO would not favor any class of transmission users.”).
PDF page 2
2
control by any market participant or class of participants” given “that the independence of an RTO ultimately depends on who makes the decisions.”4 The Commission also requires that “RTOs, in order to ensure their independence from market participants, must have the independent and exclusive right to make section 205 filings that apply to the rates, terms and conditions of transmission services over the facilities operated by the RTO.”5
While PJM and its board have been structured to be independent of market participants, experience has shown that the structure of the PJM stakeholder process is impairing the ability of PJM to act independently and effectively to advance policies that it views as serving the needs of the region. The existing governance structure has resulted in a stakeholder process that is susceptible to gridlock and that can prevent proposed solutions to pressing market issues from moving forward through the process. Additionally, the existing board structure can create disincentives for board members to vote for proposals that may not align with the interests of certain stakeholders to avoid adversely affecting their reelection prospects. These issues are compounded by the fact that PJM does not enjoy the full suite of filing rights that public utilities have historically been entitled to under Section 205 of the Federal Power Act (“FPA”). These aspects of PJM’s stakeholder process and governance structure are not new. But the significant challenges that PJM has faced in recent years have exposed the shortcomings of the existing stakeholder process and governance model. PJM itself has observed that “[t]he PJM region is now navigating a convergence of three structural forces that have pushed the system into
4 Order No. 2000, 65 Fed. Reg. at 854. See also 18 C.F.R. § 35.34(j)(1)(ii) (“The Regional Transmission Organization must have a decision making process that is independent of control by any market participant or class of participants.”).5 Order No. 2000, 65 Fed. Reg. at 858. See also 18 C.F.R. § 35.34(j)(1)(iii) (“The Regional Transmission Organization must have exclusive and independent authority under section 205 of the Federal Power Act (16 U.S.C. 824d), to propose rates, terms and conditions of transmission service provided over the facilities it operates.”).
PDF page 3
3
disequilibrium.”6 These forces include a supply shortage that has resulted in the last two PJM Base Residual Auctions clearing over 6,000 MW short of PJM’s RTO-wide reliability requirement7 and an “urgent need to bring new Capacity Resources online quickly to serve the remarkable load growth in the PJM Region.”8
If PJM is going to address these and other challenges, the PJM stakeholder process and governance framework must be reformed to ensure that PJM can take decisive action to address pressing market design issues while ensuring accountability for market outcomes. As discussed in more detail below and in Geronimo Power’s responses to the issue list developed by the Commission and attached hereto as Attachment A, Geronimo Power believes that the PJM governing documents and manuals should be modified in a manner that ensures that PJM is able to move its preferred proposals efficiently through the stakeholder process—with advisory input from stakeholders and state authorities—and provides PJM with the Section 205 filing rights required to allow it to pursue necessary changes.
Geronimo Power also believes that board member terms should be modified to further insulate board members from political pressure, provide them with greater autonomy to exercise independent judgment, and allow the board to pursue policies needed to advance the interests of the region. Extending the standard terms of PJM board members to five years and establishing a two-term limit will both (1) provide board members with greater latitude to vote in a manner that they believe aligns with the interests of the region as a whole without concern for their reelection
6 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability at 4 (May 6, 2026), available at: https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market- design.pdf?_sp=cab50bb7-7325-471c-a9ba-7eeed5235c22.1786828904496.7 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from New Load Adjustments at 7-8 (July 31, 2026).8 PJM Interconnection, L.L.C., Docket No. ER26-1563-000, Proposed Tariff Amendments for Expedited Interconnection Track at 3 (Feb. 27, 2026).
PDF page 4
4
prospects or fear of retribution and (2) ensure the PJM board benefits from the infusion of new talent and perspectives while also mitigating the potential for undue influence that can accompany unlimited re-election to the board.
