AD26-7-000 · 2026-08-26 · Federal Energy Regulatory Commission

Transcript of the 07/23/2025 Meeting held in Washington DC re the PJM Governance and Stakeholder Reforms

Word notes use stable document IDs, such as [fn:8], which can differ from printed footnote numbers.

Document text

1



          1   UNITED STATES OF AMERICA

          2   

          3   FEDERAL ENERGY REGULATORY COMMISSION

          4   

          5   PJM Governance and Stakeholder Reforms

          6   

          7   Docket No. AD26-7-000

          8   

          9   THURSDAY, July 23, 2026

         10   

         11   9:00 a.m.-4:00 p.m.

         12   

         13   

         14   

         15   FEDERAL ENERGY REGULATORY COMMISSION

         16   

         17   888 FIRST STREET, NE

         18   

         19   WASHINGTON, D.C. 20426

         20   

         21   

         22   

         23   

         24   

         25   





                                                                        2



          1   APPEARANCES:

          2   

          3   FERC COMMISSIONERS:

          4   CHAIRMAN LAURA V. SWETT

          5   COMMISSIONER DAVID ROSNER

          6   COMMISSIONER LINDSAY S. SEE

          7   COMMISSIONER JUDY CHANG

          8   COMMISSIONER DAVID A. LACERTE

          9   

         10   MODERATORS:

         11   ALANDRO VALDEZ

         12   STEPHANIE EYOCKO

         13   

         14   REMARKS OF INVITED SPEAKERS:

         15   THE HONORABLE JAMES. P. DANLY, Deputy Secretary, U.S.

         16   Department of Energy

         17   PETER LAKE, The White House, Senior Director of Power,

         18   National Energy Dominance Council

         19   

         20   

         21   

         22   

         23   

         24   

         25   





                                                                        3



          1   PANEL 1: PJM GOVERNANCE MECHANICS-BOARD AUTHORITY, STATES'

          2   ROLE, FILING RIGHTS, AND DOCUMENT ARCHITECTURE:

          3   

          4   PANELIST:

          5   

          6   DAVID MILLS, PJM Interconnection, L.L.C., President and CEO

          7   THE HONORABLE PAT WOOD III, Hunt Energy Network, Executive

          8   Chairman

          9   THE HONORABLE KELSEY BAGOT, Virginia State Corporation

         10   Commission, Chair

         11   JACOB FINKEL, Pennsylvania Governor Josh Shapiro's Office,

         12   Deputy Secretary of Policy

         13   STACEY BURBURE, American Electric Power, Senior Vice

         14   President, Transmission, Regulatory Engagement & Compliance

         15   MAJORIE ROSENBLUTH PHILIPS, LS Power, Senior Vice President,

         16   Wholesale Market Policy

         17   MARIA GULLINI, ISO-NE, Vice President, General Counsel, and

         18   Chief Compliance Officer

         19   

         20   

         21   

         22   

         23   

         24   

         25   





                                                                        4



          1   PANEL 2: PJM STAKEHOLDER PROCESS-DESIGN, TRANSPARENCY, AND 

          2   DECISION-MAKING

          3   

          4   PANELIST GROUP 1:

          5   ASIM HAQUE, PJM Interconnection L.L.C., Executive Vice

          6   President Governmental and Member Services

          7   SUZANNE JAWOROWSKI, Indiana Governor Mike Braun's Office,

          8   Secretary Of Energy and Natural Resources

          9   J. ARNOLD QUINN, Vistra Corp., Senior Vice President,

         10   Regulatory Policy

         11   STEVEN LIEBERMAN, American Municipal Power, Inc., Vice

         12   President of Transmission & Regulatory Affairs

         13   ABE SILVERMAN, Johns Hopkings University Ralph O'Connor

         14   Sustainable Energy Institute, Assistant Research Scholar

         15   KENT CHANDLER, R Street Institute, Non-Resident Senior

         16   Fellow, Energy and Environmental Policy

         17   PAMELA QUINLAN, GQS New Energy Strategies, Principal

         18   

         19   PANELIST GROUP 2:

         20   DAVID ANDERS, PJM Interconnection L.L.C., Senior Director of

         21   Stakeholder Affairs

         22   GLEN THOMAS, PJM Power Providers Group, President

         23   JODI MOSKOWITZ, Public Service Enterprise Group Inc., Vice

         24   President Regulatory Law, Deputy General Counsel and RTO

         25   Strategy Officer





                                                                        5



          1   JAMESON TWEEDIE, Delaware Division of the Public Advocate,

          2   Public Advocate

          3   MASON EMNETT, Constellation, Senior Vice President of

          4   Public Policy

          5   BRIAN GEORGE, Google, Senior Lead, U.S. Energy Markets

          6   SUSAN BRUCE, PJM Industrial Customer Coalition, Counsel

          7   DR. JOSEPH BOWRING, Monitoring Analytics, President and PJM

          8   Independent Market Monitor

          9   

         10   

         11   

         12   

         13   

         14   

         15   

         16   

         17   

         18   

         19   

         20   

         21   

         22   

         23   

         24   

         25   





                                                                        6



          1                      P R O C E E D I N G S

          2              MR. VALDEZ:  Good morning, everybody.  My name is

          3   Alandro Valdez.  I am from the Commission's Office of

          4   Technical Reporting and Economics.

          5              We are pleased to welcome you to this

          6   Commissioner-led technical conference to discuss PJM's

          7   governance and stakeholder processes.

          8              The purpose of this technical conference is to

          9   explore specific governance features and stakeholder

         10   processes in PJM that affect timely actions on

         11   operational and market needs.  The conference will also

         12   explore potential reforms to PJM's governance and

         13   stakeholder processes.

         14              Before we begin with opening remarks from the

         15   Chairman and the Commissioners, I will outline some

         16   logistics for the conference.  

         17              This technical conference will run from 9:00

         18   a.m. to 4:00 p.m. today.  We will have opening remarks from

         19   invited speakers in the first session, followed by two

         20   panels, with three slates of panelists.

         21              We will start with our opening speakers, followed

         22   by the first panel, on the PJM governance structure.  This

         23   will be followed by a second panel, on PJM's stakeholder

         24   processes, which will have two slates.

         25              We will have a break between each panel, one hour





                                                                        7



          1   for lunch after the first panel and a 15-minute break

          2   between the two second panels.

          3              Only the commissioners, panelists, and a small

          4   group of Commission staff will have speaking roles during

          5   the conference.  We will not be taking any questions from

          6   the audience.

          7              The conference is being webcast and transcribed

          8   and a recording will be available for future viewing.

          9              Commenters are also invited to file

         10   post-conference comments in the docket, AD26-7, following

         11   the conference.

         12              For those standing in the back of the room, we

         13   invite you to go to hearing room one, for overflow seating,

         14   where the conference is being livestreamed from here.

         15              As a reminder for all panelists, we will not

         16   discuss at this technical conference any specific proceeding

         17   before the Commission, including proceedings that involve

         18   similar issues, whether listed on the supplemental notice

         19   issued July 16th, or not.

         20              We ask that panelists, similarly, refrain from

         21   such discussion.  If anyone engages in these kinds of

         22   discussions, my colleagues from the Office of the General

         23   Counsel will interrupt the discussion to ask the speaker to

         24   avoid that topic.

         25              With those initial matters out of the way, I'll





                                                                        8



          1   now turn it over to Chairman Swett for her opening remarks.

          2              CHAIRMAN SWETT:  Thank you very much.  Good

          3   morning, everyone.  I don't think we've ever been so

          4   popular.  It's probably because of our guest speakers to my

          5   left, but it's probably more likely due to the gravity of

          6   the situation.  Thank you all for being here.

          7              I want to begin by grounding us in why we're

          8   convened today and why this conversation is so urgent and

          9   necessary.  As many of you know, at PJM's annual meeting in

         10   Baltimore this past May I remarked on the history of the

         11   market nearly a century ago when it formed and the brave

         12   leadership and oversight that -- of the foresight of the

         13   utilities that banded together in 1927 to form a power pool

         14   that produced benefits greater than any one of them could

         15   achieve individually.

         16              For many decades, that spirit drove PJM to be a

         17   leader in pursuing innovative market designs and operating

         18   one of the largest, most complex, transmission systems in

         19   the world.  We appreciate, at this commission, how difficult

         20   that task is and how it has grown increasingly difficult

         21   today, as PJM sits at the crossroads of 13 states and the

         22   District of Columbia, and there are divergent regulatory

         23   structures, resource portfolios, and politics, across the

         24   footprint.  It's a very difficult needle to thread.

         25              But we're here today because PJM is facing a





                                                                        9



          1   grave legitimacy crisis, frustrations are mounting, the

          2   collaborative spirit that underpinned the market's formation

          3   is fracturing, and some transmission owners are openly

          4   discussing leaving the RTO altogether.  Put plainly, market

          5   participants have lost confidence in PJM's decision-making

          6   abilities.

          7              But we are not here to cast blame today or point

          8   fingers or simply just air grievances.  I convened this

          9   conference today for one purpose.  That is to right the

         10   ship.  We are at a global inflection point, where nations

         11   are competing with the United States to harness the power of

         12   AI in ways that will reshape economies and geopolitics, for

         13   our lifetimes and generations after that.

         14              Our adversaries are hard at work and it's time

         15   that the companies and institutions represented in this room

         16   come together to chart the path towards a well-functioning

         17   RTO that can deliver for the American people.

         18              As I have said before, PJM is the tip of the

         19   spear, it's the laboratory of national and economic security on

         20   which our country may rise or fall.  And I'm not being

         21   dramatic; I truly believe that, and it is critical that we

         22   come out of today's conference with solutions.

         23              We need PJM to act decisively and reinstill the

         24   confidence in investors that is necessary for the region to

         25   attract the billions in capital that we need to build





                                                                       10



          1   generation and harden our infrastructure.  To do that, we

          2   have to fix the cracks in the foundational governance

          3   structure.

          4              I want PJM to be set up for success as this

          5   country navigates once-in-a-generation opportunities to

          6   cement American leadership in the global economy.

          7              As we consider potential reforms today, we can't

          8   lose sight of the 67 million Americans who directly feel the

          9   consequences of our actions on their pocketbooks. 

         10   Hard-working American families have enough on their plates

         11   and the price of electricity cannot be another source of

         12   strain.  Families in the PJM footprint should not be asked

         13   to shoulder the financial burden of processes that are

         14   slow, fragmented, or opaque.

         15              I define success as a well-functioning RTO that

         16   delivers stable, transparent, and cost-effective outcomes. 

         17   Today we begin the process of identifying and evaluating

         18   actionable reforms that will allow PJM to operate with

         19   speed, transparency, and accountability.

         20              Here is what I ask of everyone participating

         21   today.  First, be candid.  If a rule or process is failing,

         22   say so.  If things need to be eliminated, streamlined, or

         23   strengthened, we want to hear why.  We want specifics and we

         24   want the truth.

         25              Second, on the point of specificity, I personally





                                                                       11



          1   despise equivocations and hollow pledges.  We are looking

          2   for the reforms that are clearly articulated, evaluated, and

          3   we want them to be filed under Section 205, or Section 206,

          4   as appropriate.  If there are roadblocks to turning those

          5   reforms into realities, I want to hear what those are and

          6   how to cut through them.

          7              Third, I ask that each company and institution

          8   approach today's conversation with an eye towards reaching

          9   common ground.  This is not the time to fall back on

         10   familiar positions that have been worn over time and decades

         11   of businesses.  Reaffirming immovable stances is not

         12   productive.  We need change.  The market is facing change,

         13   and we're not going to succeed without it.  That means that

         14   you need to listen as much as you speak and acknowledge

         15   valid concerns, even when they come from a different side of

         16   the table.

         17              It also means looking at practical compromises

         18   and being willing to adjust longstanding positions, for the

         19   benefit of the 67 million Americans who are depending on us

         20   to get this right.

         21              And, if we can't all agree, then FERC will be in

         22   a position where we may have to do it for you.  And I would

         23   rather not be in that position.

         24              So... we will not discuss at this technical

         25   conference any specific proceedings before the Commission, including





                                                                       12



          1   proceedings that involve similar issues, whether listed on

          2   the supplemental notice or not, and we ask that the

          3   panelists similarly refrain from such discussions.  If

          4   anyone engages in these types of discussions, my colleagues

          5   from the Office of General Counsel will interrupt the

          6   discussion to ask the speaker to avoid that topic.

          7              With those initial matters out of the way, I will

          8   turn to my colleagues for their opening remarks. 

          9   Commissioner Rosner.

         10              COMMISSIONER ROSNER:  Thank you, Chairman, for

         11   convening this important conference and thank you to the

         12   panelists that will be appearing today for being here and

         13   contributing your perspective.  

         14              Thanks to everyone who filed comments, and thank

         15   you to Secretary Danly and to Peter Lake for joining us.

         16              And I'd be remiss if I didn't also thank the FERC

         17   staff for organizing the conference.

         18              Yes, PJM has problems.  Yes, they should be

         19   fixed, and it's urgent to do so.  But I want to take a

         20   moment to just acknowledge that, since it was created, PJM

         21   has saved consumers billions of dollars, year after year. 

         22   PJM has also ensured that the grid has remained reliable. 

         23   And this has been particularly evident over the last few

         24   years, when PJM has managed challenging conditions, to keep

         25   the lights on.





                                                                       13



          1              So, while we're convened here today to discuss

          2   changes to PJM to ensure that the nation's largest energy

          3   market remains sustainable and viable in the coming years,

          4   it's also important not to lose sight of PJM's importance

          5   and value.

          6              So, turning to the topic at hand, effective

          7   governance processes, are critical, for PJM to continue

          8   delivering for the region.  My hope is that today we build

          9   consensus on durable, lasting, reforms, and I'm encouraged

         10   by the hard work of reaching agreement that has already

         11   begun in earnest, and I'm optimistic that we can continue

         12   moving that ball forward today, because the opportunity

         13   before us today is one we can't afford not to capitalize on.

         14              I'm approaching today's conversation with an open

         15   mind.  That said, I'd like to offer a few opening thoughts

         16   on five categories of potential reforms that stakeholders

         17   have discussed with me, both in meetings in person and in

         18   comments.

         19              First, I agree that states need an enhanced role

         20   in the governance process, and this must be a real role,

         21   with teeth.  For example, some form of increased state

         22   participation in selecting the board sounds very reasonable,

         23   appreciating that there are many different pathways to

         24   achieve this.

         25              Second, I see support for enhanced board





                                                                       14



          1   independence.  To succeed, the PJM board needs to be able to

          2   make decisions confidently and openly, and decisively act

          3   once it's reached the best possible decision.  Achieving

          4   this outcome also can come in many different forms.

          5              Third, I'm interested in discussing pathways,

          6   either in the stakeholder process or in another venue, to

          7   amplify state input on issues related to resource adequacy. 

          8   Under the Federal Power Act, jurisdiction between the

          9   federal government and states is shared.  States are

         10   critical partners in ensuring resource adequacy, because

         11   states are ultimately responsible for siting and permitting

         12   the generation and transmission that is needed to ensure

         13   reliable and affordable power.  And I'll have more on this

         14   later.

         15              In this area, I hear a variety of potential

         16   solutions, ranging from concepts like we have in other RTOs,

         17   where state entities have opportunities to present issues

         18   directly to the board, as well as processes like the one

         19   that we set up in Order Number 1920, where we required public

         20   utilities to tell FERC what states agreed to on

         21   tranmission cost allocation.

         22              And that takes me to the fourth area of focus,

         23   state input on transmission cost allocation.  In my view,

         24   the expectation, the norm, should always be that states and

         25   their utilities agree on how to allocate the cost of





                                                                       15



          1   transmission such that a process like the one we established

          2   in Order Number 1920 is never needed.

          3              And, on that Order Number 1920 cost allocation in

          4   PJM, I'm optimistic that we will get that agreement.  But

          5   the point here is that states should always be able to

          6   formally communicate to PJM, and to FERC, in turn, what they

          7   agreed to.

          8              Fifth, I also believe it's important to have an

          9   entity for the governors' designees, and with this they can

         10   ensure -- we should ensure that they have the resources

         11   needed to organize themselves and their positions.

         12              Next, as we consider PJM governance in the

         13   stakeholder process and particularly a meaningful,

         14   potentially expanded, role for the states, very

         15   respectfully, states must also ensure that they make

         16   progress on the issues within their own jurisdictions,

         17   because I mentioned before, it's shared.

         18              For example, we need states' help with retail

         19   rate design, to ensure that they can assign wholesale costs

         20   to the right customers.  We also need states' help on

         21   curtailment priorities, otherwise known as emergency load

         22   reduction rules, for large loads.  And we need states to put

         23   in place cost allocation rules for a backstop auction, if and

         24   when we have one.

         25              And all of this, PJM state governors committed to





                                                                       16



          1   doing this backstop cost allocation when they signed the

          2   "statement of principles" regarding PJM agreement, in

          3   January, with the White House, and it's time for these

          4   provisions to be in place across the region.

          5              I also note that the Virginia SCC and the Data

          6   Center Coalition, a state and industry working together,

          7   proposed both backstop cost allocation and curtailment

          8   rules, in June, and I hope that the rest of the PJM states

          9   will join, and provide some place where we can have

         10   transparent information on the status of their member

         11   states' progress on these critical deliverables.

         12              And I wouldn't be doing my job here if I didn't

         13   also mention that we need states' help on permitting.  No

         14   matter what signal the PJM market sends or what governance

         15   reforms are implemented, PJM will not succeed without our state

         16   colleagues also ensuring that we timely get generation and

         17   transmission built.  We need help from states to make sure

         18   that they can identify resources they want to see built in

         19   their state, and then ensure that those resources get built

         20   and connected fast.

         21              For example, if your states has clean energy

         22   goals, ask yourself, "How long does it take to get a permit,

         23   the CPCN, all the authorizations to build a battery?"  If

         24   it's longer than 60 days, that sounds like a problem.  If

         25   you don't know the answer, to me that sounds like a problem





                                                                       17



          1   too.

          2              If your state wants to embrace demand response

          3   and demand side flexibility, how much retail demand response

          4   currently participates in your state?  Does your state allow

          5   aggregators access to retail meter data?  Do your utilities

          6   allow negative peak load contribution values, to enable

          7   innovative business models that can provide real RA during

          8   stress periods?

          9              And finally, on transmission, we all know that

         10   transmission is needed, to interconnect new resources.  We

         11   can have the fastest queue in the world, but if there's not a

         12   grid to plug it in there is nothing we can do fast.  So, how

         13   quickly and durably can transmission be developed in your

         14   state?

         15              So, thank you for humoring my request for

         16   assistance from our state colleagues.  While the Commission

         17   works to make progress on issues within our jurisdiction, we

         18   really need PJM, the market participants, states and other

         19   stakeholders, to make progress on these issues that are

         20   beyond our reach.

         21              But together I'm very confident that we can

         22   address the challenges we face, and I remain optimistic

         23   about PJM's future.

         24              With that, I'm very much looking forward to the

         25   conversation today and I turn it back to you, Chairman.





                                                                       18



          1              CHAIRMAN SWETT:  That was a nice balance to my

          2   brimstone.  Commissioner See?

          3              COMMISSIONER SEE:  There are tech conference and

          4   there are tech conferences, and I think it's obvious from

          5   the people who are here today and the attention that's been

          6   placed on this issue that we're in the latter category.

          7              First of all, a well-deserved round of thanks. 

          8   The prep work and the background for conversations like I

          9   hope we'll have today don't just happen.  So, thank you,

         10   Chair Swett, and to your office for bringing us together and

         11   focusing on these issues.  Thank you to our FERC staff for

         12   all of their work here, to PJM for being here and for

         13   helpful conversations along the way.

         14              To our distinguished guests and our panelists, I appreciate

         15   your willingness to put your name to ideas and engage with

         16   us on that as well.  And to the many other commenters who

         17   have already given us a strong record to start from.

         18              We have a lot to do today, so here's how I see

         19   the problem statement.  PJM, like other organized markets,

         20   has delivered huge value to customers over the years.  When

         21   functioning right, competitive markets and the economies of

         22   scale that can come with them can mean lower-cost power and

         23   better operational reliability for millions of Americans.

         24              But PJM hasn't been living up to that legacy

         25   recently.  Even with market intervention, we still have





                                                                       19



          1   sky-high prices, and last week was the second time that the

          2   auction failed to secure enough capacity to meet the reserve

          3   threshold in PJM.  To put it lightly, those are serious

          4   concerns.

          5              Now, to be clear, some of the big factors for

          6   this are outside of PJM's control.  Markets are designed to

          7   withstand some fluctuation, but the pace and scale of large

          8   load growth is well beyond an ordinary demand spike.

          9              So, I don't see the need for reforms as the

         10   problem itself.  For these conditions, we need real changes

         11   in the short term, to get us through this time and to allow

         12   PJM to keep delivering benefits into the future.

         13              As I do see it, the problem is twofold.  First,

         14   PJM's unique stakeholder process and system of voting may

         15   work in many contexts, but it hasn't led to results in some

         16   of the most consequential questions PJM is grappling with

         17   now.  We need action, not stalemates.

         18              And second, as a result of these and other

         19   struggles, states, utilities, developers, and other

         20   stakeholders have lost confidence in PJM.  Either of these

         21   are serious issues on their own, but together they put PJM

         22   at a crisis point.

         23              And that's why governance reform and the

         24   conversation today matter.  It's because I take so seriously

         25   the substantive challenges PJM has had that we have to





                                                                       20



          1   address how to get governance right.  PJM needs a process

          2   and a structure that can get these reforms done and can give

          3   stakeholders confidence enough in them to bet their money

          4   and their customers on the results.

          5              So I think today we need more than just

          6   conversation.  I'm really hoping to see us flesh out viable

          7   options and see where there is, or can, or should be

          8   consensus, moving forward.

          9              We've had a lot of strong ideas teed up already

         10   and I'm really grateful for that.  Some feel like they could

         11   be low hanging fruit or areas where we should be able to get

         12   easier momentum.

         13              For me, that category includes ways to make the

         14   board more transparent and accountable, so ideas like

         15   lengthening board terms, reevaluating selection criteria and

         16   conflict of interest rules, to get more members in the PJM

         17   region and others with direct experience and investment,

         18   consistent with good governance principles.

         19              I also think we can talk, in this category, about

         20   ways to increase board members' interaction with states and

         21   stakeholders and to have more transparency around board

         22   decisions.  So let's talk about these and other areas, where

         23   we may be able to get some relatively fast wins.

         24              But, there are other areas, of course, where I

         25   acknowledge, as we all do, it'll be harder to get reforms in





                                                                       21



          1   place.  But that's all the more reason we have to talk about

          2   them here, with the breadth of interests and expertise

          3   represented, and the urgency of the stakes.

          4              So I'm very interested in discussions about how

          5   to give states a more meaningful voice in PJM and in selecting its

          6   leadership.  State representation on the nominating

          7   committee seems an obvious step forward, for me, in this

          8   area, and I'm also interested in talking about ways to

          9   strengthen OPSI or expand the states' formal mechanisms to

         10   help set PJM's direction.

         11              And I'm very focused on how we can make the

         12   stakeholder process more effective and let PJM act more

         13   decisively.  So, let's not shy away, today, from whether an

         14   advisory stakeholder process, which is almost unique from

         15   other markets, is the right path forward for PJM.  That

         16   would undoubtedly be a big change, and I do have an open

         17   mind on this issue.

         18              But, paired with jump ball filing rights and

         19   similar 4C mechanisms for collaboration, it could be a

         20   method that lets PJM act in a faster and more decisive way

         21   than it can now.

         22              So, I'm interested in hearing from the panelists

         23   why that is, or isn't, the path forward, and what it would

         24   take to get there.

         25              Now to be clear, in closing -- and I have respect





                                                                       22



          1   for PJM, especially when I talk with the technical staff,

          2   it's clear that they are approaching the generational issues

          3   in front of us, with nuance and thoughtfulness.  But we need

          4   more.

          5              As a PJM ratepayer and an American, I want PJM to

          6   succeed.  As a FERC commissioner, I also take seriously our

          7   regulatory responsibilities to make sure the market operates

          8   in a just and reasonable way.  

          9              So, success requires action, and let's work

         10   together today to make sure that that can spur it on.  Back to you.

         11              CHAIRMAN SWETT:  Thank you.  Commissioner Chang?

         12              COMMISSIONER CHANG:  Thank you, Chair.

         13              Welcome, everyone.  Thank you for being here on

         14   this very special day, and thank you again for staff, that

         15   has prepared us for this very important technical

         16   conference.  And thank you for our guests and, of course,

         17   all of the speakers that will make today's conversation very

         18   focused on the task at hand.

         19              I too want PJM to succeed.  I think we're all

         20   here because we want to make contributions to PJM's success.

         21              The way I see this is the problem in PJM's market

         22   is actually a collective problem, and it needs to be solved

         23   collectively, so this is definitely not a finger pointing

         24   exercise.

         25              I also want to acknowledge that PJM has





                                                                       23



          1   successfully -- and we talked about benefits, my colleagues

          2   here have talked about the benefits, that PJM has yielded. 

          3   PJM also has successfully attracted merchant investments,

          4   just on combined natural gas combined cycles, since the

          5   inception of its capacity market, as the way, more or less,

          6   that was designed today, over 30 -- about 39 gigawatts of

          7   just combined cycle.  I'm not even talking about the other

          8   resources.

          9              And PJM also, through the last decade or two,

         10   successfully facilitated the retirement of some

         11   generation by enhancing its grid.  So, there have been

         12   successes in the past, and I just want to make sure that

         13   people don't forget about that.

         14              But recently, I think, the resource adequacy has

         15   been a tremendous concern for everyone, and while today's

         16   governance discussion will not address all of the problems

         17   and all the resource adequacy concerns, I think this is a

         18   very important component of this.

         19              I also want to acknowledge that PJM has been

         20   relatively responsive to states, in the past, particularly

         21   when certain states have specific needs, and studies.  And I

         22   was working in New England when I jealously looked at PJM

         23   and its staff, working with certain states in the PJM

         24   footprint, to help them facilitate their needs.

         25              So, I just want to make sure -- it's easy to





                                                                       24



          1   forget the challenges that PJM has overcome over the past

          2   decade, so I appreciate the interest today and over the last

          3   few months, the interest of so many stakeholders in

          4   exploring potential ways to improve PJM's governance.

          5              Now, in discussing governance, we need to think

          6   carefully about which of PJM's challenges stem from PJM's

          7   governance and decision-making, and which are rooted elsewhere. 

          8   Many factors outside of PJM's control have contributed to,

          9   somewhat, this perfect storm, a combination of geographic,

         10   political, regulatory, diversity of PJM's states, the unique

         11   history of the markets reacting to FERC policy changes

         12   including the minimum offer price rules, and the

         13   happenstance that PJM happens to be ground zero for global

         14   data center developments, at least the first in the US, have

         15   all contributed to the recent resource adequacy challenges.

         16              Now, as for solutions, I said earlier PJM cannot

         17   do this alone.  Everyone, including FERC, and certainly the

         18   states, and power producers, and the utilities, should take

         19   collective responsibility and, correspondingly, work

         20   constructively to develop long term solutions.

         21              I say this because I want to make clear not every

         22   problem at PJM will be fixed through changes of the

         23   governance structure.  And, you know, certainly we will talk

         24   about today the stakeholder process, the decision-making

         25   process, and who gets input, and how much input, including





                                                                       25



          1   voting structures.

          2              But these process-related challenges, even if we

          3   can fix it quickly, we won't fix some of the technical and

          4   market issues.  I just want to sort of set the stage to

          5   make sure that our expectation of change, we set the proper

          6   expectations for change.

          7              But what is important is that these

          8   process-related challenges, the answer to these challenges,

          9   is swift decision-making.  You know, in some ways I think

         10   about these questions in a very simple way.  How can we help

         11   PJM make decisions made more swiftly?

         12              The markets have always evolved.  Not just in PJM

         13   but in all of the market design, all the market structures,

         14   and their designs.  So, we need to make certain decisions,

         15   understanding that these markets will evolve and we continue

         16   to enhance them and improve them.

         17              I want to just highlight two areas.  One is state

         18   representation, when we discuss governance issues.  I

         19   support, just like I supported, in Order 1920, strong state

         20   representation.  I support having more representation from

         21   consumer advocates, as well.

         22              In PJM's decision-making process, in market

         23   design, in system planning -- in system planning.

         24              You know, coming from New England, I'm very

         25   interested in how other regions might have included state





                                                                       26



          1   participation in their decision-making and how that can be

          2   borrowed or that can enhance PJM's processes.

          3              I'm very interested in hearing about formalized

          4   options for states, and I know that in the last few weeks we

          5   have heard from many stakeholders, including the state

          6   representatives, of their proposal.  So today I hope to hear

          7   more about that.

          8              In the New England experience, I can speak

          9   firsthand that states often are frustrated with ISOs' or

         10   RTOs' decision-making process not formally inviting states

         11   to be either at the center or even at the side in the voting

         12   structure, so I think this is an important aspect of the

         13   governance that we need to consider.

         14              The second is stakeholder process.  Ultimately,

         15   it's about speed to making decisions.  I don't claim to, you

         16   know, know, and I hope to hear more about exactly how the

         17   voting structures lead to either gridlock or swifter

         18   decision making.  But I think, at this juncture, we really

         19   need PJM and its leadership, along with stakeholders and

         20   along with us, to make swift decisions.  In some ways you

         21   might not make the perfect decisions, but we need to make

         22   those decisions and then enhance them as we go along, and

         23   I'm very interested in how either PJM or its stakeholders

         24   bring ideas about how we can, sort of, get through this

         25   gridlock and trying to get on with some of the reform that's





                                                                       27



          1   necessary for the markets.

          2              Again, I just want to say where I started.  I

          3   want to make sure PJM succeeds, and I'm confident that PJM

          4   will overcome the challenges of today.  So, with that, I

          5   hand it back to you, Chair.

          6              CHAIRMAN SWETT:  Thank you.  LaCerte?

          7              COMMISSIONER LACERTE:  Good morning.  James,

          8   welcome back.  Thank you for your continued service over at

          9   DOE.  Peter Lake, welcome back to the building.  I know

         10   today is a big day for the White House, with their

         11   "Ratepayer Protection Pledge 2.0."  It's a big day for our

         12   nation.  There's a lot of governors in town.  There's a lot

         13   of utility leaders in town.  So, I want to thank the White

         14   House and all the work you've done to continue to drive that

         15   conversation forward.

         16              Thank you for everyone here today, helping us

         17   move forward with solutions to the impediments that we've

         18   observed regarding PJM governance mechanics and the

         19   stakeholder process.

         20              I've said publicly that the status quo is

         21   untenable, and that seems to be the public perception, the

         22   perception of the Americans that rely on PJM, and the

         23   investors that are necessary to dig PJM out of the hole that

         24   they find themselves in.

         25              We have a diverse group of participants and





                                                                       28



          1   different perspectives, but we share a common interest in

          2   ensuring that PJM is fully equipped to tackle the region's

          3   operational and market challenges with the urgency that is

          4   required of the moment.

          5              PJM is confronting rapid, larger load growth,

          6   from the proliferation of data centers, reindustrialization,

          7   and at the same time the capacity market is under increasing

          8   pressure to send the right investment signals, while

          9   maintaining reliability and affordability in a tighter

         10   resource environment.

         11              Transmission planning is also becoming more

         12   complex, as PJM must better anticipate where new generation

         13   and load will emerge, accelerate needed upgrades, and

         14   coordinate long term regional planning with greater speed

         15   and certainty.  Addressing these challenges requires an

         16   effective and inclusive stakeholder process, and a board

         17   that is responsive, decisive, and accountable.

         18              Success today will be measured not by the number

         19   of viewpoints expressed or the ability of one stakeholder to

         20   advocate their position over others, but by your ability to

         21   build consensus.  PJM has a binding stakeholder process that

         22   is untransparent and designed to protect the interests of

         23   those who profit.  The days of this being acceptable

         24   management structure for our nation's largest grid operator

         25   are in the past.





                                                                       29



          1              Operating a regional grid is much like a team

          2   sport.  You know, we have the stakeholders that are the

          3   players on the field, we have the board, who operate as the

          4   referee.  But PJM operates this in a little bit different

          5   manner.  The players get to call the shots that the referees

          6   inherently have to make, and it creates a conflict in which

          7   it drives the players to unilaterally advocate for their own

          8   positions and their own bottom lines.

          9              To make matters worse, if the players on the

         10   field do not like the calls that the referees make, guess

         11   what.  They can replace those referees that are more

         12   beneficial, to ones that are going to make the calls that

         13   are more beneficial to their area.  So, this is an

         14   unsustainable operation that we have, at PJM.

         15              Today's discussion should be more than just an

         16   exchange of ideas or an airing of grievances.  The dialogue

         17   today should take the tenor of a negotiation or mediation,

         18   candid, respectful, and focused on finding workable common

         19   ground.

         20              I told you previously that I expect all parties

         21   here to have settlement authority and to make your positions

         22   known.  That sometimes means ceding ground when you have a

         23   stalemate, and trusting that with a strong record of success

         24   in other RTOs these changes will be good for continued

         25   business and investment in PJM, and thus good for the





                                                                       30



          1   public.

          2              We'll talk today about accountability and

          3   transparency.  These objectives not only apply to the

          4   PJM board but to the stakeholders as well.

          5              By the end of the summer I'd like to see an

          6   agreement in principle for an instrument with common sense

          7   reforms, that are negotiated through this technical

          8   conference.  And, if that doesn't happen, I want to know

          9   why, I want to know where the roadblocks are, and my fellow

         10   commissioners and I will take independent action to protect

         11   the public.

         12              Let's get started.

         13              CHAIRMAN SWETT:  Thank you.  Alandro, we're ready

         14   to proceed.

         15              MR. VALDEZ:  Thank you, Chairman.

         16              We will now hear from our invited speakers.  We

         17   have James P. Danly, Deputy Secretary of the Department of

         18   Energy, and Peter Lake, Senior Director of Power at the

         19   White House's National Energy Dominance Council.  Chairman.

         20              CHAIRMAN SWETT:  Thank you, Secretary Danley, for

         21   being here today.  We are very much looking forward to your

         22   remarks and really appreciate the time that you have taken

         23   to be with us, because of the gravity of this issue.

         24              SECRETARY DANLY:  Thank you.

         25              So, it is a pleasure to be back here.  You can





                                                                       31



          1   imagine how much fun it is for me to return to the hearing

          2   room.  Other than poking my head in a little while ago to

          3   see that my portrait was properly aligned -- (laughter) -- I

          4   haven't been here since I left, in 2025.

          5              So anyway, the purpose of this technical

          6   conference couldn't be more important.  PJM has had quite a

          7   few problems.  We'll get into that in a second. 

          8              First, I just want to say how much fun it is to

          9   see former colleagues, Joe McClelland and my long-suffering

         10   deputy, David Morenoff when I was general counsel, and John

         11   Katz, my partner in labor, and so many other people here. 

         12   It's great to see you.

         13              And I have to say, also, that I am gratified and

         14   a little bit surprised by the crowd we have here.  I don't

         15   think I've ever seen the hearing room this full before. 

         16   That was even when we had truly-contentious questions up for

         17   debate.  This is -- I mean, did I hear that is actually an

         18   overflow room for this?  That's remarkable.

         19              So I think we should all take a moment to wallow

         20   in the fact that we're the kind of people who were excited

         21   and invigorated to be here at 9:00 a.m. on a weekday, to

         22   talk about RTO governance.  This is a special crew that we

         23   have assembled.

         24              (Laughter.)

         25              SECRETARY DANLY:  So, I've written a lot about





                                                                       32



          1   PJM over the years, and I think everybody is aware of the

          2   fact that I have pretty strong opinions on the subject. 

          3   And, before the technical conference begins, I'd like to say

          4   that, at least from my standpoint, any of the critiques,

          5   criticisms, and properly-laid charges at various parties'

          6   feet does not include that of the staff of PJM.

          7              There are truly excellent, capable, staff at PJM. 

          8   I think we all probably agree about that.  I think that Stu

          9   is very talented.  I think Chris O'Hara is an excellent

         10   lawyer.  Oh, and he's actually in the audience; I didn't

         11   realize that.

         12              (Laughter.)

         13              SECRETARY DANLY:  So, avert your -- I didn't see

         14   you before -- avert your eyes.  Pretend you didn't hear

         15   that.

         16              It is not the technical capacity of PJM's staff,

         17   who are truly talented; it is something much more

         18   fundamental than that.  So, I just want to highlight that

         19   one point first, so that everybody understands that we're

         20   talking about the mechanics of the institution and not about

         21   the individual people who work at PJM, who are very good,

         22   who have a very challenging problem set in front of them.

         23              That being said, PJM is a mess.  Right?  This is

         24   a market that has committed what I would consider to be some

         25   of the gravest crimes against the FPA that we have witnessed





                                                                       33



          1   in the history of the Commission.  Right?

          2              Shortening auction cycles, to make it more

          3   difficult to deploy capital.  Right?  Re-running auctions in

          4   obvious violation -- and I said it at the time -- obvious

          5   violation of the filed rate doctrine.  Pure madness.  Right?

          6              We've had an institution that has not wanted to

          7   show confidence in its own reliability pricing model. 

          8   Right?  That mechanism was one of the great frontiers that

          9   was created in the concept of organized markets.  The entire

         10   mechanism established was supposed to take into account the

         11   signs of scarcity and super abundance and then correct

         12   organically to those over time, and when we got to a point

         13   of scarcity signal, that caused people to panic, and a

         14   complaint was mooted out with a self-imposed restriction on

         15   the prices that are necessary to get formation.

         16              What do we have now?  Two auctions in a row that

         17   failed to meet the capacity requirement.  That is not a

         18   functioning market.  

         19              One wonders what all that money is spent for, in

         20   the capacity market.  It sounds to me like those rates may

         21   be not J and R.  If you were paying money for a capacity

         22   market, to secure supply, and it doesn't happen, why are we

         23   paying it?

         24              I really do despair for the actual mechanics of

         25   the market, and that is something that can be laid at the





                                                                       34



          1   feet of PJM very, very solidly.

          2              So, what is the problem that we're facing, with

          3   the governance of PJM?  It is, I think, fundamentally a

          4   question of transparency and accountability.  Who is

          5   responsible for what?

          6              I was sitting right over there, where

          7   Commissioner Rosner is, when we had another technical

          8   conference.  I asked the question of everybody from PJM and,

          9   in fact, Joe Bowring was there, and I said "Who is responsible

         10   for resource adequacy?" and he said "We all are."

         11              That means nobody is.  Right?  You need to have

         12   an absolutely clear line of responsibility and clear

         13   authority.  So let's go back to the paradigm that I always

         14   use when I want to chasten a market.  I talk about what the

         15   paradigmatic utilities, the vertically-integrated IOU, in an

         16   old-fashioned state, how they operate.

         17              You have a CEO, who is responsible to a board of

         18   directors, who is, himself -- or who are, themselves --

         19   responsible to shareholders.  All of them are subject to the

         20   oversight of a public utility commission, and they are all

         21   subject to the state laws that require them to serve their

         22   customers.

         23              In the case of an RTO, it's just a different

         24   model.  And in the case of PJM it's unclear exactly who it

         25   is that's responsible for what.





                                                                       35



          1              I will note that in PJM's governing documents,

          2   while there's plenty of talk about the capacity market

          3   itself, there is very little when it comes to public

          4   interest.  Right?  These are not the same institutions as

          5   the IOUs created in a regulatory compact that guarantees a

          6   franchise monopoly in return for serving every single

          7   person in their franchise territory with the service that is

          8   necessary, or at least deemed necessary by the public fiat. 

          9   Right?  It's not the same model.

         10              It is not the way PJM works, where you have that

         11   clear line of demarcation who's responsible for what. 

         12   Instead, we don't really know who does what, in PJM or, you

         13   know -- this is particularly problematic, because not only

         14   do we have a tension in the basic structure of an

         15   independent board, and I take Commissioner LaCerte's point

         16   here, that the board is only independent insofar as it is

         17   chosen by the people that are going to be overseen by it, so

         18   there is a complexity there, and it is a real tension.

         19              I think that when you have self-interested

         20   stakeholders -- and, by the way, nothing wrong with being

         21   self-interested.  Right?  Every adjudicator relies upon the

         22   pleadings of self-interested parties.  That's fine.  But we

         23   do have a question of what board independence means, when

         24   you have the self-interested parties actually having a say

         25   in who the board members are.





                                                                       36



          1              But it's even worse than just that tension. 

          2   Further, we have the issue that the filing rights are split

          3   between any number of different parties.  Right?  You have

          4   the board has some filing rights.  They can direct PJM to

          5   make filings on some subjects.  You have a stakeholder

          6   process.  The TO's have retained some of theirs in the

          7   operating agreement.

          8              That means that we are deviating from the basic

          9   premise of the Federal Power Act and, indeed, basically

         10   every state commission law, which is you have a utility that

         11   files its tariff revisions.  Right?  When you have it broken

         12   down into different committees, and subcommittees, and

         13   boards, you know, it's sort like "Committees and board,

         14   utilities, oh my!"  The are so many different parties that

         15   are playing the game that it's impossible to know exactly

         16   who's doing it and to have a coherent picture.  That is

         17   problematic.

         18              I think that splitting those rights in the way

         19   that they have been has been hard.  And then, on top of

         20   that, we have the actual misery that is the PJM stakeholder

         21   process.

         22              So, a quick poll in the room.  How many people

         23   have, at any times in their lives, endured any part of the

         24   torture that is a stakeholder meeting?  Raise hands.

         25              (There was a show of hands.)





