ER26-3515-000 · 2026-08-31 · Google LLC

Answer of Google LLC in Support of the Organization of PJM States, Inc.’s 08/28/2026 Motion for Extension of Time

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
)
)
)
)

Docket No. ER26-3515-000

ANSWER OF GOOGLE LLC

Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy
Regulatory Commission (“Commission”),1 Google LLC (Google) respectfully submits answer in support of the Organization of PJM States, Inc.’s motion for an extension of time in which to respond to PJM Interconnection L.L.C.’s (“PJM”) filing in the above-captioned proceeding. Simply put, this is a proceeding motivated by and largely about retail customers and how they are regulated—matters over which the Federal Power Act reserves exclusive jurisdiction to the States. 2 For that reason, it is absolutely vital that the States have the time they need to formulate a fulsome response to PJM’s proposal.  The Commission cannot issue a well-reasoned decision without that input.  Accordingly, Google urges the Commission to grant the request for an extension.

Respectfully submitted,

[Signatures on next page]

1 18 C.F.R. § 385.213 (2026). 2 16 U.S.C. § 824(b); FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 279 (2016) (FPA Section 201(b) “‘limit[s] FERC’s sale jurisdiction to that at wholesale,’ reserving regulatory authority over retail sales (as well as intrastate wholesale sales) to the States.” (quoting New York v. FERC, 535 U.S. 1, 6 (2002)).

PDF page 2

-2-

/s/ Brian George
Brian George
Sr. Lead, US Energy Markets
Elizabeth Savage
Strategic Negotiator
Google LLC
655 New York Ave., NW
Washington, DC 20001
(202) 999-0990
briangeorge@google.com
eomsavage@google.com

Matthew Christiansen
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
mchristiansen@wsgr.com
bshpall@wsgr.com

Counsel for Google LLC

Dated:  August 31, 2026

PDF page 3

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.

Dated:  August 31, 2026
Washington, D.C.

/s/ Bryan Shpall
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006