A. PJM’s Stakeholder Process Must Be Reformed
PJM’s current reliance on a consensus-driven stakeholder process in which multiple committees and subcommittees develop, modify, and ultimately approve (or disapprove) of proposals is impairing the ability of PJM to move decisively to address market design issues and ensure reliability for the PJM region.9 Under the existing framework, an individual proposal often is required to navigate layers of committee and task force review before a proposal reaches the senior committees and, ultimately, the board.10 New initiatives, regardless of their importance or the timeline upon which they should be addressed, must generally proceed from an issue charge, through task force or subcommittee deliberations, to standing committee review, before receiving votes from the Markets and Reliability Committee and Members Committee.11 Throughout these stages, stakeholders are encouraged to resolve their differences and develop consensus packages, with proposals often requiring majority or supermajority support before a proposal can advance.12 The existing consensus-based approach ensures that all stakeholders can provide input on relevant proposals and register their objections. But it also creates opportunities for delay, procedural disputes, the preservation of the status quo, and results in compromise policies that too often fall short of what is necessary to address critical market design issues. The result is that the
9 PJM Manual 34: PJM Stakeholder Process § 8 (Revision 22; effective Sept. 25, 2025).10 Id.11 Id. § 8 and App. III.12 Id. § 8.3 (“The goal of the Standing Committees is to reach as much agreement as possible on a single proposal, unless the Senior Standing Committee requests multiple options.”); id. § 7.4 (“The goal is to reach as much agreement on as many elements of the issue as possible, where consensus is defined as unanimity – where all consenting parties can accept or will not object to the proposed solution.”).
PDF page 5
5
proposal that ultimately emerges from this process—to the extent it is not effectively blocked by a coalition of Members—may be a stakeholder compromise rather than the solution that best advances market operations and reliability. While this stakeholder process may have been appropriate when PJM functioned principally as a power pool and the region’s needs were less diverse, it is increasingly ill-suited to an RTO responsible for administering complex regional markets and addressing rapidly evolving reliability and market-design challenges. Geronimo Power believes that PJM, as a public utility and the independent entity charged with administering its markets, should take responsibility for determining which issues warrant action and for developing the proposals that it believes best advance reliability, competitive market outcomes, and the interests of the region as a whole in consultation with stakeholders and the states. Geronimo Power also believes that the multi-layered committee review and voting procedures that characterize the current PJM stakeholder process can no longer be permitted to delay proposals that PJM seeks to implement on a more expedited timeline. PJM must have the ability to timely implement proposals that it believes will best address the region’s needs. PJM should establish and manage a transparent, time-limited, proposal-development process for significant market-design initiatives. Each year, PJM should establish a work plan setting out the initiatives that it believes should be pursued in the upcoming year, establishing the scope and objective of each stakeholder initiative, and setting a time frame for the development and implementation of proposals.13 This workplan should be established in coordination with stakeholders with a designated timeframe for stakeholders to comment on the workplan and offer
13 Although PJM should have the flexibility necessary to modify the timeline for stakeholder initiatives as necessary to account for issues that may arise during the policy development process, PJM should endeavor to stick to the timelines established in the workplan. If it is unable to do so, then it should be required to provide an explanation to stakeholders and the board of why such timelines were not met and outline its plan to complete the initiative within a reasonable period of time.
PDF page 6
6
ideas of other initiatives that PJM should pursue. Once a final workplan is established, PJM should take the lead in driving the relevant stakeholder processes forward, including developing any initial scoping materials or proposals, publishing relevant data and analyses, and soliciting, evaluating, and incorporating stakeholder feedback. After considering relevant stakeholder input, PJM would publish a revised proposal and ultimately a final staff recommendation to the PJM board explaining the basis for its proposed approach, why it will better address market needs than relevant alternatives, and its response to stakeholder concerns.