                                                                       37



          1              SECRETARY DANLY:  Okay.  Now, put the hands down. 

          2   How many of you enjoyed it?

          3              (Laughter.)

          4              (There was a show of hands.)

          5              SECRETARY DANLY:  Oh, come on!  (Laughs.)  There

          6   is always one or two.  All right.

          7              So, I actually believe you guys.

          8              (Laughter.)

          9              SECRETARY DANLY:  So, I do not enjoy them, and I

         10   think that the fact that everybody else kept their hands

         11   down -- and this isn't a shy audience; they all raised their

         12   hands before -- I think that we have learned that, other

         13   than the two masochists here --

         14              (Laughter.)

         15              SECRETARY DANLY:  -- this is not a process that

         16   people like and it certainly is not one that delivers good

         17   results.  Right?

         18              We have had cases in which issue charges that are

         19   critical cannot make it over the threshold even to be fully

         20   considered.  And these are things that everybody would even

         21   acknowledge that they want to see handled and talked about,

         22   but the formal process does not allow for it.

         23              I don't know.  I am glad that the Chairman

         24   convened this.  I think it's long overdue.  

         25              The worry that I have, to the extent that I have





                                                                       38



          1   one, is that in the inevitable arguments that are going to

          2   ensue that were going to lose sight of the actual

          3   substantive issues that have to be dealt with.  Right? 

          4   Because PJM has real problems in the way that it operates

          5   its market.  

          6              So we have this question about the long term

          7   viability of the construct, but we also have another

          8   question, which is "What are we going to do right now about

          9   the capacity market?  What are we going to do about the fact

         10   that we're gigawatts short and we need to get that capacity

         11   as quickly as possible?"

         12              What are we going to do about the

         13   interconnection, both for load and gen?  These are the

         14   substantive issues that need immediate resolution, because

         15   PJM is -- I forget who said it, I'm sorry -- the first wave

         16   of data centers being developed, have been developed there. 

         17   There is huge demand.  We are facing demand signals like

         18   we've never seen before, certainly not in my entire time in

         19   utility, and PJM has frictions that need to be fixed

         20   immediately.

         21              So my charge to everyone, both the Commission and

         22   everybody in attendance, is while trying to work through this

         23   subject of governance reform -- right? -- don't lose sight

         24   of the fact that we actually have to fix the problems that

         25   are inhibiting the biggest problem we have, which is getting





                                                                       39



          1   as much supply on line as quickly as possible, and doing so

          2   while protecting rate payers.  Right?  That is the number

          3   one priority and it cannot be forgotten.

          4              In everything we're doing, in all of our federal

          5   policy, what we're trying to do is get as much supply

          6   developed and put in service as quickly as we can, while

          7   protecting the rate payer.  That is the objective that

          8   everybody shares, here at PJM, and PJM's board, as an

          9   institution, needs to recommit itself to the market

         10   functions that it was originally designed to oversee and

         11   execute, and they need to do it protecting the rate payer

         12   and getting as many of those obstacles out of the way as

         13   they can.

         14              So, we're shortly going to be entitled to hear a

         15   bunch of people talk, and I am looking forward to it.  I am

         16   actually going to be leaving.  I will look at it later,

         17   though.

         18              (Laughter.)

         19              SECRETARY DANLY:  I will listen to it later.  And

         20   I'm looking forward to it.  I am curious, though, to see who

         21   advocates for what.

         22              And, going back to this point about

         23   self-interested parties, like, you know, we're going to,

         24   doubtless, hear various people say that "I, I alone, am the

         25   one that should have the filing rights of this type or





                                                                       40



          1   another."  Arrogations of authority to make one type of

          2   filing or another kind.

          3              And we have to think about who they are and what

          4   they're asking for.  Right?  So, doubtless the states are

          5   going to say that the states should have more of a say. 

          6   Perhaps they should.  I'm agnostic as to the exact structure

          7   that PJM will ultimately take.

          8              But remember that the states, at least from my

          9   witnessing it over the years, seem to only agree on thing,

         10   which is that PJM needs reform.  I haven't seen a whole lot

         11   of common consensus on other subjects besides that.

         12              So, to the extent to which you think the states

         13   are going to be the salvation of PJM, just think to

         14   yourself, of any potential 205 or -- you know, filing that

         15   might come out -- how many of the states are going to agree?

         16              We're going to have TOs that are going to

         17   advocate for one policy or another.  They who plan on, you

         18   know, load forecasts that don't necessarily eventuate --

         19   right? -- we're going to have a board who is going to ask

         20   for more specific authorities, who have been reluctant to

         21   exercise those authorities that they have now, even in the

         22   face of capacity shortfalls.

         23              So, I think a certain amount of clear-eyed -- a

         24   clear-eyed view of how the different stakeholders, all of

         25   whom, as I say, are self-interested -- and that is just fine





                                                                       41



          1   -- how it is they're going to see their roles, and a bit of

          2   deliberation and discretion is going to be called for from

          3   the Commission when listening to everything that's said

          4   here.

          5              What is the ultimate objective?  I think we

          6   should all understand that when we try to figure out the

          7   ultimate governance structure what are we looking for.  We

          8   want a transparent process for all of the filings that PJM

          9   makes and the way PJM operates, including its board.  We

         10   want the board to not be shrouded in mystery or secrecy; we

         11   want to know what's going on.

         12              We want the responsibilities to be clearly

         13   outlined, who is responsible for what.  Right?  I'm not

         14   saying we have to go full-on vertically-integrated IOU,

         15   although I am a fan, but we need to know who is responsible

         16   for what part of the market.

         17              And the idea of saying that we're all

         18   responsible, we're all responsible for resource adequacy,

         19   simply cannot be true.

         20              I have in mind an Alexander Pope quote, which

         21   I'll spare you, but the basic gist is if you honor everybody

         22   you honor no one.  The same thing with responsibility.  And

         23   what we need to do is keep in mind that the PJM was created

         24   to administer a market, to harness market forces, in a

         25   utility paradigm that's not perfectly apposite to it, and





                                                                       42



          1   though the markets can deliver miraculous results for the

          2   rate payer, they don't do it when you have constant chopping

          3   and changing, and you make things -- you make it impossible

          4   for capital to be deployed.

          5              It simply will not work if that happens.  So, we

          6   want stability, as well.

          7              So, that's my two cents.  Chairman Swett, I

          8   really appreciate the opportunity to come back to FERC, just

          9   to bask in the room again.  And I appreciate everyone's

         10   attention.  Thank you.

         11              (Applause.)

         12              CHAIRMAN SWETT:  I would pay way more than two

         13   cents for those remarks.  Thank you.

         14              (Laughter.)

         15              CHAIRMAN SWETT:  That was quite the homecoming. 

         16   We really appreciate your time, Secretary, and that was very

         17   insightful framing for today.

         18              Next we have the honor of introducing Peter Lake,

         19   Senior Director of Power at the White House's National

         20   Energy Dominance Council.

         21              MR. LAKE:  Thank you, Chairman.  Thank you,

         22   commissioners, for having me today.  And more importantly,

         23   thank you for convening this very important technical

         24   conference.  Like Commissioner See said, there are technical

         25   conferences and there are technical conferences.  I





                                                                       43



          1   appreciate your leadership in calling this today.

          2              And, before I start, I want to echo Secretary

          3   Danly's comments about and appreciation for the staff of PJM

          4   and, especially from the White House perspective, appreciate

          5   the on-going dialogue we've had with the executive team and

          6   the board, for many, many months, dating back to 2025.  So,

          7   I appreciate that open communication.

          8              But we're here for a reason.  And this White

          9   House very much wants PJM to succeed, but will not tolerate

         10   continued failure.  

         11              The President will be gathering later today with

         12   multiple utilities, data center developers, co-ops,

         13   governors, state legislators, to acknowledge the expansion

         14   of the "rate payer protection pledge" that established a

         15   framework for investment in our power grid by the most

         16   highly-valued companies in the history of markets.  There is

         17   an avalanche of capital waiting to be invested in this power

         18   grid.

         19              Our President has established a framework by

         20   which that investment can be made, to not only ensure

         21   continued American lead, leadership, in AI, to continue

         22   powering our reindustrialization, but to do it in a manner

         23   that protects the average household citizens, protects our

         24   small businesses, so yes, we can build the big

         25   infrastructure this country needs.  Yes, we can maintain





                                                                       44



          1   America's lead in AI, and also protect residents and small

          2   businesses.  But we cannot do it in a broken system like

          3   PJM.

          4              You'll hear a lot of details today about the

          5   technicalities and mechanics of how these reforms should

          6   take place.  I'll spare you my thoughts on the details of

          7   those.  I won't add to the nuts and bolts.

          8              But I will offer some observations from someone

          9   who has dealt with a failed power grid.

         10              We've been there before.  The bad news is that

         11   PJM is broken.  The good news is we know how to fix power

         12   grids, in this country.

         13              When I took over responsibility of the Texas

         14   power grid, in April of 2021, I inherited a power grid that

         15   had been four minutes and 37 seconds away from total black

         16   start failure, that would have caused millions of people to

         17   be without power for not days but weeks.  Many people in

         18   this room are familiar with that.

         19              That was a very tough few years, righting that

         20   ship, and turning ERCOT around.  But thanks to decisive

         21   leadership from Texas Governor Greg Abbott, the Texas

         22   legislature, some outstanding folks on the ERCOT team, and

         23   some incredible folks at the Public Utility Commission of

         24   Texas, we did it.

         25              And, today, ERCOT, five years later, stands as a





                                                                       45



          1   great example of how to build big infrastructure in this

          2   country while also delivering power at affordable prices, to

          3   all of your citizens.

          4              The important part of why I bring up the ERCOT

          5   experience is that while the mechanical parts of that

          6   failure during winter storm Uri were about wellheads

          7   freezing over and pipes freezing up, and fuel access being

          8   constricted, the root cause of that failure was a failed

          9   governance structure and a failed stakeholder process, the

         10   same ills that haunt PJM today.

         11              PJM is clearly broken, multiple failed capacity

         12   markets, capacity auctions, sky high price increases.  And

         13   to be clear, when we throw around the term "failed capacity

         14   auction," to be clear, for the general public out there,

         15   that means that in the winter of 2028-2029, in the event if

         16   another -- not even "in the event" -- when another winter

         17   storm comes, when another Winter Storm Fern hits, the PJM

         18   market will be short six to eight hundred megawatts. 

         19   That's what that means.

         20              This market will not have enough power, a supply

         21   of power, to meet demand, in the winter of '28-'29 -- that's

         22   two winters from now -- when we have another cold... and if

         23   we don't have a cold winter storm in '28-'29, we'll have one

         24   in '29-'30.  That's what a failed capacity auction means. 

         25   It has real impacts, on real people on the ground.





                                                                       46



          1              And to Secretary Danly's point earlier, markets

          2   only work if you let them work.  If we're not going to let

          3   this market work, let's stop pretending that PJM has a

          4   market.  The cure for higher prices are high prices.  The

          5   cure for low prices is low prices.  If we're going to have a

          6   market, we've got to let it work.

          7              And, perhaps there is no greater testament to the

          8   failure of the existing stakeholder process than the fact

          9   that when, as the Secretary said, the rare occasion that all

         10   13 governors in PJM actually agreed on something, in the

         11   statement of principles, along with Secretary of Energy

         12   Chris Wright, Secretary of Interior and Chairman of the

         13   National Energy Dominance Council Doug Burgum, and the

         14   President of the United States, all agreed on a path forward

         15   to redress the most acute problem facing PJM, the lack of

         16   reliable, dispatchable, power, as it has evidenced in the

         17   failed capacity auctions, with the alignment of all of those

         18   stars, this system, this stakeholder process at PJM, could

         19   still -- still -- not deliver, even without all of that

         20   alignment.  No better indication that this is broken.

         21              And this is the only industry in the world that

         22   can stare in the face of trillions of dollars of expected

         23   investment and argue amongst each other so effectively as to

         24   scare off that investment.  The technology world is begging

         25   to invest in this market, in this infrastructure, in these





                                                                       47



          1   utilities, and the failure of this system to move forward

          2   productively in the stakeholder process, to move forward

          3   productively, is scaring away that investment.

          4              At the end of the day, the core function of PJM,

          5   and any grid provider in the United States, is to delivering

          6   reliable, affordable, power, to homes and businesses.  And,

          7   like the Secretary said, when everyone is accountable, no

          8   one is accountable.  We experienced that in ERCOT before

          9   Winter Storm Uri.  Everyone was accountable.  The market

         10   was accountable.  The stakeholders were accountable.  The

         11   legislature was sort of accountable.  But nobody was truly

         12   accountable.

         13              And we have, again, other examples around the

         14   country of how to do this right.  That's the good news.  We

         15   know how to fix this.

         16              ERCOT is in the midst of the early stages of one

         17   of the largest transmission buildouts in American history,

         18   with the 765KV lines out to west Texas.  That's a lot of

         19   happy capital being deployed.  That's a lot of happy

         20   investors that are able to grow their businesses, grow their

         21   invested capital base.  That doesn't happen in PJM.

         22              At risk of only talking about ERCOT, as the Texas

         23   representative, MISO just next door has a very

         24   well-functioning market, that is building things.  Happy

         25   investors.  Happy stakeholders.  Reliable grid operations.





                                                                       48



          1              When I took over in Texas, and for the next 2-1/2

          2   years, ERCOT did not experience any EEA event.  None.  PJM

          3   has experienced two this month.  That's not a stable grid

          4   and that's certainly not a grid poised for growth and ready

          5   to accept the capital investment that the world is waiting

          6   to put into this ecosystem.

          7              In winter storm Fern, again, PJM, near miss. 

          8   Kudos to the control room at PJM, kudos to the team on the

          9   ground at PJM for keeping the lights on.  But another EEA

         10   event -- energy emergency event.  Barely got by.  Excellent work.

         11   Those are not easy to get through.

         12              But again, in a testament to know how to do this. 

         13   We know how to fix this, in this country.  ERCOT walked

         14   through winter storm Fern and shrugged it off.  Five years

         15   earlier, a similar storm broke the back of that grid.

         16              MISO, similar outcome.

         17              And it's important.  I mention ERCOT and MISO

         18   because both of those grids have almost diametrically

         19   opposite regulatory regimes.  And yes, every grid is

         20   different, every grid is unique, and those are two very

         21   different grids that somehow manage to function quite well.

         22              What do they have in common?  ERCOT is fully

         23   deregulated and MISO is all vertically integrated utilities. 

         24   What do they have in common?  They have a stakeholder

         25   process that provides member companies a voice but not a





                                                                       49



          1   veto, and they have an independent empowered board that can

          2   make decisions in the public interest without being so

          3   fearful of the members "jumping on their shadow" that

          4   they're forced into inaction.

          5              Change is coming to PJM, one way or the other. 

          6   As we can see with the failed capacity auctions, in a few

          7   years PJM won't be able to handle winter storm Fern.  They

          8   won't be able to handle, as they didn't handle, winter storm

          9   Elliott.  And those are only going to get worse and worse.

         10              So, whether it's a coming affordability crisis or

         11   a major load shed event, change is coming.  My hope -- and I

         12   believe it's the hope of this commission, is that the change

         13   can come sooner than that.  It can be proactive,

         14   collaborative, change, led by this commission, led by the

         15   stakeholders, led by the board.

         16              State leadership is demanding change.  FERC is

         17   demanding change.  The White House is demanding change. 

         18   Investors are demanding change.

         19              We need to let this market function.  We need to

         20   put in the reforms that we know lead to positive outcomes,

         21   that lead to broader investment, better outcomes, more

         22   reliability, and lower prices for our citizens, our

         23   businesses, and the data centers and technology companies

         24   that we're counting on to maintain America's lead in AI.

         25              We need to align authority with accountability. 





                                                                       50



          1   The states must have a more substantial role.  They also

          2   need to bring more to the table.  As was mentioned earlier,

          3   the states have a key role in siting, permitting, and cost

          4   allocation.  They need to step up to the plate as well.

          5              PJM must identify "the north star."  What is our

          6   guiding light?  What is the compass that guides every action

          7   in this grid?  It cannot exist purely for the profit of the

          8   companies that operate in it.  Reliability and

          9   affordability.

         10              PJM needs an independent, transparent, board,

         11   that can take action and make tough decisions, without fear

         12   of being fired after every board meeting.

         13              They need a functional stakeholder process.  And

         14   I'll be the first to say, after a lot of tussles in Texas

         15   with the stakeholders and the advisory group down there, it

         16   is incredibly important.  Again, aligning accountability

         17   with affordability.  The governors have accountability but

         18   so do the stakeholders.

         19              They're the ones that have to live with the

         20   technical realities on the ground, of running the power

         21   plants, operating the transmission system.  They need a

         22   voice in the stakeholder process but it cannot be a veto.

         23              We must accelerate gen and load interconnect in

         24   PJM, and we must immediately implement the statement of

         25   principles that were agreed upon by all 13 governors and the





                                                                       51



          1   President of the United States to deliver the reliable,

          2   dispatchable, power that we need.  Quickly.

          3              Texas didn't have the chance to right the ship

          4   before the tragedy of winter storm Uri.  I hope the

          5   companies in PJM, the PJM executive team and board, will

          6   take the chance to right the ship in PJM.  Change is coming,

          7   one way or the other.  I hope it's proactive, collaborative,

          8   and yields great results for the people of PJM, the

          9   companies that operate in PJM, and PJM the entity that

         10   keeps the lights on.

         11              Never before has there been so much investment

         12   poised to deploy in our US power grid, and especially in

         13   PJM.  I'm speaking to a group of investors later today that

         14   represent over a trillion dollars in capital, and they're

         15   wondering why they would strand their capital in a broken

         16   PJM system.  We should be able to tell them that that is an

         17   opportunity.

         18              We've never before had a framework agreed upon

         19   across the entire political spectrum that allows, provides,

         20   a blueprint to build infrastructure at a pace never before

         21   seen in this country, at a scale never before seen in this

         22   country, and protect rate payers, protect the average

         23   household citizen.

         24              The President will be holding that event later

         25   this afternoon.  Over 200 utilities, co-ops, data center





                                                                       52



          1   developers, governors, legislators, representing 80 percent

          2   of all the power delivered in this country, are signed onto

          3   the President's rate payer protection pledge.  That is a

          4   blueprint on how to do this.  I hope PJM can take advantage

          5   of that.

          6              And so, in closing, please, be proactive.  Seize

          7   the opportunity to deliver this change.  Work together.  And

          8   please find a way to get to yes.

          9              Thanks, Chairman.

         10              (Applause.)

         11              CHAIRMAN SWETT:  Thank you, Peter. 

         12   Congratulations on your historic deal that you helped

         13   broker.  And sorry the most powerful Americans can't be

         14   there this evening to celebrate.  (Laughs.)

         15              (Laughter.)

         16              CHAIRMAN SWETT:  And back to you, Alandro.

         17              MR. VALDEZ:  Thank you, Chairman.

         18              We will now start with our first panel, on the

         19   aspects of PJM's governance mechanics that may impede PJM's

         20   ability to address operational and market needs.  The

         21   panelists include a PJM representative, representatives from

         22   PJM states, members of the five PJM member sectors, and

         23   others.

         24              Each panelist submitted in advance a statement

         25   that includes their position on the questions on the





                                                                       53



          1   counsel's agenda.  To maximize the amount of time for

          2   discussion, we will be foregoing opening remarks from

          3   panelists, to go directly to the questions from the Chairman

          4   and the commissioner.

          5              Please, if you're on panel one, please come up.

          6              (Pause.)

          7              MR. VALDEZ:  Panelists, to answer a question from

          8   the Chairman or the commissioners, please tip your name tent

          9   like so.  When you are called on, you will know when your

         10   mic is on when the LED is glowing green.  There is a gray

         11   button at the base of the microphone that you have to press,

         12   to turn it on.

         13              To maximize the time of the discussion, please

         14   keep your answer concise.

         15              I'd like to introduce our panel one panelists

         16   before I turn it back to the Chairman.  First, we have David

         17   Mills, President and CEO of PJM Interconnection, L.L.C.

         18              Next to him we have Pat Wood, Executive Chairman

         19   of the Hunt Energy Network.

         20              Then we have Kelsey Bagot, the Chair of the

         21   Virginia State Corporation Commission.

         22              Next to her we have Jacob Finkel, Deputy

         23   Secretary of Policy for Pennsylvania Governor Josh Shapiro's

         24   Office.

         25              Then we have Stacey Burbure, Senior Vice





                                                                       54



          1   President of Transmission Regulatory Engagement and

          2   Compliance at American Electric Power.

          3              Then we have Marjie Rosenbluth Philips, Senior

          4   Vice President of Wholesale Market policy, at LS Power.

          5              Then finally we have Maria Gulluni, Vice

          6   President, General Counsel and Chief Compliance Officer for

          7   ISO New England.

          8              Welcome, panel.  I'll now turn it over to

          9   Chairman Swett to ask the questions.

         10              CHAIRMAN SWETT:  Good morning, everyone.  Thank

         11   you for being here.  You all were very deliberately selected

         12   for your expertise, your backgrounds, the organizations you

         13   represent, and you are all specifically sitting here because

         14   this commission is very interested in what you have to say. 

         15   So, we really appreciate your time and the preparation that

         16   went into your testimony, and your being here.

         17              And, like I said in the beginning, we would

         18   really appreciate your candor.  We want to dig in today and

         19   really drive toward some solutions.  So, we very much

         20   appreciate that.

         21              I'm going to start with Stacey from AEP.  So,

         22   many people, obviously, have heard that AEP is considering

         23   leaving the market.  And, for a lot of us, that was a huge

         24   alarm bell for us, looking at the markets across the

         25   country, that a utility like AEP would be considering





                                                                       55



          1   publicly such a move.  So, can you please help us

          2   understand what led AEP to consider that option and what

          3   solutions you would like to see in order to recalibrate how

          4   you're thinking about PJM?

          5              MS. BURBURE:  Thank you for the question,

          6   Chairman.

          7              And before I begin, I'd like to thank the

          8   Commission for its leadership in convening this technical

          9   conference and for recognizing the importance of PJM

         10   governance to the future of the electric grid.

         11              As Peter Lake outlined, I also want to

         12   acknowledge the unique bipartisan leadership of the PJM

         13   governors, the Department of Energy, the White House, and

         14   FERC.  The fact that leaders across political parties and

         15   across federal and state governments have come together

         16   around the need to strengthen PJM governance underscores

         17   that this is not a partisan issue; it is a reliability,

         18   affordability, and national competitiveness issue.

         19              And that is the light through which AEP views its

         20   membership in PJM.  Fundamentally, it's about our customers. 

         21   It's about whether we can meet the needs to bring on new

         22   generation quickly and interconnect load.

         23              We are at a crossroads, from a national security

         24   standpoint, with respect to the need to meet this

         25   imperative.





                                                                       56



          1              We also see the stakeholder process in PJM not

          2   driving forth solutions.  There is continued deadlock, and

          3   this is symptomatic.  It's seen in the market results, but

          4   this has been an underlying issue in PJM for some time.

          5              So, we need to see innovation.  We need concepts

          6   like the accelerated load infrastructure, generation, and

          7   network planning model that AEP has put forward, holistic

          8   solutions, focused on speed, to meet the needs of customers.

          9              And we also support a role for states, in terms

         10   of what happens at PJM.  But that role must function with

         11   accountability.

         12              To Deputy Secretary Danley's point around

         13   responsibility for resource adequacy, that question is

         14   currently lacking at PJM.

         15              So, this is the view through which we see the

         16   question of PJM membership.  It's a question of can PJM be

         17   fixed, and can it meet the needs of our customers.

         18              CHAIRMAN SWETT:  Thank you for that explanation.

         19              So, you specifically recommend an advisory

         20   stakeholder structure with non-binding votes, in your

         21   testimony.  What changes would you like to see the board

         22   structure, composition, or selection criteria, that may be

         23   necessary to complement the board's expanded authority under

         24   an advisory stakeholder structure?

         25              MS. BURBURE:  I want to say that AEP is





                                                                       57



          1   approaching this conversation in exactly the way that you've

          2   requested, Chairman.  We are open to particular options with

          3   respect to the composition of the board and what any reform

          4   looks like.

          5              Our focus is on "Have we fixed the problem?  Have

          6   we resulted in a governance structure that drives

          7   solutions?"

          8              So, with respect to the board composition itself,

          9   yes, we agree with Peter Lake's comment that stakeholders

         10   should have a voice but not a veto, and we see the advisory

         11   process in MISO working well.  We think that's something

         12   that could be copied in cases, in terms of RTO governance

         13   best practices.

         14              With respect to the board, we agree with Deputy

         15   Secretary Danly's remarks and some of the commissioner

         16   remarks around transparency.  We agree with the need for

         17   additional expertise with respect to the qualifications of

         18   board members.

         19              But there is no one particular issue on which we

         20   are saying that this is a gating or threshold item, a must

         21   have.  We are approaching this conversation holistically and

         22   with an eye towards whether or not we've solved the problem.

         23              So, we're at this table in a constructive fashion

         24   and one that we hope is helpful to drive consensus.

         25              CHAIRMAN SWETT:  Thank  you.





                                                                       58



          1              COMMISSIONER ROSNER:  Wonderful.  Thank you,

          2   Chairman.

          3              So, I just wanted to, first, turn to Maria

          4   Gulluni for a question.  I was recently up in New England,

          5   at the NECPUC, which is the state regulator convening up

          6   there, and I was overwhelmed by how happy everyone was.

          7              (Laughter.)

          8              COMMISSIONER ROSNER:  All the state regulators

          9   were happy with ISO, and, you know, some of my generator

         10   friends had some things that they were concerned about but

         11   overall felt well engaged.  And so I just wanted to ask you,

         12   you know, my understanding is that a decade ago, and

         13   Commissioner Chang probably mentioned this a little bit in

         14   her opening -- a decade ago that was not the case.  I mean,

         15   I'm old enough to remember, you know, hearing from the state

         16   regulators in New England and they were not happy with ISO,

         17   at that point.  And I won't say that they're perfectly

         18   happy, but they're much happier today than they were then,

         19   is my observation.  And my guess is that this did not happen

         20   by accident.

         21              And so, I was wondering if you could speak at a

         22   high level, just for a minute or two, about how -- what did

         23   ISO New England do, to foster this really collaborative

         24   culture of engaging with the states, and how did you turn

         25   that tide around?  What are some of the things you could do? 





                                                                       59



          1   And if you have observations that maybe might resonate with

          2   your view of how things are going in PJM, that would be

          3   great.

          4              MS. GULLUNI:  Thank you for the question.

          5              It is true that we've had rockier times than

          6   we're having now, and I will give all the credit to the

          7   states.  So, the states have two organizations in New

          8   England.  So, NECPUC, you were at the symposium, is the

          9   organization of public utilities commissioners, which

         10   represents the states on issues including water, et cetera.

         11                             They also have a regional state

         12   committee, NESCO, the New England State Committee on

         13   Electricity, that is funded through a tariff and is very

         14   well resourced.  They are, the NESCO managers are appointed

         15   by the governors, so they include a mix of energy policy

         16   folks as well as PUC commissioners.

         17              And, about a decade ago, they came to us with a

         18   vision statement.  All of them reached consensus on things

         19   they wanted ISO New England to do.

         20              When the states reached consensus, across six

         21   states, we sit up and we listen.  It's very important to us. 

         22   We have the same reaction when the six sectors of our market

         23   participants have consensus on an issue.  It's an important

         24   issue; it warrants our attention.

         25              In the case of the New England states' vision





                                                                       60



          1   statement, their primary concern was transmission related. 

          2   They wanted longer term studies from us.  So, we staffed up

          3   to do it and we now have a set of rules around longer term

          4   transmission planning that the states asked for, that we

          5   worked for with them.

          6              But really I will say the vehicle is the regional

          7   state committee, appointed by governors, fully resourced,

          8   contractually obligated to work through the stakeholder

          9   process.  So, it has created an atmosphere that is conducive

         10   to reaching consensus.

         11              COMMISSIONER ROSNER:  Thank you for that.

         12              I'd also like to ask a few folks, just their sort

         13   of top line take on some of the reforms that we've been

         14   discussing and that I've seen in the statements.

         15              Marjie, I want to start with you.  Do you support

         16   an increased state role in the board selection process, at

         17   PJM?

         18              MS. PHILIPS:  So, one, thank you for the honor,

         19   privilege, and burden of testifying here today.  (Laughs.)

         20              COMMISSIONER ROSNER:  You're welcome.  Thanks for

         21   being here.

         22              (Laughter.)

         23              MS. PHILIPS:  We do.  And let me explain.  I'm

         24   probably the only person here that sat on the nominating

         25   committee at PJM a number of times, and others.  And, Jacob





                                                                       61



          1   and I had a great discussion the other day, because

          2   everybody thinks the stakeholders get in there and we come

          3   in, "Ah!  I want somebody who's gonna vote for market

          4   reform!"

          5              And the transmission owners, "I want somebody

          6   who's gonna give me the money!"

          7              It's astonishing how quickly the nominating

          8   committee consolidates over who they want.  And you know

          9   why?  We're not looking for you to support our position;

         10   we're looking for you to show leadership.  Are you going to

         11   challenge the PJM staff?  Frankly, that's our biggest

         12   concern, is who we're nominating to the board going to have

         13   the expertise, the courage?  Do they work well with other

         14   board members?  Do they seem to have a personality...

         15              So, it's kind of weird that people think it's

         16   this secret society of stakeholder interests that are

         17   nominating board members.  It's the opposite.

         18              But I understand and appreciate there's a

         19   concern, from the states, that they don't see that, they

         20   haven't participated on it.

         21              So, we suggested -- and, frankly, I'm very proud

         22   -- I was on the nominating committee that brought Matt

         23   Nelson, and Matt shared with us a lot of the NEPOOL

         24   practices, and I think has been a terrific advocate, and he

         25   was on the nominating committee.  So, he kind of made me





                                                                       62



          1   think yeah, we need to do that.

          2              So, to proceed, the concern is, and with all of

          3   this I just have to get in my side crack here, which is the

          4   TOs and the states are all saying "We want more independence

          5   but we want more 205 rights."  Right?  None of the other

          6   sectors are saying that.  Everybody's independent, but the

          7   two folks that are saying they -- two groups saying they

          8   want independence, also want greater 205 rights.  

          9              So, I just throw that out for consideration.

         10              COMMISSIONER ROSNER:  Okay.

         11              MS. PHILIPS:  But getting back to your issue...

         12              COMMISSIONER ROSNER:  All right.  So, thank you. 

         13   We have very limited time, so I want to pause you right

         14   there...

         15              MS. PHILIPS:  Yeah.  Okay.  Can I just... okay...

         16              COMMISSIONER ROSNER:  ...and Stacey, I want to

         17   ask you the same question.  Do you support increased state

         18   participation in the board selection process?

         19              MS. BURBURE:  Yes.  And a rebuttal, no.

         20              COMMISSIONER ROSNER:  We'll come to the 205

         21   question later.

         22              MS. PHILIPS:  Sorry.  Sorry.

         23              MS. BURBURE:  Okay.

         24              COMMISSIONER ROSNER:  I also -- I wanted to ask,

         25   do you support funding for a government, governors',





                                                                       63



          1   designee group?

          2              MS. BURBURE:  We support a great role for state. 

          3   What that looks like, whether it's an expansion of OPSI,

          4   whether it's a new group, whether it's on the nominating

          5   committee, whether it's a direct board seat.

          6              COMMISSIONER ROSNER:  Yeah.

          7              MS. BURBURE:  We are open with respect to the

          8   form in which that participation in a meaningful role in PJM

          9   takes place.

         10              COMMISSIONER ROSNER:  Great.

         11              MS. BURBURE:  We're focused on the outcome, not

         12   the exact structure.

         13              COMMISSIONER ROSNER:  Uh-huh.  Okay.

         14              MS. BURBURE:  And we would defer to state

         15   commissions and the governors with respect to what this role

         16   should look like and whether it fulfills their needs, in

         17   terms of their participation at PJM.

         18              COMMISSIONER ROSNER:  I agree with you.  I'm not

         19   sure what it should look like, but I hear the need.

         20              And, Marjie, do you agree as well?

         21              MS. PHILIPS:  Uh-huh.

         22              COMMISSIONER ROSNER:  Okay, great.

         23              I wanted to ask -- and I'm focusing on your two

         24   because I think you're both voting members in PJM, and I

         25   don't think anybody else is, on this panel.





                                                                       64



          1              I want to ask, there was also a desire for state

          2   input on resource adequacy issues, and this is where --

          3   we've had a lot of ideas.  There is one concept of some

          4   version of shared filings right that could be conditioned

          5   on, you know, if agreement isn't reached.  Or other things,

          6   like in New England they have an MOU with NESCO and NEPOOL

          7   and the ISO.

          8              But I want to ask this general question.  You

          9   know, holding aside all the different iterations, some of

         10   which are more widely agreed to or not, do you support

         11   additional state input on resource adequacy issues, at PJM? 

         12   I'll start with Stacey.

         13              MS. BURBURE:  Yes.  But we agree with Deputy

         14   Secretary Danly that that responsibility should also be in

         15   alignment with accountability, and that roles with respect

         16   to resource adequacy should be better defined throughout

         17   that process.

         18              COMMISSIONER ROSNER:  I don't disagree with you.

         19              MS. PHILIPS:  Agree.  Our concern is what are the

         20   states' interests.  We're not New England, which has a very

         21   consolidated view of "No more gas, we want renewables."

         22              PJM's 13 states, D.C., some want coal, some want

         23   renewable, some want gas.

         24              So what are the states' interests?  What's what

         25   we're challenged with.  We absolutely agree they need a





                                                                       65



          1   greater role, but they don't come together on many issues,

          2   so our challenge is how do we give them a greater voice,

          3   while still acknowledging and accepting that they have very

          4   different policies goals.  That scares us a little bit.

          5              COMMISSIONER ROSNER:  Uh-huh, uh-huh.  You know,

          6   in my mind, I think it's one thing to provide the greater

          7   role, and it's a second to have that accountability on the

          8   issue of resource adequacy.

          9              And that leads, really directly, to my next

         10   question, which is another area that I saw in the comments

         11   was this increased role for board independence, so that the

         12   board can make hard decisions on things that right now, as

         13   was discussed earlier, entities have the opportunity to

         14   veto, or preclude, the board from acting, if we can't reach

         15   agreement among the stakeholders.

         16              And so, my question is, you know, one idea was we

         17   could move pieces that are currently in the operating

         18   agreement into the tariff under certain conditions or under

         19   no conditions.  And so my question is do you support moving

         20   markets, and more the transmission planning authorities,

         21   into the boards' more direct responsibilities?  Stacey, then

         22   Marjie.

         23              MS. BURBURE:  I want to make sure I understand

         24   the question, because I think there are some nuances there. 

         25   So, I'll address it and then you can tell me if you'd like





                                                                       66



          1   me to elaborate on anything.

          2              COMMISSIONER ROSNER:  Yeah.

          3              MS. BURBURE:  I just want to be direct and

          4   candid.

          5              So, with respect to the planning protocols,

          6   certainly we believe that should be in the tariff, and PJM

          7   is unique in not having direct filing authority over that

          8   aspect.

          9              With respect to the market, that is an

         10   interesting one in terms of how is that authority exercised. 

         11   But again, we support an advisory stakeholder model.

         12              COMMISSIONER ROSNER:  Uh-huh.

         13              MS. BURBURE:  So, overall, if that reform were

         14   implemented, by definition it empowers the board to make

         15   more decisions on an overall basis.

         16              COMMISSIONER ROSNER:  Got it.

         17              MS. BURBURE:  So, functionally, it's consistent

         18   with the types of reforms that we support.

         19              MS. PHILIPS:  Do you want candor or not?

         20              COMMISSIONER ROSNER:  I think we're here for

         21   candor.

         22              MS. PHILIPS:  Okay.  Here it comes.

         23              COMMISSIONER ROSNER:  I think the Chairman

         24   charged us all with candor.

         25              MS. PHILIPS:  Here it comes.  So, we've already





                                                                       67



          1   filed our comments.  There was a case that was before you

          2   and then went to the courts, and so you know where we stand

          3   on moving 205.

          4              The challenge to PJM is when the board feels

          5   pressure from the states, FERC has not always been the

          6   economic regulator.  We're here because of MOPR, RMRs,

          7   collars.  Those are all straight state-driven initiatives,

          8   and FERC was not always acting as an economic regulator.

          9              So, our message is the board needs to be

         10   independent.  So does FERC.

         11              You know, a couple years ago, we all thought

         12   we're going to drive energy markets to incorporate

         13   renewables.  Now we're worried about are combined cycle is

         14   going to get enough energy revenues, because those are the

         15   units that you want to come online now.

         16              So, yes, the PJM has complete 205 over

         17   reliability.

         18              COMMISSIONER ROSNER:  Uh-huh.

         19              MS. PHILIPS:  We did say we think the states

         20   should have more rights on cost allocation.  But we think

         21   the allocation of 205 rights, as they exist now, are

         22   correctly done.  And everybody always has a 206 right, and

         23   the Commission has acted very quickly on them sometimes, and

         24   sometimes they sit on your shelves for years.

         25              So, there are alternative approaches, when the





                                                                       68



          1   205 rights are not moving fast enough.

          2              COMMISSIONER ROSNER:  Thank you.  And thank you

          3   for humoring this line of questions.

          4              CHAIRMAN SWETT:  Wait.  Before we move on -- I

          5   will give you some of your time back.

          6              COMMISSIONER ROSNER:  Oh!  Please!  Yes, yes.

          7              CHAIRMAN SWETT:  I think we should hear from Mr.

          8   Mills what he thinks about board independence.

          9              MR. MILLS:  Thank you, Madam Chair, and thank

         10   you, commissioners, for putting this together.  I am very

         11   much enjoying the conversation, so far.

         12              So, that is one of the things I intended to talk

         13   about, was that we believe -- and I speak on behalf of the

         14   board -- we believe that the board would be more independent

         15   and able to act more quickly if we had those 205 rights over

         16   the operating agreement, which is the energy and ancillary

         17   services market.

         18              As Marjie pointed out, we do have those rights

         19   currently, under the resource adequacy agreement, which is

         20   the capacity market, and to correct the record, we have used

         21   those rights.  In fact, we've used the 205 and capacity

         22   market 13 times since 2023.  So, it is a tool that we are

         23   able to use.

         24              The reason I think that's important is -- and

         25   I'll point to what we call "the reserve certainty senior





                                                                       69



          1   task force" -- this is a task force we put together to make

          2   sure that we are putting a number out there, a market number

          3   for reserves, that comports with the status of the system.

          4              It's a very technical and very detailed,

          5   complicated, discussion to have.  A lot of time has been

          6   spent educating members and, to some extent, ourselves.  But

          7   that process has now languished for three years.  And yet,

          8   to date, our reserve problems continue.

          9              So, there is an instance where, with a

         10   time-delimited basis, after a fulsome stakeholder process,

         11   the board, if we're allowed to file a 205, we would

         12   potentially, depending on the board's adjudication, we'd be

         13   done with that and moving on to the next issue.

         14              So, I do support, and the board supports, that,

         15   and that's one of the things we think the Commission look

         16   forward to, or look towards.

         17              CHAIRMAN SWETT:  And we all have heard, at this

         18   table, the board's concerns that they cannot act freely

         19   because they are concerned about termination.  Can you weigh

         20   in on that?

         21              MR. MILLS:  Well, it's public record that two

         22   annual meetings ago, in Virginia, we had taken, the board

         23   had taken, a couple of what I'll say was independent

         24   actions.  They had had consultation with stakeholders in

         25   advance, but they were clearly outside of the pale of the





                                                                       70



          1   standard protocol for the board.  And, as a result, two

          2   board members were not reconfirmed.  So, I think that's a

          3   real concern.

          4              And, the challenge with the construct of the

          5   nominating committee and the appointment of the board, to

          6   date, it's a three-year term, and so I came to PJM after 40

          7   years of experience elsewhere in this country, in this

          8   industry, and it was like starting over.

          9              So, the reason I say that three years is a

         10   problem is that, three years, you're just now figuring out

         11   the decoding of the acronyms, and now you're standing for

         12   renomination, or could be voted out.

         13              One of the proposals that I've seen, and we

         14   haven't taken a position on it, but it has some appeal, is a

         15   single appointment, for a longer duration of board members. 

         16   That would alleviate that.

         17              The board has demonstrated, over the last year,

         18   that we are capable of taking care of any performance issues

         19   of our fellow board members.  And that record, I think,

         20   stands.

         21              So, if this is a matter of we believe the members

         22   need to weed out the poor-performing board members, believe

         23   me, this board will take care of that themselves.

         24              CHAIRMAN SWETT:  So, longer board terms.  I

         25   think, did you say, five years?





                                                                       71



          1              MR. MILLS:  I didn't specify.  Longer than three.

          2              CHAIRMAN SWETT:  So, what's the number?

          3              MR. LACERTE:  Why don't you specify it for us? 

          4   Yeah.

          5              MR. MILLS:  I would say, Commissioner, given the

          6   complexity of the issues and that we want a board that looks

          7   forward to a long term focus, I would say six to nine years.

          8              CHAIRMAN SWETT:  And, would you change the

          9   ability to terminate or not renew board members, for

         10   performance?

         11              MR. MILLS:  They would not come up for -- through

         12   the nominating committee -- if it were a nine-year term,

         13   every year the nominating committee would meet, to find a

         14   new board member, for one that was going off.  So there'd be

         15   no reconfirmation.  At the end of nine years you're termed

         16   out and you're done.

         17              Does that answer your question?

         18              CHAIRMAN SWETT:  Yes.  And I have another follow

         19   on.  So, if we were to implement, or PJM were to file to

         20   implement such a thing, would  you propose that the existing

         21   board members be grandfathered in to that timeline?