Other RTOs/ISOs have adopted similar structures. For instance, the California
Independent System Operator Corporation (“CAISO”) has adopted a stakeholder process in which CAISO staff has primary responsibility for working with stakeholders to identify issues of concern, establishing a timeline for addressing relevant issues, and driving necessary market design changes forward through the stakeholder process. Each year CAISO staff uses its market policy catalog and roadmap process to solicit proposed initiatives from stakeholders, assess stakeholder support for taking up matters in the stakeholder process, determine the relative priority of various initiatives, and establishing a workplan and timeline for moving forward with the development and implementation of necessary market design changes.14 Once an initiative is added to the stakeholder roadmap, it enters the proposal development process based on its priority, with CAISO staff taking the lead in publishing issue papers and proposals, leading stakeholder discussions, and ultimately crafting a final proposal for presentation to the CAISO board. Throughout the process, stakeholders can provide written comments, participate in stakeholder meetings, exchange information with the CAISO and other stakeholders, and discuss proposed market design
14 CAISO, Stakeholder Process: A Guide for Stakeholders to engage and participate in policy development at the California ISO at 4 (Dec. 2025), available at: https://www.caiso.com/library/stakeholder-center.
PDF page 7
7
changes.15
While shifting to a framework where PJM staff has responsibility for driving proposals forward would streamline the existing stakeholder process and place more responsibility on PJM, stakeholders must continue to have the opportunity to provide meaningful input on proposals prior to when they are submitted to the PJM board and the Commission for review. Indeed, Geronimo Power agrees with the sentiment expressed at the Commission’s technical conference and in many of the comments filed in this proceeding that a strength of PJM’s stakeholder process is that it ensures that a broad range of market participants and stakeholders are able to provide input on proposed reforms. Geronimo Power also agrees that allowing PJM states to fully participate in debates among PJM stakeholders and to provide PJM with critical information related to how proposals under consideration may affect their citizens is beneficial.
For that reason, Geronimo Power believes that stakeholders must continue to have the opportunity to provide input on what issues are pursued through the stakeholder process and on proposals crafted by PJM staff through participation in stakeholder meetings, written comments, and advisory votes. Specifically:
• Members and other stakeholders, including the states, should be afforded the opportunity to submit written comments on PJM’s proposals as they are vetted through the stakeholder process. To promote transparency, stakeholder comments should be posted publicly. Additionally, PJM staff should have an obligation to provide a response to stakeholder comments. While an individual stakeholder-by-stakeholder response may not be necessary, PJM should be required to respond to the substance of stakeholder concerns so that stakeholders and the PJM board can understand how PJM accounted for stakeholder input, including why PJM elected not to pursue relevant alternatives offered by stakeholders.
• PJM should have the ability to determine what committees, subcommittees, or working groups a proposal is assigned, including discretion to have a proposal go directly to a standing committee, the Markets & Reliability Committee, or the Members Committee. PJM’s existing stakeholder process often results in proposals being delayed as they
15 Id. at 5-6.
PDF page 8
8
progress through multiple levels of working group, subcommittee, and committee review. Yet these multiple levels of review are not always necessary for the development of a proposal. This is particularly true when a proposal does not raise the sort of technical implementation issues that PJM’s working groups and subcommittees are often positioned to address. Additionally, if PJM determines that the implementation of a proposal is time sensitive, it should have discretion to proceed immediately to the Markets & Reliability Committee or the Members Committee.
• Members should continue to have the opportunity to vote on proposals that proceed through the existing committee structure. However, these votes should be advisory in nature rather than determinative of whether a proposal advances or not. While PJM should have the discretion to make modifications to its proposal to account for the results of a vote, the results of any vote should not determine whether a proposal moves forward.
• The record developed in the course of the stakeholder proceeding, including any written comments, the results of stakeholder votes, sector-specific positions, and relevant alternative proposals should accompany any recommendation that PJM provides to its board—who would act as the ultimate decision-maker on whether a filing is made with FERC—to ensure that the board has a transparent record of both PJM’s proposed solution and the degree and nature of stakeholder support or opposition.
Such a structure would preserve the benefits of robust stakeholder participation while recognizing that responsibility for the timely and independent administration of the PJM markets ultimately rests with PJM and the board.
Reorienting the PJM stakeholder process from a consensus-driven decision-making structure to an advisory structure would preserve transparency and stakeholder participation while reducing procedural obstacles that impede timely action. The PJM board would continue to serve as the ultimate decision maker, informed by PJM’s recommendations and stakeholder input, but regional reforms would no longer depend upon a prolonged process that requires obtaining successive committee approvals before meaningful action can occur. And to the extent that stakeholders are concerned that such an advisory role may prove insufficient, they would still have the rights afforded to them under the FPA to express their support or opposition to a given PJM
PDF page 9
9
proposal in front of the Commission through comments, protests, or complaints.16
B. PJM Should Have All FPA Section 205 Filing Rights Necessary For It To
Administer Its Markets And Plan And Operate Its System
1. PJM’s Section 205 Rights Should Be Expanded To Allow It To Make
Section 205 Filings Respecting The Tariffs That It Administers
Section 205 of the FPA reflects Congress’s determination that public utilities—not FERC or other third parties—should have the unilateral right to propose changes to the rates, terms, and conditions of service that it provides. As the courts have explained, “Section 205 of the Federal Power Act gives a utility the right to file rates and terms for services rendered with its assets.”17 If FERC or other third parties wish to make changes to the rates, terms, and conditions of service, then they are required to make a filing under Section 206 of the FPA demonstrating that the existing rate is unjust and unreasonable and the proposed alternative is just and reasonable.18
The allocation of Section 205 filing rights in PJM has strayed from this statutory scheme. In PJM, Section 205 filing rights are divided between PJM and the PJM Transmission Owners Committee depending on the governing document and subject matter. PJM generally has the right to make Section 205 filings proposing changes to its Open Access Transmission Tariff (“OATT”) or the Reliability Assurance Agreement (“RAA”),19 while the PJM Transmission Owners retain exclusive rights over transmission revenue requirements, regional transmission rate design, and recovery of transmission-related costs.20 Additionally, PJM’s ability to make a Section 205 filing respecting the Operating Agreement is conditioned upon approval by a super-majority vote of the
16 More specific information regarding Geronimo Power’s proposed reforms to the PJM stakeholder process are included in Geronimo Power’s responses to the issue list developed by the Commission and attached hereto as Attachment A.17 Atl. City Elec. Co. v. FERC, 295 F.3d 1, 9 (D.C. Cir. 2002).18 PJM Power Providers Grp. v. FERC, 88 F.4th 250, 259 (3rd Cir. 2023).19 PJM OATT § 9.2.20 Id. § 9.1(a).
PDF page 10
10
Members Committee.21 The result, as Deputy Secretary of Energy James Danly observed in his opening remarks at the Commission’s technical conference, is a situation where responsibility for ensuring that the PJM markets operate effectively is dispersed among multiple actors and bodies and it is “unclear who it is that’s responsible for what.”22
PJM should be responsible for market outcomes and should have the filing rights under Section 205 of the FPA necessary to propose tariff revisions that it believes are required to maintain the efficiency and reliability of the PJM markets. This includes being permitted to file revisions to the operating, planning, and markets rules in the Operating Agreement, including unilateral changes to Schedule No. 1 (PJM Interchange Energy Market), Schedule No. 2 (Component of Cost), and Schedule No. 6 (Regional Transmission Expansion Planning Protocol), without any obligation to obtain approval from stakeholders.
Indeed, if PJM’s FPA Section 205 filing rights remain constrained, the stakeholder reforms discussed above may be of limited effect. After all, a PJM-driven stakeholder process in which stakeholders and states play an advisory role will have little benefit if PJM is unable to file its preferred reform to the Operating Agreement unless it has obtained the requisite support from stakeholders. PJM should be granted the FPA Section 205 rights necessary for it to present its preferred reforms, regardless of stakeholder approval, to the Commission.
2. FERC Should Reject Requests To Give States FPA Section 205 Rights
Granting states Section 205 filing rights would be inconsistent with the FPA, whether these rights are exercised directly by the state regulator or indirectly by compelling PJM to file a state’s preferred rates, terms, and conditions of service with FERC. Section 205 authorizes a public
21 PJM Operating Agreement § 8.4(c).22 FERC, Commission-Led Technical Conference on PJM Governance and Stakeholder Reforms (July 23, 2026) (Opening statement of Dep. Sec. of Energy J. Danly at 41:58), available at: https://www.ferc.gov/news- events/events/PJM-Governance-Stakeholder-Reforms.