         22              MR. MILLS:  That's a great question, and my

         23   initial reaction is yes.  But I can also see reasons why

         24   that they were brought in under one set of agreements and so

         25   you would snap a chalk line on every board member from them. 





                                                                       72



          1   So, I guess I don't have a clear answer to that.

          2              MR. LACERTE:  I'd like the stakeholders to

          3   respond to Mr. Mills there, and what is your position?

          4              MS. PHILIPS:  I don't disagree.  I think nine

          5   years is too long, to be honest.  I think that, given the

          6   concerns about on-going independence, I think nine years is

          7   a long time to go without any sort of stakeholder input.

          8              But I think we would certainly be open to

          9   extending the period.  Maybe five years sounds very

         10   reasonable.

         11              The one thing I think we might disagree with is

         12   that if somebody serves for five years, that they would be

         13   allowed to be renominated.  I think, if somebody's doing a

         14   great job and they've understood the system and all of that,

         15   they should be allowed to be renominated.

         16              MS. BURBURE:  I would agree with Marjie on that

         17   point, with respect to the terms.  I also will note the

         18   thing that struck me the most about Mr. Mills' remarks was

         19   how much experience in the PJM region matters, regardless of

         20   the length of your experience in this industry, and so also

         21   examining board qualifications I think is an important

         22   consideration.

         23              COMMISSIONER SEE:  I think this is really

         24   interesting, the discussion about the length and

         25   renominations.  I'm curious, David, your response.  So, if





                                                                       73



          1   it was five years, would your view on the ability for a

          2   board member to be renominated to a next term change?

          3              MR. MILLS:  I think that should be allowed, but I

          4   think it should be -- it should be indicated early on, to

          5   that expiring board member, that that's the preference of

          6   the members.

          7              To date, the renomination process includes an

          8   interview in front -- this is for an existing board member -

          9   - an interview in front of that nominating committee, and

         10   judgment thereof at some later date.  I think an

         11   acknowledgement of positive indications that "Hey, the

         12   members and the board would like to consider you.  Are you

         13   willing?"  I think under that, then yes.

         14              COMMISSIONER CHANG:  Can I just have a quick

         15   followup on the independence?  I heard "independence." 

         16   Could you just elaborate or maybe -- maybe Stacey, Marjie,

         17   but also David -- this independence.  So, is there a lack of

         18   independence today?  Is that the view?  Or is there an

         19   enhanced independence you're looking for?  Or is it less

         20   independence?  Could you elaborate, please?

         21              MS. PHILIPS:  I mean, the decisions that have

         22   come out, that led us to where we are, were, in our view, a

         23   very -- they were politically driven.  And I'm not

         24   criticizing, we believe, at all, but they were decisions

         25   tilted towards very direct outcomes.  Less gas, so prices go





                                                                       74



          1   down, and they were all state driven.

          2              We think it's critical.  We don't think the

          3   states and governors have enough direct discussion with PJM,

          4   and we would like to see that enhanced.  But we don't want

          5   that to lead to the misconception that PJM has to do what

          6   they want them to do.

          7              So, if PJM would benefit from understanding where

          8   the states are coming from, understanding where the

          9   governors are -- and we can talk about the collaborative and

         10   where OPSI and the collaborative go.

         11              But so, yes, they need better representation and

         12   input.  Collective management, at PJM, is a great example. 

         13   They didn't tell the states they were thinking about.  That

         14   would have had such a better, robust, introduction into the

         15   stakeholder process had the state been told "Hey, this is

         16   what we're thinking.  This is your role."  Whatever.  And

         17   they really weren't given a lot of advance warning.  So, we

         18   think that process can be really enhanced.

         19              But we think it's very much short of a vote, and

         20   we think that PJM, at the end, the board has to remain

         21   independent.  Just because a particular state, or five

         22   states, want something, that may mean a lot of other states

         23   don't support it.  

         24              But they need a voice, absolutely.  And they need

         25   a better voice.





                                                                       75



          1              CHAIRMAN SWETT:  Staying on this vein of the

          2   board -- and I think we'll probably sit on this for a while

          3   -- but The Honorable Pat Wood has very deep experience at

          4   FERC and with these types of issues.

          5              And, in your testimony you call for greater

          6   transparency and public accountability, for the board,

          7   including publish performance metrics and ethics documents. 

          8   Can you talk a little bit about your proposal?

          9              CHAIRMAN WOOD:  It's really just thank you, and

         10   thank you all for -- this is my first time back since I

         11   left, so this is kind of an emotional day, to walk up the

         12   street again.

         13              COMMISSIONER ROSNER:  Welcome back.

         14              CHAIRMAN WOOD:  It's nice to be back.

         15              Just looking at things -- again, the bottom line,

         16   and I heard it from our two guest speakers today, who did a

         17   great job -- is do you have the buy-in.  Do the people feel

         18   like you're working for them?  Do they know that you're

         19   accountable, that you're not influenced by the "backdoor

         20   stuff" that goes on, you know, not just in this city but

         21   across the country?

         22              And so, the transparency aspect of that is really

         23   what permeates that part of my recommendations, Madam

         24   Chairman.

         25              And I'm looking at, kind of, other -- I'm looking





                                                                       76



          1   at ERCOT, I'm looking at MISO, looking at other of the RTOs,

          2   because we've done this for a generation.  So, let's

          3   consolidate the best practices and just get on with it.

          4              So, I think that's where those ones that you

          5   mentioned specifically, Chairman, came from, or specifically

          6   MISO and ERCOT, that had more display, more transparency,

          7   with regard to those public disclosures.

          8              And again, the goal is to create a lot of

          9   confidence that the people making decisions that affect 67

         10   million of us, of y'all, becuase I live in ERCOT --

         11              (Laughter.)

         12              CHAIRMAN WOOD:  But, the decision makers are on

         13   the up and up.  And, you know, it's not much deeper than

         14   that.

         15              CHAIRMAN SWETT:  Thank you.  Deputy Secretary

         16   Finkel, I saw you had your tent raised.

         17              DEPUTY SECRETARY FINKEL:  Yes.  Thank you.  Thank

         18   you very much.

         19              I just wanted -- my head is sort of still

         20   ringing, from the amazing set of introductory remarks from

         21   the Commission and from the guest speakers, and this great

         22   discussion that we're having here, that laid out the stakes

         23   and the reason why we're here.

         24              So, I just wanted to zoom back for one second. 

         25   We're here because the market is in crisis, the market needs





                                                                       77



          1   to be fixed, and the market can't be fixed by the failed

          2   governance that currently exists.  Those are the stakes. 

          3   That's why you have 12 governors' offices in the seats

          4   behind me.  These folks have a lot of other things they

          5   could be doing.  They're here because it matters to every

          6   governor, because it matters to 67 million people.

          7              And I just -- so that we have to get to

          8   solutions.  And I appreciate -- I feel we've almost, sort

          9   of, fallen from the skies of those consequences down to "Is

         10   it five years or is it nine years?"  And there's a realm of

         11   reasonableness in there, and reasonable minds can disagree. 

         12   But, I think we all agree on longer board terms.

         13              But I just want to respond to this, to me very

         14   strange, idea that the independence of the board is somehow

         15   polluted or sullied by the public interest being represented

         16   on the board nominating committee.  What you have today on a

         17   nominating committee -- and I appreciate, we had a great

         18   conversation, and I appreciate it very much, Marjie -- but

         19   what you have today are the private interests represented. 

         20   They have five seats on the "nomcom."  The existing board

         21   has two seats on the "nomcom."  So, every instance, the

         22   incumbent interests who have a financial stake in the

         23   outcome control who's on the board.

         24              And then those nominees go to the member

         25   committee, again, dominated by those interests.  And there's





                                                                       78



          1   nothing wrong with that.  Those interests have a financial

          2   and fiduciary duty to their stakeholders to maximize the

          3   outcomes.  And they are zealous to do that and it's to their

          4   credit.

          5              But the idea that having public representation in

          6   that process is somehow going to impair some paradigm kind

          7   of independence -- it's not independent; they are -- the

          8   outcomes and the, candidly, what we see is the blind spots

          9   in the board's outlook, are a direct and logical result of

         10   the process.

         11              So, we think it's necessary for the states to

         12   have more of a role.  Not as a -- and I take Deputy

         13   Secretary Danly's point -- the governors and the states are

         14   not here saying, as some have said, "The solution is just

         15   give us more power.  That will solve it."  We hear that a

         16   lot.

         17              That is not the solution.  Just handing the

         18   states more power is not the solution.  We agree with that. 

         19   That's why the governors are here, with some practical,

         20   actionable, steps, that will improve that.  That includes

         21   more power for the states, because the states need to be at

         22   the table, but it also includes steps to improve PJM.

         23              So, I just -- you know, very respectfully -- want

         24   to push back on that idea that there's something wrong, or

         25   incorrect, about the states being on the nominating





                                                                       79



          1   committee.

          2              MS. PHILIPS:  Thanks, Jacob.  You can see we like

          3   to talk about this.

          4              First of all, there is a consumer advocacy seat on the

          5   nominating committee, so consumers are, through the

          6   stakeholder process, do have a vote on the nominating

          7   committee.  I know.  I've served on it.  They were there.

          8              The concern is, you know, our proposal is to have

          9   the chair of OPSI on it as a non-voting.  There are

         10   confidentiality issues.  The are FOIA concerns, that if the

         11   states are on it, they can't receive anything in writing. 

         12   The whole thing is to protect the anonymity of candidates.

         13              We are not, as a stakeholder, on the nominating

         14   committee, I'm not allowed to go back to my colleagues and

         15   ask them questions, "Do you like this?  What do you want?"

         16              Right when it starts, we talk about what we're

         17   looking for, and it's very prescriptive, what the board --

         18   the seat that we're trying to fill.  And then I can ask them

         19   about the renomination of existing board members.

         20              But, once we go into discussion, I can't come

         21   back and say "Oh, hey, there's some concern that's been

         22   expressed."  That's it; it's a "cone of silence," so we're

         23   concerned about FOIA.  

         24              We're concerned, again going to the policy, you

         25   pick three states.  So, you pick a state that's in RGGI one





                                                                       80



          1   year, out of RGGI another year, a commissioner -- what, are

          2   you going to pick somebody who likes coal, somebody who

          3   likes renewable, somebody who... it doesn't -- it assumes a

          4   lack of integrity in the process that exists.

          5              And that's why we think someone from OPSI should

          6   be on the board, to get confidence in the integrity of the

          7   process.  But we don't want the process to be politicized in

          8   and of itself.

          9              DEPUTY SECRETARY FINKEL:  I just have to respond. 

         10   And I don't want to -- you know, we all know we could debate

         11   this all day, as you say, and we would enjoy doing that. 

         12   But the end use sector does include consumer advocates.  It

         13   also includes large industrial customers, who may not have a

         14   vote in that in the same vein.  So, I don't think that's

         15   fair to say that's a seat just for consumer advocates.

         16              And, you know, I guess I'm just -- I'm sort of

         17   baffled by the idea that people in public office, who have

         18   responsibility, can't have confidential information.  I

         19   mean, thank goodness we don't allow national security

         20   information to go to public officials.  Right?  Only private

         21   corporations control national security information?

         22              I mean, it just -- it's kind of ludicrous, to me. 

         23   To the extent that's a good faith concern, we're happy to

         24   have a discussion and work around any FOIA issues.  But, you

         25   know, commissioners and members in the governors' office





                                                                       81



          1   deal with confidential and sensitive matters literally all

          2   day long, every day.  So that's not a reason not to have

          3   them.

          4              And I'd just go back to what Commissioner Rosner

          5   said.  The state role has to have teeth.  Either the states

          6   are respected partners in the process, which they have to

          7   be, or they're not.  And being a non-voting observer is just

          8   not going to do that.

          9              COMMISSIONER ROSNER:  And I see Maria has her

         10   card up, and maybe there's something from New England that

         11   you wanted to offer.

         12              MS. GULLUNI:  Yes, I just wanted to say we do

         13   have a seat for the state, on our nominating committee.  But

         14   our nominating committee is composed half of sitting board

         15   members.

         16              And we also have given a very narrow role to the

         17   committee, to look for -- to fill vacancies.  The board

         18   still controls the election, and the board decides whether

         19   directors who are eligible for reelection can stand for

         20   reelection.

         21              It's a very narrow role, that we think ensures

         22   the independence of our board.

         23              COMMISSIONER LACERTE:  And Kelsy had her card up

         24   and then she put it down.  She put it back up again.  So, I

         25   want to hear her opinion.





                                                                       82



          1              CHAIR BAGOT:  I'll be brief, because I think

          2   Jacob hit on some of the points.

          3              But I guess what I'm struggling with, Marjie, is

          4   on the one hand you say our current board nominating process

          5   is not necessarily broken.  Right?  But you recognize that

          6   the folks that sit on that are voting members that are

          7   self-interested organizations to some extent.

          8              So, I don't really understand the distinction

          9   between those entities being able to successfully evaluate

         10   and select independent board members, and that that should -

         11   - we should have confidence in those board members, but the

         12   states, in holding that role, are unable to also exercise

         13   that same reasonableness and degree in selecting.  Right?

         14              And, stepping back from arguing about, you know,

         15   the makeup of the board nominating committee, just from a

         16   practical perspective, you raised concerns with the process

         17   being overly -- political results driving PJM

         18   decision-making.  And I a hundred percent agree.  So that is

         19   something that has happened and that is something that

         20   cannot happen, and that is why I think we are supportive of

         21   more board independence, to avoid perceptions, whether

         22   correct or not, that politics are sort of driving

         23   decision-making that's happening.

         24              But, the practical reality is that if states, if

         25   legislators, governors, OPSI, do not feel like their voices





                                                                       83



          1   are being adequately considered, by an independent board --

          2   right? -- and they can't trust that process, they're going

          3   to use whatever blunt instruments they have, to try to make

          4   their voice heard.  And I think that's something that nobody

          5   wants to happen.

          6              And so, we can argue about, you know, whether

          7   it's functioning or not, and the number of seats, but we

          8   have to find a way for those states to feel like they have

          9   trust in the process and in the independence of the board's

         10   decisions.  And without that, no matter what solution, or

         11   disagreements about whether it's independent now or not,

         12   you're going to see intervention that is not helpful to the

         13   long term stability of decision-making at PJM.

         14              So, just practically, I think we have to keep

         15   that in mind.  Even though it's fun to debate these little,

         16   you know, differences, like from a practical

         17   solutions-oriented -- like, we can't lose sight of what's

         18   going to happen without state confidence in these

         19   processes.

         20              MS. PHILIPS:  So, I'm not authorized to speak on

         21   behalf of LS, so this is me.  So, I think we should -- I

         22   think it's compelling that we have a voting member.  I think

         23   three is too much.

         24              So, in the spirit of compromise, I throw out one. 

         25   (Laughs.)





                                                                       84



          1              COMMISSIONER LACERTE:  I wanted to piggyback on a

          2   couple of these things.  I think, Marjorie, obviously you're

          3   very well versed in all these topics but I think you've lost

          4   a little bit of perspective here.

          5              I think FOIA concerns are not real, with the

          6   states participating.  There's plenty of deliberate process

          7   protections on FOIA, and you're speaking to a body who has

          8   to deal with FOIA issues every single day.  So, that is not

          9   a persuasive argument.

         10              I think, when we're dealing with these

         11   initiatives that you might find unpalatable, whether it be

         12   the price collar or another problem, that's not emblematic

         13   of political influence in the process.  You have a number of

         14   Democrat governors that are being driven to the White House

         15   to agree with President Donald Trump.

         16              So, if you're trying to drive, you know,

         17   unparalleled things that have never happened before, the

         18   system is the problem, and not the politics is the problem.

         19              If we had a functional board, we had a functional

         20   governing system in PJM, the Democrats would not be rushing

         21   to the White House to agree with the President.

         22              MS. PHILIPS:  But, Commissioner LaCerte, the

         23   Democratic governors are not doing what they said they'd do. 

         24   They need -- you know, I don't disagree with you.

         25              COMMISSIONER LACERTE:  I fully agree.





                                                                       85



          1              MS. PHILIPS:  So, it's easy to agree to

          2   principle, but when it gets to implementation, that's where

          3   the accountability has to come in.

          4              COMMISSIONER LACERTE:  Look, the initiatives

          5   which are problematic are the product of a system that has

          6   failed to produce alternatives.  And this is the root cause. 

          7              And I think that there needs to be more state

          8   voices at the table, and their solutions to finding the

          9   avenues in which your concerns are addressed.

         10              COMMISSIONER SEE:  Let's stay on this topic of,

         11   kind of, state involvement, and I will say I've really

         12   appreciated this conversation so far.  And Jacob, I liked

         13   the way you put it, of just kind of noting the contrast

         14   between the abstract discussions about broad ideas, and then

         15   getting down to the minutiae of five versus nine.

         16              And frankly, I was hoping that we would have both

         17   today, because I think we need both of those, in order to

         18   find some actionable solutions.

         19              So, in the spirit of that, I want to talk a

         20   little bit more about the proposals on the table for state

         21   reform and kind of take it from a view of, sort of,

         22   categorizing and prioritizing.

         23              So, Chairman Bagot, I'm going to start with you

         24   on this one, although I know others have views here too. 

         25   The way I see it, I think we've got basically three buckets





                                                                       86



          1   that have been proposed.  Right?  The first is states'

          2   involvement in board selection.  The second is, you know,

          3   the states having more of a directional voice.  You know,

          4   kind of an OPSI or a second organization, on more of an

          5   involvement in PJM strategic direction.  And then the third

          6   is filing rights.

          7              So, I guess the first question is "Is that a fair

          8   lay of the land of what we have?  Is there a fourth bucket

          9   we need to be considering here?"

         10              And then, we've talked a lot about, kind of, the

         11   merits of those, and I'm happy to keep doing that.

         12              But I think what I'm most interested in is your

         13   views on priority between those.  You know, what should we

         14   be focusing on?  How do they interact?  You know, if we have

         15   one, do we need three?  Right?

         16              If we pair other reforms, you know, how important

         17   are the others?  At what point do they become

         18   counterproductive?  

         19              So, I think I'm really interested in your

         20   reactions on that, of do we have the right proposals out on

         21   the table, and how should we be viewing them together?

         22              So, I'm going to start with you and then, I know,

         23   David, you talked a little bit about this.  I know Pat and

         24   Jacob, in particular, your comments did.  I know we've got

         25   reactions at this end of the table too.  But I'd like to





                                                                       87



          1   start at this end of the table on this question.

          2              CHAIR BAGOT:  Sure.  So, I'll say up front that I

          3   think OPSI and I are very closely aligned, though we're not

          4   entirely aligned, so I'm not necessarily speaking on behalf

          5   of OPSI; I'm speaking on behalf of myself.

          6              And I appreciated your kind of terse but

          7   introductory remarks of putting out honesty but also

          8   practicality.

          9              COMMISSIONER SEE:  Uh-huh.

         10              CHAIR BAGOT:  And so, that's really what I'm

         11   trying to come here today, what are practical,

         12   implementable, solutions that are not going to have us in

         13   litigation over these issues for the next three years.

         14              And so, as I mentioned before, I think when

         15   you're -- the most important thing, in my mind, is board

         16   independence.  Right?  And confidence that the board not

         17   only can weigh the feedback that is given to it by its

         18   stakeholders, but then make an independent decision on what

         19   is the optimal solution, going forward, but that also is

         20   empowered to make that decision, to move that initiative

         21   forward, and that can't be stagnating or, you know, in

         22   gridlock, in the stakeholder process.

         23              And so, I think that would be a huge fix, in

         24   terms of moving the ball in the right direction.  Right? 

         25   And then some other things trickle out.





                                                                       88



          1              So, states asking for 205 rights, it makes sense

          2   in the past, for --  up 'til now, that that's been a really

          3   important initiative for the states, because they don't feel

          4   like they have a voice in the process.

          5              So, we do meet with the board three times a year,

          6   and I've sat in on those meetings, and they don't feel

          7   productive.  We talk at each other.  There's no actional

          8   items or solutions that come out of it.  Oftentimes it's an

          9   argument -- right? -- with the board supporting an

         10   initiative that maybe the transmission owners or another

         11   group have put forward, or saying that they don't have the

         12   power to go make that filing effort.  Right?  So, it doesn't

         13   feel productive.

         14              So, 205 rights are a way to, one, make sure that

         15   your voice is heard, because it's a point of leverage. 

         16   Right?  If you don't -- if you don't listen to us, don't

         17   consider us in your filing, we're going to come and change

         18   it.

         19              Two, it gives the Commission options.  Rather

         20   than having to reject, it's an alternative.  Right?  To move

         21   the ball forward.

         22              But I think that my -- to the extent that we feel

         23   like the board has the ability to make its independent

         24   decisions, I don't know that those 205 rights become as

         25   necessary in that sort of, like, blunt force way.  Right?





                                                                       89



          1              And so, I think, if we have board independence,

          2   paired with an opportunity for states to be part of the

          3   discussion, develop the strategic priorities for PJM, and to

          4   feel like their voice is heard equally by the PJM board,

          5   then I think you maybe don't need those same blunt tools.

          6              And I lay out a couple different ways I believe

          7   these states could have some more meaningful communication,

          8   going forward.

          9              I do have to agree, when I put my tent card up

         10   before, is that accountability is really important.  And I

         11   personally believe that the states do need to think, you

         12   know, look in the mirror and say "How have we engaged in the

         13   past?"  Right?  "Have we engaged in a productive way?  Have

         14   we come with solutions?  Have we held up our end of the

         15   bargain?"  Right?  "Have we delayed the process or have we

         16   been efficient in providing our feedback?"

         17              We need to also be accountable on that, and too

         18   for this process to work, and so I'm certainly working with

         19   my state colleagues to make sure that we're doing our own

         20   homework there.  And that's an important piece of the

         21   puzzle.

         22              And one way that we could actually be held

         23   accountable, I think, is very clear defining boundaries on

         24   what are the states' responsibilities with resource adequacy

         25   and what are PJM's.  Right?





                                                                       90



          1              And then, if we have those boundaries, the states

          2   can be held accountable for what their role in that is.  And

          3   I think some of that is being explored in the on-going

          4   discussion about, like, future market reforms in a capacity

          5   market, and the white paper that PJM put out.

          6              And they have been engaging with the states, to

          7   figure out what is the appropriate state role there.  So, I

          8   think there are opportunities to draw that boundary very

          9   clearly.

         10              COMMISSIONER SEE:  That's really helpful and I

         11   appreciate it.  I don't want to put words in anybody's

         12   mouth, but what I think I heard you saying is we've got the

         13   right buckets that we're considering.  If we make meaningful

         14   change in bucket one and some version of bucket two, bucket

         15   three is not quite as important.

         16              But bucket two, you know, involves the states'

         17   involvement and voice.  It has to come with accountability.

         18              CHAIR BAGOT:  Yes.

         19              COMMISSIONER SEE:  Is that fair?

         20              CHAIR BAGOT:  Yes.

         21              COMMISSIONER SEE:  Okay, thank you.

         22              David, you can take this one next.

         23              MR. MILLS:  Yeah.  Thank you, Commissioner.  And

         24   since I may not get a lot of opportunities, I do need to say

         25   that both the board and the company, as well as myself, we





                                                                       91



          1   are fully committed to rise to the challenge here.  I just

          2   want to be really clear, that you are not going to hear me,

          3   or anybody from PJM, including our board, make excuses.  In

          4   fact, I'm working to take accountability for the things PJM

          5   may have done in the past that led to some of the issues we

          6   are under right now.

          7              But, we are going to do more than our part to

          8   fulfill the challenge that's before us, and that includes

          9   the capacity market reform that the speakers talked about

         10   earlier.

         11              Now, with respect to this issue, per se, I think

         12   I'm on record as saying yeah, as Kelsey said, we meet with

         13   OPSI, the board meets with OPSI three times a year.  And I

         14   would agree, that it doesn't feel like it's very productive. 

         15   It's a good information exchange but, you know, the ball

         16   doesn't really seem to move down the field in any meaningful

         17   manner.

         18              So now we have this proposal by the governors'

         19   collaborative to add a second organization, legitimize it

         20   with funding, which I have no problem with.

         21              And then, somewhere in this, there's the concept

         22   of the consolidated counsel, of the two of them.

         23              Before I respond to which of those I prefer, I

         24   also want to point out that, you know, there's another group

         25   representing the states that is emerging as a loud voice,





                                                                       92



          1   and that is the legislators.  So, somehow that will be -- if

          2   we don't do it now, it will be the next thing we have to

          3   adjust for, to make sure that, in addition, those

          4   legislators are heard.

          5              Now obviously, from an efficiency perspective,

          6   straight down the middle, one organization would be ideal,

          7   for PJM to deal with.  Right?  Because otherwise, I worry

          8   that all we will do is legitimize and create a structure for

          9   the dissonance that exists between those functions, within

         10   their respective states.

         11              So, in Dave Mills' ideal world, we have a state

         12   regional committee that speaks for the totality of their

         13   state.  So it's that PJM can have a single point of

         14   reference and a single answer.

         15              Because, any given day -- and I'm not pointing

         16   fingers, but on any given day, I can get a different

         17   perspective from a governor than I can from a senator, that

         18   I can from a state regulator, in a given state.  And that is

         19   a problem.

         20              So, as we go down this journey, obviously my

         21   preference is for one organization, or no more than two. 

         22   (Laughs.)  At the end of the day.

         23              COMMISSIONER LECERTE:  Dream big, Dave.  Dream

         24   big.

         25              (Laughter.)





                                                                       93



          1              MR. MILLS:  Yeah.  One!

          2              COMMISSIONER SEE:  Yeah.  And I appreciate that. 

          3   I appreciate your comments.  We'll definitely hold you to

          4   that spirit of moving forward.

          5              Also, I apologize.  I was not laughing at you. 

          6   You all couldn't see, we had some legislators in the back,

          7   who were waving when you made that comment.  So, I'm happy

          8   to see all of the representation and interest we have.  I

          9   appreciate that.

         10              Pat, why don't we go to you and then Jacob, your

         11   thoughts on this.

         12              CHAIRMAN WOOD:  If states are in the kitchen

         13   cooking the meal they're not going to be writing a nasty

         14   Yelp review afterward.  I mean, that's what you want --

         15              (Laughter.)

         16              CHAIRMAN WOOD:  -- that's fundamentally -- that's

         17   fundamentally what we haven't had here.  And I want to just

         18   say the reason I'm here is I'm falling on the sword for

         19   something I didn't get done 24 years ago, which was finish

         20   the finding what the state obligation should be.

         21              We did, I think, a pretty good job of that in

         22   MISO and SBP, which were the later Order, 2000 filings, after

         23   PJM's.

         24              But I called Glen Thomas and said -- he was

         25   chairman of the Pennsylvania commission at the time, to say





                                                                       94



          1   "Can you move forward on this idea we've put out with

          2   regional state committees?"  And they went forward and OPSI

          3   was formed about the time I left FERC, and it's kind of gone

          4   on and done its own things.

          5              It wasn't a squeaky wheel at the time.  I wish we

          6   had spent more time thinking about that.

          7              But my recommendations to, really, adopt a

          8   version of the New England structure rests upon the fact

          9   that OPSI is already up and operational.  It has a role

         10   here.  I think it's a role that should be augmented and

         11   should be aligned with those parts of the Federal Power Act

         12   that align toward the states, which deal with generation,

         13   deal with transmission, the planning and integration of both

         14   of those with retail rates, with resource adequacy.  Those

         15   are some big buckets.

         16              And this RTO is an odd institution that we

         17   crafted -- well actually was crafted a little before I got

         18   here -- but to bridge those gaps that the Federal Power Act

         19   thought it was so neat and wonderful to put this with states

         20   and this with the fed, and all is an integrated blanket.

         21              And so, when you start to unweave it, it really

         22   falls apart.  So, we want to keep it weaved, and I think the

         23   best way to do that is to keep the states in a very strong

         24   role here, acknowledging that, quite frankly, with 13 of

         25   'em, how in the hell often are you going to get large





                                                                       95



          1   agreement among that?  I wouldn't do it Articles of

          2   Confederation style and require 13 votes.

          3              But, you know, that's going to be y'all's issue,

          4   to figure out how to speak as one voice.

          5              But he does need to hear that voice.  If he

          6   doesn't hear the voice and he's independent, he can take the

          7   input and then make the decision.

          8              So, I agree with Kelsey that it really does

          9   depend on the nature of the overall advisory board versus

         10   stakeholder structure that exists today, how that gets

         11   resolved.  Once that gets resolved, I think these other

         12   three buckets look kind of different.

         13              COMMISSIONER SEE:  Uh-huh.

         14              CHAIRMAN WOOD:  I don't think states -- I didn't

         15   recommend that states have the jump ball or the filing

         16   rights.  

         17              I had a long discussion -- in fact, he was

         18   sitting right in your chair, Commissioner See -- Joe

         19   Kelliher and I had this tussle over regional state committee

         20   role in Southwest Power Pool, as my last order here.

         21              And I was engaged in a more robust state role. 

         22   He didn't think that complied with the Power Act.  So, we

         23   kind of hit a middle ground there and both concurred in the

         24   outcome.

         25              But, you know, there is a tension there, that we





                                                                       96



          1   have to acknowledge.  It's not just all one way for the

          2   states.  There is a huge role that they have to play, that

          3   it wasn't clear.

          4              I voted on the first capacity market.  It went

          5   from an ICAP structure to a predecessor of today's capacity

          6   market, and I was wondering "What is this?"  Coming from

          7   Texas, we didn't have one of those, so I'm not sure what it

          8   was.

          9              But it was really an aggregation of the state

         10   saying "We don't want the retail open states to be free

         11   riders on the vertically-integrated states that are

         12   maintaining that extra reserve capacity.  We want them to

         13   carry their fair share as well."

         14              So, that was fine.  I'm like that made sense to

         15   me, so we voted for it.  But the states did that

         16   collaboratively, in the original PJM, which was growing

         17   pretty fast back then, and agree to say, "FERC, you take

         18   care of that."

         19              So, it was a clear delegation that the states

         20   were in charge but they wanted, in the interest of

         21   efficiency, and really just practicality, for that to be run

         22   on a region-wide basis.

         23              And so, PJM took over that role and, as a

         24   chairman of Dynegy for six years, which was a big player in

         25   this, in this Powerpool, it was a great place to do





                                                                       97



          1   business.  It was clear, it was very predictable, so the

          2   capacity market work had kept its own obligation.  We had to

          3   make damn sure we were ready on those cold nights and cold

          4   days to work, because we were going to have to pay big

          5   penalties if we didn't.

          6              That structure was in place.  It's worked fine. 

          7   I think people knew whose role it was to do what.

          8              But when you kind of come up to a point, and

          9   we're now dropping the price now -- of course you're not

         10   going to clear!  If the price is below what you could get in

         11   a competitive market, who wants that?

         12              So, I mean, a lot of these issues, I don't feel

         13   like the resource adequacy thing was not clearly given from

         14   the states to PJM.  The issue is "Why haven't we..." you

         15   know, we haven't dealt with some of the fundamental issues I

         16   mentioned in the last paragraph of my one-pager about -- on

         17   the state side -- about the resource adequacy implications

         18   to the state.

         19              But, so filing rights, I think it's important to

         20   have the state consultation there.  I went up to the line

         21   and said "File the OPSI agreement, if there is one, and it's

         22   not the same as what PJM board wants to do.  File that at

         23   FERC."

         24              I didn't say if that was a jump ball filing or

         25   not.  But I think FERC needs to know where the states land,





                                                                       98



          1   and the states need to know it's incumbent on them to come

          2   together and get an answer for that.  Because that's really

          3   going to be the challenge, I think, for my friends at the

          4   state level, is to get consensus across the broad thing, but

          5   not to allow that lack of consensus, if it's not achieved,

          6   to stop what the board and the PJM need to get done.

          7              COMMISSIONER SEE:  Thank you for that.  I really

          8   appreciate the detail you added to that conversation.

          9              There were a lot of really good points in there. 

         10   You know, one of them that's not lost is, I think, how

         11   important it is for us to think through these reforms on

         12   their own, how they stand or fall, but the idea that so much

         13   of this is tied to what other decisions are, as well.

         14              So, thank you for highlighting that.

         15              I think let's go to Jacob, and I know Kelsey had

         16   yours up too, so let me complicated the question a little

         17   bit, especially because I know this is an area that you have

         18   thought about a lot and have a lot of thoughts about.

         19              But, when we're talking about the state voice --

         20   right? -- and so much has come up about "What does the state

         21   voice mean?"  And that's always a difficult question.  I

         22   spent seven years in state government in a PJM state.  You

         23   know, I understand that not all PJM states think alike. 

         24   That can be an understatement, right?

         25              But state government doesn't think alike as well. 





                                                                       99



          1   You know, working in the AG's office, you know, the

          2   legislators and the governors, you know, and other agencies,

          3   are sometimes not always on board.

          4              So, there's a lot to be said about how do we make

          5   sure that there is right input coming in and effective

          6   inputs, and some of this comes down to I know you have a lot

          7   of thoughts about one versus two bodies.  So, let's just

          8   complicated the question and put a little bit of that on the

          9   table too.

         10              DEPUTY SECRETARY FINKEL:  No, I really appreciate

         11   it.  And I'll just say I really agree with Judge Bagot and

         12   with what Chairman Wood said.  I think there's a whole bunch

         13   of things I'd love to engage on there, but I think in terms

         14   of the one versus two, we have spent a lot of time thinking

         15   about this.

         16              I don't think there is one perfect answer.  I

         17   think that reasonable minds can differ and there's no

         18   perfect solution, as you see across the country, we have

         19   different, multi, RTOs, a lot of ways this can work, and it

         20   does work.

         21              I think, as much as I would love to live in Dave

         22   Mills' ideal world, I understand the reasons why, one, it's

         23   efficient.  I do think it's a little bit of a red herring,

         24   or a double standard, though.  I mean, the TOs, or the

         25   generators, or any other group, do not speak with one voice. 





                                                                      100



          1   There's a diversity of voices, and you don't say "Oh well,

          2   the TOs don't get a vote because they can't agree."

          3              The states are a diverse bunch.  We're diverse

          4   politically, we're importers, we're exporters, we're

          5   diversely integrated, we're restructured.  Right.  We are

          6   diverse.  And there are 67 million people.  So there's going

          7   to be a diversity of viewpoints.

          8              I think it's sort of too simple to say "Well, you

          9   have to be on the same page or you don't get to count." 

         10   That diversity is a challenge and it's also a strength.  And

         11   that's PJM's unique role in this, and I think we need to

         12   lean into that.

         13              And what we've proposed, what we've put forward,

         14   is a two-part proposal, because I think there's a different

         15   role for the policymakers than there is for the regulators,

         16   and we think that -- so, I guess I would just sort of

         17   clarify the three buckets you laid out, Commissioner.  I see

         18   that as two buckets.  I see it as kind of strategic, long

         19   term, direction.  I put the board in that.  And then I see

         20   it as kind of the filing advice and the day to day, and I

         21   see the policymakers really absent from this conversation. 

         22   Or, as Judge Bagot said, like, they're not going to be

         23   absent, because they're going to be, you know, involving

         24   themselves late in the process and in the public arena and

         25   using the bully pulpit that they possess.





                                                                      101



          1              We would much rather institutionalize that, give

          2   them a proper place and a proper role, and be involved early

          3   on in setting the direction and in choosing who sits on the

          4   board, and then not being there, you know, last minute,

          5   because of a crisis.

          6              And, at the same time, we think the regulators

          7   who are dealing with this every day, and who have a really

          8   important responsibility on the retail side, when this comes

          9   from the wholesale side to the retail side, you know,

         10   there's a throughput there, and the regulators have to be at

         11   the table.

         12              So, I think, you know, we think it's really

         13   important, these three seats on the nominating committee to

         14   have a real role in that process and some real teeth.

         15              And I'll just say that three is not a random

         16   number.  Three is an important number because, as you think

         17   about the three, those three state voices, imagine that they

         18   were a unified bloc, which may not always be the case, but

         19   imagine they were, and then the two incumbent board members

         20   who vote on that committee, that's half that committee.

         21              And then you have the private interests, the

         22   other half of that committee, and that rough parity, we

         23   think, is really important, if you're going to have

         24   confidence in the public interest being expressed

         25   meaningfully in that process.





                                                                      102



          1              And then, just on the filing rights, we do think

          2   it's important -- and I really agree with the way Judge

          3   Bagot framed it, and I would go back to what Chairman Swett

          4   said about "What does success look like?"  I think we should

          5   be focused on we're not here to say "Oh, we have to have

          6   blank," or we don't have a red line.  What we want to do is

          7   focus on what is a successful outcome, and it's what Judge

          8   Bagot said.  It's the states being listened to and being

          9   respected and being part of these problems that we have an

         10   important shared role in implementing.

         11              It doesn't do anyone any good for PJM to have a

         12   solution, no matter how great they may think it is, and go

         13   all the way down the road and submit it to this commission

         14   and have it be implemented, and then the states hate it and

         15   don't work out of their -- or it doesn't go well.  That's

         16   not in anyone's interest.  You've got to have the states

         17   there early, and we think what we've seen in the other

         18   regions, this is not something that is novel.  All the other

         19   regions, the states have some form of filing right over some

         20   aspect of this process.

         21                             We think having those filing

         22   rights is sort of the language in which this entire entity

         23   speaks, and you need to have that in order to be a

         24   meaningful participant.  If there are other variants, huge

         25   respect for Chairman Wood, he has a different idea on that,





                                                                      103



          1   this consultation idea, I think we're open to that, as long

          2   as it gets to that same result.

          3              Because what we don't want is to say, you know,

          4   sort of, we'll listen -- you know, you can have a

          5   conversation, you can be heard, but not actually

          6   meaningfully be listened to.  That doesn't move the ball. 

          7   That doesn't solve what we need to solve.

          8              So, I think we're open to variants of doing that,

          9   but we have to focus on what is the outcome and what does it

         10   get to.

         11              COMMISSIONER SEE:  Thank you.  Before I move on

         12   to this conversation, I definitely want to make sure to pass

         13   it on to my colleagues for other directions.  I do see a

         14   couple cards up.  But Marjorie, if you can keep it brief,

         15   and David if you can as well if you want to and then, yeah,

         16   and Chair Bagot if  you wanted to have the final word on

         17   this one.

         18              MS. PHILIPS:  I'll try.  Using Pat's analogy, too

         19   many cooks in the kitchen, we know what happens.  So, we

         20   need a chef, and the sous chefs can tell the chef what they

         21   see, what they're looking at, but the chef is chef.

         22              I think I would like to go back to our proposal,

         23   which was to expand OPSI, to have a governors appointing...

         24   the reason is we are trying to minimize the amount of

         25   change.  Chairman Swett, you put it so great.  We're looking





                                                                      104



          1   to fix the cracks.  We're not looking to pull out the

          2   bricks.

          3              And we're trying to look -- we want to focus on

          4   getting market rules in place.  We don't want the governance

          5   discussion to be a sideshow that we're all focused on.  And

          6   so, we think that's the beauty of using OPSI.  You can do it

          7   quick, you amend OPSI, the governors appoint.

          8              Most critical, that we haven't talked about, is

          9   the states need the resources to participate meaningfully,

         10   and that's something that NESCO does really well, which is

         11   we support greater funding for OPSI so that they get the

         12   expertise, they understand the issues, and it's a very

         13   selfish ask, because we find, in New England, we can go and

         14   negotiate and talk to NESCO.  We may not agree, but they're

         15   sophisticated, they understand our concerns, and that's some

         16   of the happiness you see, which is we can compromise

         17   because they see "Oh, the generators aren't being greedy;

         18   this is a real issue."

         19              So I would emphasize no matter what you take away

         20   from this, OPSI needs experts and they need more funding,

         21   and we really support that, so that we can have a better

         22   participation.

         23              CHAIRMAN SWETT:  And, if OPSI is better funded,

         24   then what is your ideal role for them, in the stakeholder

         25   process?





                                                                      105



          1              MS. PHILIPS:  So, they can present issues now. 

          2   They can do user groups, they can write letters to the

          3   board, and they can intervene at FERC.  There's not a lot of

          4   that they can't do.

          5              The problem is they often don't speak in one

          6   voice and they often speak in generalities.  So, if OPSI

          7   wants to make a presentation, that's why it needs the

          8   experts.  Come with a proposal, not just "We don't like

          9   this.  It's going to raise costs, it's going to lower

         10   costs."

         11              So, the idea is that they meet with the board

         12   and, as we have heard between David and Kelsey, that needs

         13   to be more meaningfully enhanced.  We think a board member

         14   should be assigned to the states, to deal with the

         15   governors, so that even though we don't want the board to be

         16   responding singly to a government, they need to understand

         17   "This is Pennsylvania's concerns.  This is Virginia's

         18   concerns."

         19              And so, they need to understand individual state

         20   concerns.  A board member has responsibility for

         21   relationship with the state, at the governors level.

         22              And then OPSI becomes a more meaningful voice in

         23   the stakeholder process.  And, if they were, we could talk

         24   to them and get them more involved in the proposals.

         25              I know my company has, in the past -- we often





                                                                      106



          1   volunteer to, like, let us talk to OPSI, let us explain

          2   what's going on.  And frankly, the participation is pretty

          3   low.

          4              And so, we would like to see OPSI more involved,

          5   but more meaningfully understanding the issues.  So, it

          6   would be -- they would have rights to the board.

          7              There's a reason they don't have voting rights. 

          8   When PJM was formed, the states didn't want voting rights. 

          9   The commissions wanted not to be treated to the ex parte

         10   rules of the stakeholders.  They wanted to be able to

         11   consult with the board separately.