PDF page 11
11
utility—and no other entity—to make filings respecting its rates, terms, and conditions of service.23 Section 205 of the FPA “governs changes that the utility itself proposes, not those that a state regulator requires it to propose.”24 Allowing states to compel a utility to make Section 205 filings would be inconsistent “with the purposes of the entire procedural scheme.”25
Indeed, providing states Section 205 filing rights would be inconsistent with the limitations established on FERC’s authority by Congress. Section 201 of the FPA explicitly exempts states and political subdivisions of the state from FERC jurisdiction. As the courts have recognized, the “structure of the Federal Power Act clearly reflects Congress’s intent to exempt governmental entities from the Federal Energy Regulatory Commission’s” authority.26 Even if PJM were inclined to delegate filing authority to state regulators, placing FERC in the position of passing judgment on rates, terms, and conditions proposed by state actors under Section 205 of the FPA is inconsistent with the intent of Congress and the plain language of the FPA.
There also is no compelling reason that states need to be granted Section 205 rights, as Congress already has granted them ample opportunities to ensure that their views are considered by the Commission. States can intervene27 in proceedings concerning PJM and lodge protests (or supporting comments) in response to filings with FERC. Moreover, if a state views an existing tariff provision as unjust, unreasonable, or unduly discriminatory or preferential, it can file a complaint with the Commission under FPA Section 206 and, if successful, require the utility to revise such provision.
23 16 U.S.C. § 824d(c) (authorizing a “public utility” to make filings respecting the rates, terms, and conditions of FERC-jurisdictional service).24 Mass DPU v. FERC, 729 F.2d 886, 887 (1st Cir. 1984).25 Id. at 888.26 Transmission Agency of N. Cal. v. FERC, 495 F.3d 663, 673 (D.C. Cir. 2007).27 In fact, any state commission automatically becomes a party to a proceeding after timely filing a notice of intervention in such proceeding. 18 C.F.R. § 385.214(a)(2).
PDF page 12
12
To be clear, Geronimo Power believes that states have an important perspective that should, as discussed above, be considered as part of a PJM-driven stakeholder process. But elevating states in a manner that allows them to dictate the Section 205 filings made by PJM is incompatible with the statutory scheme enacted by Congress. And, as courts have recognized, elevating the role of states in a multi-state region like PJM so that they have effective FPA section 205 filing rights “threatens confusion, possibly chaos” when different states seek to impose different filing demands on PJM.28 To the extent states want to pursue options that differ from PJM’s preferred approach, they have ample opportunity to express these views through existing PJM functions (e.g. the PJM state relations function), by participating in stakeholder meetings and by making filings with FERC. These avenues, however, must remain consistent with the framework of the FPA and ensure that PJM, as the entity ultimately responsible for operating efficient markets and maintaining a reliable system, has Section 205 filings rights that allow it to carry out its core operations, planning and market functions.
C. PJM Board Service Should Be Limited To Two, Five-Year Terms
Geronimo Power believes that the existing framework for electing members of the PJM board—coupled with their three-year terms—creates a disincentive for board members to make decisions that have the potential to trigger opposition from certain constituencies within the region. Since board members are nominated by a committee of PJM Members and must be approved by the Members Committee, board members have a keen understanding of how their votes, particularly when their term is near expiration, may affect their chances to be re-elected to the board. This structure has the potential to undermine independent decision-making in a manner that is in tension with the independence that is at the core of PJM’s mandate.
28 Mass DPU v. FERC, 729 F.2d 886, 888 (1st Cir. 1984).
PDF page 13
13
The terms of PJM board members should be modified to mitigate the risk of political pressure and provide board members with greater flexibility to take the actions necessary to serve the interests of the region as a whole. PJM board members currently serve three-year terms.29 These short three-year terms leave board members that would like to serve longer than three years in a politically sensitive position knowing that any decision they make upon taking their board seat may be held against them by the PJM Nominating Committee or Members Committee if they seek reappointment. This issue is compounded by the rules allowing board members to be reappointed for additional terms without limit and also risks the entrenchment of such board members with particular interests or perspectives that may not always align with the needs of PJM. Geronimo Power urges PJM and the Commission to extend the term of PJM board
members to five years and limit the ability of board members to serve an additional term to a single additional term. Establishing a five-year term for PJM board members will further insulate board members from political pressure and provide these individuals with greater latitude to vote for those proposals that they believe align with the longer-term needs of the region. Moreover, providing board members with the ability to seek only one additional term will better ensure that board members retain their independence and that fresh perspectives are regularly introduced to the board.30 A board member that may only seek reappointment one-time at the conclusion of a five-year term will have more independence to cast votes based solely on what is best for the PJM region as a whole than board members that can seek continual reappointment following short three- year terms.
29 PJM Operating Agreement § 7.3(b).30 More specific information regarding the reforms Geronimo Power believes should be implemented to ensure the PJM board’s independence is included in Geronimo Power’s responses to the issue list developed by the Commission and attached hereto as Attachment A.
PDF page 14
14
II. CONCLUSION
Geronimo Power respectfully requests that the Commission take actions consistent with its filings in this proceeding.
Respectfully submitted,
/s/ Matthew Morais
Matthew Morais
Senior Director, Policy
Kurt Rempe
Assistant General Counsel
GERONIMO POWER, LLC
8400 Normandale Lake Blvd., Ste. 1200
Bloomington, MN 55437
mmorais@geronimopower.com
krempe@geronimopowre.com
On behalf of Geronimo Power
Dated: August 21, 2026
PDF page 15
Attachment A
Geronimo Power, LLC’s
Responses to Commission Issue List
PDF page 16
Post-Conference Comments of Geronimo Power, LLC
PJM Board Independence
Question
Yes
No
Comment
1) Should Board members' terms be extended to five or more years?
X
A three-year term without term limits
undermines Board independence.
Our preference is a five-year term, renewable once, with a ten-year maximum tenure and staggered expirations. The essential elements are a term of at least five years and a stated maximum tenure.
These changes combined with a deeper
candidate pool, achieved through liberalized qualification criteria that are related to the core ISO/RTO functions and general industry subject matter and elimination of locational restrictions and cooling off periods (as discussed in subsequent responses), weakens the case for any extension beyond the 2- term/10-year cap.
2) Should there be a maximum number of years that a Board member may serve (e.g., 10 years)? X
A stated maximum tenure is the necessary counterweight to a longer term and to
elimination of repeated reconfirmation. Two five-year terms, capped at ten years, will limit the political pressure on board members and will mitigate the risk of complacency and the associated potential for undue influence that can accompany unbounded tenure.
3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?
X
Board members should be selected based on their qualifications (i.e., relevant ISO and industry experience) rather than residence. (Note – support functions, such as finance and governance expertise, can be recruited from within the industry so individuals with expertise in those areas also understand ISOs and the industry). Regional residence is not a proxy for relevant experience, and to sacrifice the latter for the inconsequential illusory benefits of the former will undermine
identification and selection of the best candidates.
A residency preference also risks making the conflict problem worse rather than better. The pool of qualified residents in the PJM footprint is likely weighted toward former member- company
executives
and
former
state
regulators, both of which could find it difficult to ignore their past experiences, affiliations
PDF page 17
Question
Yes
No
Comment
and
potential
inherent
biases
(whether
intentional or not) that the financial-interest screen exists to exclude. Accordingly, such a restriction unnecessarily forces a tradeoff between regional presence and independent expertise
with
no
potential
inherent
stakeholder or regulator bias with respect to PJM matters.
Geronimo is not aware of a demonstrated problem
that
residency
corrects.
Term
structure and transparency are effective accountability mechanisms.
4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?
X
Geronimo would also support eliminating the cooling off period. The prohibition on financial interests in Member companies operates independent of the waiting period and it is that prohibition, together with disclosure, that actually
achieves
the
goal
of
Board
independence.
The cooling off period adds recruitment friction without adding protection. A candidate who spent a career at a Member company will be perceived as affiliated whether one year has passed or five; elapsed time does not cure the appearance.