         12              And we think that's a great structure to keep.  I

         13   hope that's responsive.

         14              CHAIRMAN SWETT:  Uh-huh.  So, you raised the

         15   point in your testimony and so did PJM, at the formation

         16   that states did not want a voice.  So, to our state

         17   representatives, it seems like those circumstances have

         18   changed, and perhaps your ex parte concerns are no longer

         19   the same?

         20              CHAIR BAGOT:  Well, I don't know that it's

         21   inconsistent.  I don't hear either of us advocating for us

         22   to have a vote on the members committee.  And that's

         23   something that we opted not to be.  We're not members.  So

         24   we don't have a vote right now, and that's how things sort

         25   of move through the stakeholder process.





                                                                      107



          1              I think the tradeoff there was that OPSI would

          2   then have direct access to the board, and we have these

          3   board meetings.

          4              But, if that is not meaningful, if we don't have

          5   a vote, and we also don't feel like we have meaningful

          6   engagement with the board, or we have no ability to sort of

          7   help develop what the strategic direction of PJM needs to be

          8   going forward and what broader initiatives they need to

          9   focus on -- right? -- and that's what, I think, is

         10   appropriate for us to say, is to help shape the direction of

         11   "These are the reforms that we really need to see," I don't

         12   know that we necessarily need to be telling the board

         13   exactly what those little nitpicky things are.  I think we

         14   can participate in the existing stakeholder process and

         15   provide that feedback that way.

         16              So, I don't think we're asking for a vote.  I

         17   think what we're asking for is to make sure that the

         18   existing process is working the way that it should be

         19   working.

         20              And I think some of the discussion -- I mean,

         21   Marjie has had a lot of experience with the PJM process, and

         22   I hear her frustration with working with the OPSI states and

         23   whether we're coming with the type of feedback that she

         24   wants us to come to.

         25              And that goes to my point with accountability. 





                                                                      108



          1   The states do need to figure out how to engage in a more

          2   meaningful way.

          3              But this sort of discussion I think is

          4   illustrative of why the states feel like they don't have a

          5   voice.  Right?  It's because that's often the response that

          6   we get from stakeholders, is "Well, you guys don't know what

          7   you're talking about," or, you know, instead of the

          8   assistance that maybe we need or helping direct us to, sort

          9   of, the right sort of decision points we should be thinking

         10   about.

         11              And so, I think this sort of illustrates the

         12   challenge that we have in participating in this process.

         13              I do just want to say one thing that Pat Wood

         14   brought up, which is that, you know, we need to think about

         15   these roles in very distinct ways, and I think when we're

         16   talking about the roles of the states, whether it's 205, or

         17   consultation, or -- it would be helpful, and it would be

         18   helpful, and it would help the states have accountability,

         19   if we had well-defined roles, in terms of what areas the

         20   states need to be part of the discussion.  Right?

         21              Like, what elements of resource adequacy should

         22   we be working with the PJM board to say, you know, in the

         23   next one year, two years, three years, these are the things

         24   that we should be focused on, and that should be working

         25   through the stakeholder process.  Right?





                                                                      109



          1              Because I don't know that it makes sense for the

          2   states just to have equal input of blanket across the board

          3   on all of the issues, and it makes it hard, I think, for us

          4   to be accountable and provide that meaningful feedback, when

          5   we don't have that sort of very specific and precise

          6   directive of where we sit.

          7              So, I think, with states, greater state

          8   involvement, comes also greater clarity on what role they

          9   play and where they should really be speaking up, and where

         10   maybe it's not appropriate.

         11              CHAIRMAN SWETT:  Have the states coalesced around

         12   the finer point on which issues you should be involved in?

         13              CHAIR BAGOT:  Well, this -- I'm going to let

         14   Jacob go -- this maybe is not the exact answer that you're

         15   looking for.  But on the one group versus two groups, I

         16   think I agree with Jacob that we don't necessarily need one

         17   group; we need different bodies, that have different

         18   purposes, and that they're very clearly defined.

         19              And so, it makes sense for the governors to play

         20   a role on the nominating committee.  It probably makes

         21   sense, to the extent that they're sort of a steering

         22   committee or strategic committee, that sits down with PJM

         23   board and helps develop what the initiatives are going to be

         24   over the next one, two, three years.

         25              It makes sense that there probably is both a role





                                                                      110



          1   for OPSI and as, like, sort of the technocratic experts, but

          2   also for the policymakers at the states.  Right?  It

          3   probably makes sense that both of those voices are there.

          4              But then, when we get into, like, the

          5   consultation requirements for 205 rights, and you get into

          6   providing feedback in the stakeholder process, well maybe

          7   greater engagement or resources provided by PJM to OPSI, to

          8   be able to provide that more meaningful technical feedback,

          9   along the lines of what Marjie suggested, that I think is an

         10   OPSI role, because we live the day to day of, like, what

         11   these market rules mean, and how they affect our utilities

         12   and how that impacts retail rate makers.

         13              And so I think, if you have those very defined

         14   roles, then you're not going to run into the issues that

         15   David addressed, where you're hearing multiple states,

         16   conflicting state voices, weigh in on the same issues.

         17              COMMISSIONER LACERTE:  I wanted to get back to an

         18   analogy that Marjorie made a minute ago, when you said "The

         19   chef is the chef."  And I presume the chef, in this

         20   situation, is the PJM board, as let by the CEO.  Okay.

         21              So, would you agree that the sous chefs should

         22   not have two-thirds voting rights to tell the chef what to

         23   do?

         24              (Laughter.)

         25              MS. PHILIPS:  I don't think that the sous chefs





                                                                      111



          1   get the right to tell PJM what to do.  There are 205 rights,

          2   but the time you've gotten to that, pretty much the chef has

          3   bought into the sous chef.  I can't think of -- the chef...

          4              COMMISSIONER LACERTE:  It's not that complicated

          5   of a question.

          6              (Laughter.)

          7              MS. PHILIPS:  My ex-husband was a chef, so --

          8   this is touchy.  (Laughs.)

          9              (Laughter.)

         10              CHAIRMAN SWETT:  You're triggering her.

         11              COMMISSIONER ROSNER:  Ask it without "chefs."

         12              (Laughter.)

         13              CHAIRMAN SWETT:  She brought "chef" up.  Maybe

         14   she wants to talk about it.

         15              MS. PHILIPS:  I did.  I'm guilty.

         16              COMMISSIONER LACERTE:  So when we say a chef has

         17   to be a chef, we have to have somebody in charge.

         18              MS. PHILIPS:  I actually, I go back to my view,

         19   that it seems like the states -- I know it's hard for you to

         20   get -- and I believe the states need to be invested because

         21   they don't feel they are, but I can tell you from a

         22   stakeholder perspective it looks like the states have had

         23   far more influence on the board than the stakeholders.

         24              And so that's why it's hard for me to answer the

         25   question "Are the stakeholders the sous chef."





                                                                      112



          1              COMMISSIONER LACERTE:  I don't know if anyone

          2   agrees with that statement.  I think, by and large, the

          3   prevailing opinion of everyone in this room is contrary to

          4   that statement.

          5              And I think that the boards themselves have told

          6   me point blank that their position is that they are not

          7   afraid of the governors or the states.  They are afraid of

          8   the stakeholders.

          9              So, I think that it's important that we listen. 

         10   When we say this is not a secret society, that's exactly

         11   what a secret society would say.

         12              (Laughter.)

         13              COMMISSIONER LACERTE:  So, we have to listen to

         14   these concerns; we can't wish them away.

         15              MS. PHILIPS:  So, to be clear, I am not -- I want

         16   to be clear that we absolutely support a larger role, and if

         17   they want to create a two-step organization with the

         18   governors and the states, have at it, because I agree, I

         19   don't want PJM being attacked from the outside.  I want

         20   everybody inside the tent and working collaboratively.

         21              What I'm concerned with, if I could just give one

         22   example, Jacob brought a proposal to the PJM stakeholder

         23   process.  It was to go to seasonal markets.  Everybody

         24   agrees PJM has to go there.  But we didn't agree on the

         25   timing, because we were stuck with the ELCC, which was a





                                                                      113



          1   mess, in implementing, and nobody understood it.

          2              So, what I'm concerned about is the governors

          3   come to PJM and, by the way, PJM wanted to input seasonal

          4   markets, and they finally realized it was too complicated.

          5              What I'm worried about is that the governors come

          6   to PJM and say "This you must do," and as stakeholders we're

          7   the ones working in the rules.  I'm the one investing.  I'm

          8   having trouble telling my lenders what the ELCC is.  I don't

          9   want to go back and tell them not only do I not know what

         10   the ELCC is, but we're going to go to seasonal markets, and

         11   nobody knows what that means.

         12              So, I am speaking from my paranoia as a

         13   stakeholder, looking to find that balance.  So, it is really

         14   important that governors be there, to tell PJM what they

         15   think.  It's really important that the states do that.

         16              But I'm looking for the balance that the board,

         17   at the end of the day, remains independent.

         18              And the stakeholders, we're advisory.  Right?  I

         19   mean, we have 205 votes, but it's on the energy market.

         20              COMMISSIONER LACERTE:  But you're not advisory. 

         21   You are not advisory!

         22              MS. PHILIPS:  But we're here because of the

         23   capacity market.  That's why we're here.  Because we're not

         24   getting enough built.  And that is an RAA issue, and that is

         25   205 to PJM.





                                                                      114



          1              COMMISSIONER LACERTE:  Do you support the

          2   stakeholders being advisory or not?  Or as an investor.

          3              MS. PHILIPS:  If I thought PJM could truly be

          4   independent, and that the FERC would back them up, as what

          5   is economically sound, what are just and reasonable rates...

          6              COMMISSIONER LACERTE:  We've got to take a leap

          7   of faith here.

          8              MS. PHILIPS:  Speaking for Marjie Philips, right 

          9   Not my company.  We could maybe get there.  It's a concern

         10   that the board is not independent.  

         11              Again, we're as paranoid as the states.  Right? 

         12   (Laughs.)

         13              COMMISSIONER LACERTE:  Stacey, the same question. 

         14   Absent the chef sidetrack.

         15              MS. BURBURE:  AEP supports advisory voting.

         16              COMMISSIONER LACERTE:  Thank you.  I'm glad we

         17   could put a bow on that one.

         18              COMMISSIONER CHANG:  Is Jacob going to speak

         19   next?

         20              DEPUTY SECRETARY FINKEL:  Can I just make a

         21   comment?  Because you mentioned the seasonal issue charge. 

         22   And that was such an educational experience for me, because

         23   -- this was a year or so ago -- and the Pennsylvania

         24   governor's office went to PJM, checked every box, went

         25   through the whole process, we did an issue charge or problem





                                                                      115



          1   statement.  We went through this entire thing.

          2              And it was just so clear to me that the -- again,

          3   I think the members have such an important role and they

          4   should retain an important role.  They know their businesses

          5   better than anyone.  They know the market they work in

          6   better than anyone.

          7              But they don't have the strategic vision for the

          8   larger, bigger, picture.  PJM is unable to take big, bold,

          9   action, which is what is needed in this moment.  And I think

         10   that's why the board does need to be empowered, and the

         11   states need to be part of that conversation.

         12              And I am just struck -- after the last CIFP, the

         13   first CIFP, last fall, 12 different packages to solve,

         14   large load integration, really every possible choose your,

         15   you know, favorite menu option, the solution, everything was on

         16   there.  All 12 were voted down by the members.  They hated

         17   all the options.  Right?

         18              And, the day after that, I went back to Valley

         19   Forge for -- they had, like, a post mortem on what had

         20   happened, and I could not believe my ears, that the members

         21   went around patting themselves on the back for what a

         22   thoughtful, deliberative, you know, creative, process they

         23   had just gone through.

         24              And I was, honestly, the only person in the room

         25   saying "This is a failure.  You have not advanced the ball. 





                                                                      116



          1   You have not actually given the board clear direction or

          2   told them which way you want them to go.  This is just a

          3   muddle and a failure."

          4              So, I just -- I take the criticism of the states,

          5   and I think the states have not been perfect, and we can be

          6   better, and I appreciate increased funding and increased

          7   support, and we're open to that.  But, I just think, again,

          8   taking it back one level, this is broken.  This is not

          9   working.  And there needs to be a change.

         10              COMMISSIONER CHANG:  Maybe that's a great segue

         11   for some of my questions.  I want to summarize.  Sorry,

         12   David, we'll give you a chance in a second here.

         13              I want to summarize a little bit about the

         14   states' involvement, because I hear a few things, and first

         15   I think states want to be on the nominating committee, or

         16   some representation on the nominating committee.  And states

         17   might also want some version of I'll call it "jump ball,"

         18   which basically says if PJM and its stakeholders presenting

         19   a proposal of some kind -- let's stick with capacity market

         20   just because we need -- there's different 205 rights with

         21   different parts of the market.  Let's say capacity market,

         22   or resolution of some changes in the capacity market.

         23              If PJM and its stakeholders present some kind of

         24   proposal that the states really don't like, or can't -- that

         25   states might want some ability to present another counter





                                                                      117



          1   proposal or alternative proposal -- that's what I'm hearing. 

          2   Whether you exercise that right or not is a different

          3   question.  But just having that right gives you more

          4   leverage in saying "Look, you know, maybe I don't have a

          5   voting right in the members committee, but I have this other

          6   potential jump ball."  Right?

          7              Which is not, by the way, how New England works,

          8   but we can save that for some other clarification.

          9              Is that -- okay -- so, another topic on the

         10   states' participation, I personally feel like -- I hear what

         11   David had mentioned, which is I think it would make more

         12   sense, to me, sort of, like, thinking how Dave might think,

         13   is having one organization or some collective organization,

         14   collected voices from the states, would be much easier for

         15   PJM to deal with and understand, which then pushes the

         16   obligation and the burden of getting to some kind of

         17   agreement to the states. 

         18              I think this was, you know, when we talked, a few

         19   days ago, this is where, you know, be careful what you wish

         20   for because coming to an agreement with 13 states and D.C.

         21   is not easy, but perhaps you're ready to take that on.  And

         22   I take, you know, Chair Bagot, your point earlier, which is

         23   if you don't get it in the front end, you're going to have

         24   to get it at the back end.  You're going to try to oppose it

         25   some other way, you're going to inject -- or the states,





                                                                      118



          1   some states might interject the other way, or "We don't like

          2   the prices because we never believed in the market design,

          3   so now we're going to do something else."

          4              So I do believe that states must have some way of

          5   interacting and actually decision-making rights, whether

          6   that's a 205 jump ball type of rights, or some other way,

          7   and I think that has to be consolidated some way so that PJM

          8   is -- because that's what PJM does today.  Like, you know,

          9   "What does Virginia want?  What does Pennsylvania want? 

         10   Well, what does Ohio want?"

         11              Like, I don't think it helps PJM when the states

         12   don't have maybe not one voice, but at least some

         13   consolidated voice.  So those are what I've already heard,

         14   and I feel like that's coming -- to solidify in my head.

         15              I do want to bring up another topic.  You can

         16   answer them all together if you'd like.  Which is some

         17   parties have discussed giving PJM more filing rights, and

         18   this is no longer the states' jump ball rights; this is

         19   PJM's filing rights.  And can someone just explain more

         20   about the tradeoffs of that?  So, are we taking some rights

         21   from the stakeholders, the TOs, and giving it to PJM?  And

         22   what would look like, David, if that were the case?  Would

         23   that come from -- how would you make those decisions?  Is

         24   that the board making those decision?  And then what are the

         25   tradeoffs?





                                                                      119



          1              And I don't mind who wants to go first, but

          2   probably, David, if you can go first.

          3              MR. MILLS:  Yeah.  Our perspective is not --

          4   we're not talking about giving the board 205 rights on the

          5   transmission cost allocation, CPOA.  What we are talking

          6   about is the operating agreement, which would be the energy

          7   and ancillary services model.

          8              And I think that, you know, we would run a

          9   fulsome stakeholder process.  And here I'm probably filling

         10   in details that would be yet to be filled in, but I think

         11   for illustrative purposes I need to do that.

         12              And let's say we put a time limit on a

         13   stakeholder process.  I don't know, six months, a year,

         14   we'll all figure out a number.  But if the members are not

         15   able to get to a conclusion at that point in time, the board

         16   would be empowered to make a 205 filing.  That's how we had

         17   thought about it.

         18              COMMISSIONER CHANG:  But this is limited to all

         19   the energy and ancillary services (off microphone).

         20              MR. MILLS:  Well, in an ideal world, that would

         21   be the first stop, but in an ideal world it would also

         22   include the transmission planning aspect, in the RTEP.  That

         23   would be the third dimension.

         24              But the one thing I want to be careful of is

         25   sometimes we're -- and the panelists in their pre-filed





                                                                      120



          1   testimony we were sort of doing this, and I want to make

          2   sure we don't do it here live, is that we're talking about

          3   jump ball rights for the states when, in fact, who are they

          4   sharing those with?  Because it seems -- it would be

          5   inconsistent from this independent discussion that we're

          6   having for the states to have a jump ball right on rights

          7   that the PJM board doesn't even have.

          8              COMMISSIONER CHANG:  Are there other tradeoffs

          9   you want to elaborate on?  Maybe not.  Okay.

         10              (Laughter.)

         11              DEPUTY SECRETARY FINKEL:  I'll just, to

         12   anticipate advisory voting and moving the 205 rights that

         13   are in the OA to the tariff, and giving the board control

         14   over those, I think we're open to that idea, because we

         15   understand things have to happen more quickly.  I would

         16   encourage six months, not a year.  The shorter the better.

         17              But I think we're open to that, as long as it is

         18   balanced with a counterweight that serves the public

         19   interest, because I think our fear is yes, we need to

         20   empower the board, yes, we need to get to yes faster and

         21   more predictably, but a board that is untethered from checks

         22   and balances can go in any direction, and you need to have

         23   some check in that process, which is why we think, if you

         24   give the states a meaningful role in the nominating

         25   committee and you give them these jump ball filing rights,





                                                                      121



          1   those are important checks on an otherwise unrestrained

          2   board.  That allows us to feel comfortable with that

          3   process.

          4              And I just wanted to clarify, in terms of the

          5   filing rights, our vision of it is actually quite narrow

          6   jump ball filing rights on resource adequacy.  So not

          7   dealing with other issues.

          8              And, to David's point, not dealing with things

          9   the board doesn't have today.  And we would envision that to

         10   be an informal arrangement between the states and PJM.  We

         11   would not envision that being something that would come to

         12   this commission for approval, or to even have the necessary

         13   force of law, but more of a convention or a practice that

         14   would be solemnized in some sort of MOU or something, that

         15   when a super majority of regulators disagree really

         16   strongly with something, PJM is going to file in resource

         17   adequacy and that pure nexus, where the states have an

         18   important interest, PJM agrees voluntarily it would file a

         19   state alternative alongside it, and this commission would

         20   decide.

         21              So, we think that's a really -- again, we are

         22   trying to be extremely reasonable and practical and get

         23   solutions that can come quickly.

         24              And to your point, Commissioner Chang, I mean, I

         25   totally hear the reasons why one is better than two, and one





                                                                      122



          1   would be more manageable than two.  I think, just in the

          2   spirit of solving, improving, governance, not perfecting

          3   governance but improving governance and getting on to

          4   solving the market problems we face, we think it's just a

          5   lot more advisable to have, you know, a distinct governors'

          6   group, to Judge Bagot's point, that has a distinct role and

          7   set of responsibilities from what the regulators do.  And we

          8   think those two things, as they are in New England, can

          9   coexist in a productive way.

         10              COMMISSIONER LACERTE:  I have a followup question

         11   for Stacey, as it relates to that.  In AEP's comments, they

         12   stated that they support providing states with defined

         13   authority under Section 205 to cause filings to be made

         14   before the Commission, on matters within their collective

         15   jurisdiction.

         16              Can you elaborate on that?  Is that a jump ball

         17   right?  Is that something that looks more like RSC has in

         18   SPP?  Can you go a little further?

         19              MS. BURBURE:  Thank you, Commissioner, for the

         20   question, and the wording there was deliberate, because our

         21   focus is on action rather than being hung up on how exactly

         22   those rights are defined, the precise implications or

         23   boundaries of that.

         24              The real question that we are asking is "Is this

         25   a process that is going to drive us to big, bold, ideas, to





                                                                      123



          1   better solutions for PJM?"  That's what we need, at the end

          2   of the day.

          3              COMMISSIONER LACERTE:  I thought your comments

          4   were very all written, so compliments to whoever, behind the

          5   scenes, helped compile those things.

          6              MS. BURBURE:  Thank you.

          7              COMMISSION CHANGE:  Marjie, do you want to talk

          8   about 205?

          9              MS. PHILIPS:  Can I be the defender of

         10   stakeholder rights?

         11              COMMISSIONER LACERTE:  You could try.

         12              MS. PHILIPS:  It's kind of interesting that the

         13   four sectors, in their filings, all said that PJM is

         14   working.

         15              What's not working is that we don't have

         16   deadlines and discipline, and that is a different issue than

         17   205 rights.

         18              And I give you an example.  When PJM really

         19   thinks there's something wrong, they file a 206.  

         20              In EL-2226, there as a transmission congestion

         21   penalty constraint issue.  That was a market issue.  PJM

         22   filed.  Within 18 days, the Commission responded.

         23              So, let's not pretend -- let's not ignore that

         24   the rights that PJM has to act expediently.

         25              The stakeholder process needs discipline, I





                                                                      124



          1   agree.  It was not a success that we had 14 proposals.

          2              But I can tell you, as a stakeholder that's

          3   worked through the process, like the Reserves Project, LS

          4   brought a proposal, three years ago, and the PJM staff

          5   didn't buy into it.  And so, if we don't get PJM's staff to

          6   buy into it and then we go to the stakeholder proposal

          7   process, it's kind of dead on arrival.

          8              So, there is some logic to it.  Just like we all

          9   felt that PJM personnel were going to get bonused if they

         10   went to seasonal markets, and nobody in the stakeholder

         11   process felt we were ready.  And that's the reason we like

         12   that 205 check, and there's nothing wrong with it, if we

         13   disciplined the process, if we had deadlines, that you can

         14   only, you know, talk about something.

         15              If you had -- you know, one of the stalling

         16   things in PJM is "I need more education."  That can push

         17   discussions out for years.

         18              And so, we need more discipline around how

         19   stakeholders exercise the 205 rights.  And it's only the

         20   energy markets.  Right?

         21              But I think that that balance does create

         22   discipline, that PJM staff can't just do what they think is

         23   right, without talk about the people who are investing, and

         24   interpreting, and dealing with these rules.  And yet, also,

         25   if PJM staff doesn't support the stakeholders, it's not





                                                                      125



          1   going to go anywhere in the stakeholder process.

          2              So it works.  It's just the actual mechanics of

          3   the stakeholder process are lost.  There used to be decision

          4   makers that came to these meetings, and you could vote. 

          5   That doesn't happen anymore.  You get wonks like me, that

          6   are coming and trying to defend my company's decision --

          7              COMMISSIONER ROSNER:  So, Marjie, the deadlines

          8   and discipline look like, you know, we have some deadlines

          9   on the stakeholder process, and then, if it's still -- those

         10   are unable to resolve the issue, is there openness to the

         11   board having access to the tools that they currently do not?

         12              MS. PHILIPS:  Speaking for Marjie Philips, not

         13   LS, I think that is not an unfair outcome.

         14              COMMISSIONER ROSNER:  Okay.

         15              MS. PHILIPS:  For energy now.

         16              COMMISSIONER ROSNER:  For the areas of the

         17   operating agreement that they don't clearly have a tariff.

         18              MS. PHILIPS:  Right.  It's energy and ancillary

         19   services.  I mean, they even control collateral.  Right? 

         20   They have the 205 rights over collateral.

         21              COMMISSIONER ROSNER:  Yep.

         22              MS. PHILIPS:  So, yes.  I don't think that's

         23   unfair.

         24              COMMISSIONER ROSNER:  Okay.

         25              MS. PHILIPS:  I think David has one.





                                                                      126



          1              COMMISSIONER ROSNER:  I wanted to ask -- oh, Mr.

          2   Mills, please.

          3              MR. MILLS:  It's come up twice, and so I just

          4   need to address it.  I'm sort of a -- you know, this is week

          5   11 and I'm sort of a quick wins sort of person.  And one of

          6   the things that was clearly identified as a result of the

          7   prefiling is I believe that the board needs to take

          8   ownership for prioritizing the work streams that come into

          9   the stakeholder process.

         10              So, the development of that, whether it's an

         11   annual work plan or whether it's a longer term view, I think

         12   we have to put some guardrails around the amount of material

         13   and issue charges that are coming through the process,

         14   because it is absolutely unwieldly.

         15              I know I want to respect the members' ability to

         16   bring discussion and bring topics in, but I think an

         17   appropriately empowered board should be able, from a

         18   strategic perspective, to at least prioritize the issues

         19   that come in to the stakeholders.

         20              MS. PHILIPS:  Can I follow up on that?

         21              COMMISSIONER ROSNER:  Yes.

         22              MS. PHILIPS:  To me, that's PJM leadership,

         23   whether it's the board or your team.

         24              MR. MILLS:  Yep.

         25              MS. PHILIPS:  What's standing in your way of





                                                                      127



          1   prioritizing your work streams?

          2              MR. MILLS:  It is the crisis of the moment type

          3   issues.  And I think we just have -- we don't, today, have a

          4   very good filter about "How does that crisis of the

          5   moment..."

          6              COMMISSIONER ROSNER:  Do you need authority from

          7   us, to be able to do that?

          8              MR. MILLS:  No.  This is something I am just

          9   letting you know, because it's come up twice, about the

         10   unwieldy process and the number of issues.

         11              COMMISSIONER ROSNER:  Okay.  Great.

         12              MR. MILLS:  And there's something that I am all

         13   over right now.

         14              COMMISSIONER CHANG:  But this is not because

         15   someone's stopping you from prioritizing it.

         16              MR. MILLS:  No.  Not at all.

         17              COMMISSIONER CHANG:  Okay.  Okay.

         18              MR. MILLS:  It's just a missing element right

         19   now.

         20              COMMISSIONER ROSNER:  I just want to take a

         21   moment to acknowledge Senator Hester.  Thank you for coming,

         22   and hello.  I have met with you and I appreciate you being

         23   here.

         24              I wanted to ask one more question.  You know,

         25   someone made the point that politics were muting market





                                                                      128



          1   forces, and you know, that's something of great concern.  I

          2   think Chairman Wood, you mentioned it.  Marjie, you

          3   mentioned this too.

          4              One of the steps back that I have taken on that

          5   is that two years ago we had a dramatic increase in the

          6   capacity market clearing price.  We had a lot of new demand. 

          7   And what we didn't have in place at that time was mechanisms

          8   to get the cost of new infrastructure on some of the new

          9   users of that infrastructure that have emerged.

         10              And I think a lot has changed since then, but the

         11   big thing that was missing was, really, retail rate tariff

         12   design, that's since happened.  And, a general comment,

         13   we're not going to talk about.  But the FERC has also been

         14   taking some steps there, that I think work well with that.

         15              But I think one thing that is urgent, that needs

         16   to keep happening in order to have the political

         17   sustainability of, you know, markets need to signal scarcity

         18   in order to get responses, we need to make sure that all the

         19   PJM states have gone through that process, which I think on

         20   the Federal Power Act it's reserved for you all, to make

         21   those judgments on, what classes of customers pay for what,

         22   and we're there, to work with you, in our 206.

         23              But I just want to underscore that that is urgent

         24   for this market to work, and I don't want to take on Judge

         25   Bagot, because I know you have been very active there and I





                                                                      129



          1   know a number of PJM states have as well.  Pennsylvania as

          2   well.  But that work, it's urgent that it gets completed, if

          3   it's not already.

          4              And I would say the same for -- as we discussed

          5   earlier -- the backstop auction, should there be one, Mr.

          6   Mills.  We need the cost allocation in place for that now,

          7   and the fact that it's not here is creating dramatic

          8   uncertainty.

          9              And we need you all, states, to do, with your

         10   values judgment, the curtailment priority of which users,

         11   should there not be enough energy, in 2029, who should have

         12   access to that energy.  We need you to do that.  Urgently.  

         13              And we also need really fast permitting, of

         14   generation, transmission.  And I'd love to see a race to the

         15   bottom on timelines, among the PJM states, on who can go the

         16   fastest, on things that you want to build.

         17              And so, I would just ask, Judge Bagot, Jacob,

         18   with the tools that you have at OPSI, and hopefully soon the

         19   tools that you have to convene governors and state

         20   legislatures, and however we can accommodate those with

         21   interests here, would OPSI be able to have a transparent,

         22   you know, tracking mechanism so that we can all see what

         23   states have done the large load tariff design, which states

         24   have implemented the backstop auction, which states have

         25   revisited curtailment priority, how long it takes to build a





                                                                      130



          1   battery in Pennsylvania, or Maryland, or a gas plant for

          2   whoever wants it -- whatever it is -- or a transmission line

          3   or a substation.  Just like how long it takes to get a CPCN

          4   and whether it can be faster.

          5              I think all of that needs to be a lot more

          6   public, and in the meantime we're here to hear concerns

          7   about the prices that our markets deliver.  But we need your

          8   help to get those prices, in ways that actually get

          9   infrastructure built.

         10              Thank you.

         11              CHAIR BAGOT:  If I can just react quickly, on

         12   your last call to transparency on what's happening in the

         13   states, and if we can provide that, I think the answer is

         14   yes.

         15              I think really what you're asking for, along with

         16   transparency, is accountability, and that's a way to force

         17   accountability and make sure states are sort of staying on

         18   top of the issues that are within their jurisdictional

         19   realm, if people can transparently see what they are or are

         20   not doing and where they are in the process.

         21              I just want to point to the last bullet in my

         22   comments, which maybe does not seem the most significant,

         23   but I think really is, which is that there are things that

         24   we can do today with OPSI, the states, and PJM, that don't

         25   require 205 action, that don't require changes to the





                                                                      131



          1   governance process.  Right?

          2              Connect and manage I think is a place where, if

          3   we had a more systematic process for communicating changes -

          4   - right? -- in the stakeholder process, we could sort of

          5   bring the states, and PJM, in at the same time, and say

          6   "Here's the things... if we go down this route, there's the

          7   PJM role and the decisions that go there, and here's the

          8   decisions that are complementary, that are going to have to

          9   happen at the state level and they're going to have to

         10   happen at the same time, and so let's create a forum where

         11   we can start working on those issues at the same time."

         12              There are ways that we can do that, that we are

         13   not now, and we took the first step, or I'm trying to take

         14   that first step, with respect to curtailment tariffs, and

         15   other things, and that was discussed and announced at the

         16   last PJM stakeholder meeting.

         17   `          But I think there are very easy pathways forward,

         18   to start to have that collaborative discussion where we can

         19   work along parallel tracks, and we don't need 205 for that.

         20              And I hear PJM saying that it's willing to work

         21   with the states on that, and I think it's going to take both

         22   of us sitting down and creating that framework and then

         23   really executing on it.  But I think there's a path there.

         24              COMMISSIONER ROSNER:  And that's wonderful to

         25   hear.  And I would just say that that's urgent.  And I'll





                                                                      132



          1   give you, like, a practical effect of that coordination not

          2   being present so far, is that we probably spent a year

          3   talking with PJM about proposals like "connect and manage,"

          4   which I won't go into any more details about.

          5              But, because of the critical input that they need

          6   from all the PJM states to be on the same page on, "Here's

          7   how we plan to do this," they actually can't move forward

          8   with that, or they have been unable to.  So, you know, that

          9   alignment just makes a lot of sense, and I really appreciate

         10   your openness to working on that.

         11              CHAIR BAGOT:  One last -- I guess my ask of PJM,

         12   I think, to help the states be able to be more helpful

         13   partners in that process, is tell us what you need, like

         14   tell us what you need to know from us in order to haves a

         15   coherent process.  Right?

         16              And you have the ability to even be, sort of, an

         17   informal convening body to get the states together, to say

         18   "Okay, if we do X, states, here's your role.  What's a way

         19   that we can get you all in a room together, talking about

         20   what that means, and let's put some aspirational timeframes

         21   around it."  Right?

         22              So, I think we can work together to create a

         23   more, like, systematic process, going forward, where, when

         24   these sorts of things come up, we are already have the

         25   framework in place to engage in that way.





                                                                      133



          1              COMMISSIONER CHANG:  I just want to say that I

          2   heard from Marjie and I hear from you as well, that, you

          3   know, there's no substitute for communication.  I feel like

          4   communication has broken down.  Communication with the

          5   states and many multiple entities of the states, and maybe

          6   communications with stakeholders even, or making decisions

          7   in a timely manner, that has failed.

          8              So, even if we change completely the governance,

          9   you can't substitute communication.  So, I do think -- and I

         10   sort of understand this also from my time in New England, is

         11   that there's got to be so much communication, and you have

         12   more states.  So, more people to talk to, and more alerts

         13   and more, you know, heads ups, and nobody likes surprises,

         14   particularly states and particularly governors.  Nobody

         15   likes surprises.

         16              So I think there's no substitute for

         17   communication, no matter what the governance structure is. 

         18   But I also wonder if this is a moment where, like, yes, we

         19   need to increase so much communications and so much more

         20   leadership.  But there is something else in the governance

         21   that has to change, and it sounds like maybe some version of

         22   states' way of getting their version of proposals -- again,

         23   they don't have to exercise it, but just the ability to have

         24   jump ball with you, it sounds like is it's with you, not

         25   with FERC, that's one area, and perhaps -- I also hear that





                                                                      134



          1   205 filing rights for PJM, if the stakeholders -- there's

          2   got to be a, you know, timeline on the decisions on the

          3   stakeholders.  It can't just be forever  stakeholdering.

          4              And then PJM and its board have to make certain

          5   decisions and make the filings.  I feel like that's the

          6   urgency piece that's also missing.

          7              CHAIRMAN SWETT:  So, I'm going to exercise my

          8   chairman's rights now. We've got 15 minutes left, and I'm

          9   going to channel the Senate.  I would like each of you, and

         10   we're going to go down the line, in one or two sentences, if

         11   there is one thing that you think is the most important

         12   thing to fix PJM, I'd like to hear what that is.  With no

         13   rebuttals and no extra window shades. 

         14              So, I'll start with you, Mr. Mills.

         15              MR. MILLS:  Thank you, Madam Chair.  It's always

         16   great to be first.

         17              (Laughter.)

         18              CHAIRMAN SWETT:  That's why they pay you the big

         19   bucks, right?

         20              (Laughter.)

         21              MR. MILLS:  And this is one thing that we've only

         22   tangentially talked about here today, but I think the most

         23   binding constraint and largest risk is not getting new

         24   generation online and into the auctions.  And they could be

         25   hung up anywhere in the food chain, from permitting to





                                                                      135



          1   siting to financing to the actual interconnection.

          2              And my datapoint is the last two auctions which,

          3   yes, cleared short and, yes, cleared high at the cap.  They

          4   showed an incredible lackluster amount of new generation.

          5              So, you have to ask why.  What's driving that?

          6              Now, to answer Commissioner Rosner's question, we

          7   will very soon announce a backstop auction, with the details

          8   that come around it.  We didn't want to distract from this

          9   hearing.  So, in the next 72 hours, that will drop.

         10              But, I think that while this governance and

         11   stakeholder issue is completely -- and this has been a

         12   wonderful discussion -- I don't think that those are to

         13   blame for what's happening with the market right now.

         14              CHAIRMAN SWETT:  You're going way over two

         15   sentences and you're not answering my question about the

         16   states' rights or board independence, that are the subject

         17   of this panel.

         18              MR. MILLS:  Okay.  Sorry.

         19              CHAIRMAN SWETT:  So, if you have a magic wand,

         20   what is the one thing that would fix those issues?

         21              MR. MILLS:  I would create an augmented OPSI

         22   organization that speaks for the, in totality of, the

         23   states, and I would afford the PJM board 205 rights on the

         24   operating agreement and transmission planning.

         25              CHAIRMAN SWETT:  Perfect.  Thank you.  And I'm





                                                                      136



          1   not trying to be trite about the...

          2              MR. MILLS:  No, I completely understand.  No

          3   problem.

          4              CHAIRMAN SWETT:  ...about the very great concern

          5   that you raised, and...

          6              MR. MILLS:  I'll read it to you later.

          7              (Laughter.)

          8              CHAIRMAN SWETT:  Great.  Chairman Wood?

          9              CHAIRMAN WOOD:  I think we should make it really

         10   clear, not just here but in all the RTOs, that the board

         11   members have a responsibility to the public interest

         12   consistent with the FPA, which draws in the just and

         13   reasonable rate.

         14              I think everything else follows from that,

         15   because the public interest includes your co-sovereigns. 

         16   That's the states.  It includes an active and empowered

         17   stakeholder group, which I think we've got a good basis for

         18   that from 90 years in the PJM.

         19              And I think public interest flows through with

         20   the issues with transparency, and communication, and, you

         21   know, clear leadership, that I think we've all pointed out

         22   here today can be stepped up.  So, we're putting a lot on

         23   your back, Mr. David, but I think you all can do it.

         24              CHAIRMAN SWETT:  We're oh for two on two

         25   sentences.





                                                                      137



          1              (Laughter.)

          2              CHAIRMAN SWETT:  Chairman Bagot, I have faith in

          3   you.

          4              CHAIRMAN WOOD:  That was a lot of commas.

          5              (Laughter.)

          6              CHAIR BAGOT:  I'm going to --

          7              CHAIRMAN SWETT:  That's fair; you are from Texas. 

          8   I stand corrected.

          9              CHAIR BAGOT:  I'm going to echo Pat's comment,

         10   but I'm going to add to that, that in addition to providing

         11   them or clarifying that mandate, we actually have to make

         12   sure that they have the authority to carry that mandate out. 

         13   And that means independence, and that means the ability to

         14   make filings and brings positions before the Commission, to

         15   the extent that they view that as the optimal or the

         16   appropriate path forward.

         17              CHAIRMAN SWETT:  Okay.  So that's two votes for

         18   an independent board.  Deputy Secretary Finkel?

         19              DEPUTY SECRETARY FINKEL:  Three votes for an

         20   independent board, a real seat on the table for the states

         21   with teeth and remembering that the reason that we need that

         22   is because we need a function and a credible market, to

         23   solve the governance, to solve these market problems before

         24   it's too late.

         25              CHAIRMAN SWETT:  Great.  Thank you.  I'm giving





                                                                      138



          1   up on two sentences, but pleased proceed.  (Laughs.)

          2              MS. BURBURE:  What he said.

          3              CHAIRMAN SWETT:  Oh!  You win!  Okay, thank you.

          4              (Laughter.)

          5              CHAIRMAN SWETT:  Marjie, this is going to be

          6   tough for you.

          7              MS. PHILIPS:  I'm trying.

          8              (Laughter.)

          9              MS. PHILIPS:  Board independence, better

         10   structure around how PJM communicates with the governors and

         11   states so they have a meaningful role, and I have to sneak

         12   in for David, governance isn't about permitting; it's that

         13   we can't get the generators.  It's that we can't -- we don't

         14   have the load, signing onto the contracts.  All the

         15   governance in the world isn't going to get us -- and we

         16   want to focus on that -- we want to spend as little time on

         17   governance as possible.  We want to spend our attention on

         18   getting new generation and enhancing existing generation on

         19   the system.

         20              CHAIRMAN SWETT:  That was four, right?

         21              MS. PHILIPS:  I don't think so.

         22              (Laughter.)

         23              CHAIRMAN SWETT:  But, well said.  Maria.

         24              MS. GULLUNI:  205 rates to the board.  Actually,

         25   let me say that, 205 rights to PJM, and the board should be





                                                                      139



          1   an oversight body.  Management should be running the company

          2   on a day to day basis.  Management should be controlling

          3   stakeholder process.  With the 205 rights, management should

          4   be making the market and planning changes and prioritizing

          5   their work.

          6              CHAIRMAN SWETT:  Excellent.  Thank you.  So, do

          7   any of my colleagues have any closing remarks, or can we

          8   stop torturing these people 10 minutes early?

          9              All right, thank you all very much.  That was

         10   very engaging, illuminating.  I appreciate you coming before

         11   us today.

         12              And we will adjourn until 1:00 p.m. on the dot.

         13              (Whereupon, the session adjourned for the lunch

         14   break, at 11:50 a.m.)

         15   

         16   

         17   

         18   

         19   

         20   

         21   

         22   

         23   

         24   

         25   





                                                                      140



          1                        AFTERNOON SESSION

          2                             1:02 p.m.

          3              MS. EYOCKO:  Good afternoon, everyone, and

          4   welcome back.  My name is Stefanie Eyocko, and I'm from the

          5   Office of Energy Market Regulation, here at the Commission.

          6              We'll now begin with the first half of the second

          7   panel, which will be a roundtable with energy

          8   representatives, that will examine how PJM's stakeholder

          9   process, including established sectors, committees, and

         10   voting structures affects the RTO's ability to take

         11   necessary and timely actions, including Section 205 filings,

         12   to address the region's operational and market challenges.

         13              Each panelist did submit an advanced statement

         14   that includes their position on the questions and the

         15   conference agenda.  To maximize the amount of time today, we

         16   will be foregoing opening remarks and go directly to

         17   questions from the Chairman and commissioners.

         18              Panelists, to answer a question from the chairman

         19   or the commissioner, please tip your name tent like so.

         20              When you're called upon, please turn your

         21   microphone on, with the gray button at the base of the

         22   microphone in front of you.  You will know your mic is on

         23   when the LED light is glowing green.