This unnecessary restriction
potentially bars highly qualified individuals whose experience is most relevant (consistent with the prior response, Geronimo notes that ex-Member personnel always
have the
potential for bias relative to their past positions and organizations, but they can also present as high quality candidates).
5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?
X
A Board expected to exercise independent judgment on contested matters needs access to the parties affected by it. However, any communication between the Board and
stakeholders should be formalized through procedures such as requests for information and documented in a publicly available record to ensure transparency.
6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?
X
Yes, Board votes should be public and the Board should state its reasoning for accepting or rejecting proposals advanced by PJM, including discussing relevant alternatives and stakeholder views at a level sufficient to show that they were considered.
7) In order to increase transparency, should some Board meetings be open or available to the public? X
Yes, for portions dealing with policy direction and stakeholder matters. Executive session
PDF page 18
Question
Yes
No
Comment
should be preserved for personnel, litigation, market-sensitive and CEII matters.
8) Should PJM's governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?
X
PJM's mandate is already defined by function: reliable and safe delivery of energy at the most efficient price.
An open-ended public interest principle is a standard that is not capable of being
meaningfully implemented. Across a footprint of thirteen states and D.C. it would be construed differently in each jurisdiction and could result in PJM being held to varying operational
and
market
performance
requirements and/or benchmarks unrelated to the ISO core functions and associated
outcomes. Where the states are aligned the language adds nothing; where they are not it becomes a lever for whichever coalition is assembled at the time. PJM and the Board should answer to an objective standard focused on the efficiency and effectiveness of its core functions – markets, operations, and planning.
The concern applies with greater force to affordability. Affordability is a legitimate objective that PJM serves through efficient dispatch,
competitive
procurement,
and
disciplined planning, but as a governing principle it can be used as a justification for suppressing price levels in a manner that undermines competitive markets, mutes long- term price signals, raises the cost of capital for new supply, undermines resource adequacy, and increases costs to consumers in the long- term.
9) Should state representatives have at least one voting member on the Nominating Committee?
X
No. A state-selected voting seat introduces an additional political element
into Board
composition.
No
single
state-selected
representative can be expected to speak for thirteen states and the District of Columbia on all matters.
10) Should PJM adopt public performance metrics and tie management compensation to their achievement? X
Compensation should be administered by the Board within its sole discretion in terms of both the scope of the metrics, the related achievement
benchmarks
and
their
accompanying
compensation
impact.
Compensation should also be weighted toward outcomes
PJM
controls
such
as
interconnection throughput, planning cycle time, operational performance, and timeliness of filings. Compensation should not be tied to achieving particular price levels, which would encourage
operator
intervention
and
undermine market integrity.
PDF page 19
Question
Yes
No
Comment
Geronimo supports public metrics and public reporting of performance. Geronimo does not believe that the compensation of individual PJM employees need to be published.
Section 205 Filing Rights
Questions / Comments
Yes
No
Comments
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board? X
Yes. PJM must have the right to make unilateral Section 205 filings respecting core RTO functions such as planning, markets, and operations.
An advisory role does not mean that PJM should be free to disregard stakeholder input, but the obligation on the Board to consider stakeholder advice should be modeled on an administrative rulemaking process where parties can submit comments, but the agency (or in this case PJM) ultimately decides. PJM should be required to respond to stakeholder comments, but should retain control over whether a proposal moves forward through the stakeholder process. Similarly, when the Board makes a decision it should publish the reasons for its decision, including addressing the positions of stakeholders at a high level. This is similar to the process the Commission follows in a rulemaking.
Stakeholders that believe that a market rule needs to be changed will retain their rights under Section 206 to file a complaint with FERC.
12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
X
PJM must have authority over the core RTO functions of planning, markets, and operations, including the ability to make Section 205 filings concerning these matters. Geronimo also supports relocating Operating Agreement Schedules 1 (PJM Interchange Energy Market) and 2 (Component of Cost) to the Tariff (and Schedule 6 as discussed further below). As the utility responsible for administering its markets, PJM should have the right to make Section 205 filings without being obligated to obtain approval of two-thirds of the Members Committee.
13) Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members Committee? X
PJM is an outlier among RTOs in lacking filing authority over its own regional planning protocol. As stated above, PJM must have authority over the core RTO functions of
PDF page 20
Questions / Comments
Yes
No
Comments
planning, markets, and operations, including the ability to make Section 205 filings related to the Regional Transmission Expansion
Protocol.
14) Should OPSI have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?
X
No. The FPA already provides states with the ability to seek to reform tariff rules through a Section 206 complaint. There is no need to grant states any rights to compel PJM to submit states’ preferred proposal to FERC under Section 205 of the FPA. States also retain their own authority over siting, procurement, retail policy, and large-load tariffs. Additionally, states also have the ability to support the construction of new transmission through the state agreement approach.
The goal of this proceeding should be to increase the efficiency and effectiveness of the stakeholder and governance process in PJM. Creating a host of new entities with filing or “jump ball” rights is contrary to that objective.
15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?
X
No. The FPA already provides members with the ability to seek to reform tariff rules through a Section 206 complaint. There is no need to grant members any rights to compel PJM to submit their preferred proposal to FERC under Section 205 of the FPA. Stakeholders also have the right to submit comments on
proposals as they work their way through the stakeholder process and when filings are submitted to FERC under Section 205 of the FPA.
Granting new “jump ball” rights will only add further complexity and chaos into the PJM governance framework. PJM is responsible for administering its markets; there is no
compelling reason for a “jump ball” filing right for stakeholders. Geronimo encourages the Commission to pursue reforms through this proceeding that streamline the stakeholder process rather than creating a host of new filing and jump ball rights for stakeholders and the states.
The goal of this proceeding should be to increase the efficiency and effectiveness of the stakeholder and governance process in PJM. Creating a host of new entities with filing or “jump ball” rights is contrary to that objective.
PDF page 21
Questions / Comments
Yes
No
Comments
Stakeholder Process
Questions / Comments
Yes
No
Comments
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector- weighted voting?
X
If the stakeholder vote is not advisory as Geronimo recommends, a lower threshold should be established since it makes it more likely that PJM’s proposals will move forward and not be vetoed by a minority of
stakeholders, which increases the risk of undue influence and delay.
Geronimo's first preference is that the vote be advisory
(Question
11).
Lowering
the
threshold, and reconsidering sector weighting, are the appropriate secondary reforms if the vote remains binding.
17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?
X
The disparity between lower and senior committee voting rules invites positioning at the level where it is least visible and produces inconsistent signals as an issue moves upward. Making stakeholder voting advisory would address this issue.
If stakeholder voting is not made advisory, Geronimo supports aligning the manner of voting at standing committees with the Members Committee, and permitting disclosed proxy voting subject to the same affiliate restrictions.
State Participation
Questions / Comments
Yes
No
Comments
18) In addition to OPSI, should there be a second state representative group consisting of governors' representatives
and/or
state
legislators'
representatives?
X
OPSI represents an important voice. State commissions play an important role in the actual substantive matters that impact core ISO functions – e.g. siting, procurement, permitting of generation, large-load interconnection, and numerous other policies. Another organization devoted to governors’ representatives and/or state legislators’ representatives is unnecessary because to the extent those bodies/forums have positions on the substantive ISO functions their respective utility commissions are best suited to communicate those positions to the ISO.
State commissions are capable of consulting their governors' offices and legislatures and representing those positions in OPSI. PJM
PDF page 22
Questions / Comments
Yes
No
Comments
also already maintains a well-developed state relations
function.
OPSI
and
state
commissions are also well positioned to represent their states’ interests in front of FERC, where the executive and legislative branches of the states are also free to participate.
19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?
X
Yes, BUT any vote should be advisory only and the nature of the vote cast should be transparent to other stakeholders.
20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?
X
PJM makes filings at a volume that a general consultation obligation would be impracticable and slow down the process. OPSI should be permitted to provide input through the
stakeholder process, which provides more than adequate process to understand and provide input on any issue.