         24              To maximize the time for discussion, please keep

         25   your answers concise.





                                                                      141



          1              We do not intend to discuss, at this technical

          2   conference, any specific proceedings before the Commission,

          3   including proceedings that involve similar issues, whether

          4   listed on the supplemental notice or not, and we ask that

          5   panelists similarly refrain from such discussion.  If anyone

          6   engages in these kinds of discussions, my colleagues from

          7   the Office of General Counsel will interrupt the discussion

          8   to ask the speaker to avoid that topic.

          9              And now, to introduce group one of the second

         10   panel, we first half Asim Haque, who is the Executive Vice

         11   President of Governmental and Member Services at PJM.  

         12              We have Suzanne Jaworowski, the Secretary of

         13   Energy and Natural Resources at Indiana Governor Mike

         14   Braun's Office.

         15              We have Arnie Quinn, who is Senior Vice President

         16   of Regulatory Policy at Vistra Corp.

         17              We have Steve Lieberman, Vice President of

         18   Transmission & Regulatory Affairs at American Municipal

         19   Power.

         20              And we have Kent Chandler, who is the

         21   Non-Resident Fellow of Energy and Environmental Policy at R

         22   Street Institute.

         23              We have Pamela Quinlan, who is the Principal at

         24   GQS New Energy Strategies.

         25              And finally, we have Abe Silverman, who is an





                                                                      142



          1   Assistant Research Scholar at the Johns Hopkins University

          2   Ralph O'Connor Sustainable Energy Institute.

          3              Welcome panelists.

          4              I will now turn it over to Chairman Swett for

          5   questions.

          6              CHAIRMAN SWETT:  Thank you.  Very well said. 

          7   Welcome, everyone.

          8              Again, I will reiterate that you all have been

          9   handpicked, based on your experience.  There are some big

         10   thinkers on this panel.  And please be candid.  I expect

         11   Pamela to throw some bombs, at the very least.

         12              (Laughter.)

         13              CHAIRMAN SWETT:  No, you're very shy, I know.

         14              (Laughter.)

         15              CHAIRMAN SWETT:  So, we'd like to focus this

         16   panel, in particular, starting out on drilling down into the

         17   stakeholder process, which everyone is pointing a lot of

         18   fingers on, and I really want to reemphasize that we want

         19   some very pointed suggestions, and problem identification. 

         20   So, Mr. Haque, I will start with you.

         21              In the pre-conference comments that we got, many

         22   stakeholders, including AMP, and we're going to turn to AMP

         23   next, have expressed concern with the way that lower-level

         24   voting is misaligned with voting at senior committees.

         25              For example, they explain that the current





                                                                      143



          1   process impedes stakeholder decision-making because, at the

          2   lower level committees the members have one vote, including

          3   affiliates, but at the senior committees each corporate

          4   entity only received one vote.  So, members with more

          5   affiliates control the flow of proposals from the lower to

          6   upper level committees. 

          7              So, with that as a table setting for the

          8   question, can you please discuss why PJM's processes are

          9   structured this way, and if there is broad support that

         10   you're aware of, including in PJM itself, for changing that

         11   structure, as there seems to be, at least from the outside,

         12   and how can PJM implement those reforms?

         13              MR. HAQUE:  Yeah.  Madam Chair, commissioners,

         14   good afternoon.  Thank you for the invitation to be here,

         15   and I realize we're going to spend some time talking about

         16   the particulars of the stakeholder process, and specifically

         17   the stakeholder process, we believe, has, you know,

         18   functioned well for a particular period of time.  In this

         19   particular period of time where we are focused on speed and

         20   efficiency, I think the process has struggled.

         21              Specifically with respect to the committee

         22   structure, there are a number of stakeholder committees at

         23   PJM.  There are two senior standing committees.  That is the

         24   Markets and Reiability Committee and the Members

         25   Committee.





                                                                      144



          1              Beneath that structure, there are four standing

          2   committees.  Planning, Markets, Operations, and Risk.

          3              And then, beneath that standing committee

          4   structure are a series of subcommittees.

          5              Now, you are correct, Chair; in the lower

          6   committee structure, the voting differs than in the senior

          7   standing committee structure.

          8              Now, that conceivably could prevent proposals

          9   from advancing from the lower committees all the way up to

         10   the highest committees. 

         11              There is a check and balance there.  So, once a

         12   lower committee vote, assuming that the lower committee

         13   votes a proposal in the affirmative, gets up to the senior

         14   standing committee and the voting structure changes, well

         15   that voting structure change moves to this concept called

         16   "sector-weighted voting."  Okay?  

         17              And that sector-weighted voting could act as a

         18   check against the         lower committee proposal that

         19   could have advanced.  Simultaneously, that proposal, which

         20   would have, hopefully, advanced to the lower committee, may

         21   not eventually get there, because of the voting structure in

         22   the lower committees.

         23              PJM's position, "at the end of the day," is, you

         24   know, these voting structure frameworks are codified in

         25   Manual 34.  Manual 34 requires two-thirds sector-weighted





                                                                      145



          1   vote to amend.

          2              Would we be willing to take a look at lower

          3   committee voting structures?  Sure.  And make sure that they

          4   align with the upper level committees?  Sure.  And

          5   vice-versa.

          6              I think what we're really trying to do is find

          7   speed, and I think an interesting conversation to be had is,

          8   frankly, whether we need all of these lower committees or

          9   that we need so many committees that are leading up to PJM's

         10   most senior committees.

         11              CHAIRMAN SWETT:  Okay.  So you're teasing a

         12   potential solution, which is cute.  But what do you think we

         13   actually need to do?

         14              (Laughter.)

         15              CHAIRMAN SWETT:  Are you saying that we should

         16   get rid of all of the lower committees or the voting

         17   structure?

         18              MR. HAQUE:  I think the standing committees and

         19   the senior standing committees are essential to do business

         20   operations.  I do question whether the lower committees are

         21   necessary, underneath those standing committees, in order to

         22   do business on behalf of the organization.

         23              CHAIRMAN SWETT:  Okay.  And maybe this is not a

         24   fair question, and if you don't know the answer then I

         25   totally understand.  But why was the structure originally





                                                                      146



          1   conceived to have this type of imbalance?

          2              MR. HAQUE:  Yeah.  I'm going to show my longevity

          3   here at PJM, which is tipping over just about seven years. 

          4   You've got a panelist coming up, on panel three, who we like

          5   to call the "Elvis Presley" of the stakeholder process,

          6   named David Anders, who has been here from the very, very

          7   beginning.

          8              An answer that I'm going to give you, that I

          9   don't know that you will love with respect to our

         10   stakeholder process, is that that is just how it was done,

         11   very early on in the process, and you're going to hear that

         12   answer for quite a few of the particulars hat occur in the

         13   stakeholder process.

         14              CHAIRMAN SWETT:  So, will the stakeholder process

         15   be more successful in producing efficient results if PJM

         16   does get rid of the lower committees?

         17              MR. HAQUE:  They will certainly be more timely. 

         18   And the reason why I say that is because when an issue is

         19   advanced, in these lower committees, just think about it, if

         20   you start here, at a lower committee, that lower committee

         21   proposal then has to go to the next committee level, and the

         22   next committee level, and the next committee level.

         23              Again, the stakeholder process is great at

         24   receiving feedback.  It's great at hearing from

         25   stakeholders.





                                                                      147



          1              What it was not designed for was speed.  And so,

          2   if we are going to enter this new era, if we're really going

          3   to take big swings, I do think we need to think about that

          4   over-arching committee framework and whether or not that

          5   over-arching committee framework still makes sense.

          6              CHAIRMAN SWETT:  Okay, thank you.  Yes, sir.

          7              MR. LIEBERMAN:  Good afternoon.  Steve Lieberman,

          8   American Municipal Power.  Thank you for having this

          9   conference.

         10              I do want to, perhaps, disagree slightly with the

         11   comments that Mr. Haque just made.

         12              So, the reason we have these lower level

         13   committees is so that we could focus our attention on a

         14   specific issue.  So, Asim talked about we have these

         15   standing committees, like the Planning Committee, and Market

         16   Committee, and what not.

         17              In the first panel we heard from David Mills.  He

         18   talked about the Reserve Certainty Senior Task Force.  So,

         19   that is a -- and he said it's a very technical discussion,

         20   and on and on.

         21              So, that is an example where, intentionally, we

         22   have decided to have a technical discussion on a very minute

         23   subject, and that's all we talk about.  We don't talk about

         24   anything else, at that senior task force, in that instance.

         25              So, in my opinion, I would not support a magic





                                                                      148



          1   wand waving away of all these lower level committees.  I

          2   think they have a purpose, in order to kind of focus subject

          3   matter experts on a specific issue, and not detract from a

          4   senior committee that's going to talk about more broad

          5   topics or multiple topics.

          6              CHAIRMAN SWETT:  So, how can they move more

          7   quickly, if we keep them?

          8              MR. LIEBERMAN:  Yeah, and I'd like to also talk

          9   about that same task force that David Mills mentioned.

         10              He said well, you know, this committee, the

         11   senior task force, it started its initial meeting like three

         12   years ago, and we hope to get something to FERC by October

         13   this year, and it met 42 times.

         14              So, taking advantage of AI, I found out that

         15   there's 36 months between, basically, October, 2023, and

         16   October, 2026, and if we met 42 times that's about 1.27

         17   times per month.

         18              So, if we want to advance the ball quicker, we've

         19   got to meet more frequently than 1.27 times per month.

         20              PJM is in complete control of the cadence in

         21   which it schedules stakeholder meetings.  So, if we're

         22   talking about -- and you mentioned this at the annual

         23   meeting -- about moving quicker, well, PJM's got a schedule

         24   that was meeting stakeholders, states, OPSI.  We have no

         25   say, no input, over when PJM schedules meetings on any





                                                                      149



          1   topic.

          2              In fact, Manual 34, that Asim just mentioned,

          3   specifically says that PJM assigns the role of the secretary

          4   of the Members Committee, which is Dave Ander, and that

          5   person is fully in charge of setting the meetings.

          6              So, when we want to get stuff done quicker, we've

          7   got to meet more frequently than 1.27 times per month.

          8              CHAIRMAN SWETT:  So, you're telling me that the

          9   stakeholder process is slow because you don't have more

         10   meetings?

         11              (Laughter.)

         12              MR. LIEBERMAN:  I'm saying if there is an issue

         13   that's of paramount importance to PJM, then meeting more

         14   frequently than once a month is probably the way to get

         15   things done.

         16              CHAIRMAN SWETT:  Okay.

         17              COMMISSIONER LACERTE:  Steve, let me challenge

         18   you on that.  Wouldn't these subsidiary meetings just happen

         19   in an informal basis without there being a formal process

         20   within a PJM manual?  Wouldn't these people just get

         21   together in the nature of, like, the endless nature of --

         22   couldn't this meeting have been a conference call?  Could

         23   this conference call have been an email?

         24              MR. LIEBERMAN:  Uh-huh.

         25              COMMISSIONER LACERTE:  Like, couldn't we move





                                                                      150



          1   faster in that direction without it being a fixture of the

          2   manual?

          3              MR. LIEBERMAN:  It's possible.  You know, and I

          4   would say that, you know, certainly there are a lot of

          5   meetings that we have that could be done more efficiently

          6   and done remotely.

          7              And, in fact, after -- when PJM reopened after

          8   the lockdown, we have conducted a lot of our meetings in a

          9   remote manner.  So, we don't necessarily have to travel to

         10   Valley Forge and meet.  We do a lot of them through -- yeah.

         11              COMMISSIONER LACERTE:  So, could these frontline

         12   discussions happen in an informal basis, outside the

         13   requirement in the manual?

         14   

         15              MR. LIEBERMAN:  Yeah.  And I think to a degree

         16   they do.  I think that's part of what stakeholders do, is

         17   they contact each other outside of, let's say, "PJM hours,"

         18   and talk about issues and figure out where their positions

         19   are.

         20              Yes, sir.

         21              CHAIRMAN SWETT:  Pamela.

         22              MS. QUINLAN:  Thank you so much for convening

         23   this conference.  I think working even on the pre-filed

         24   statement gave time in our schedules to really think through

         25   these really hard questions that we need to understand





                                                                      151



          1   what's the purpose of these stakeholder processes, what is the

          2   benefit to get there?  And, if we can't do things quickly

          3   when they need to happen quickly, then we're obviously not

          4   serving the region.

          5              But there is a distinction between things that

          6   need to be responded to so fast, and things that are really

          7   worth taking time to really get into some of the details. 

          8   And I think the more I thought about it, the more I think

          9   there's a distinction as to what you use the stakeholder

         10   process for, and what you actually really don't need to

         11   necessarily use it for.

         12              And I think coming up with direction and

         13   leadership of where we want to go is really helpful to get

         14   from PJM leadership and the board.  And the details of how

         15   you get that done and what that means, there's really no

         16   replacement for the breadth of the PJM stakeholders and

         17   their expertise across the board.

         18              And I think, if you erase those lower committee

         19   meetings -- I mean, whether it's in a committee or at

         20   special sessions of the MIC, I mean, I've been around the

         21   PJM stakeholder process long enough to see, like, many

         22   iterations of subcommittees, task force, workshops, like...

         23              But the point is you want to make sure that there

         24   is a transparent way that parties who are going to be impacted,

         25   have the ability to understand where this is going, and





                                                                      152



          1   explain how it uniquely impacts them.

          2              That doesn't mean you need to meet a certain

          3   amount of times, or however many times you said for that

          4   meetings.

          5              And I think, back to the earlier panel, where

          6   they talked about priorities.  I think getting feedback on -

          7   - you see this in other regions and other RTOs where, like,

          8   this is a schedule -- and we start off with that in PJM

          9   often.  Like, here is the plan of how many meetings we're

         10   going to have, and we're going to have an objective for

         11   that.  

         12              We're not usually held to it.  Oftentimes it

         13   continues to move on, beyond that.  But also a narrowing of

         14   "Here's the specific areas that we're looking for

         15   stakeholder feedback," and it's not necessarily open-ended

         16   to anything anyone wants to talk about.

         17              And I don't know that there's a limitation and a

         18   manual that says you can't do that, but that's generally not

         19   been the culture.

         20              So I think, when we have these discussions, I

         21   think there is a distinction between -- we shouldn't throw

         22   the baby out with the bathwater.  Like, the idea of having

         23   technical expert people from across the industry provide

         24   details on how this will work in practice cannot be

         25   replicated.





                                                                      153



          1              Because if you remove it, we're going to have

          2   unintended consequences and those can be very severe.

          3              COMMISSIONER SEE:  I hear you, on trying to get

          4   this line right, between deliberation and speed can be

          5   different for different issues.  Can you or others maybe go

          6   into more detail of what that might look like?  Because I'm

          7   also concerned about creating dual tracks and more process

          8   and adding more complexity to -- that's what we're talking

          9   about here, is a process that's so complex we can't get

         10   things done at the speed that we need.

         11              So, can you give some more detail of what it

         12   might look like to be able to have different processes

         13   without adding to the complexity?

         14              MS. QUINLAN:  I think part of that gets down to

         15   prioritization and understanding what the urgency is for

         16   something.  And every different stakeholder is going to have

         17   a different view.  Like, if this is the way your company

         18   makes money, then that's the biggest issue to you.

         19              But I think going back to, like, the PJM board

         20   and leadership, trying to figure out public interest and

         21   trying to figure out public interest and understanding,

         22   like, that's what's important to PJM as a whole and what's

         23   going to be the critical path for its success.

         24              Right now we have the resource adequacy issue. 

         25   That can't be bogged down in details of everyone negotiating





                                                                      154



          1   every single component to it.

          2              And I think that gets down to priorities upfront

          3   and you can decide and, you know -- and I know we're not

          4   talking about state involvement on this panel, so I don't

          5   want to get too much into it, but I think in areas where it

          6   involves the states, the states should work with PJM and

          7   identify which ones are the priorities that cannot go

          8   through such an exhaustive stakeholder process.

          9              But you can just put time bounds on it.  And

         10   then, if you think you need to have infinite meetings -- I

         11   think part of the challenges folks have had to date, in all

         12   of the years that I've heard, now is that, for people

         13   complaining about the stakeholder process, it was that

         14   there's too many meetings and you can't follow all of this,

         15   and I don't have enough resources to staff out every single

         16   task force.

         17              So, creating more of those is difficult.  There's

         18   no simple answer to this.  If there was, we wouldn't have to

         19   talk about it.

         20              But I think coming up with "These are the

         21   critical things that we are going to move forward, no matter

         22   what, and this is the date certain that we're going to move

         23   forward," we want to take input from the stakeholders, and

         24   the areas where the board or PJM leadership specifically

         25   needs feedback can hone in and narrow those conversations,





                                                                      155



          1   then you actually can have less of those meetings.

          2              And if people don't think those are the right

          3   things to bring, then they can come at FERC and fight that.

          4              And then, for areas where it's really, like, we

          5   have a timeline, we're going to have some software changes,

          6   it's going to take time to get there, whatever reason, you

          7   have more details for that, then I think you can have a more

          8   full, kind of, stakeholder process and try to get the tier

          9   one consensus, because there's not this, like, firm deadline

         10   on it.

         11              But, having an infinite number of issues, with

         12   never-ending creations of new task forces, puts folks that

         13   are less well capitalized being able to not be able to

         14   participate in that, they don't have the resources for it,

         15   and you're not getting, like, the full suite of stakeholder

         16   inputs, which was the intention in the first place.

         17              So, prioritization becomes key, I think, and then

         18   I think you can put things on actual timelines.

         19              CHAIRMAN SWETT:  Arnie?

         20              MR. QUINN:  Yeah, I want to thank you for the

         21   opportunity to be here.  I completely agree with I think

         22   where Steve and Pamela were going, that the deliberative

         23   part of this is not the part that we want to lose.  That's

         24   particularly important.

         25              The issue is, though, PJM works on more issues, I





                                                                      156



          1   think, than any other ISO, certainly that we're in.  So, we

          2   participate in, essentially, every ISO in the country,

          3   including ERCOT, except for SPP.  I think we work on more

          4   issues, in PJM, than any other ISO does in the country, and

          5   so I think the challenge is, you know, how do you make all

          6   of this go faster, how are we able to do these processes

          7   with more speed.

          8              You know, to Steve's point, how do you meet more

          9   often if that's what it takes to get something done more

         10   quickly?  Part of it is we've got to decide, on the front

         11   end if there are some of the things that we deal with today

         12   that we don't need to be dealing with right now, that there

         13   are lower priority items, and there are almost certainly

         14   examples that, you know, we could come up with, where you

         15   identify somethings that we talked about for three years

         16   that was a small, incremental, improvement, but if we had

         17   sat down at the beginning of the year and said "Where does

         18   this stack up with all of our priorities?" it would have

         19   gone on the low priority part of the list, and we wouldn't

         20   have dealt with it, and we would have had more time for

         21   other things.

         22              So I think that is crucially important, if we're

         23   going to solve this.

         24              Going back to the voting, I will note that there

         25   is something that is difficult about the voting structure. 





                                                                      157



          1   We happen to have an advantage.  We're a large company with

          2   a lot of affiliates.  So we, on paper, have an advantage on

          3   those lower committees, where we have more ability to shape

          4   what goes to the higher companies.

          5              For our company, we would conform the voting

          6   structures.  We would take away what appears to be an

          7   advantage, because in truth we're not just a good company

          8   and a good corporate citizen; I actually think we don't get

          9   that much of an advantage.

         10              Because we can shape something that goes to the

         11   higher committees, and then at the higher committees they

         12   fail.  So, whatever we gained earlier on, we've probably

         13   lost by the time we get to that higher committee, and now

         14   we've spent more time.

         15              So, in my mind, conforming the voting,

         16   thinking this is one company speaking, there would be some

         17   value to that, and that would potentially have an ability to

         18   compress some of the process.  Not losing that important

         19   deliberative element, but have people vote at the same

         20   nature so that you have some confidence that, as it's being

         21   developed, it can actually move forward.

         22              CHAIRMAN SWETT:  "Conforming the voting," what

         23   does that mean?

         24              MR. QUINN:  There would be sector-weighted voting

         25   all along the way.  So, as it's going from lower committees,





                                                                      158



          1   if we continue to have lower committees to higher

          2   committees, we are not asking to say "Let's keep the

          3   affiliate voting."  We would say do sector-weighted voting

          4   that we do at the upper levels, do that earlier in the

          5   process, if that's something that we continue to do.

          6              CHAIRMAN SWETT:  That's very charitable of Vistra

          7   to offer.

          8              MR. QUINN:  I will say yes, it is.

          9              (Laughter.)

         10              MR. QUINN:  And, I also -- and I don't think we

         11   get that much of an advantage, because in reality we get a

         12   temporary win to have a later on loss.

         13              CHAIRMAN SWETT:  Abe?

         14              MR. SILVERMAN:  Great.  Thank you all very much

         15   for the invite to be here.

         16              So, I want to come back to this prioritization

         17   piece, and I want to make sure we're focusing on the right

         18   thing.  I actually don't think it's the lower level

         19   committees that are bogging us down.  It's when we ask

         20   committees to decide policy.

         21              And again, I think the data center issue and the

         22   large load integration is a perfect example of this.  We

         23   would have saved so many hours of meetings for, I think,

         24   most of the people up here, had we had input at the very

         25   beginning from the states, and from the board, directing PJM





                                                                      159



          1   staff what to do, and then we could have had stakeholder

          2   meetings on how to implement it.

          3              And I think that's the key thing.  Right?  It's

          4   not about the lower level committees.  Christine Cidione,

          5   you know, five years ago, wrote her wonderful paper, and she

          6   made the point that the stakeholder process in PJM works

          7   fine for non-controversial issues.  And "the wheels come

          8   off" as soon as it gets hard.

          9              And so, if we had that prioritization element,

         10   where the states were coming in, PJM was sitting with them

         11   at the table, to come up with the priority how to deal with

         12   some of these issues of first impression, the whole thing

         13   would have just gone so much faster and smoother and,

         14   frankly, resulted in something that was politically durable,

         15   that investors could actually respond to.

         16              CHAIRMAN SWETT:  So, who should set the agenda?

         17              MR. SILVERMAN:  I think on different items,

         18   especially things dealing with resource adequacy and issues

         19   of first impressions, or where we need a cooperative

         20   federalist approach.

         21              I mean, I think everybody in this room would

         22   agree that the only way to deal with large loads is to have

         23   state and federal regulators and PJM sitting at the same

         24   table, dividing up the universe and saying "This is your

         25   responsibility.  This is our responsibility, but let's do it





                                                                      160



          1   together and hold hands while we do it."

          2              Had PJM sat down and really had that type of

          3   partnership with the states, we would have had fewer

          4   meetings and better outcomes.  

          5              And so I think, on these issues, it really is PJM

          6   potentially sitting down with states, perhaps without a lot

          7   of other stakeholders at the table, and deciding how we want

          8   to address these things for where there is this inherent

          9   federal-state nexus.

         10              I mean, I mentioned in my comments you could have

         11   a FPA Section 209 joint board which, frankly, is probably

         12   what we need here, where you have state and federal

         13   regulations that need to be synced up.

         14              You know, you probably don't actually have to go

         15   to the -- actually having that formal process, but that, if

         16   PJM were to internalize that approach, where states are

         17   partners and they were going to sit down and solve problems

         18   together at the very beginning, we would set an agenda that

         19   was durable.

         20              You know, we talked about restaurants before, but

         21   to me this is about when the parents are fighting we can't

         22   have a happy investment climate.  And here the parents are

         23   fighting.  They're not on the same page.  So, if we bring

         24   states and PJM together at the very beginning of the

         25   process, instead of the very end of the process, you know,





                                                                      161



          1   the children would be much better off.

          2              CHAIRMAN SWETT:  So, PJM and the states should

          3   set the agenda for the entire stakeholder process.

          4              MR. SILVERMAN:  I think on select issues.  To me

          5   there's a clear state nexus with resource adequacy, and

          6   there's a clear state nexus when you have issues of first

          7   impression such as, you know, unprecedented data center load

          8   growth.

          9              CHAIRMAN SWETT:  Uh-huh.

         10              MR. SILVERMAN:  There's not a right or wrong

         11   answer.  Right?  It really is an inherent policy choice, and

         12   I think this gets to where having the governors in there, as

         13   well as the legislators, and OPSI, because they all have

         14   three very different approaches to these kinds of issues. 

         15   So, I think bringing everyone to that table early on will

         16   just make the whole process more efficient and more

         17   durable.

         18              CHAIRMAN SWETT:  What's your reaction to that,

         19   Asim?

         20              MR. HAQUE:  Chair, there's a lot of different

         21   threads in the very initial question that you asked.  On the

         22   concept of prioritization, PJM has tried to prioritize

         23   efforts in the stakeholder process, in the past.  It has not

         24   been terribly successful.

         25              And my panelist colleagues here, fellow





                                                                      162



          1   colleagues, they're right in that we haven't tried to

          2   enforce the priorities that we set out at the beginning of

          3   the year, received feedback on, et cetera.

          4              I think because it's getting such a spotlight

          5   here, today, my hope is that if we try to enter into another

          6   prioritization effort with the stakeholders, that it will be

          7   better adhered to.  

          8              But, it does lend itself to, kind of, a few

          9   thoughts that I think we've got to sort of get clear with

         10   the stakeholders, which is if these are the priorities and

         11   you want, and inject -- you want to inject something into

         12   the stakeholder process to get worked via this problem

         13   statement issue charge framework, you know, please note that

         14   it will not get worked, you know, this year.  Even though

         15   it's your priority, it's not going to get worked within

         16   this particular frame of time where we have set our

         17   priorities for the organization.

         18              We should undoubtedly get feedback from the

         19   members and the states, when we are setting that priority

         20   list.  But that, once we have set those priorities, assuming

         21   that there is not a, you know, burning issue that has

         22   occurred within the region that we have to tackle, you know,

         23   that prioritization needs to be adhered to, and there

         24   shouldn't be an expectation that PJM and the stakeholder

         25   process team are just going to bend over backwards to take a





                                                                      163



          1   problem statement issue charge that was not already on the

          2   prioritization list and work it and have it worked within

          3   the stakeholder process.  That expectation should not be

          4   there if we are going to truly, collectively -- and I mean

          5   it -- I mean "collectively," everybody prioritize the work.

          6              The only other thing I wanted to say on this

          7   issue is it does tie into the 205 rights issue.  Okay? 

          8   Because we can prioritize the work, and for whatever reason

          9   we could be at a standstill in how to proceed, and

         10   eventually someone's going to have to make that call, of

         11   what to file.

         12              And so, if PJM did have 205 rights over energy

         13   ancillary services, planning protocol, et cetera, it would

         14   make that situation sort of at least -- I'm not going to way

         15   easier, but at least a little more clear on delineating the

         16   sort of linking authority and accountability.

         17              CHAIRMAN SWETT:  Well, you said PJM has not

         18   enforced its priorities.  Why?

         19              MR. HAQUE:  Generally speaking, our perspective,

         20   as a stakeholder team, has been that it's the members

         21   process.  They oversee Manual 34.  That is basically the

         22   bylaws for the stakeholder process.

         23              Now, everything that we do in the stakeholder

         24   process is so incredibly meaningful to the day to day and to

         25   the long term viability of the organization, and so you





                                                                      164



          1   might feel like there is a disconnect there.  Maybe there is

          2   a disconnect there.

          3              Am I confident that if, after this prioritization

          4   topic has received such spotlight here at the Commission, am

          5   I confident that PJM, it's management stakeholder affairs

          6   team could sit down with the members in the states and come

          7   up with, in 2027, "Here are our..."

          8              Because our -- listen.  Our priority, in Pam

          9   Quinlan's comments, you know, excellent, very solidly done -

         10   - our priority is, right now, resource adequacy.  Right?  I

         11   mean, if we don't have an eye towards -- if we don' have an

         12   eye towards getting more infrastructure built, and getting

         13   more supply on the system -- our priority, clearly, is

         14   resource adequacy.

         15              We've got our paper out there.  We need to drive

         16   home a solution for what the next iteration of this

         17   marketplace is going to be.  But sans that, let's say we get

         18   together and we say, a few months' process, 2027, here --

         19   you know, here are our priorities, look, we could figure out

         20   a way to try and give, you know, us more, greater,

         21   legislated or codified authority in that space, I think we

         22   can work it out with our members and our states, if we do

         23   set those priorities.

         24              Maybe it's something that we file with you all,

         25   preview with you all, so that you have a sort of -- you have





                                                                      165



          1   a glimpse, or there is light on what our gameplan is next

          2   year, so if we don't adhere to it, you know, on the

          3   collective side, you could sort of say "Hey, all of you, PJM

          4   member states, why didn't this happen?"

          5              COMMISSIONER LACERTE:  What's stopping you from

          6   doing that now?

          7              MR. HAQUE:  I don't think anything is stopping us

          8   from doing it now, and I think we should do it now.  So,

          9   commissioner, it's a very fair question.

         10              I will say, we have, like I said, we have tried

         11   these prioritization efforts in the past and they have

         12   generally failed.  But I do think that, again, you all

         13   putting a light on it will hopefully bring everybody through

         14   to getting this done.

         15              COMMISSIONER LACERTE:  But if you're a well

         16   capitalized stakeholder with a bunch of affiliates, not

         17   naming any names --

         18              (Laughter.)

         19              COMMISSIONER LACERTE: -- and if PJM says your

         20   priorities are not on this year's schedule, what's stopping

         21   them from saying "We vote no on everything until you come to

         22   the table?"

         23              MR. HAQUE:  Nothing.  But we know Arnie would not

         24   behave like that.

         25              (Laughter.)





                                                                      166



          1              COMMISSIONER LACERTE:  He's come to the table and

          2   I'll give him a large degree of deference on that.

          3              But -- so what you're saying, again here, is that

          4   the issue is one of the two-thirds vote.

          5              MR. HAQUE:  The issue -- I don't think that this

          6   particular issue is one of the two-thirds vote.  The issue

          7   is that, you know, the actual prioritization -- actually

          8   just a quick aside -- there is actually, in Manual 34, our

          9   stakeholder process bylaws, there actually is a requirement

         10   that we come up with an annual workplan.  It's actually

         11   member driven.

         12              Now, we haven't seen that process play out

         13   recently.  It's not something that we have done recently.

         14              COMMISSIONER LACERTE:  I was just going to say

         15   those work plans are not very good, if they're not...

         16              MR. HAQUE:  Yeah, that's right.  So, I think this

         17   prioritization effort is a worthwhile effort to try and

         18   undertake -- I am trying to -- I am trying to be sort of

         19   gracious with our members who, like we said -- that feedback

         20   is really important to everything that we do day to day, and

         21   I'm trying to be gracious with the states to say...

         22              COMMISSIONER CHANG:  Can I interrupt you?

         23              MR. HAQUE:  Please.

         24              COMMISSIONER CHANG:  Sorry.  Can I just try to

         25   understand this?  Are you saying that today PJM cannot work





                                                                      167



          1   with its members or stakeholders to come up with a short

          2   term, and a long term, priority list and a work plan?  Is

          3   that what you're saying?

          4              MR. HAQUE:  No, I'm not saying that.

          5              COMMISSIONER CHANG:  Okay.

          6              MR. HAQUE:  I think we can.  I think we just need

          7   to adhere to it as a collective.

          8              COMMISSIONER CHANG:  "Collective" meaning you

          9   take a leadership role, you work with your market

         10   participants, your stakeholders --

         11              MR. HAQUE:  Correct.

         12              COMMISSIONER CHANG:  -- and states inputs --

         13              MR. HAQUE:  Correct.

         14              COMMISSIONER CHANG:  And you prioritize and say

         15   "Okay, everybody, this is good.  2027 priority list."  And

         16   three year priority, one year priority, like we're going to

         17   work on these things.

         18              MR. HAQUE:  Yeah.

         19              COMMISSIONER CHANG:  Like, you can do that today,

         20   with no changes to whatever bylaw agreement, et cetera.

         21              MR. HAQUE:  We can do that today.

         22              COMMISSIONER CHANG:  Okay.

         23              MR. HAQUE:  And what I would say is we have tried

         24   to do that in the past, but we have not collectively adhered

         25   to it.





                                                                      168



          1              And one of the things that I did reference is

          2   when a member says "We want to work this issue in the

          3   stakeholder process," we say "Yes, we are going to work this

          4   issue in the stakeholder process."  That moves something

          5   else off of the priority list.

          6              And so on and so forth.  So, I do think that

          7   there -- like I said, these are sort of soft authorities. 

          8   There is no sort of true codification of this anywhere.  But

          9   I do think that the collective -- again, now that you all

         10   have shown a big bright light on it, can work together to

         11   try and create what a right prioritization framework should

         12   be, going forward.

         13              COMMISSIONER SEE:  Is that too optimistic, this

         14   idea that, you know, now that we've shown a spotlight, we

         15   can do this?

         16              MR. HAQUE:  Optimism by heart...

         17              COMMISSIONER SEE:  I guess the question is do we

         18   need a formalized process for this sort of direction

         19   setting?

         20              MR. HAQUE:  My honest answer is I don't know.  I

         21   think that, on one hand, the organization has really strong,

         22   solid, members that participate in the stakeholder process.

         23              We have all admitted, on multiple occasions

         24   today, that sometimes those interests get entrenched.  And

         25   there's nothing wrong with that, as was also said.  Everyone





                                                                      169



          1   is going to be pushing within their self-interest.

          2              But I do -- so, I do think that, that sort of

          3   lingers over this particular issue.  And so, I think I am

          4   interested, after the -- like I said, after the kind of

          5   light that you all have shown on this issue, if we can get

          6   it done, if the Commission was to say "We want to have PJM

          7   and the stakeholders prioritize work, have it be submitted

          8   to us as part of a suite of reforms that come through to

          9   PJM," then sure.  I think the codification of that would be

         10   good too.

         11              COMMISSIONER CHANG:  You know, I would say I sort

         12   of push back when the Chairman says PJM's too big to

         13   function, whatever the words are.  But I feel like, in this

         14   conversation...

         15              CHAIRMAN SWETT:  I didn't say that.

         16              COMMISSIONER CHANG:  Okay.  But this conversation

         17   makes me agree with the Chairman.

         18              (Laughter.)

         19              COMMISSIONER CHANG:  Like, are you too big to

         20   make decisions and prioritize work plans?

         21              MR. HAQUE:  No.

         22              COMMISSIONER CHANG:  Okay.

         23              MR. HAQUE:  Yeah, my response is firmly no.  We

         24   all just need to adhere to it.  And we'll see my colleagues

         25   have multiple times up too. 





                                                                      170



          1              (Laughter.)

          2              MR. HAQUE:  I'm not trying to push back.  I am

          3   curious about their opinions on this as well.  I am curious

          4   about their opinions on this.

          5              COMMISSIONER ROSNER:  Let's hear from --

          6              COMMISSIONER LACERTE:  Let's go down the line. 

          7   Okay.

          8              COMMISSIONER ROSNER:  Let's go down the line,

          9   okay.  Secretary?

         10              MS. JAWOROWSKI:  Thank you very much.  Good

         11   afternoon.  Thank you, Chairman Swett and the Commission for

         12   having me here today.

         13              Before I became Secretary of Energy and Natural

         14   Resources of the State of Indiana, I was Executive Director

         15   for Stakeholder Services at MISO, and so I see this from

         16   another perspective, and I do recognize and respect how

         17   complex the stakeholder process is, how extremely important

         18   those voices are.

         19              But I think a major issue that should be

         20   addressed is the fact that Asim said it is the stakeholders'

         21   process.  It is their process.  They are running this show.

         22              And my other colleague said, you know, when it

         23   comes to policy, this is where we need the states' input. 

         24   And so, there are a few recommendations that I might make

         25   from that observation, respectfully, and that is that I





                                                                      171



          1   really believe that the stakeholders' voices should be

          2   advisory in this.

          3              To ask a group of individuals that have different

          4   motivations to come together to create policy and 90-day

          5   plans, hundred-day plans, that are going to be

          6   comprehensive, is a really challenging task to do.

          7              The observation I made at my time at MISO was

          8   often the technical staff would create a recommendation and

          9   the stakeholders can weigh in from different committee

         10   perspectives.

         11              And so, I think that the recommendations that I'm

         12   heading towards are advisory roles for the stakeholders, for

         13   PJM itself, as an entity, to have more leadership and

         14   authority over the process, so that they can make

         15   recommendations and be more swift.

         16              Because right now we are in an unprecedented

         17   time.  I think Secretary Danly said it very well. 

         18   Everything is changed.  And what I see, from a front row

         19   seat, in a state like Indiana, is speed to electrons.  Speed

         20   to electrons.  And that is sometimes replacing former

         21   plants.  That is building new capacity.  That is our deep

         22   pocketed partners who need large load supply.

         23              And so, anything we can do to be speeding up this

         24   process will benefit the PJM footprint.

         25              And then finally, asking respectfully for a stake





                                                                      172



          1   for the governor's offices -- our offices have a broader

          2   view on policy, economic development issues, and I agree

          3   with the comments from my colleagues about having that

          4   worked in as part of the process.  Not asking to be involved

          5   in every decision, by any means.  We don't have the

          6   bandwidth or interest, I don't believe, for that.

          7              But I do think in January we came together with

          8   the 13 states on the statement of principles, and all

          9   solidly agreed on those resource adequacy perspective

         10   issues.  So I think, in summary, advisory roles for the

         11   stakeholders, a more leadership role for the board, and PJM

         12   as an organization, and a voice and a vote, as was said

         13   earlier, for the state leadership.

         14              Thank you.

         15              COMMISSIONER ROSNER:  Thank you.  Arnie, would

         16   you like to respond to Asim?  And, as you do that, I'd love

         17   to get -- as a PJM member, I'd love to get  your opinion on

         18   a couple of the things we just talked about.  Should PJM

         19   management be empowered to prioritize the issues that the

         20   stakeholder process considers over the course of the year?

         21              I'm also curious on your reaction on this concept

         22   of should the PJM board be more empowered to make decisions

         23   independently, either on some of these issues that are in

         24   the operating agreement, completely in an unconstrained way

         25   or the other idea we heard was if stakeholders fail to





                                                                      173



          1   agree.

          2              And the other question I just want to throw in is

          3   should there be a time limit on some of the stakeholder

          4   process deliberations, and should that be, you know, binding

          5   in some way?

          6              I just would recognize, you know, we just were

          7   visiting with Congress yesterday, and Congress talks to us a

          8   lot about permitting timelines and shot clocks, and you

          9   know, one of the things that Congress is often surprised

         10   about is, on the Federal Power Act, we have a 60-day clock,

         11   and I think our staff and our commission does a really great

         12   job with most of those.  Except for the very few that come

         13   back through the courts.

         14              But what you do is you staff to meet the need. 

         15   And so sometimes a deadline is helpful, so I've love your

         16   opinion on all those things.

         17              MR. QUINN:  All right.  Thank you.

         18              So, on the prioritization, I'll start with just

         19   saying we do it in almost every other ISO that we're in, and

         20   so I have a lot of confidence that it can work, as it works

         21   everywhere else we are.  And I think that is not directly

         22   related to who has filing rights or not, but I will get to

         23   that element of it.

         24              Asim is right, though, that stakeholders are

         25   going to have to be disciplined.  And in our other ISOs we





                                                                      174



          1   have to be disciplined, to recognize that once the work plan

          2   is set, yes, we are going to come to the ISO occasionally to

          3   say this is a really emergent issue and I think that you

          4   should prioritize it.

          5              And they should be open to that conversation, but

          6   we should all be disciplined in recognizing that the answer

          7   is mostly going to be no, because that's the point of

          8   prioritization, that if is a Vistra only issue, then that's

          9   something for me to bring up in the next annual plan.  If

         10   it's a Vistra and all of the other stakeholders issue, then

         11   maybe we should talk about that.

         12              But, and in PJM, we do have this issue charge

         13   problem statement that anyone can issue.  We're going to

         14   have to either become disciplined about that or reform that,

         15   because the prioritization has to be the place we do it.

         16              Commissioner See, you asked about whether it has

         17   to be a formal process.  I think the benefit of it being a

         18   formal process is that that creates another avenue for the

         19   states to have input, and so having a formal process that is

         20   run so that the states have a very known place to go, along

         21   with other stakeholders, to say "Hey, we have to -- please,

         22   these are our priorities for the next year.  Could you put

         23   those on the list, and could you please prioritize them?"

         24              At the end of the day, it does need to be the ISO

         25   that finalizes that plan and says "This is what we're





                                                                      175



          1   adhering to."

          2              COMMISSIONER ROSNER:  So, would that require a

          3   change in this Manual 34?  It sounds like it would.  But

          4   we'll go back and read it.

          5              MR. QUINN:  Perhaps.  Perhaps.

          6              COMMISSIONER ROSNER:  I had it open a minute ago

          7   here.  It's kind of long.

          8              MR. QUINN:  Yes.  Yes, that's what you'll find.

          9              (Laughter.)

         10              MR. QUINN:  On voting, or on 205 rights, what

         11   I'll say is I've heard a lot of positive things about

         12   stakeholder advisory -- and I will say, as a participant in

         13   all the other markets, in MISO and in California, where it

         14   is purely advisory, I will note that you want your ISO to be

         15   both independent and responsive.

         16              And, as we're working on the hard stuff, it's

         17   always about a set of tradeoffs.  It's never a clear action;

         18   it's always about a set of tradeoffs.

         19              Vistra has a set of tradeoffs, the things that

         20   are the most important.  My other stakeholders here would

         21   say there's another set of tradeoffs, and the ISO has to,

         22   kind of, develop the final set of tradeoffs that they're

         23   managing.

         24              In the markets where it is purely advisory, our

         25   experience is the ISO is not as responsive to our set of





                                                                      176



          1   tradeoffs, and the reality in this is mildly controversial. 

          2   Our experience in those markets where it's purely advisory,

          3   the transmission owners do get a little bit additional

          4   benefit, a little bit additional say, because they are kind

          5   of the core of that ISO.  If they leave, the ISO doesn't

          6   exist.

          7              So, I would -- I think we would be supportive of,

          8   for instance in the energy market, a time clock to get

          9   something done, and if we don't get done, then PJM has 205

         10   rights.

         11              The other idea that we talked about in our

         12   comments was the New England stakeholder -- or New England

         13   jump ball.  Again, I don't think most of our problems are

         14   about filing rights, and I think filing rights are going to

         15   be controversial and are going to take a lot of time.

         16              COMMISSIONER ROSNER:  Yeah.

         17              MR. QUINN:  We do like the jump ball process

         18   because it disciplines the process.  It makes the ISO more

         19   responsive because they know the stakeholders.  If it's not

         20   just a Vistra issue, if it's a 60 percent of us issue, we

         21   are going to come up with an alternative so that gives the

         22   ISO more incentive to listen.

         23              And I will note that in ISO New England the

         24   states have a very central role in that process.  If you

         25   want to get a 60 percent vote, the best place to do that is





                                                                      177



          1   to go talk to NESCO and see if they agree with you and you

          2   can collectively find a coalition, and that's just a very

          3   positive dynamic.

          4              COMMISSIONER ROSNER:  Thank you.

          5              COMMISSIONER LACERTE:  A following up question. 

          6   So, your concern is over responsiveness within the RTO, and

          7   those concerns, you're saying, would be alleviated by a jump

          8   ball process?

          9              MR. QUINN:  I think they are.  I think they're --

         10    again, I think all of the -- to start with, all of the

         11   ISOs, the staff are all excellent, they're all public

         12   service minded, they're all completely well intentioned.  It

         13   is simply a power structure.

         14              COMMISSIONER LACERTE:  Yeah.

         15              MR. QUINN:  It is the question.  And, for us,

         16   having the jump ball there balances the power.  So that the

         17   responsiveness is improved.

         18              COMMISSIONER LACERTE:  And I understand your

         19   point on the responsiveness and the level of participation

         20   and them, you know, heeding your call.  But respectfully,

         21   the other ISOs aren't running a massive capacity deficit,

         22   and we're more and more worried about that, these days.

         23              MR. QUINN:  I am not sure that's true.

         24              COMMISSIONER LACERTE:  Well, not to this level. 

         25   Perhaps a smaller level.





                                                                      178



          1              MR. QUINN:  I don't know.  I think California --

          2   I mean, they're all my best friends.

          3              (Laughter.)

          4              COMMISSIONER LACERTE:  We're not going to solve

          5   California's problems today, but noted.  I want to make sure

          6   we have time.

          7              MR. QUINN:  All right.

          8              COMMISSIONER ROSNER:  And, Arnie, you know, I

          9   appreciate the view there.  You know, again, I don't have a

         10   preferred outcome on time clock, jump ball.  I mean, I think

         11   the thing that I'm hearing is that, with the two-thirds

         12   majority required, 34 percent of the folks in the

         13   stakeholder group can stop a process from happening.

         14              And the thing that I think I would like to see

         15   unfold here is more compromise happen in the stakeholder

         16   process before it has to go to the board.  And so that's, I

         17   think, a really important goal, and I think the question

         18   that I'm searching for especially member input on is "What

         19   are ways that we can turn the dial, to get more of a real,

         20   you know, need to agree, and an opportunity for excellence

         21   in the stakeholder process so we don't have to go to the

         22   board."

         23              But I also do think that having the independent

         24   board and having those tools is important, but I -- and

         25   you've just laid out some of them, but I just wanted to say





                                                                      179



          1   that in response to your comment.

          2              MR. QUINN:  No, I appreciate that.  And I should have

          3   also noted that at the end of the day we're not here because

          4   the energy market in PJM isn't working well.  We're here

          5   because the capacity market is challenged.  And that is a

          6   part of the tariff for which PJM has 205 rights today.

          7              So, in that sense, stakeholders are already

          8   advisory, in that sense.  And, for me, that is...

          9              COMMISSIONER ROSNER:  But Arnie, you know, I just

         10   see those two things as inextricably related, and so we are

         11   asking PJM to make changes to one without being able to have

         12   the autonomy to do the other.  And so I just -- I hear you

         13   but also there's a constraint here.

         14              MR. QUINN:  I think that's fair.  I do think that

         15   if I try to identify why the PJM capacity market is

         16   challenged, it does come back to a lot of the nuts and bolts

         17   stuff that we're talking about, where we haven't prioritized

         18   it because we've been working on so many other things --

         19              COMMISSIONER ROSNER:  Yes.

         20              MR. QUINN:  -- that we've been distracted from

         21   the thing that's right in front of us.

         22              COMMISSIONER ROSNER:  All right.  Well, we could

         23   keep going down the line, or other commissioners, please.

         24              CHAIRMAN SWETT:  Let's continue down the line.

         25              COMMISSIONER ROSNER:  Yeah.  The folks that are





                                                                      180



          1   waiting, yeah.

          2              MR. LIEBERMAN:  Thank you.  So, a few things. 

          3   Well, yeah, a few things.

          4              So, one of them is, you know, the board can

          5   prioritize issues today.  In fact, they do that.  PJM talked

          6   a little bit about that in the first panel, with the connect

          7   and manage and the backstop process.  That was a board

          8   initiated thing.  They said "Hey, we're going to do this and

          9   we're going to do it now.  And it's going to wrap up by this

         10   date."  And that date was June 30th.

         11              So, the board was in a position to prioritize an

         12   issue, outline the schedule, schedule the meetings, which

         13   ultimately led to a vote, and now we're waiting, as PJM

         14   announced I guess, 72 hours they'll file something.  So,

         15   that's an example.

         16              But another thing to note, and I'm sorry I don't

         17   remember where it is, if it's in the manual or which

         18   governing document, but these senior task forces and the

         19   like, they actually do have a lifespan, and it's a two year

         20   thing.  So, after two years you have to go back and say

         21   "Hey, you know, 'Mother, may I have another?'"

         22              But what is supposed to happen is after two years

         23   it ceases to continue working.  And that may not be enforced

         24   today but that doesn't negate the fact that that rule

         25   exists.





                                                                      181



          1              And I just wanted to also remind -- I mean, we

          2   talked, you know, about getting the governors more involved. 

          3   The governors did announce, and I'm looking for my notes, a

          4   PJM governor collaborative.  They announced this in

          5   September of last year.  It was signed by, I think 11 of the

          6   13 PJM state governors.

          7              So, the governors have gotten together, and they

          8   explained how they're going to get more involved and, you

          9   know, I think that's a great thing.  I'm not sure that we

         10   have to do more.  I mean, they've already said that they are

         11   going to do something.

         12              But an example, also, of where it can be

         13   difficult, you know, where we come out with a work plan and

         14   we say "Okay, that's the work plan for the year," is, you

         15   know, if the White House does -- you know, like today,

         16   they're going to announce the rate payer protection pledge. 

         17   I don't know if it's 2.0 or just people, more people, are

         18   signing onto it.  I was a little confused.

         19              But depending on what comes of that, you know, we

         20   may have a fresh crop of work that we need to reprioritize

         21   our existing work.  So, we've got it.  We should have a work

         22   plan.  But it shouldn't necessarily be set in stone.  We

         23   have to recognize that Arnie might have an issue, and it is

         24   really pressing, and maybe we do need to talk about it

         25   sooner than later.  Thank you.





                                                                      182



          1              CHAIRMAN SWETT:  Kent?

          2              MR. CHANDLER:  Yeah, I'll speak quickly on this

          3   in hopes of maybe getting asked another question later.

          4              (Laughter.)

          5              MR. CHANDLER:  So, I do think -- Arnie alluded to

          6   it -- but I do want to put a finer point.  I don't think

          7   they're -- sort of channeling Thomas Sowell, like there are

          8   no solutions; there are only tradeoffs.  This idea that

          9   we're going to get an answer to this or an answer to that;

         10   it's just going to be a matter of tradeoffs.

         11              So we're going to give up things as we move or

         12   transition or do things differently.  But this idea that a

         13   lot of this prioritization can't just be done by the board

         14   is not something that I adhere to or believe.  There is

         15   nothing keeping the board from meeting with OPSI right now,

         16   for instance, and sitting down and talking about the next

         17   one in three years of joint goals or prioritization.

         18              And then, there's nothing in Manual 34 that keeps

         19   PJM from identifying how they want to use their internal

         20   resources towards prioritization.

         21              One thing I've learned from CPCNs and shot clocks

         22   and being a recovering state regulator is that just because

         23   you have a statutory deadline that's not when the work

         24   starts.  It's when it starts for the regulators.  But

         25   usually the applicant has done a lot of work ahead of





                                                                      183



          1   starting the process or filing an application.  Right?

          2              So, there's nothing to say that if there's a shot

          3   clock or a timeline on a stakeholder process that that's

          4   when PJM has to start working on it, for the -- a straw

          5   proposal or to start running numbers on certain items. 

          6   Like, they could be doing a lot of this work behind the

          7   scenes, prior to initiating a proposal or bringing it to

          8   stakeholders, and then the time-limited part could be the

          9   engagement with, sort of, the outside world.

         10              CHAIRMAN SWETT:  So, what do you think the

         11   biggest problem is, and what's the solution?

         12              MR. CHANDLER:  The biggest?  (Laughs.)  How much

         13   time do we have?

         14              CHAIRMAN SWETT:  Two minutes.

         15              (Laughter.)

         16              MR. CHANDLER:  Yes.  So, what is the biggest

         17   problem, and the solution on the stakeholder process front? 

         18   I think it's -- I do think it goes back to who has the power

         19   to act. 

         20              I mean, you know, I put this in my comments, but

         21   I think to a certain extent some of the solution lies here. 

         22   Some of the solution lies within stakeholders, of just

         23   mutually agreeing to do things differently.  Frankly, a lot

         24   of it, I think, is things the board can do unilaterally.

         25              I think, for one, folks need to be prepared to be





                                                                      184



          1   occasionally told no.  I see a lot of the issues that stem

          2   from this is actually a lot of, just like, folks upset

          3   because they don't necessarily win on a particular issue and

          4   the easiest way to effectuate change from that is to throw

          5   up your hands and say "Oh, I lost.  That must mean

          6   everything is wrong."

          7              I think that setting things up like a

          8   prioritization, I think that a big solution is telling

          9   people what the consequences of not following through on the

         10   prioritization is, so that everybody knows the rules to

         11   start the game.  PJM has not done a great of that.

         12              I remember, a long time ago, like seven years

         13   ago, PJM, the board told everybody "If you don't fix the

         14   energy market we're going to, this is what our filing is

         15   going to look like."

         16              The members couldn't come to agreement.  PJM

         17   showed up at FERC with a proposal that did not look -- that

         18   did not adhere to what they told stakeholders it would look

         19   like if they didn't come to agreement.

         20              So I think a lot of it is just having

         21   transparency and conveying expectations early, and then

         22   holding each other accountable to the outcomes.

         23              CHAIRMAN SWETT:  So, PJM should threaten the

         24   stakeholders more with concrete filings?

         25              (Laughter.)





                                                                      185



          1              MR. CHANDLER:  I think that there should be clear

          2   expectations going into -- I mean, "threat" is probably a

          3   strong term but, you know, "eye of the beholder."  I think

          4   there should be expectations and folks, I don't know, the

          5   chips fall as they may.  You say "This is what we're going

          6   to do."

          7              And I think the same thing for FERC, right?  It's

          8   like we're not going to hear sore -- the commissioners

          9   saying "We're not going to hear from sore losers.  Just

         10   because it didn't work out your way, we're not necessarily

         11   going to be a sympathetic ear."

         12              I also think this idea that you can't

         13   reprioritize prioritization, based off of, like, ad hoc

         14   needs or emergency is, I don't know, I just don't believe in

         15   that. 

         16              I think that if the vast majority of stakeholders

         17   agree, they should be able to, like, redo the

         18   prioritization.  Or, if folks agree that it's a pressing

         19   issue and it's not going to be prioritized, show up here

         20   with a 206.  I mean, that makes you all's job a little bit

         21   harder but, you know, heavy is the head...

         22              CHAIRMAN SWETT:  We can do it.  Pamela?

         23              MS. QUINLAN:  So, I agree with a lot of what

         24   everyone's saying, and I think there's a lot of agreement on

         25   this panel about some of the challenges here, on





                                                                      186



          1   prioritization.

          2              And to exactly what you're saying, yes, I think

          3   it's not just prioritizing; it's prioritizing with action

          4   coming.  Right now, if you are benefiting with the existing

          5   rules, you have a really strong incentive to delay the

          6   entire process, because the existing rules work for you.

          7              And no one wants to compromise off of what

          8   they're going to litigate, if they think that they can win

          9   at the end.  So, if you know that there is going to be a

         10   filing coming, and you say -- and this isn't getting into

         11   whether or not there needs to be expanded 205 rights, because I tend to

         12   think we're not using the legal authority that they have

         13   today.  Today they can say "I'm going to make a 205 filing

         14   under -- for resource adequacy issues," or "We'd like to see

         15   a 205 filing made with stakeholder support, but this is a

         16   big enough issue, and we will bring it to FERC with a 206. 

         17   Here is the timeline in which we are setting to evaluate

         18   this, and if you can't compromise, we're going to do what

         19   PJM thinks is best and file that with the Commission."

         20              And during that time period they have told FERC

         21   "This is what we're doing.  Here is the update for it," so

         22   nothing's a surprise to anybody.  And that doesn't require a

         23   single change.  That's just leadership and how we're

         24   executing.  And that will drive compromise, because people

         25   will compromise if they think that they're going to lose





                                                                      187



          1   something if they don't.

          2              But there's going to be some things that people

          3   will never agree upon, and that can't be the -- it's like

          4   consensus can't be the prerequisite for leadership.  You

          5   have to lead, even when people do not come to agreement,

          6   because that is undoubtedly true, and it's particularly true

          7   when it comes to issues of resource adequacy.

          8              Going back to Secretary Danly, you asked the

          9   question of who has the responsibility.  I spent some time

         10   in my comments talking about this because I think until we

         11   fix that specific issue, related to resource adequacy, the

         12   stakeholder process will not be freed up to actually work on

         13   the largest value proposition that PJM brings to these 13

         14   states, which for my view is the IT SCED, that's the

         15   security constraint security dispatch and long term

         16   planning, and if we keep fighting over resource adequacy

         17   decisions that the stakeholders did not make and cannot

         18   change, if states can sign up new loads without a plan to

         19   serve it or force early retirement with a plan to replace

         20   it, and we are trying to figure out how to change a market

         21   to undo that, we can't do that, as a stakeholder body.

         22              So, that needs to be fixed.  There's probably

         23   multiple ways to do that.  And I think, to Commissioner

         24   LaCerte, your point about PJM being -- comparing to other

         25   markets -- that, to me, is where PJM is really different. 





                                                                      188



          1   It's the only region that relies upon a centralized capacity

          2   market to solve resource adequate, where there's load growth.

          3              And that's never really been tested before, and

          4   we can talk -- like, when we put the RPM together in the

          5   first place, when we started this, and I started my career

          6   and we were talking about the RPM and it was coming to be

          7   new in PJM, and have seen it through many different phases,

          8   the realities that underpin the assumptions of why that

          9   would work are just not true anymore.  And that has to do

         10   with, like, a lot of things that are outside of

         11   stakeholders' control, for sure, outside of FERC's control

         12   as well, and we have to think about how we actually can fix

         13   the largest challenge we have right now, which is "Why don't

         14   we have enough infrastructure?"  And there is no governance

         15   rule change that I think we can do to change that.

         16              But I do think we need to act more quickly, and I

         17   think the best way to get people to compromise on things

         18   that are achievable is to actually threaten them with action

         19   if they don't.

         20              So, thanks.

         21              COMMISSIONER LACERTE:  I think in our comments to

         22   the technical conference here, I expect to hear all of the

         23   multiple ways in which we can fix it.  Submitted within 30

         24   days by you.  So, I appreciate that.

         25              CHAIRMAN SWETT:  Abe?





                                                                      189



          1              MR. SILVERMAN:  Yeah, I'm actually going to

          2   largely dovetail with that.  You know, the one thing you

          3   will not find in Manual 34 is a sense of urgency.  And I

          4   don't know where that urgency comes from, other than

          5   leadership.

          6              Interconnection.  It took us how many years to

          7   get that done?  Large load growth.  Billions of dollars were

          8   getting transferred for every day of delay and yet we're a

          9   year into a process with no, really, end in sight.

         10              These are fundamental problems.  And I think that

         11   leadership needs to come from PJM and it needs to come from

         12   this commission.  And I think we need to act to empower

         13   PJM's staff, because it's a wonderful staff, but I often

         14   feel bad criticizing PJM because they're wonderful,

         15   dedicated people.

         16              I think the things that we can do, largely talked

         17   about in the earlier panel, independence for the board, so

         18   that they're not afraid to make tough decisions, more

         19   transparency, and then, again, coming back and getting the

         20   governors, OPSI, and the legislators bought in.  Because, if

         21   we get all the principals, all the sovereign stakeholders,

         22   aligned, on a direction, then PJM can just move a lot

         23   faster.

         24              But, you know, that's just -- that sense of

         25   urgency, it's just -- you're not going to find it in Manual





                                                                      190



          1   34, and we can't be in the situation where issues like

          2   interconnection fester for years.  The fact that we're not

          3   holding auctions on time.  So, thinking about "How do we

          4   align the board structure so they can act?"  And I do think

          5   that is 205 filing rights for states at the end of the day,

          6   so there is some enforcement mechanism.  But it's also

          7   giving PJM more authority, and insulating that board from,

          8   you know, stakeholder concerns, when they don't like the way

          9   the answer is going.

         10              But sometimes it is more important to make a

         11   decision than that the decision be the platonically correct

         12   or best outcome.

         13              COMMISSIONER SEE:  And I think that's important,

         14   because this has been a really helpful conversation about

         15   what we can do now and what we can do through a formal

         16   process to set priorities.  I think that's been really

         17   great.

         18              But that's one part of it.  Right?  Because where

         19   we started this panel is "How do we work those priorities,

         20   and dealing with complexity and time?"

         21              It seems like one of the things that's been on

         22   the table from a number of you is let's have deadlines that

         23   have teeth.  So I guess I've got two questions.  The first

         24   is "Is that something that PJM can do now, or does that

         25   require changes?  Can there be enforceable deadlines on this





                                                                      191



          1   action?"  And then, what else would be on that list?

          2              Now, we started with, you know, reevaluating the

          3   committee structure.  Do we need to do that as well?  Is

          4   this just really a time and a deadline issue?

          5              So, I'm not sure who to address that one to, so

          6   whoever wants to jump in.

          7              MR. SILVERMAN:  I'll just start.  I mean, part of

          8   the problem when we talked on Manual 34 was this idea that

          9   it's a member organization.

         10              COMMISSIONER SEE:  Uh-huh.

         11              MR. SILVERMAN:  And again, you know, PJM needs to

         12   step up and set that agenda.  It would be much faster.  And

         13   then do it with real input from the states.

         14              CHAIRMAN SWETT:  Uh-huh.

         15              COMMISSIONER LACERTE:  I really like Kent,

         16   Pamela, and Abe's answers to the tail end of going down the

         17   line there, and I think you make a good point.  I think Kent

         18   said that PJM doesn't utilize the authorities it has as

         19   much.  And Kent and Pamela both said that they need to

         20   engage more with the states, and they don't.

         21              And I think the reason why that doesn't happen

         22   now is a culture issue in PJM, and the cultural issue, I

         23   don't see us getting around this without breaking the chains

         24   of making the stakeholder process advisory.  

         25              I think that I've never had, in my entire life,





                                                                      192



          1   sometime tell me they were afraid of fired, before, until

          2   the PJM board.  And I've worked in the White House!

          3              (Laughter.)

          4              COMMISSIONER LACERTE:  So, it's just I don't know

          5   how to get around it without making breaking the system up,

          6   to where the board is empowered to get a backbone.  And I

          7   think -- you know, I appreciate the Chairman's comments, and

          8   Judy's comments about PJM being too big to function,

          9   perhaps.  But to me it's just question of nerve, and

         10   backbone, and strength, and this is a cultural quagmire that

         11   they've developed by eroding the board in the past and

         12   creating this fear of being terminated, to where they're not

         13   using their authorities, they're not engaging with the

         14   states, because they don't want to get out of line with what

         15   the stakeholders want.

         16              And that is a fundamental problem of culture in

         17   PJM, and I don't see a way around it by keeping the status

         18   quo.

         19              MR. HAQUE:  Commissioner, I just wanted to

         20   comment on -- look, I think we are certainly in a different

         21   moment today than we have been in our history.  For sure. 

         22   What we are seeing, the external forces that we're seeing,

         23   are incredibly dynamic, and I don't think we can do business

         24   as usual.

         25              So, I am with you on that.  We've talked about





                                                                      193



          1   board independence.  We've talked about the lengthening of

          2   board terms.  We've talked about 205 rights.

          3              On the engagement with the states, I think it's a

          4   good topic to explore.  We do a lot of engagement with our

          5   states.  A lot.

          6              Of course, that world has evolved quite a bit. 

          7   It used to just be we would interact with OPSI.  Now it's

          8   governors' offices, energy offices, legislators, and all of

          9   which  bring, sort of their own unique spin to, you know,

         10   what their particular perspective is.

         11              Look, I think that we're -- and getting back to

         12   the stakeholder process, we, for a long time, have tried to

         13   -- if the stakeholder process is the venue where stuff gets

         14   done, we have tried to encourage OPSI in particular's

         15   engagement in the stakeholder process.  Okay?

         16              I think, after a few years on this job, I will

         17   tell you, it really does feel like trying to fit a square

         18   peg into a round hole.  For a variety of reasons.  Namely,

         19   like we've talked about, the sheer volume of meetings, it's

         20   hard, I think!

         21              I'm a former state regulator myself.  It's hard,

         22   when you have a day job, to go sit in a jillion stakeholder

         23   meetings and monitor them, and participate in them.  It's

         24   not an easy task.

         25              And so, what we have started to do with our





                                                                      194



          1   states, and the real proof will be in the pudding on this

          2   market reform issue, is we've basically started to do

          3   parallel tracks with them.  Not just keeping them informed

          4   about what's going on in the stakeholder process.

          5              But, to Judge Bagot's point this morning, for

          6   instance Order 1920, we said "We're going to work this issue

          7   with you," because this is so central to -- this long term

          8   planning framework is so central to the states, and you all

          9   put them in sort of a driver's seat there as well.

         10              So, we worked a separate track with them, were

         11   able to get them to get them to a point where they felt

         12   really good about the framework that we are advancing

         13   together.  We're going to do the same on the market reform. 

         14   That is the biggest, sort of, thing.

         15              Look, on the PJM front, I appreciate all the

         16   praise that's been given to PJM's staff.  They're certainly,

         17   sort of, the kind of -- everything in the PJM sphere that

         18   has gone from, you know, whether it's criticism or whatever

         19   it is, that has gone from boutique to mainstream.  Okay?

         20              I don't see it in Valley Forge.  I really don't. 

         21   I see a lot of dedicated staff who are running day ahead and

         22   real time markets, planning the system, processing queue

         23   requests, operating the power grid in the control room when

         24   we were at an all-time peak a few weeks back.  Okay?

         25              And I think we made a lot of progress.  Queue





                                                                      195



          1   backlog cleared, we're advancing long term planning, refined

          2   load forecasting, connect and manage and the backstop are

          3   going to be submitted to you.  David said 72 hours.  I want

          4   to clarify that's 72 business hours.

          5              (Laughter.)

          6              MR. HAQUE:  And then -- and then -- the thing we

          7   need to focus on, the big thing, the big ticket thing -- and

          8   again, I'm going to praise Pam Quinlan and her comments; I

          9   thought they were excellent -- is how are we going to get

         10   infrastructure built, ultimately?

         11              COMMISSIONER CHANG:  Can I interrupt?

         12              MR. HAQUE:  Please.

         13              COMMISSIONER CHANG:  And you brought up a segue

         14   here, because we have seven minutes.

         15              MR. HAQUE:  I'm so sorry.

         16              COMMISSIONER CHANG: And I want to -- sorry, I

         17   know there are many cards -- but it's getting really crystal clear,

         18   to me, like, what needs to happen.  I'm not going

         19   to articulate it right now, but I do want to ask you a

         20   question.

         21              MR. HAQUE:  Please.

         22              COMMISSIONER CHANG:  Which is, back to the --

         23   you know, there's the culture issue, there is sort of

         24   setting priorities, et cetera.

         25              But I want to get back to the filing rights





                                                                      196



          1   because that's something specific.

          2              MR. HAQUE:  Yes.

          3              COMMISSIONER CHANG:  What -- Pamela mentioned --

          4   look, we have an urgent thing.  It's resource adequacy, and

          5   PJM has filing rights on capacity market, or resource

          6   adequacy.  So, that shouldn't be a hurdle.  Like, you

          7   already have filing rights.

          8              My question to you is:  Is that true?  Because,

          9   to me, the resource adequacy problem is not only whether the

         10   capacity market parameters are correct, whether ELCC is

         11   correct.  To me it's the interconnection process, it's the

         12   transmission planning process, which I think the states need

         13   a role and a voice in.

         14              And so, my question to you is:  Is there a 205

         15   filing right issue associated with solving the resource

         16   adequacy problem?  But really, it ties into the

         17   interconnection process and planning process, which PJM does

         18   not have 205 filing rights.

         19              MR. HAQUE:  I think that -- and, Commissioner,

         20   are you asking specifically about a 205 filing opportunity

         21   for the states?  Is that what you're asking about.

         22              COMMISSIONER CHANG:  Well, I just want to know if

         23   anything needs to change, to solve the resource adequacy

         24   problem, because I don't think it's just like "Oh, PJM has

         25   resource adequacy filing rights, so they should just be able





                                                                      197



          1   to solve it right now."  That's my question.  What needs to

          2   change, to solve the resource adequacy?  Specifically on

          3   205.

          4              MR. HAQUE:  Well, first of all, I do -- yeah,

          5   look, if we are going to be accountable for all things, I

          6   think giving PJM the authority, as the grid operator for 67

          7   million consumers, and the largest grid operator, 205 rights

          8   over all of its core business functions makes sense.

          9              COMMISSIONER CHANG:  Including transmission

         10   planning and --

         11              MR. HAQUE:  Including transmission planning.

         12              COMMISSIONER CHANG:  -- and all the parameters

         13   associated with transmission planning.

         14              MR. HAQUE:  Yes.  I believe it's schedules one...

         15              COMMISSIONER CHANG:  And interconnection

         16   agreements, interconnection processes.

         17              MR. HAQUE:  Yes, Commissioner.  I think in the

         18   operating agreement it's schedules one, two, six, 6A, and

         19   6B.

         20              COMMISSIONER CHANG:  Okay.

         21              MR. HAQUE:  That are in the operating agreement

         22   right now.

         23              COMMISSIONER CHANG:  That's how I think about

         24   this, but I wanted to hear from PJM.

         25              CHAIRMAN SWETT:  Kent's been waving his card.





                                                                      198



          1              MR. CHANDLER:  Yes, for being quiet for 50

          2   minutes, I'm so aggressive now.

          3              (Laughter.)

          4              MR. CHANDLER:  I think that's the first half of

          5   it.  So, in my comments, I think I would reiterate, two

          6   years ago the vast majority of OPSI commissioners advocated,

          7   or agreed that the PJM board should have 205 rights over the

          8   regional transmission expansion plan; they just objected to

          9   the way it was proposed to be moved to the board from the

         10   members.

         11              But there was agreement amongst the states that

         12   the board should have those 205 rights.

         13              I think that is only part of the answer to your

         14   question.  I still think that just the board having those

         15   205 rights doesn't fundamentally change the way regional

         16   transmission planning is done in PJM, and I don't think you

         17   will get the optimal level of regional transmission planning

         18   in PJM, which is a significant hurdle to getting new

         19   capacity online, until and unless you fix the independence

         20   issue with -- in some way with -- voluntary RTO membership.

         21              And I think the fact that transmission owners in

         22   PJM and in any RTO can effectively threaten or say they're

         23   going to leave the RTO if they don't get their way, and

         24   effectively take the backbone of the RTO with them, given

         25   their inherit capital bias to invest in transmission, and





                                                                      199



          1   the benefits of regional transmission planning, and leading

          2   to more cost effective transmission investment rather than

          3   utility by utility investment, leads to sub-optimal outcomes

          4   in regional transmission planning, whether the board has the

          5   205 rights or not.

          6              COMMISSIONER CHANG:  So it's essential but not

          7   sufficient.  Okay.

          8              CHAIRMAN SWETT:  Do you think that PJM can

          9   transfer the RTEP protocol to the tariff on its own, or is it

         10   perpetually beholden to the TO's control?

         11              MR. CHANDLER:  I believe that...

         12              CHAIRMAN SWETT:  And I'd like to hear from Asim

         13   after this.

         14              MR. CHANDLER:  I believe that the transmission

         15   expansion, the RTEP protocols, can be transferred from the

         16   operating agreement to the tariff or to the board, through a

         17   Section 206 filing, whether it's Sua sponte by the

         18   Commission or through a complaint under Section 206.  There

         19   are likely conforming changes that would need to be made to

         20   other governing documents, but they are in them -- those

         21   other governing may or may not have all the Sierra

         22   provisions, et cetera.  (Laughs.)

         23              I think there would need to be conforming changes

         24   to other governing documents, but those, themselves, don't

         25   have to have the 206 complaint file against them.





                                                                      200



          1              CHAIRMAN SWETT:  Okay.  And Asim, we'll give you

          2   the last word here.

          3              MR. HAQUE:  Agree.  I agree with Kent on that.

          4              CHAIRMAN SWETT:  Okay.  That was easy.  All

          5   right.  Well, I don't -- who had their flag up first? 

          6   Because we've got 2-1/2 minutes.  Secretary.

          7              MS. JAWOROWSKI:  Thank you very much.  I wanted

          8   to first make one note, that in the first panel Jacob Finkel

          9   was here on behalf of the governors' collaborative, and I

         10   was also asked to be here on behalf of the governors'

         11   collaborative.  So, that organization has been very active

         12   in a lot of recommended solutions.

         13              Also, I want to say I completely agree with you,

         14   Commissioner LaCerte.  It's a culture issue that needs to be

         15   changed and shift, and the power is with the stakeholders

         16   right now, and having an advisory, non-binding, stakeholder

         17   engagement would -- and then giving the power to PJM and the

         18   board is essential for change.

         19              We also believe that the governors should have

         20   some input that is voting, and an opportunity for a veto on

         21   operational agreements and resource adequacy matters.

         22              But, another note I'd like to make is -- I made

         23   it in my testimony that was written, and that is the at MISO

         24   the short term incentives are something that is built into

         25   the culture there.  People know that there are seven





                                                                      201



          1   categories of goals that the organization is working towards

          2   all the time.  All the staff know that.  All the board know

          3   that.

          4              The board then ranks the organization on how well

          5   they're going after those priorities and achieving those,

          6   and then there are bonsuses given out to the staff based on

          7   that.

          8              It is a very effective tactical tool to ensure

          9   the priorities are right in line, and the board and the

         10   staff have the authority to do that.

         11              The stakeholders are well respected.  The staff

         12   does not like to go against stakeholder recommendations, but

         13   they will when it comes to affordability and reliability,

         14   and they have the authority to do that.  So, I think that's

         15   an essential part of why MISO is operationally sound.

         16              CHAIRMAN SWETT:  Thank you for bringing us back

         17   to first principles, and thank you all for your time, and

         18   the very thorough preparation.  This has been very riveting,

         19   and going against the stereotype of a tech conference.

         20              COMMISSIONER LACERTE:  I've got a final question

         21   for Steve I didn't get to ask yet.

         22              CHAIRMAN SWETT:  Oh, please.

         23              COMMISSIONER LACERTE:  So, do you believe that

         24   the sou chefs should have two-thirds voting rights authority

         25   over the chef?





                                                                      202



          1              (Laughter.)

          2              MR. LIEBERMAN:  No.

          3              COMMISSIONER LACERTE:  Good answer.

          4              (Laughter.)

          5              CHAIRMAN SWETT:  Thank you all.  We have -- and

          6   go ahead.

          7              MS. EYOCKO:  All right.  Thank you, Chairman, and

          8   commissioners, and thank you to panelists.  We have reached

          9   the end of this panel.  We will now take a 15-minute break. 

         10   I believe it's 2:15.  So, please come back here at 2:30. 

         11   Thank you very much.

         12              (Brief recess.)

         13   PANEL III

         14   2:31 p.m.

         15              MS. EYOCKO:  Welcome back, everyone.

         16              As a reminder, the first two rows are reserved

         17   for all the panelists.  And next door, in the hearing room,

         18   there is additional seating.  All right, let's get started.

         19              Again, my name is Stefania Eyocko, and I am from

         20   the Office of the Energy Market Regulation here at the

         21   Commission, and we are going to begin the final portion of

         22   the second panel, which will be similar to earlier, a

         23   conversation with energy representatives, that will examine

         24   how the PJM stakeholder process, including established

         25   sectors, committees, voting structures, affects the RTOs'





                                                                      203



          1   ability to take necessary and timely actions, including

          2   Section 205 filings, to address the region's operational and

          3   market challenges.

          4              As a reminder, panelists did submit an advanced

          5   statement that includes their position, and so, to maximize

          6   the amount of time for discussion, we will be foregoing

          7   opening remarks from the panelists and go directly to

          8   questions from the commissioners and the chairman.

          9              Panelists, to answer a question from the chairman

         10   or the commissioners, please tip your name tent like so, and

         11   when you're called upon please turn your microphone on with

         12   the gray button at the base of the microphone in front of

         13   you.  You will know your mic is on when the LED light is

         14   glowing green.

         15              As a reminder from earlier, we do not intend to

         16   discuss at this technical conference any specific proceeding

         17   before the Commission, and we ask that panelists similarly

         18   refrain from such discussion.  If anyone engages in these

         19   kinds of discussions, my colleagues from the Office of

         20   General Counsel will interrupt the discussion to ask the

         21   speaker to avoid that topic.

         22              And now, for the panelists.

         23              We first have Dave Anders, the Senior Director of

         24   Stakeholder Affairs in PJM.

         25              We have Glen Thomas, President of PJM Power





                                                                      204



          1   Providers Group.

          2              We have Jodi Moskowitz, Vice President of

          3   Regulatory Law and Deputy General Counsel and RTO Strategy

          4   Officer with the Public Service Enterprise Group,

          5   Incorporated.

          6              We have Jameson TWEEDIE, Public Advocate for the

          7   Delaware Division of the Public Advocate; Mason Emnett,

          8   Senior Vice President for Public Policy at Constellation;

          9   Brian George, Senior Lead for U.S. Energy Markets, at

         10   Google; Susan Bruce, Counsel for the PJM Industrial Customer

         11   Coalition, and finally we have Dr. Joe Bowring, who is the

         12   President of Monitoring Analytics and independent market

         13   monitor for PJM.

         14              Chairman, please take it away.

         15              CHAIRMAN SWETT:  Thank you for being here,

         16   everyone.  I am expecting a spicy discussion to take us home

         17   for the day.  We're going to continue our Supreme Court

         18   style here, but the chief justice will be Commissioner See

         19   for this panel.

         20              (Laughter.)

         21              COMMISSIONER SEE:  Great.  Thanks for the

         22   promotion.

         23              (Laughter.)

         24              COMMISSIONER SEE:  All right.  We're going to

         25   bring it home strong, for the last panel of the day.





                                                                      205



          1              Brian, I'm going to start with you.  It is a very

          2   easy question.  So, you're not a PJM member, but you have

          3   significant financial stakes in PJM.  You've also been

          4   sitting here all day.  You've heard a lot of proposals that

          5   are on the table.

          6              So, I want to start focusing things a little bit. 

          7   You know, we've heard some of them that PJM could enact

          8   tomorrow.  We've heard some of them that are obviously going

          9   to take some more time, to go through a process.

         10              So, from your perspective, what are the proposals

         11   that will give us the highest value add, and kind of, how do

         12   you discount that, based on the time that some of those

         13   solutions are going to take?

         14              MR. GEORGE:  Yeah, well thank you, "chief

         15   justice" See, for the question.

         16              (Laughter.)

         17              MR. GEORGE:  And thank you, Chair and

         18   commissioners for the invitation.

         19              So, you know, I think, as you articulated, we've

         20   made a tremendous bet on this market, as we have many other

         21   markets in the U.S.  We have billions of dollars of capital

         22   that have already been invested in the region.  Right?  And

         23   we have operating data centers across the footprint, and we

         24   continue to add to that fleet, as we grow.

         25              And so, the ability to serve those sites, to





                                                                      206



          1   serve our customers, to serve our demand reliably, is

          2   critical to our ability to grow and continue to provide the

          3   services that we all use.

          4              And so, I think, when it comes to the PJM

          5   process, what I've heard today, the discussion I've heard, I

          6   think someone mentioned it really well, on the preceding

          7   panel, which is consensus is not a prerequisite for

          8   leadership.  Right?

          9              At the end of the day, we know that PJM has 205

         10   filing rights over the capacity market, and we know the

         11   central issue in front of us is resource adequacy.  Right? 

         12   And we know that PJM can act on the things that it wants to

         13   do to fix that problem.

         14              I think over the past year -- right? -- we've

         15   seen various, well two specifically, CIFP processes -- that

         16   we, as Google, have been very engaged in from the beginning. 

         17   Despite being a non-member of PJM, we've worked with other

         18   members, and other non-members of PJM, to build consensus on

         19   proposals, on positions, to move forward.  Yet, we still

         20   don't see a pathway out of this.

         21              And so I think what is really frustrating, from

         22   that point of view, is that, for us to go out and make the

         23   investments in the things that we are expected to -- right?

         24   -- not just data centers, but to the rate payer protection

         25   pledge, bringing our own new generation, building, buying that,





                                                                      207



          1   going out and deploying the capital to do that, we can't do

          2   that without the certainty that the market rules are going

          3   to exist in such a way that we know that investment is going

          4   to be worthwhile.

          5              And so, where I see us today, we just need some

          6   leadership on what we're going to do next.  Right?  We've

          7   heard discussions about proposals, we've seen changes. 

          8   Sometimes those changes happen with very little

          9   transparency.  Right?  And so, in addition to leadership, I

         10   think we need transparency as to why we're making the

         11   decisions we are.

         12              But, at the end of the day, we've had enough

         13   discussion about the issues in front of us, that we do need

         14   to move forward.  And, without that ability to move forward,

         15   we're not going to be able to deploy the capital that we

         16   want to, in a manner that we have agreed to do it, to go out

         17   and serve our businesses, to grow.

         18              COMMISSIONER SEE:  So, clear direction, assertive

         19   leadership, and transparency around those decisions.

         20              MR. GEORGE:  Yeah.

         21              COMMISSIONER SEE:  Great.  I suspect others may

         22   have thoughts on that question, so if there are others who

         23   want to jump in on where are our highest value-add

         24   solutions, especially when we're considering the time it

         25   takes to put those into place.





                                                                      208



          1              We'll start doing a couple of tent cards.  I

          2   suspect my colleagues will jump in at some point before

          3   everybody answers this one, so we'll keep going until that

          4   happens.

          5              Dr. Bowring.

          6              DR. BOWRING:  Thank you.  Thanks for the

          7   opportunity to be here.  I'll defend my honor against James

          8   Danly's comments later.

          9              (Laughter.)

         10              DR. BOWRING:  I'm not the spokesperson for lack

         11   of accountability.  Sorry, James.

         12              So, I mean, I agree about leadership.  I mean, I

         13   think there are two key things.  One is the independence of

         14   the board, which has been talked about a lot.  But there are

         15   two ways to -- two, at least two, essential ways to get

         16   there.  One is the nominating committee, but the other is to

         17   ensure that the board cannot be voted out by members without

         18   at least some participation by states.  We made a specific

         19   recommendation about that.

         20              So, at the moment -- and again, nothing I say

         21   should be taken as a comment about any individual person. 

         22   The folks at PJM and the board are all doing, you know,

         23   great jobs, but they are constrained by the structural

         24   nature or the structural facts of the positions they're in.

         25              And the board, at the moment, as Commissioner





                                                                      209



          1   LaCerte pointed out, is, at the moment, worried about being

          2   fired, as they should be, because they can be.  That means

          3   they cannot be independent.  That's just a fact, not a

          4   criticism.

          5              The nominating committee is really part of that

          6   as well.

          7              But one of the issues that has not been talked

          8   about as much is also about the staff.  PJM's staff.  Again,

          9   not a criticism of PJM's staff role.  Obviously they are

         10   very smart, they keep the lights on.

         11              But what, exactly, are the staff's goals?  The

         12   staff's goals should be specified as acting in the public

         13   interest, not acting in the interests of their members.  And

         14   those are two very different things.

         15              And Asim pointed out that some members -- members

         16   driven -- but that's what the stakeholders are about; it's a

         17   members process.  But it shouldn't be a members process. 

         18   Obviously the members are part of it.  PJM has to listen to

         19   the members.  But ultimately PJM's staff and the board's

         20   role, in our view, should be stated clearly, as acting in

         21   the public interest, consistent with the Order 2000.

         22              And one last piece of independence, which was

         23   raised by Kent, is the TO.  Now, if there's a veto power

         24   anywhere, it's the TO's veto power, the ability to leave,

         25   and that has to be addressed.





                                                                      210



          1              While I don't expect the Commission to rule that

          2   membership is mandatory in an RTO, I do think there need to

          3   be clear, specific, rules about when a TO could leave, and

          4   when that threat could be credible.  Otherwise, that threat

          5   hangs over every decision that PJM staff and the PJM board

          6   makes.

          7              COMMISSIONER SEE:  Dr. Bowring, I was hoping that

          8   we could start streamlining the solutions but, of course,

          9   leave it to you to put more on the table.  But no, I really

         10   appreciate your thoughts there.

         11              DR. BOWRING:  No.  Three things.  Three things. 

         12   Board independence, staff independence.

         13              COMMISSIONER SEE:  Yeah.

         14              DR. BOWRING:  Adress the TO question.

         15              COMMISSIONER SEE:  Great.  Thank you.

         16              DR. BOWRING:  Thanks.

         17              CHAIRMAN SWETT:  Wait, I'm sorry.  Just on that

         18   point, do you think the staff is not independent?  And, if

         19   they are not, then what needs to change?

         20              DR. BOWRING:  I think the question is "What are

         21   their objectives?"  Are their objectives to make the members

         22   happy, to do what the members ask them to do?  When members

         23   come and say "I want a particular kind of rule," is it their

         24   job to make that work, or is it their job to say "We don't

         25   think that's in the public interest, we don't think that's





                                                                      211



          1   consistent with the overall interest of the market?"

          2              So, I would hope it's the latter.  I don't think

          3   it is, from my experience.  I think it is member driven.

          4              Again, nothing, nothing -- there is something

          5   wrong with it but it's nothing -- they're not -- staff is

          6   not doing anything wrong.  I think that's the culture, as

          7   we've talked about.

          8              CHAIRMAN SWETT:  So what's the fix for that?

          9              DR. BOWRING:  The fix about that is to make sure

         10   that the board directs the staff that their sole objective

         11   is to act in the public interest, consistent with Order

         12   2000, competitive markets, the lowest possible cost, not

         13   catering to the specific issues of individual members, which

         14   may not be consistent with that overarching goal.

         15              CHAIRMAN SWETT:  Okay.  Please continue.

         16              COMMISSIONER ROSNER:  And does this have to do

         17   with this, the board's charter, or operating document,

         18   saying that it should act in the public interest?  Is that -

         19   -

         20              DR. BOWRING:  Well, I think that is true, and

         21   that's what Order 2000 said, and that is what the board is

         22   supposed to be doing, and that's what the staff is supposed

         23   to be doing, and that's what the board should be directing

         24   the staff to be doing.  But something's gotten lost along

         25   the way.  I don't think that's happening effectively enough,





                                                                      212



          1   and I don't think 205 rights are the solution.

          2              MS. BRUCE:  First of all, I'll add my thanks for

          3   the invitation to speak on this very important panel.

          4              You know, hopefully -- one of the things, in

          5   terms of thinking about the stakeholder process and reform

          6   looking forward at this moment, this inflection point, is thinking

          7   a bout what needs to be done to get things built.  In the

          8   the stakeholder world, what are the processes that are

          9   forestalling investment?

         10              And I think that that is a lens, as we think

         11   about prioritization.  Maybe there's issues that we've not

         12   even thought about, within the stakeholder process, that

         13   should be on that list?  What are those issues that are

         14   within PJM's control?  What are those issues that are within

         15   the states' control, and where is there a joint issue, a

         16   really clear plan on what do we need to do to get things

         17   built, whether or not it's, you know, in front of the meter

         18   generation, if it's battery storage, you know, anything? 

         19   Anything and everything, all of the above.  What can we do

         20   to get things built?

         21              And I think, as we think about that, there's

         22   probably an element of speed that's necessary, speed to

         23   market, speed to deal with the supply chain, how do we deal

         24   with some of those issues, are there interventions that are

         25   necessary, to accelerate that?  So, speed is an undeniable





                                                                      213



          1   feature of all of this.

          2              But I will also add in -- and I don't -- the role

          3   of stability, as well, because in this investment climate,

          4   when people are being expected, or want to invest billions

          5   of dollars, knowing what the rules of the road are, and

          6   keeping them stable is, I think, also a consideration, as we

          7   think about speed.  Where is speed necessary?  Where is

          8   stability necessary?  And being really thoughtful about

          9   that, as we think about any plan, any work plan that the

         10   stakeholders might undertake and those that regulate us.

         11              And, the other tension that's inherent here is

         12   the tension between where is there a place for consensus and

         13   where is the role of independence?  Consensus can build

         14   really durable solutions, but they might not -- they're

         15   harder ones.  And it requires us thinking about things in a

         16   more comprehensive way. 

         17              And I think one of the stakeholder processes

         18   we've not talked about a lot is that we talk about a lot of

         19   things in silos, and to get real, durable, consensus

         20   probably means looking at a couple of issues together so

         21   that you can have real tradeoffs across issues. And where

         22   are we asking the board to be independent, and then how is

         23   that independence -- what is guiding that independence, what

         24   is the metric?

         25              And I do think that it's being really the -- in





                                                                      214



          1   my comments I raised the question of whether or not the PJM

          2   board should be more mindful of -- or the operating

          3   agreement being amended to consider the retail market

          4   considerations, because there is that element here too.

          5              But I think that, hearing the conversation today,

          6   really thinking about the public interest and understanding

          7   what that means, and having the board be -- having that be

          8   part of their mantra when they're making their decisions. 

          9   It's a useful thing.

         10              COMMISIONER SEE: I think you have the tensions

         11   right there, and I speak in tensions a lot too.  Right? 

         12   Between speed and deliberateness, and independence and

         13   consensus.  But, we're trying to find solutions here too.

         14   

         15              MS. BRUCE: I know, I know. 

         16              COMMISSIONER SEE:  So tell me, like, when you

         17   think about that, where do you think we're able to draw that

         18   line better?

         19              MS. BRUCE:  In terms of speed...

         20              COMMISSIONER SEE:  You can take either one.

         21              MS. BRUCE:  Either one, either one?

         22              COMMISSIONER SEE:  Yeah.

         23              MS. BRUCE:  You know, I think that it goes to the

         24   work plan.

         25              COMMISSIONER SEE:  Uh-huh.





                                                                      215



          1              MS. BRUCE:  And being very deliberate about it. 

          2   What are the ones, again, going back to that, you know, what

          3   do we need to do?  We need to get things built.  And it's

          4   generation, transmission.  We need to think about demand

          5   response in, perhaps, new ways.  Focus on those.  Those are

          6   the places where we need speed.

          7              You know, sort of, some of the bigger questions,

          8   about where we need stability, I think knowing -- are we

          9   going to have a capacity market in two or three years? 

         10   That's a scary thing, if you're asking people to make -- and

         11   when is that decision going to be made?  Because people are

         12   making decisions today, about -- they made them yesterday --

         13    about whether or not they're going to be building.

         14              So I think that that is a lens, and I know it's -

         15   - but I'm hopeful that that kind of prioritization and lens

         16   of looking at things might be helpful in terms of framing

         17   things.  So, thank you.

         18              COMMISSIONER SEE:  I appreciate that.

         19              CHAIRMAN SWETT:  I saw -- I know Glen has had his

         20   up for a while.  I lost track of the order for everyone

         21   else.

         22              MR. THOMAS:  Yeah.  No, thank you.  And again,

         23   thank you for the invitation and for all the commissioners

         24   to be here.

         25              You know, we're going to give you a unique





                                                                      216



          1   moment.  Commissioner Rajiv always talked about people

          2   building consensus.  I agree with everything Susan just

          3   said.

          4              So, literally, you have somebody representing the

          5   largest consumers in the PJM footprint, and somebody

          6   representing the largest suppliers in the PJM footprint

          7   agreeing wholeheartedly.

          8              Maybe I'll stand on a few things and she may or

          9   may not agree with these things, but at least I'll expand on

         10   a couple of them, to your question, Commissioner See. 

         11   (Laughs.)

         12              First of all, in terms of low hanging fruit, I

         13   think state involvement and state input is the easiest and

         14   the lowest hanging fruit here.

         15              Before I had this job as chairman of a public

         16   utility commission, before that I was an advisor to a

         17   governor.  I actually had Jacob's job well before Jacob had

         18   that job.  (Laughs.)  So, I've seen this market from a bunch

         19   of different areas and I've seen the evolution of state

         20   participation in the capacity markets in a very unique way.

         21              And Dave will remember some of these stories, but

         22   I've told this a couple times.  I'll spare you all the

         23   details.

         24              But when I was chairman of the commission, I was

         25   told I was not allowed to meet with the PJM board.  Very





                                                                      217



          1   specifically.  That has evolved a lot.  A lot.  To the point

          2   where commissioners are regularly meeting with the PJM

          3   board, having unique input throughout the process.

          4              Can more be done?  Certainly.  You know, are

          5   states important players in this game?  A hundred percent.

          6              The introduction of the governors into the

          7   conversation I think, at the end of the day, could be very

          8   helpful, because let's face it, five-six years ago most

          9   governors probably didn't hear, had never heard, of PJM. 

         10   Now they certainly most all have.  And getting the governors

         11   more involved, I think, could ultimately be helpful to the

         12   overall credibility of, you know, the enterprise we're

         13   trying to work on here.

         14              What I would suggest there is exactly what we did

         15   with OPSI when I stood it up in -- what was the year of

         16   that?  2005.  Yeah.  

         17              So, funny story.  I actually wrote all the bylaws

         18   and left the Commission before I had a chance to actually

         19   serve on OPSI.  I actually served on OMS, as a member of the

         20   organization's MISO states.  I was one of the charter members

         21   of that, one of the original signers of those documents.

         22               But, you know, we developed a piece of paper in

         23   OPSI.  We brought it to the stakeholder process and we

         24   talked about it with the PJM stakeholders.  There was a give

         25   and take about what OPSI would look like, how it would be





                                                                      218



          1   funded.

          2              You know, but ultimately, you know, we worked it

          3   through the process.  And I would suggest doing exactly that

          4   here.  There's nothing preventing, you know, the governors,

          5   OPSI, collectively, individually, what have you, putting a

          6   proposal in front of the stakeholders and let's have at it.

          7              I mean, I think you've heard -- I don't think

          8   you've heard any objections here today to governors and

          9   commissions being involved in the PJM process in a very

         10   constructive way.  I think we can make that happen.

         11              Let me talk a minute about board independence,

         12   because it's come up multiple times today.  And to me, you

         13   know, there's a couple critical cogs in this situation here. 

         14   And board independence is one of them.

         15              Having a board independence, that's not too

         16   dissimilar to a regulatory commission that can take input,

         17   hear from the various sides, make reasoned decisions that

         18   are in the best interests of the market.  That's a good

         19   thing, and that's ultimately the role that the board plays.

         20              What also should be appreciated in that is the

         21   role that you all play, as the regulator, because it's

         22   almost like a shared responsibility because PJM could come

         23   up, you know, with all the best ideas in the world, but they

         24   ultimately have to get through this body.

         25              So, having an engaged commission on these issues





                                                                      219



          1   is critically important.  And having a focused commission as

          2   well.  Because, let's face it, I mean, this commission has

          3   the ability to set an agenda as well.  That's why we're here

          4   today.  Right?  Because you all have identified some issues

          5   that are our priorities, and you have the ability do that as

          6   well.

          7              So I would, maybe, challenge you all a little

          8   bit, you know, to evaluate how FERC can be, you know,

          9   helpful in that prioritization at the RTO level.

         10              And maybe I'll stop there.  I'll save a few

         11   comments maybe for later, in the interest of time.  But

         12   those are just a few initial thoughts on constructive things

         13   that could be done right away.

         14              CHAIRMAN SWETT:  Are you saying that we should

         15   focus more on PJM at this juncture?

         16              MR. THOMAS:  I did not say that.  (Laughs.)

         17              (Laughter.)

         18              MR. THOMAS:  I did not say that.

         19              CHAIRMAN SWETT:  All right.  Just checking.  Just

         20   checking.

         21              MR. THOMAS:  Well, let me maybe -- I mean, offer

         22   a few...

         23              (Laughter.)

         24              MR. THOMAS:  Yeah.  Well, and that maybe goes to

         25   the point of board members getting fired.  Right?  I mean,





                                                                      220



          1   you know, the comments come up that, a couple times, that

          2   board members shouldn't be afraid of being fired.  And, you

          3   know, I would respectfully say, if I'm a board member and

          4   afraid of being fired, I'm in the wrong job.  You know?  I

          5   should be feeling, as a board member, empowered to make what

          6   I think are the best interests of the organization,

          7   reportable to the operating agreement, and if I can't handle

          8   the pressure, and if I'm afraid of being fired -- you all

          9   live with that pressure every day.  So, I --

         10              COMMISSIONER LACERTE:  The nominating the

         11   committee.

         12              MR. THOMAS:  Huh?

         13              COMMISSIONER LACERTE:  Somebody's controlling the

         14   nominating committee, then who is making the decisions to

         15   nominate the people who are afraid of being fired?  Like,

         16   how deep down the hole do we need to go?

         17              MR. THOMAS:  The nominating -- well, the way it

         18   works, from a process perspective, the nominating committee

         19   goes forward, they put up their nominees.  The members vote

         20   and go forward accordingly.  So, if the nominating committee

         21   can agree on the candidates, whether they're for renewal or

         22   somebody new, that's part of the process as well.

         23              But, like I said -- I mean, you could talk to the

         24   people that serve on the accountability, or have served on

         25   the nominating committee.  I'd be surprised if any one of





                                                                      221



          1   them said to you "We're not reappointing this member because

          2   of a vote that the PJM board made."

          3              First of all, we don't know who voted what.  We

          4   don't know what's going on in those discussions.  I know

          5   that's probably one of your issues as well.

          6              COMMISSIONER LACERTE:  Right.

          7              MR. THOMAS:  So...

          8              COMMISSIONER LACERTE:  Neither do we.

          9              MR. THOMAS:  Right.  You know, and that could be

         10   -- that's a separate conversation.

         11              COMMISSIONER LACERTE:  Who does?

         12              MR. THOMAS:  Huh?

         13              COMMISSIONER LACERTE:  If you can narrow it down

         14   by who does know who voted?

         15              MR. THOMAS:  Yeah, there are a few people.

         16              COMMISSIONER LACERTE:  The non-secret society.

         17              MR. THOMAS:  Right.

         18              COMMISSIONER SEE:  To hijack a little bit, to

         19   drill on this, you mentioned that we haven't heard

         20   disagreement about state involvement in a more formalized,

         21   involved, process.

         22              MR. THOMAS:  Right.

         23              COMMISSIONER SEE:  Great.  An areas where we did

         24   hear some disagreement, that was state involvement on the

         25   nominating committee.  So, I'm interested in getting





                                                                      222



          1   specific perspectives on that.

          2              MR. THOMAS:  Yeah, I mean, here would be my

          3   thought.  I mean, I think -- I think there's a general

          4   unappreciation of how the nominating committee works.  And

          5   Marjie served on the nominating committee.  I think it would

          6   be really helpful to talk to the folks who have served on

          7   that nominating committee, including the PJM board members

          8   that have served on that nominating committee, so you all

          9   have a better sense of how that works.

         10              Yeah, I -- it seemed like there was a little bit

         11   of an impression that people aren't voting their interests

         12   and people are -- you know, there's a lot of votes being

         13   taken, and things like that.

         14              I don't think it works that way.  I have never

         15   served on the nominating committee, so I can't offer you

         16   that perspective.  And even those who serve on that

         17   committee -- I mean, there are some very strict rules about

         18   what they can and cannot say about their participation in

         19   that.

         20              But I think it would be helpful to get a better

         21   appreciation for how that works.

         22              I think having state involvement in that process

         23   can be constructive.  I don't know that three, and how

         24   they're appointed, and everything else like that -- you

         25   know, maybe you want to reserve judgment on that.





                                                                      223



          1              But one thing I will offer, that when I was on

          2   the commission -- this goes to, maybe, a point Commissioner

          3   LaCerte made earlier -- at that point states did not have

          4   access to confidential data at PJM.  And we had to go

          5   through a series of rule changes in order for states to have

          6   that access.

          7              We sat down with the stakeholders.  We actually

          8   had a situation where we thought the markets were being

          9   manipulated, we couldn't see the details, we wanted to see

         10   the details.  And I had obligation under state law at the

         11   time to investigate.

         12              So, we actually had to sit down and rewrite

         13   tariff provisions that were eventually approved by this

         14   commission, to allow states to have access to it, where we

         15   addressed things like confidentiality and other things.

         16              But, in my mind, we've got to go through a

         17   similar process with this.  So, at the end of the day, you

         18   want some sort of confidence in the process.  And I don't

         19   know that we want to rush into that conversation 'til we

         20   have a full visibility into, you know, really what all the

         21   consequences could be if we don't do it right.

         22              COMMISSIONER ROSNER:  But what I hear is you're

         23   not sure you're there on three seats, but you're not opposed

         24   to some number.

         25              MR. THOMAS:  Some level of participation,





                                                                      224



          1   assuming some other boxes can be checked, yes.

          2              COMMISSIONER LACERTE:  So, is that a yes?

          3              MR. THOMAS:  It is.  Yeah, no, it's a yes but,

          4   like, until you see -- as you know, Commissioner, until you

          5   see all the details, it's hard to give an unequivocal yes.

          6              COMMISSIONER LACERTE:  Yes, sure.

          7              COMMISSIONER ROSNER:  And on this topic, you

          8   know, I'll just note, you know, there's a variety of things

          9   that we've talked about.  Everything from terms, length of

         10   the terms, to the number of people on the board, to the

         11   concept that Chairman Wood had, of the public interest

         12   charter, you know, the board operating in the public

         13   interesting, making that explicit, to things I've heard

         14   about, you know, maybe we need more people from the region,

         15   or maybe we need to make sure that some amount of the board

         16   lives in the region, to get that better understanding and

         17   more engagement with the states here.

         18              You know, from my perspective, you know, I think

         19   we have a lot of dials to turn here.  But also, you know,

         20   the big gap, and what you described as low hanging fruit --

         21   somebody here did -- is that engaging the states more in

         22   this process, especially based on what we've heard about the

         23   nominating committee, so far, is that, based on its rules,

         24   you know, it sounds like if Marjie can do it, someone from a

         25   -- you know, the state governor might want to -- should be





                                                                      225



          1   able to do it as well.

          2              And so, you know -- but it is very helpful to

          3   have that feedback and I hear your reservations, and we want

          4   to get those dials turned.

          5              MR. THOMAS:  Yeah, and if I could just make one

          6   last comment, then I'll allow others to speak, one of the

          7   challenges I have heard from the nominating committee

          8   process is -- and PJM actually addressed this very publicly

          9   a few year ago -- it is challenging finding qualified

         10   candidates that pass all the screens in terms of conflicts

         11   and everything else like that, whether they're financial or

         12   otherwise.

         13              So, it has been a frustration of mine that we

         14   haven't seen representation from the PJM footprint, but

         15   that's more, my understanding, a reflection of the conflicts

         16   than some sort of institutional bias against people who live

         17   in the area.

         18              COMMISSIONER LACERTE:  James Danly just moved to

         19   the area, if you're interested.

         20              (Laughter.)

         21              MR. THOMAS:  He might be conflicted.  (Laughs.)

         22              (Laughter.)

         23              COMMISSIONER SEE:  Maybe.  You have to respond to

         24   that.  I do think it's interesting, on the state involvement

         25   in the nominating committee.  One of the responses we've





                                                                      226



          1   heard is that the members of the committee are not

          2   necessarily voting their own interests, because there's lots

          3   of processes in place.

          4              But one thing that occurs to me in that case is,

          5   then, why are we so concerned about the states being the

          6   ones who are doing that, as well?  So, we'll throw that out

          7   there, and you can respond to it if you want to.

          8               But it's been about 30 minutes and we haven't

          9   heard from PJM yet.  So maybe we have David, and then we've

         10   got a couple people in the middle who haven't talked either,

         11   so you can keep adding to the list of things you want to

         12   tell us about.

         13              MR. ANDERS:  Thank you very much for inviting us

         14   to be here today, and I'm really pleased to be with you. 

         15   So, thank you.

         16              Chair Swett, you asked for candor.  I hope to

         17   fulfill that.  And thank you for all the questions.

         18              There's a couple things I wanted to share with

         19   you, right at the top, and these aren't necessarily to your

         20   point, Commissioner See, about what's the low hanging fruit. 

         21   But things that I see as needing to be taken care of.

         22              COMMISSIONER SEE:  The most impactful.

         23              MR. ANDERS:  And important.  And one of those,

         24   actually, Commissioner LaCerte, you touched on, on the last

         25   panel, which is culture.  And we heard Joe talk about





                                                                      227



          1   culture, in a way, talking about PJM staff and so forth. 

          2   And I think it's a really important discussion to have.

          3              I'm going to bring it back a little bit, in a

          4   "way back machine," if you will.  (Laughs.)  If it's

          5   helpful.  I don't want to waste all of your time with too

          6   much detail about history here, but I think there's a couple

          7   things that are important.

          8              Number one is why are schedules one and six in

          9   the operating agreement to begin with?  

         10              I met with our founding CEO -- well first of all,

         11   I became secretary of the members committee in 2002, so that

         12   dates me.  Tuesday's meeting will be my 250th as secretary

         13   of the members committee.  

         14              And that may actually ask you -- or point your

         15   questioning to well maybe all the problems are mine. 

         16   (Laughs.)

         17              (Laughter.)

         18              MR. ANDERS:  And, as a result of this technical

         19   conference, I may be entering therapy, and David, I may be

         20   expensing my therapy.

         21              But I do want to share a few things.  I met with

         22   then-CEO Phil Harris, founding CEO, about many things.  And

         23   one time I asked him, you know, "Why do we have schedule one

         24   and schedule six in the operating agreement to begin with?"

         25              And, at that time, schedule six was -- it deals





                                                                      228



          1   with the RTEP protocol.  It's the planning process

          2   protocol.

          3              Schedule one, the energy markets looked different

          4   then, but, you know, it's the energy markets.  And, at that

          5   time, we had the rudiments of an early-early capacity market

          6   in the operating agreement as well.  They were taken out

          7   when the RPM went into effect, in roughly 2005.

          8              But the energy markets, and the RTEP protocol

          9   were put in there because, at the early stages of the RTO --

         10    or PJM, as it was being formed, it was being formed by

         11   folks who were turning over their assets to this new

         12   fledgling organization that hadn't really -- I mean, we'd

         13   operated as PJM since 1927, in different forms, but it was a

         14   new, independent, organization, not run by the TOs.

         15              And it was a new board, that hadn't even been

         16   seated yet, and what -- maybe you'd call this hearsay, but

         17   what Phil shared with me was that there was a certain level

         18   of confidence that they didn't have at the time, in this new

         19   board, in this new organization.

         20              And so, one way to ensure that their assets were

         21   being operated in a way that was appropriate, in their view,

         22   was to maintain some level of control over certain functions

         23   at PJM, and to do that through a document they clearly

         24   controlled, which was the operating agreement.  Anything in

         25   the tariff, you know, the public utility, PJM, has the 205





                                                                      229



          1   filing authority and so on.

          2              So, if you go back to that, there's this level of

          3   confidence in PJM, and there's also a strong cultural norm

          4   within PJM, the community of PJM, not just PJM staff; the

          5   full community, that it's a very member-centric

          6   organization.  It's a very stakeholder-centric organization.

          7              And, frankly, I think that's a strong -- a very

          8   fundamental strength of PJM, is our desire, our true desire

          9   and commitment, to serving the community.  The whole

         10   community, including all of our 67 million customers.

         11              I think where I want to help people understand

         12   the impact of that on not only staff but how the stakeholder

         13   process works is that there's this concentration on what the

         14   stakeholders are seeing as their priorities, or what their

         15   inputs are and so forth.

         16              And so, when that translates into the stakeholder

         17   process, if there's no firm deadline that can be put in

         18   place, you know, this issue of who holds the 205 rights, on

         19   those two critical pieces, discussions continue, and

         20   continue, and continue, even though we might try to put a

         21   deadline on it.  We might say "Hey, there's a line in the

         22   sand.  We need to get something done by a certain date," we

         23   meet those 42 times...

         24              Now, albeit it was over 36 months.  Perhaps we

         25   can work on that.  We get to the end of that time and we





                                                                      230



          1   have people telling us, still, that they don't understand,

          2   or they need more time.

          3              So, what do we do with that?  You know, we're

          4   left saying "Okay, we've got to, you know, call the

          5   question, but we're still going to have to file it under

          6   Section 206."  And so it's not really helpful.  Right?

          7              And so, I agree with you that there is a cultural

          8   aspect to this, but I think it can be tied, in a way, and

          9   it's a nuance that others haven't explored yet -- it can be

         10   tied to the 205 authorities here.  And I think it's very

         11   important.  So...

         12              It's funny.  I was wondering whether we were

         13   channeling, because I have culture at the top of my page,

         14   and I was happy to hear you say that earlier.

         15              COMMISSIONER LACERTE:  I saw your notes.

         16              MR. ANDERS:  Yeah.  (Laughs.)

         17              (Laughter.)

         18              MR. ANDERS:  There are a couple.

         19              COMMISSIONER CHANG:  Can you be a little bit more

         20   specific?  You're saying we should tie it to the 205, and

         21   it's cultural.  So, what do we need to do?

         22              MR. ANDERS:  So, I think we need to remove

         23   schedule one, and its derivative, schedule two, and schedule

         24   six and its derivatives, schedule 6A and 6B, from the

         25   operating agreement.





                                                                      231



          1              Now, schedule one is already in the tariff.  It's

          2   the addendum to attachment K.  So, nothing more needs to be

          3   done, aside from removing it from the operating agreement.

          4              Schedule six and its derivatives would, then,

          5   need to be put in the operating agreement -- or excuse me,

          6   in the tariff.

          7              COMMISSIONER CHANG:  Is that something that PJM

          8   is willing to spearhead?

          9              MR. ANDERS:  I would need to discuss that with

         10   David and others, but speak with the folks on the board. 

         11   But...

         12              CHAIRMAN SWETT:  David, do you want to come back? 

         13   For that?

         14              (Laughter.)

         15              COMMISSIONER CHANG:  Sorry, can you be more

         16   specific about that?  I don't know the schedules like you

         17   do.

         18              MR. ANDERS:  Schedule one is the energy and

         19   ancillary services markets.

         20              COMMISSIONER CHANG:  Yeah, but what does it mean

         21   when you say take it out?  What are you precisely saying?

         22              MR. ANDERS:  So, the operating agreement, when we

         23   look at the filing authorities on the different governing

         24   documents we have -- so, three primary governing documents

         25   we -- well, that PJM has some level of input on.  We've got,





                                                                      232



          1   probably, four, and some others.  But we have the CTOA,

          2   which...

          3              COMMISSIONER CHANG:  No, but what are you trying

          4   to say?  What does it mean to "take it out" of the operating

          5   agreement?  What's the implication?

          6              MR. ANDERS:  PJM doesn't have the authority to

          7   take it out of the operating agreement.  To change the

          8   operating agreement, under Section 205, requires a

          9   two-thirds sector majority, you know, weighted vote.

         10              COMMISSIONER CHANG:  Yeah.

         11              MR. ANDERS:  Of the members committee.  So...

         12              COMMISSIONER LACERTE:  And you anticipate not

         13   getting a two-thirds vote from the members committee to

         14   accomplish this task.

         15              MR. ANDERS:  I have suggested removing these

         16   schedules from the operating agreement all the way back to

         17   when we were working in the GAST, the Governance

         18   Assessment Special Team, back in 2008.

         19              COMMISSIONER CHANG:  But what's the implication

         20   of that?

         21              MR. ANDERS:  The implication is that we're going

         22   to continue doing what we've been doing.  We're going to

         23   continue with the same inability to call that question, and

         24   people are still wanting to talk, and talk, and talk.

         25              And then, the other implication, which, you know,





                                                                      233



          1   we haven't talked about yet -- people talked, on other

          2   panels, about it -- is with respect to the prioritization.

          3              So, yeah, people have asserted that we have the

          4   205 rights on the tariff.  We've got the ability to do

          5   prioritization.  And, for some reason, we're not actually

          6   grasping that and going forward with it.

          7              Certainly there's some accountability there, for

          8   PJM.  I'm not trying to shirk that, whatsoever.

          9              But, when we take independent action, when we say

         10   we're not going to work on this thing in the stakeholder

         11   process, it becomes -- it's just a -- it's almost, like, a

         12   PR nightmare.  You have members accusing us of not being

         13   attentive to their needs, not listening to them, telling us

         14   that we're not operating in that customer centric.

         15              COMMISSIONER CHANG:  Okay.

         16              COMMISSIONER ROSNER:  So, Dave, let me drill down

         17   a little more, and you have to excuse me, I went to a

         18   football school, so you've got to be slow with me sometimes.

         19              So, what you're telling me is you don't believe

         20   you're going to get the mandate from the stakeholders to

         21   accomplish this task

         22              MR. ANDERS:  I don't.

         23              COMMISSIONER ROSNER:  And you think FERC needs to

         24   file a 206 to accomplish it.

         25              MR. ANDERS:  That would be one way of doing it,





                                                                      234



          1   yeah.

          2              COMMISSIONER ROSNER:  What would be another?

          3              COMMISSIONER LACERTE:  Well, the members could

          4   agree.

          5              COMMISSIONER ROSNER:  Well, without the members

          6   agreeing.

          7              MR. ANDERS:  I think that some people, over the

          8   years, have floated that there's some legal argument that

          9   PJM's being a public utility and not having the ability to

         10   file under Section 205 to amend its rates, terms and

         11   conditions, service, doesn't comport to the FPA.  But I'm

         12   not a lawyer.  That's, again -- I'm speaking -- I'm way out

         13   over my skis on that.

         14              COMMISSIONER ROSNER:  But also to reflect -- you

         15   can jump back in here, but just to offer a point, what I've

         16   heard from the other panels is some openness from the

         17   members to discuss changes to the encumbrance on the 205

         18   rights of these aspects of the operating agreement.

         19              I haven't heard everyone say, you know, "We're

         20   willing to just move it carte blanche."  I've heard

         21   discussions of "If we fail to agree, after some period of

         22   time, it might make sense to revisit -- or revisit the

         23   two-thirds threshold."  But I haven't asked the people on

         24   this panel that question, but I want to.

         25              COMMISSIONER LACERTE:  Well, let's put the





                                                                      235



          1   stakeholders who are on the panel on the spot.  

          2              COMMISSIONER ROSNER:  Yeah.

          3              COMMISSIONER LACERTE:  Like, what do you have to

          4   say about the proposal?

          5              MS. MOSKOWITZ:  I'll jump in, and first just echo

          6   the thanks for inviting me to participate on this panel. 

          7              I'm going to just start by harkening back to

          8   where Chairman Swett started this morning, and reminding

          9   everyone that PJM, or the predecessor to PJM, was formed in

         10   1927.

         11              It turns out that I am with PSE&G, and we are one

         12   of the three founding members of PJM.  So, we have been, not

         13   surprisingly, thinking about the issues of PJM governance

         14   and how to make PJM work effectively, for quite a long time.

         15              And, in our opinion, these issues have been

         16   percolating for a long time.  That, in our opinion, the

         17   governance has been broken for a long time.

         18              But externalities now, and the extreme supply and

         19   demand imbalance -- and that's kind of a multi-faceted, very

         20   complicated, problem -- but that has brought all the

         21   governance problems to light.

         22              But this did not happen two years ago or, you

         23   know, even five years ago.  It's been there for a while.

         24              Before I jump into specific solutions, I just

         25   want to respond quickly to this notion -- I've been hearing





                                                                      236



          1   this on a few of the panels -- that somehow the TOs have

          2   veto power, and I feel like I have to speak, since I'm the

          3   TO rep on this panel.  That we have veto power and that we

          4   can, you know, "vote with our feet," and we can leave PJM.

          5              I mean, the reality is you don't see many TOs

          6   leave RTOs, because it's really, really expensive to do

          7   that.

          8              So, I want to just level set that.  And this

          9   notion that the TOs have veto power -- I was speaking to

         10   someone a little while ago and we were talking about, kind

         11   of, what happened when, a few years ago, there was

         12   discussion about moving schedule six, the RTEP planning

         13   protocols, from the operating agreement to the tariff.  So,

         14   the very issue that we're talking about now, and that there

         15   seems to be some, you know, at least some, support for that

         16   notion, the fact is that went to a members committee vote

         17   and it was voted down 80 percent, by 80 percent.

         18              So, the only sector that voted in favor was the

         19   transmission owner sector.  Because we strongly believe that

         20   that was going to be necessary, to empower PJM to get to the

         21   right decisions and to have that authority over its RTEP

         22   planning protocols, like every other RTO does.

         23              So, I just -- I want to be clear about that.  So,

         24   to start with solutions, as you can tell, we've had concerns

         25   with the sector-weighted voting for a while.  We don't think





                                                                      237



          1   that it works, because it doesn't sufficiently align voting

          2   interest with accountability.

          3                             There's been some discussion,

          4   earlier, about affiliate votes.  I mean, the fact is PSEG

          5   has a 1-1/2 percent vote in the process, even though we own

          6   a significant amount of transmission assets and generation

          7   assets.  We have a less than half percent vote in the

          8   affiliate voting.  So, for us, it's all the same problem.

          9              Now, one way to deal with that -- and there's

         10   been a lot of discussion today -- is about -- is potential

         11   move to advisory, stakeholder advisory voting.  I mean, that

         12   is -- and we talked about it in our comments -- that maybe

         13   that's not our preferred approach right now, but I can see

         14   some merit in it, if we are comfortable that it's going to

         15   get us to better outcomes, and that it's going to then

         16   empower PJM to make the decisions that it needs to make.

         17              But, it's clear to us the current voting doesn't

         18   work, there need to be changes to voting.

         19              In terms of, maybe, lower hanging fruit -- and I

         20   think this is -- it's difficult and complicated, but

         21   certainly wouldn't require operating agreement changes, is

         22   what Dave is talking about.  And maybe it's tied to filing

         23   rights, I'm not sure, but culture, leadership.

         24              I will say, and we've communicated this to PJM,

         25   that we were disappointed in the white paper that PJM issued





                                                                      238



          1   a few months ago on market reform, because it didn't really

          2   set forth, kind of, a long term strategy and an actionable

          3   plan.  You know, it put out to stakeholders three potential

          4   paths, one of which was lower reliability, which seems like,

          5   you know, when you -- when I read that, as a transmission

          6   owner that has, you know -- we have 2-1/2 million electric

          7   customers -- the idea of lower reliability doesn't seem like

          8   the right answer.

          9              So, we want PJM to have the tools and be

         10   empowered to act, to get to better outcomes.  And, you know,

         11   I know, Commissioner See, you asked about the nominating

         12   committee.

         13              I mean, I don't know how much that moves the

         14   needle.  I mean, we certainly support more state engagement. 

         15   I think we have seen some of it working effectively

         16   recently, whether it's with the PARSEC on transmission cost

         17   allocation, or load forecasting.  I think that's an area

         18   where PJM has done a good job of working with asset owners,

         19   working with states, to get the states to give them a

         20   formalized role in the process.

         21              So, definitely understand and support the need

         22   for more state engagement.  What exactly it looks like, I

         23   think we can talk about.

         24              COMMISSIONER SEE:  Great.  One of the benefits of

         25   having such incredible expertise and experience here is we





                                                                      239



          1   have eight people on a panel for 75 minutes.  So, Jameson

          2   and Mason you've been incredible patient.  So, if the two of

          3   you want to give us your thoughts on any of the above,

          4   please go for it, and then I strongly suspect there'll be

          5   more questions from this side of the table, afterwards.

          6              MR. TWEEDIE:  Thank you.  So, I'll just step back

          7   one little bit, which is I'm here as the public advocate for

          8   the State of Delaware.  I'm the representative for consumers

          9   interests, and particularly residential and small commercial

         10   customers.

         11              I'm the only voice on these panels that has that

         12   specific role, and I think it's noteworthy to think about

         13   the role that we have in PJM.  We have an incredibly small

         14   voice, even though what we do is represent the interests of

         15   all 67 million consumers in the region.

         16              We have 1.5 percent for PSEG vote -- jumped out

         17   at me.  The consumer advocates have 14 votes.  That's 1.3

         18   percent.

         19              So, the representative of all the interests of

         20   consumers has less votes than many of the other members, in

         21   this process.

         22              And even in sector weighting, we have a very

         23   diminished vote.  We have roughly one-third of one-fifth of

         24   -- one-third of a sector, which is one of the five sectors.

         25              And I was really caught by something you said,





                                                                      240



          1   Chair LaCerte, and possibly somewhat in jest, but joking

          2   about PJM as a secret society.  Because when I am talking to

          3   members of the public and trying to explain what PJM is,

          4   that's very similar to the reaction I get.  A body whose

          5   members have financial interests in the decisions they're

          6   making, that are making decisions that are putting those --

          7   those decisions have direct consequences for all the rate

          8   payers in the region.  And you try and explain that to people

          9   and it is very challenging.

         10              So, one of the things that I've heard today -- I

         11   think that was the original question -- was "What is the

         12   reform  you've heard today that seemed the most meaningful?"

         13              And, to me, it is firmly and clearly establishing

         14   public interest in PJM's mission and in is operating

         15   documents, and having that operationalized through what PJM

         16   does, both in its board and through the stakeholder process.

         17              So, we've heard a lot about expanded board

         18   authority today, and expanded board authority may be very

         19   necessary.  It may be a near consensus opinion.  But that

         20   needs to come with transparency and a clear obligation to

         21   the public interest in what it does.

         22              We've heard that the board hasn't necessarily

         23   already taken all of the steps they could under their

         24   existing authority.  So, expanding this authority may be a

         25   solution, but it's certainly not sufficient in its own.





                                                                      241



          1              And we have, in our submitted comments, we had a

          2   bunch of specific proposals, and I'm happy to go through

          3   that.  But I do think that, in addition, there needs to be a

          4   more significant role for the states, and that the consumer

          5   advocates are currently the only members that are, in fact,

          6   representatives of the states and all of the customers that

          7   live in those states.

          8              And that means that we -- there needs to be a

          9   meaningful role for the states.  I think a role in the

         10   nominating process makes a ton of sense, and I think having

         11   rights to help shape what PJM does is essential.  So, thank

         12   you.

         13              COMMISSIONER ROSNER:  Thank you.

         14              COMMISSIONER SEE:  Great.

         15              MR. EMNETT:  Good afternoon.  Thank you for the

         16   opportunity to be here.  It is really great to dig in on

         17   these issues with the entire Commission.  I appreciate your

         18   attention to it.

         19              I do not have a good poker face, so you've been

         20   seeing my reaction to the whole conversation.  (Laughs.)

         21              (Laughter.)

         22              MR. EMNETT:  I'll try and kind of step back and

         23   distill what I'm hearing and then also, kind of, weave in

         24   where we come at this, as the largest generation company in

         25   the U.S., and within PJM.





                                                                      242



          1              So, what is the problem we're trying to solve?  I

          2   hear three things.  Independence, the role of the states,

          3   and leadership.  Just to kind of tick 'em off, independence,

          4   I hear there's a concern with the board, that board members

          5   have not been retained because members were unhappy with

          6   them.  That was not a nomination committee issue.  They

          7   weren't nominated by the nominating committee.  It was the

          8   members who chose not to move forward with that.

          9              What are solutions to that?  It could be term

         10   limits.  It could be other, you know, proposals put on the

         11   table, requirements associated or criteria associated with

         12   the retention, or with the incoming members.  But what

         13   problem are we trying to solve and are we tailoring the

         14   problem to that, tailoring a solution to that problem?

         15              State participation and authorities.  From my

         16   perspective, it's about clarity of expectations, staffing

         17   resources, so that states can do the job that's being

         18   expected of them, that they want to do.  And partnership

         19   within PJM, which is clearly not happening today.

         20              But that goes both ways.  Both PJM being clear

         21   here is what PJM needs input on from the states.  Where,

         22   when, how, with transparency, the decision that is made,

         23   feed back to whether the state's view was incorporated or

         24   not, as well as PJM identifying for the states, "Here is

         25   what I need from you.  Here is the infrastructure that we





                                                                      243



          1   are planning for," and the exercise of jurisdiction at the

          2   state level in order to accomplish the infrastructure build

          3   that we need, as was mentioned earlier.  Because we do need

          4   to be building things, and it's great to have a

          5   conversation on governance, but if it's not for the purpose

          6   of actually getting the things built and the customer

          7   served, then we're losing sight.

          8              Which takes me to the third issue, of leadership. 

          9   I'll just say it is a little bit telling, from my

         10   perspective, that we have heard the PJM response, today,

         11   that the members own the stakeholder process.  Well, if the

         12   stakeholders aren't reaching consensus within the

         13   stakeholder process, well, that's just -- you know, we

         14   tried.

         15              The PJM stakeholder process is managed by PJM. 

         16   PJM needs to have leadership.  They control the agendas, 

         17   They can set the priorities.  They can set the expectations,

         18   the timeline, the accountability, as was mentioned earlier.

         19              205 versus 206, I see that as a red herring.  PJM

         20   has authority to move forward, regardless of its filing

         21   mechanism.  And it can say "Here is the timeline at which we

         22   will make a decision, and we will move forward, using our

         23   authority."

         24              Most of the conversation has been around resource

         25   adequacy, over which PJM has 205 rights.  So, to say





                                                                      244



          1   expanding 205 filing rights to the issue where we don't

          2   spend most of our time fighting about is, again, not

          3   tailored to the solution.  We need to bring it back to

          4   accountability, expectations, level setting, and getting

          5   the job done using the existing authorities today.

          6              Frankly, I think that will get things done more

          7   quickly.

          8              CHAIRMAN SWETT:  David, do you have a response to

          9   that?

         10              MR. ANDERS:  A few thoughts I'd like to share.

         11              I mentioned before that the 205 issue, in my

         12   mind, is integrally linked to the cultural issue.  The

         13   cultural issue, I think, is also linked to whether or not

         14   the 205 rights are used differently with respect to resource

         15   adequacy issues, where we already have the 205.

         16              We address the stakeholder process with the same

         17   posture, regardless of what the issue is.  So, maybe what

         18   I'm hearing folks say is we ought not to do that; maybe we

         19   ought to treat resource adequacy issues differently because

         20   we already have the 205 rights.  That's something we could

         21   consider, I suppose.

         22              I want to be clear about a couple things, though. 

         23   First, Commissioner Rosner, you referred to, perhaps,

         24   flavors of the 205.  Of course, all those things could be

         25   discussed.





                                                                      245



          1              I want to be clear, though, should PJM -- should

          2   the schedule one and schedule sixes, and so forth, be

          3   removed, as I mentioned before, and 205 rights be vested in

          4   PJM, that does not mean that PJM would abandon the

          5   stakeholder processes.  We see tremendous value in the

          6   stakeholder processes.  I've invested too much of my life in

          7   these processes.  (Laughs.)    (Laughter.)

          8              COMMISSIONER ROSNER:  Just to be clear, me too.

          9              MR. ANDERS:  Yeah.

         10              COMMISSIONER ROSNER:  The point I was making was

         11   are there dials we can turn, to drive more consensus, within

         12   the stakeholder process.

         13              MR. ANDERS:  Right.

         14              COMMISSIONER ROSNER:  What people have described. 

         15   You know, they already have tools.  They could do a 206,

         16   they could do a -- you know, I get that.  But also, what if

         17   the sector, what if it required a 50 percent threshold to

         18   agree instead of the current...

         19              MR. ANDERS:  That's something we could absolutely

         20   explore.

         21              COMMISSIONER ROSNER:  Yeah-yeah.

         22              MR. ANDERS:  Yeah.

         23              COMMISSIONER ROSNER:  Or what if you don't reach

         24   agreement in six months, then you get access to make a 205,

         25   or if a stakeholder vote fails and it's something that is,





                                                                      246



          1   you know, in a category of things that is of most

          2   importance.  You know, but I just want to be clear.

          3              I think the stakeholder process is incredibly

          4   important.  And I was looking through the flow chart of all

          5   the task forces and, you know, some of them are on things

          6   that are, like, effective load carrying capability, things

          7   that we need expertise on.

          8              MR. ANDERS:  Uh-huh.

          9              COMMISSIONER ROSNER:  And so, I'm not saying

         10   anything about denigrating the stakeholder process, at all. 

         11   I think it's essential.

         12              MR. ANDERS:  Yeah.

         13              COMMISSIONER ROSNER:  What we need are decisions.

         14              CHAIRMAN SWETT:  I thought you said you wanted to

         15   bring it down.

         16              (Laughter.)

         17              CHAIRMAN SWETT:  Just kidding.  Just making sure

         18   he's awake.

         19              COMMISSIONER ROSNER:  Yeah.

         20              COMMISSIONER LECERTE:  And I think all five

         21   commissioners agree that having a robust stakeholder process

         22   is essential to positive outcome.

         23              MR. ANDERS:  Yeah.

         24              COMMISSIONER LECERTE:  But we have to have the

         25   positive outcomes, and that's what we're not getting.





                                                                      247



          1              (Laughter.)

          2              MR. ANDERS:  And not having the ability to, you

          3   know, call that question, after a certain point in time I

          4   think inhibits us from being able to do that.

          5              Now, I hear folks saying "Well, you can always

          6   file under Section 206."  Of course we can.  But there are

          7   implications to that as well.  You don't have the 60-day

          8   clock.  The thresholds for approval or acceptance by the

          9   Commission are different, and so forth.  So, that just

         10   changes the whole posture of the proceeding.

         11              CHAIRMAN SWETT:  You can always ask for a clock,

         12   in your filing.

         13              MR. ANDERS:  True.

         14              CHAIRMAN SWETT:  Susan?

         15              MS. BRUCE:  You are living in a stakeholder

         16   process.  Because I initially put my tent up when we were --

         17    that the challenge was about talking about the nominating

         18   committee.  And the conversation has moved on to very

         19   interesting places, but that was where my tent went up for.

         20              Because I am currently on the nominating

         21   committee, and I am reluctant to say that out loud.

         22              (Laughter.)

         23              MS. BRUCE:  But I do feel an obligation to PJM's

         24   stakeholder process, to be transparent about it.

         25              And the question, I think, Commissioner LaCerte,





                                                                      248



          1   that you asked around was whether or not support for the

          2   states' involvement, and speaking as Susan Bruce and as

          3   counsel, not as a PJM ICC position, I certainly -- I think

          4   that there is value in having, if states want to be part of

          5   the nominating committee, I think that there is value in

          6   terms of having the buy-in, to understand who is on the

          7   board and who is making the decisions on the board.

          8              I will say that, having served on the nominating

          9   committee several times, it is an exercise where everyone

         10   does come at it with the vantage point of being what's in

         11   the best interest of PJM.  It's something that you do not

         12   talk about with your colleagues.  My clients don't know

         13   what's going on.  No one knows.  It's really put the "What

         14   is in the best interest of PJM?  What does PJM need right

         15   now?"  

         16              And they're really, sometimes, very hard

         17   conversations, but it's always productive and respectful

         18   conversations, and certainly I think the states have a role

         19   there, especially if PJM is becoming more of an integrated

         20   grid, if you think about the 21st century grid being very

         21   different than it was 30 years ago.  So, I think that there

         22   is value in thinking about that.

         23              I think there's probably also values in thinking

         24   about what -- you know, we have struggled in terms of

         25   thinking about honoring the independence, making sure





                                                                      249



          1   there's no conflicts of interest.  There's a two year stay

          2   out provision for candidates.

          3              PJM is the largest marketplace.  And so, people

          4   that have expertise in the energy space, they touch in some

          5   respects PJM.  So, that limits the pool.  But it's really

          6   important to think about making sure that the board members

          7   don't have even the appearance that they're making financial

          8   choices personally, as opposed to what's in the best

          9   interest of PJM.

         10              Thinking about pension plans, things like that. 

         11   Those are all things that become issues of consideration.

         12              I think there's probably things to think through

         13   there.

         14              CHAIRMAN SWETT:  Let me stop you there.

         15              MS. BRUCE:  Uh-huh?

         16              CHAIRMAN SWETT:  How should we change that

         17   conflict rule?  Because several people have brought it up.

         18              MS. BRUCE:  I don't know what the right answer

         19   is, because I think that having a board that is above

         20   reproach is -- it's 67 million people and all of the

         21   businesses in it, you know, having it be something that has

         22   -- everyone can have confidence in, is really important.

         23              So, whether or not it's, you know, two years is

         24   too long, you know, one year, it becomes a balancing of the

         25   interests, as well.  Because, you know, one of the reasons





                                                                      250



          1   why there's not too many people in the footprint, and the

          2   one that we have had on the longest, she was not within the

          3   industry.

          4              So, I think that that, you know, was two years

          5   too long?  Is one year enough, to make sure people feel

          6   comfortable that they're not still thinking that they --

          7   everyone sort of has a mindset.  I represent industrial

          8   customers.  I've represented industrials for 30 years.  I

          9   know how other segments of the market think, but I know that

         10   I come at things with my own view of the world.

         11              So, I think that that element comes into the

         12   nominating committee process.

         13              COMMISSIONER SEE:  I'm curious about that.  We

         14   use one year, in government, and the interests aren't

         15   exactly the same.  But, you know, that largely works in a

         16   similar contexts.

         17              MS. BRUCE:  Uh-huh.  Uh-huh.

         18              COMMISSIONER SEE:  So that's one option.

         19              But, from your perspective -- and others may have

         20   thoughts about that too -- does changing, from two to one,

         21   meaningfully increase the pool?  Like, how much value would

         22   that give us?

         23              MS. BRUCE:  I think it would increase the pool.

         24              COMMISSIONER SEE:  Yeah, uh-huh.

         25              MS. BRUCE:  I can't say anything about anything,





                                                                      251



          1   but I do think --

          2              (Laughter.)

          3              MS. BRUCE:  -- that it would be helpful.  It may

          4   make the pool slightly larger.

          5              COMMISSIONER SEE:  I thought you might say that. 

          6   I agree with that.

          7              MS. BRUCE:  The other thing I would just throw in

          8   there is, if we're talking about boards and we're talking

          9   about the stakeholder compromises, if you're doing it well,

         10   you're pulling things from a whole bunch of different areas,

         11   and I know Section 205 rights have been discussed.  But, as

         12   that's been discussed, I think thinking about who is on the

         13   board, is it useful to have people that have experienced

         14   buying power, whether or not it's as a very large data

         15   center, or as an industrial customer, someone that has that

         16   knowing of what it's like to be on the other side of a

         17   change in law, for example, for a retail contract.  Those

         18   types of skill sets might be something to think about, in

         19   terms of expanding the qualifications for the board.

         20              Thinking about the OA changes, in terms of

         21   thinking about public interest.  But I think whether or not

         22   requiring cost/benefit analysis, sensitivity analysis, of

         23   cost impacts for customers, and having that be de rigueur

         24   and not something that you have to ask for repeatedly.  So,

         25   there's things like that, I think, that are useful to put





                                                                      252



          1   into that soup that's being made right now.

          2              So, thanks.

          3              CHAIRMAN SWETT:  Dr. Bowring?

          4              DR. BOWRING:  Thanks.  So, there's been lots of

          5   conversation about speed.  I trust it's obvious to everyone

          6   that speed to a bad decision is not the right idea.  So, no,

          7   but it hasn't been said, and speed has been emphasized over

          8   and over again.  So, speed doesn't get you anywhere, if you

          9   get to the wrong place, and I think that's what the 205

         10   filing rights are about.  It's speed, but speed to a bad

         11   decision.

         12              There's no reason -- I agree with you -- sorry

         13   for agreeing with you -- the representative of

         14   Constellation.  The 205 thing is a red herring.  That's not

         15   what the issue is.  And really, as David said, it changes

         16   the standards.  It lowers the standards.  There's no reason

         17   for PJM to have 205 rights over the tariff.  

         18              Having it -- no one has a veto.  PJM can file a

         19   206 any time they want, with the right standard.  It has to

         20   be just and reasonable, and they have to show the existing

         21   tariff is not just and reasonable.  That's a perfectly fine

         22   standard.  That's the Commission's standard.  There's

         23   absolutely no reason to change the 205.

         24              But it all comes back to none of that makes any

         25   difference.  Speed, decisiveness.  None of it makes any





                                                                      253



          1   difference unless you address these two fundamental issues

          2   that I raised at the beginning.

          3              And other people have said it.  One is about the

          4   board independence, and what does that mean.  It's both

          5   nominating and being able to be voted out.  And I don't care

          6   if you think that people shouldn't react to that fact.  They

          7   do react to it.  It is a fact.  It's a reality, and you

          8   can't avoid it and it needs to be addressed.

          9              The same thing is true for the charge of the

         10   staff.  The staff should be charged with acting in the

         11   public interest.  Unless you address both those things, all

         12   the speed and decisiveness is not going to get you anywhere.

         13              And last but not least, the members are not to

         14   blame to bogging down the stakeholder process.  

         15              And, I'm sorry, actually one other statement. 

         16   (Laughs.)

         17              (Laughter.)

         18              DR. BOWRING:  Members are not customers.  As the

         19   public advocate said.  Members are not customers.  PJM

         20   should be responsive to its customers.  And it frequently

         21   confuses those two things and calls its members its

         22   customers.  Its members are not its customers.

         23              Thank you.

         24              CHAIRMAN SWETT:  Who is to be blamed for bogging

         25   down the stakeholder process, then?





                                                                      254



          1              DR. BOWRING:  I think, significantly, PJM.  And

          2   it's because -- it's the lack of leadership, that other

          3   people have pointed to.  And it all comes back, again, to

          4   the same thing I said.  If the board were guaranteed its

          5   independence, if the staff were charged with the public

          6   interest, that would make the process work more smoothly.

          7              And look, I mean, I can point to lots of examples

          8   of what bogs it down.  We don't need to get into all the

          9   details.  But, I mean, it's a shared responsibility, to be

         10   fair.

         11              But leadership, structuring the process better,

         12   would help.

         13              And I'm a firm believer in all the subcommittees,

         14   by the way.  So...

         15              (Laughter.)

         16              DR. BOWRING:  Thanks.

         17              CHAIRMAN SWETT:  I think Jodi's was next.

         18              MS. MOSKOWITZ:  Just two points.  On the board

         19   composition, I do think, you know, it's so critical that the

         20   members have confidence in the board and in its

         21   capabilities.  I know, in New Jersey, we have rules that

         22   require our board of directors to have a certain percentage

         23   of board members who either reside in the state or have

         24   significant ties to the state.

         25              So, one thing, and I think Commissioner Rosner,





                                                                      255



          1   you mentioned this, that, you know, thinking about there

          2   probably should be requirements, to tie more board members -

          3   - to make sure that they have connections to the PJM region. 

          4   So that's one -- one point I would make.

          5              Another, broader, point to kind of -- to some of

          6   the points that Dave has been making, about culture -- and I

          7   can hear some of this on the panel here.  I think it's very

          8   important.  I don't think we're going to get to the best

          9   outcomes where there's a lack of clarity of

         10   responsibilities.  I think we have suffered from that for a

         11   while.

         12              You know, when I think about what PJM is and what

         13   they're not, PJM is a public utility, just like PSE and G

         14   is.  Fully regulated by FERC, has to make filings at FERC,

         15   show that the filings are just and reasonable.  PJM is not -

         16   - they're not a regulatory agency.  They're not a rate

         17   regulator.  They are not a siting or permitting agency.

         18              And I think that sometimes -- and look, maybe

         19   this gets to PJM taking better control of these processes --

         20    I would also add they are not an integrated resource

         21   planner, which is where, I think, we've had a lot of lack of

         22   clarity on resource adequacy, because the states do have

         23   responsibility for that.

         24              So, I think that lack of clarity on respective

         25   responsibilities and accountabilities has really hurt PJM,





                                                                      256



          1   and continues to hurt PJM.  And I think until we have more

          2   of that, we're not going to get to the outcomes that we need

          3   in an expeditious and effective way.

          4              CHAIRMAN SWETT:  Okay, we're going to -- I'm

          5   going to execute my chairman's privilege one more time.  But

          6   first we'll let Jameson make his comment, and then we're

          7   going to take another vote.

          8              (Laughter.)

          9              MR. TWEEDIE:  Thank you.  So, just on the

         10   stakeholder process, why I think it is so important that the

         11   public interest, affordability, cost, be part of that

         12   process, is because we came here and we heard the opening

         13   statements this morning.  The massive growth in large loads

         14   is creating an immense problem in this region especially,

         15   but across the country, and that is going to have

         16   consequences for consumers.

         17              And we heard -- we have had the White House and

         18   all the governors reach a statement of principles, and we've

         19   had the hyper scalers reach a pledge, a rate payer

         20   protection pledge, with the White House.  And yet, we are in

         21   a stakeholder process that is failing those goals, and for

         22   which the states cannot succeed in allocating costs not to

         23   their existing customers, if PJM doesn't succeed in its

         24   part.

         25              So, we already have an estimated 30 billion in





                                                                      257



          1   capacity costs, that are getting shared out to consumers

          2   across the region.  And those are the direct result -- thank

          3   you, Dr. Bowring, for this analysis -- of large loads. 

          4   Right?

          5              And we have proposals right now that are, in the

          6   view of consumer advocates, not sufficient and, in fact,

          7   will prevent the states from being able to properly allocate

          8   costs, because costs from data centers and this load growth

          9   will be included in things that the states can't allocate

         10   away.

         11              And so, what the states need and consumers need

         12   is a partner at PJM that will help them effectuate what the

         13   rate payer protection pledge and what the statement of

         14   principles promise, that we are all striving to do.

         15              And if consideration of costs and the public

         16   interest, in consumers, are not part of PJM's decision

         17   making and are, in fact, often rejected as part of the

         18   stakeholder process, then we are never going to get to

         19   outcomes that achieve the purposes that we all heard this

         20   morning -- and I think we all agree with -- are the basic

         21   premises that we should be trying to strive for.

         22              Thank you.

         23              CHAIRMAN SWETT:  Thank you.  Well said.

         24              So, we're going to go down the line and take a

         25   yes/no vote.  Do you, or do you not, support PJM moving





                                                                      258



          1   schedules one, two, and six -- that's the energy market and

          2   RTEP protocol -- from the operating agreement to the

          3   tariff, per David's suggestion?

          4              So, if you support David's suggestion, vote yes. 

          5   And I'll start with David because, I mean, I've got to give

          6   you something.

          7              MR. ANDERS:  I don't normally get a vote in the

          8   process, but thank you.

          9              (Laughter.)

         10              MR. ANDERS:  So, I vote yes.

         11              MR. THOMAS:  Because I don't want to be tied up

         12   in court for years when there are so many other things we

         13   need to address, no.

         14              CHAIRMAN SWETT:  Okay.

         15              MS. MOSKOWITZ:  Yes, with enhanced accountability

         16   for PJM.  But yes.

         17              MR. TWEEDIE:  I think any changes like that have

         18   to come with changes that ensure accountability,

         19   transparency, and public interest in PJM.

         20              CHAIRMAN SWETT:  So, is that a yes or a no?

         21              MR. TWEEDIE:  Neither.

         22              CHAIRMAN SWETT:  Neither!  Okay, you're

         23   abstaining.  Interesting.

         24              MR. EMNETT:  No, we need leadership using the

         25   tools that are already available.





                                                                      259



          1              CHAIRMAN SWETT:  No, okay.  Brian?

          2              MR. GEORGE:  Yes, with the recognition, to

          3   Mason's point -- right? -- that it doesn't really address

          4   the problem that's in front of us right now.

          5              MS. BRUCE:  I have to be no for now, because it

          6   doesn't get anything built.

          7              DR. BOWRING:  No, because it doesn't even begin

          8   to address the question.

          9              CHAIRMAN SWETT:  Okay.  Thank you all very much

         10   for that.

         11              COMMISSIONER LACERTE:  I wanted to open it up to

         12   Mason real quick, since we have a few minutes left, and Jodi

         13   answered my question, but we didn't get to Mason before.

         14              So, Mason, you've been in my office many times,

         15   with Constellation, which I greatly appreciate.  We've had

         16   these discussions and I've sent you back to the drawing

         17   board and told you to come back and look at things

         18   differently, which I greatly appreciate you going through

         19   the exercise.

         20              But now that you've heard me ask it many times

         21   over, I want to give you the opportunity to tell me you see

         22   things my way.

         23              (Laughter.)

         24              COMMISSIONER LACERTE:  So, essentially, like, are

         25   you a member of the sous chefs union or not?





                                                                      260



          1              (Laughter.)

          2              MR. EMNETT:  PJM is the chef.  It has different

          3   tools in is tool box.  Right?  And we don't believe that

          4   those tools need to be changed; we believe they should be

          5   used.

          6              COMMISSIONER LACERTE:  I appreciate that answer. 

          7   I also say we are in a time and place in history, at FERC,

          8   and with PJM, that we cannot simply lean back and trust that

          9   these things will occur, with PJM not receiving reforms.

         10              I think just hoping that things will be different

         11   is woefully insufficient in this environment, and we need to

         12   undertake initiatives which drive that change, from our

         13   chairs.

         14              MR. EMNETT:  If I could, what I suggest

         15   consideration of, PJM, the things that we are spending most

         16   of our time on, and the states and federal policymakers are

         17   the most concerned about are the resource adequacy planning

         18   and infrastructure issues, over which PJM has 205 rights.

         19              And so, changing 205 rights over the thing we are

         20   not fighting about does not solve the issue, and in fact

         21   might reinforce that the approach to using 205 rights, to

         22   date, is sufficient, which we don't believe that it is.  We

         23   should not use a critical infrastructure fast path process,

         24   that has "critical" in the title, to spend a good chunk of

         25   last year on developing solutions to meeting large load, to





                                                                      261



          1   end up, at the end of that process, starting another

          2   critical issues fast path, with the word "critical" in it,

          3   to get to solutions that now we hear are coming, which are

          4   great -- right?  But we needed those previously.

          5              That is about leadership and execution of

          6   responsibilities, and I appreciate that these challenges are

          7   difficult, but that's what we are all called upon to do. 

          8   Call the balls and strikes, move things forward.  If there

          9   isn't membership agreement on energy market issues, well

         10   then can move under 205, but those are not the

         11   disagreements that we have today.

         12              The one issue that is pointed to as an example,

         13   the reserve certainty task force.  So that is already ORDC

         14   2.0. 

         15              We already lived through that process of multiple

         16   years working through ORDC reforms, which made their way to

         17   the Commission, and were approved.  They ended up facing

         18   legal troubles or remand -- you know, a whole saga there. 

         19   Right?  

         20              But PJM had the ability to move that issue, and

         21   PJM could have moved on those issues in their rebirth.  Much

         22   easier.  It did not need to languish for three years, in the

         23   stakeholder process.  It could have been moved forward.

         24              Yes, there was a lot of education that was

         25   needed.  But people can get the resources to come to the





                                                                      262



          1   table and negotiate those issues, and you move forward.

          2              That's the only thing that has been pointed to,

          3   on 205 versus 206.  Everything that we're spending our time

          4   on, there are already 205 rights over.  So we just don't see

          5   the solution that's being offered as actually fixing

          6   anything.

          7              COMMISSIONER LACERTE:  So, it's your opinion that

          8   PJM simply lacks the will to make these decisions?

          9              DR. EMNETT:  We haven't seen the evidence of

         10   that.

         11              COMMISSIONER LACERTE:  Dave?

         12              MR. ANDERS:  I'll just add a couple of other data

         13   points to the RCSTF, the reserve certainty.  Years before

         14   that, it was the Energy Market Uplift Senior Task Force. 

         15   Then it was the Energy Market Price Formation Senior Task

         16   Force.  All of which languished, all of which were energy

         17   market issues in schedule one.

         18              COMMISSIONER LECERTE:  Look, I think that we've

         19   all been a little frustrated by many things, in this room

         20   today.  And, as we've stated over the course of several

         21   years.

         22              First and foremost is we don't get to see the

         23   stakeholder votes, in this process.  And very limited people

         24   get to see those stakeholder votes.  I still don't know who

         25   gets to see the stakeholder votes, in this process.





                                                                      263



          1              So, I think it's important that we all get to see

          2   these opinions and who holds them, and where those opinions

          3   fall in line.  I think we have a list of good governance

          4   reforms that are on the table.

          5              So, I think what we should do, Madam Chairman, is

          6   I think we should attach a ballot, to be sent out to all the

          7   PJM stakeholders, to put them on the record, say "Where do

          8   we stand on these issues?  Do we stand in favor of good

          9   governance reforms where we see them?  Are we opposed?"

         10              Because I do think the public believes a lot of

         11   these stakeholders vote in line with their interests.  I

         12   think that's a commonality.  And I think that's one thing

         13   that we expect the process to flesh out in that direction. 

         14   And it's just not acceptable anymore.

         15              I think that some of these proposals will drive

         16   change, in a positive manner.  Like Dr. Bowring said, we

         17   don't want to go in the wrong direction, but I think a lot

         18   of these things are very simplistic in nature.  Cooperating

         19   with the states.  A better use of our time and priorities. 

         20   Prioritizing our effort.

         21              So, I think it would be helpful for us to attach

         22   a ballot to each individual PJM stakeholder, to put them on

         23   the record as to where they stand with these issues.

         24              CHAIRMAN SWETT:  Well, thank you all very much

         25   for your time and participation today.  This has been very





                                                                      264



          1   engaging.

          2              It's very clear that there are a few frontrunner

          3   issues.  I agree with you there.

          4              So, we're going to deliver some closing remarks

          5   now.  I'll give my colleagues an opportunity.  Well, you've

          6   got five minutes, right Judy?

          7              COMMISSIONER CHANG:  No.  Less than five minutes.

          8              CHAIRMAN SWETT:  Okay, go ahead.

          9              COMMISSIONER CHANG:  I just want to say thank

         10   you, and thank you, thank you, thank you, for everyone's

         11   participation.  But I also wanted to summarize a few things

         12   that are -- I think, everybody agreed.  And I just want to,

         13   maybe, have you all take some notes and see -- maybe you can

         14   respond in writing afterwards.

         15              One is that -- I have in my notes sort of

         16   categories.  States, and then PJM management, and PJM board.

         17              For states, representation on board nomination

         18   committee, I feel like there was some, more or less,

         19   agreement.  Active engagement, PJM and PJM board, on

         20   strategy, or goals, or some sort of thing like that. 

         21              Either one or two organization of states that

         22   will -- that might have a jump ball ability with the PJM, so

         23   that they have some leverage in, like, big ticket decisions.

         24              For PJM management, I think I just want to

         25   reiterate, prioritize goals, work streams, set deadlines for





                                                                      265



          1   stakeholders.  And I put a big question mark, because

          2   listening to this panel, like, whether or not the 205 rights

          3   need to be shifted a little bit or not, or whether the

          4   existing 205 rights on resource adequacy is adequate for the

          5   current challenge, I put a question mark on that.  But I

          6   think that was raised a lot.

          7              And for PJM board, I heard a lot about

          8   independence.  The word "independence" is overused, so we

          9   probably need to define what -- independence from what.

         10              I also heard "skill sets" and residency.  But

         11   probably more like skill sets, or just qualifications in

         12   general.  I think that's something worth examining.

         13              And, board decisions transparency.  I think we

         14   heard that quite a bit, and whether it's board transparency

         15   or is voting member transparency, but there seems to be some

         16   accountability about who is agreeing to this and who is

         17   making these decisions, and how do we arrive at the final

         18   outcome.

         19              And then, need to get more empowerment for the

         20   management.  So that's, I think, between the board and the

         21   management.

         22              And then, public interest in both board and

         23   management, probably.  I think that's what we heard from

         24   states and definitely Dr. Bowring.  I think that's worth

         25   talking about.





                                                                      266



          1              And then, I put a question mark on ex parte

          2   rules, just accessibility of the board members from

          3   stakeholders.  I put a question mark.  It was raised and

          4   written up, but I put a question mark, because I don't know

          5   if we have a consensus on that.

          6              But I just want to put that out there as a straw

          7   man, so that you all can think about it in terms of "Is

          8   that a package that, or parts of a package that everyone can

          9   agree to as a solution?"

         10              So, with that, thank you very, very much.  This

         11   was such an engaging day, and thank you, Chair, for your

         12   leadership to make this happen.

         13              CHAIRMAN SWETT:  Thank you for that summary. 

         14   That was helpful.  And safe travels.

         15              So, let's -- I just want to be unmistakably clear

         16   about the path forward today.  Governance is not glamorous. 

         17   But you all did a great job of engaging us, for a very long

         18   amount of time.

         19              So, this conference was not an academic exercise. 

         20   We're on the beginning of a path, and the end of it is going

         21   to be reform.  How we get there is really up to you and the

         22   stakeholders in the market.

         23              So, here is what we're going to do.  We're going

         24   to issue a post-conference notice seeking comments on the

         25   issues that were discussed today, and per Commissioner





                                                                      267



          1   LaCerte's suggestion, that notice is going to include a list

          2   of questions for stakeholders, that are designed to gather

          3   robust and unambiguous answers to the core issues affecting

          4   PJM's governance model and stakeholder process.

          5              This is your opportunity to be heard, and I

          6   expect full engagement.  We want clear positions and a

          7   willingness to move toward solutions.  And if you do not

          8   respond, and you are a stakeholder, then we are going to

          9   assume that you do not care.  That is a rebuttal presumption

         10   that you have the opportunity to overturn.

         11              After we've received these post-conference

         12   comments, we are going to direct the Commission's dispute

         13   resolution service to convene a forum, in September.  It

         14   will be rigorously structured and time bound, so that we can

         15   finalize a package of solutions.

         16              So, 99 years ago, in 1927, September, PJM was

         17   formed, and perhaps this September is when PJM can be saved. 

         18   But I want you all to hear this plainly.  If the

         19   stakeholders cannot reach a set of credible, meaningful,

         20   reforms, or an agreement in principle, by the end of

         21   September, then this Commission is not going to hesitate to

         22   use the full extent of our legal authority to implement

         23   reforms necessary to restore confidence in PJM's governance.

         24              But I am confident that the people in this room,

         25   and the ones who are not here, can work together to reach





                                                                      268



          1   reforms, so that PJM can be on a path toward success, and

          2   hopefully without Commission intervention.

          3              Finally, I really, sincerely, want to thank

          4   Commission staff, who made this conference possible.  You

          5   did a fantastic job moderating, and so did your predecessor,

          6   and a lot of hard work went into this.  Especially Kevin, in

          7   my office, who was integral to putting this together for us. 

          8   And I hope he doesn't regret working for me, but I'm glad

          9   you're still here.

         10              And thank you all to the panelists who

         11   participated today, and thank you for enduring our grilling,

         12   and your contributions were very invaluable, and we have a

         13   lot to walk away with today and a lot to think about.  So,

         14   thank you all.

         15              So, Commissioner Rosner?

         16              COMMISSIONER ROSNER:  Thank you, Chairman.  Thank

         17   you to all the panelists and to the Commission staff, for

         18   putting this together.  I know it's non-trivial to come

         19   spend a day in Washington with FERC, and I really appreciate

         20   it.  Not just in person but your statements.

         21              I want to come back, briefly, to just why we're

         22   here.  For me, the highest priority issue is that we're

         23   6,800 megawatts short, two years from now.  And that puts us

         24   below the requirement that we have to have a reliable grid.

         25              And, for me, that's quite scary.  When you think





                                                                      269



          1   -- you heard from Peter Lake earlier, in Texas, during

          2   winter storm Uri, their reliability problem cost 246 people

          3   their lives.  And when you think about a region like PJM,

          4   where we have equally hot weather -- in fact, the hottest

          5   place in the country, two weeks ago, I believe, was here, in

          6   Washington, D.C.

          7              And so, if we move forward and we don't have

          8   enough resources to be reliable, people could die, and that

          9   is very serious business, and it's a really solemn burden

         10   that we need to solve.

         11              And so, I hear you all on the frustrations with

         12   the leadership, with the stakeholder process.  There's a

         13   variety of different opinions on where we need to go.

         14              The way I see it is that the board has not acted

         15   on this statement of principles regarding PJM, that the

         16   governors agreed to, along with the White House.  And that's

         17   because you all don't agree on how to close the 6,800

         18   megawatt resource adequacy gap, what the best way to do that

         19   is.

         20              And it's not that any particular stakeholder is

         21   wrong about the way to do it.  I think the reality is that

         22   there's a variety of different ideas for how to do that, and

         23   we've talked about many of them, both in writing and in

         24   person.

         25              But, the reality is that the board now does need





                                                                      270



          1   to decide, and they're going to do that.  And what I see the

          2   value of this conference is, is that we had a really hard

          3   time reaching agreement on that issue.  It's a very

          4   complicated issue.  And this is a very important moment for

          5   us all to think, again, about if our stakeholder process

          6   worked better, are there things that we learned from this

          7   last go-around that might make it work better in the

          8   future?

          9              Because, there will be more critical issues for

         10   us to work on then.  And so that's the takeaway.

         11              I think there's a lot that's been changing, in

         12   the energy system recently.  There's a lot of new demand. 

         13   It's demand that we just haven't seen for a generation.

         14              And part of the frustration that I heard from

         15   some stakeholders is oh, you know, a governor and states

         16   filed a complaint that limited the ability of the RPM to

         17   deliver the capacity that it was designed to deliver,

         18   because of the price cap, and there's been a big debate

         19   about that.

         20              And the reality is just that things are changing

         21   very fast.  The states, they do the retail rate allocation. 

         22   I know that's a very critical -- affordability is a critical

         23   issue.  It's a critical political issue.

         24              You know, we spent a day with the US Senate.  We

         25   spent another day with the US House.  And this is just is a





                                                                      271



          1   political issue.  And so that's why we've heard so much

          2   about governance.  That's why the state role is so

          3   important.  That's why we need our state regulators working

          4   with us, to do the cost allocation, to do the curtailment

          5   priority, to make sure that we have the CPECNs ready for

          6   things that come out of this market.

          7              But I'd encourage you, as we contemplate a next

          8   step here, which I really hope is not a long delay to a next

          9   step, is that we really think about "Are there things that

         10   we can do that might require you to give up a little bit of

         11   control, that ultimately get us better outcomes, faster

         12   outcomes, that drive you to make the harder decisions with

         13   each other, faster.  That's what I want to get out of this

         14   conference.

         15              And I think -- I feel optimistic, based on the

         16   corners of the debate we've had, that there are

         17   opportunities.  And I look forward to working on that with

         18   you.

         19              Thank you.

         20              CHAIRMAN SWETT:  Commissioner See?

         21              COMMISSIONER SEE:  Thank you to our panelists

         22   from this panel and all the others, to FERC staff and

         23   others, who worked so hard on this.  I know better than to

         24   keep everybody late.  It's coming up on four o'clock, after

         25   seven hours of the tech conference.  But I genuinely





                                                                      272



          1   appreciate everyone's engagement here.

          2              And I think the energy goes down at the end of

          3   the day, but that definitely didn't change the quality of

          4   the ideas and the discussion.  I really appreciate that.

          5              I was glad to see a number of things come out of

          6   today.  I said at the beginning of the day I hope that there

          7   was some low hanging fruit, and I think that we found that. 

          8   So, I really encourage you stakeholders in PJM, especially

          9   going into this September process, to use that as a starting

         10   point but not an end point.

         11              There's a number of things that came out of

         12   today, obviously, and "board independence" I think is

         13   probably the phrase we heard more than any other.  So, I'm

         14   also encouraged to see a lot of good discussion around those

         15   areas, paired of course with accountability and also, I

         16   think, figuring out who chooses the board matters.  And

         17   we've heard a number of compelling conversations on that

         18   point.

         19              You know, from my point, I find it pretty

         20   persuasive to have a meaningful role for the states, in that

         21   area.  So, I really look forward to continued conversation

         22   and movement in those areas.

         23              You know, I also think we talk a lot about how

         24   consensus is the gold standard for decision making and I

         25   think that's definitely true.  But we've got to figure out





                                                                      273



          1   what happens when we can't get to consensus.  We just have

          2   to figure out how to break through the stalemate.

          3              And, to my mind, we heard a lot of traction about

          4   an advisory stakeholder process.  I am not saying that that

          5   is the end of the road, but I think that, as we go through

          6   the rest of the process, we need to have some serious

          7   conversation "If not that, what else?"  Because we can't

          8   have a process where we are hoping for a consensus and don't

          9   always get there at the time that we need, especially with

         10   the urgency of the issues in front of us.

         11              Another theme that came out is there's a number

         12   of things that PJM can be doing now, and I think that's

         13   great, and I would love to see that happen.  I think there's

         14   a really helpful conversation about leadership and

         15   ownership.

         16              We talked a lot about setting priorities, of

         17   setting work streams.  We talked a lot about getting the

         18   states involved earlier, and forcing deadlines and some

         19   discipline in the stakeholder process.  There's a number of

         20   things that don't require formal changes, so why aren't we

         21   doing them now?  Let's make sure we've moving forward in

         22   that direction.

         23              We have a formal process we're going to continue,

         24   because we don't want to lose sight here, but that doesn't

         25   mean we have to wait 'til the end of the process, to move





                                                                      274



          1   forward.

          2              And I think, on that point, I'd also say, you

          3   know, especially in reflecting on this panel here, I hear

          4   from many of the stakeholders who, you know, say maybe we

          5   should be focusing on other things, or this may not be the

          6   right way to solve all these problems.  And I heard a couple

          7   of times that the tools are in PJM's hands, we don't have to

          8   make broader reforms.

          9              But we're here for a reason, because we have a

         10   process that hasn't been delivering the results we need. 

         11   So, I would really encourage you, help PJM on some of these

         12   changes that you think already exist and are possible.  Make

         13   them happen.  You know, help us figure out ways that we can

         14   be smart about the sort of additional reforms that are

         15   necessary.

         16              And if you really believe we don't need to be

         17   doing more, or that we're not focusing the right way, then

         18   we've got to have a way to show confidence that we're going

         19   to get the results we need, under the status quo.

         20              I think it's probably obvious I'm revealing my

         21   cards.  I'm skeptical that that's true, but we have to make

         22   sure that we have concrete ideas and solutions other than

         23   just "It could be better," based with the tools that exist

         24   today.

         25              So, I really encourage everyone to continue





                                                                      275



          1   working collaboratively through this process.  As we all

          2   said, we would love to not have to take additional actions

          3   as a Commission, and I have real confidence in the people

          4   and the interests that are represented in this room and

          5   across PJM, to be able to make the sort of meaningful and

          6   thoughtful changes we need, at the pace we need to.

          7              So, please do that.  We want to be a resource to

          8   help, as well.  You know, we do take seriously that we've

          9   got some timing considerations in order to make sure that we

         10   keep moving forward here.  But I am leaving today with a lot

         11   of optimism that there are some clear paths forward, and I

         12   hope that in a few months and in a year we'll be able to

         13   look back and see that PJM is weathering this really

         14   critical moment.  So, thank you for all of your work so far.

         15              We've all got a lot ahead, but I'm optimistic

         16   that we have a good outcome.  Thank you all.

         17              CHAIRMAN SWETT:  Very well said.  LaCerte?

         18              COMMISSIONER LACERTE:  I want to repeat my thanks

         19   to all the panelists today.  It takes a lot of courage, a

         20   lot of preparation, a lot of risk, to come up here and speak

         21   your mind, when you're called to -- asked your opinion on

         22   things that might not have been fully vetted with your own

         23   folks.  I know sometimes that's uncomfortable.

         24              But I want to say thank you for taking the time

         25   out to talk to us, to let us know your opinions and





                                                                      276



          1   thoughts.

          2              A couple things Dr. Bowring said that kind of

          3   stuck out to me.  I know he talked about the staff at PJM. 

          4   And I visited PJM a couple weeks ago, and I think what he

          5   means is the leadership and the board, because I've seen it

          6   firsthand.  The staff at PJM is truly talented.  And these

          7   are individuals that pour themselves out into their jobs for

          8   the common good, and are truly aligned with the public

          9   mission of keeping the lights on, in PJM.

         10              So, I want to say thank you to the staff.  They

         11   are kind of embroiled in this because they're caught up in

         12   leadership a little bit, in these key issues with

         13   leadership.  But theses are all issues that have solutions. 

         14   But we cannot let them figure it out on their own and hope

         15   that it goes away and everything's going to be okay.

         16              There's another thing Dr. Bowring said, is that

         17   we don't want to run in the wrong direction, and we don't

         18   want to run in the wrong direction.  Every single choice we

         19   have at the table entails a certain amount of risk.  But,

         20   you know, where we stand right now, where we sit, if we

         21   don't change, there's a hundred percent chance of failure. 

         22   It is going to get worse if we don't adapt and change and

         23   get better.  So, we need to be bold.

         24              Another thing is, like if I am on the board and I

         25   am David in the CEO's chair, I think there's a lot of





                                                                      277



          1   optimism out of this conference, because I take this as a

          2   mandate.  Any time you have individuals at this table saying

          3   you're not taking action, and you can, guess what I'm going

          4   to do.  I'm going to run out and I'm going to take action,

          5   and I'm going to let it rip, because that is what you're

          6   being told here today.

          7              So, you're getting top cover, from this table. 

          8   You have support from this commission.  You have all the

          9   mandate in the world to take all the action you need, to

         10   make sure the lights stay on in PJM, we procure the capacity

         11   we need, we build out the transmission we have, and we do

         12   everything we can to go to the end of the line.

         13              Now, all that being said, am I going to trust

         14   that that happens?  I think you guys know the answer to

         15   that.

         16              I think I want to see some bold action and ideas

         17   out of PJM, and if we don't get that action out of PJM, we

         18   will use every single legal authority within us, and maybe

         19   some more, to figure that out.

         20              So, that's the name of the game here.  It's a

         21   mandate and it's a charge.  

         22              You know, I am a little more optimistic here.  I

         23   mean by nature I'm a pessimist.  So that's a good thing.

         24              Again, thank you all for coming today.

         25              CHAIRMAN SWETT:  All right.  Let it rip,





                                                                      278



          1   everybody.

          2              (Laughter.)

          3              (Whereupon, at 4:02 p.m., the technical

          4   conference adjourned.)

          5   

          6   

          7   

          8   

          9   

         10   

         11   

         12   

         13   

         14   

         15   

         16   

         17   

         18   

         19   

         20   

         21   

         22   

         23   

         24   

         25   





                                                                      279



          1   

          2                CERTIFICATE OF OFFICIAL REPORTER

          3   

          4              This is to certify that the attached proceeding

          5   before the FEDERAL ENERGY REGULATORY COMMISSION in the

          6   Matter of:

          7              Name of Proceeding:

          8              PJM Governance and Stakeholder Reforms

          9   

         10   

         11   

         12   

         13   

         14   

         15              Docket No.:  AD26-7-000

         16              Place:       Washington, D.C.

         17              Date:        Thursday, July 23, 2026

         18   were held as herein appears, and that this is the original

         19   transcript thereof for the file of the Federal Energy

         20   Regulatory Commission, and is a full correct transcription

         21   of the proceedings.

         22   

         23   

         24                                  Larry Flowers

         25                                  Official Reporter