ER26-3515-000 · 2026-09-03 · Individual No Affiliation
Comments of the Chief Energy Officer Josephus M. Allmond et al. of the Commonwealth of Virginia re the PJM Interconnection, L.L.C.'s proposed Interim…
PDF page 1
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY
COMMISSION
)
PJM Interconnection, L.L.C
)
Docket No. ER26-3515-000
)
COMMENTS OF THE CHIEF ENERGY OFFICER
FOR THE GOVERNOR OF VIRGINIA
The Chief Energy Officer for the Governor of the Commonwealth of Virginia respectfully submits these comments regarding PJM Interconnection, L.L.C.’s (“PJM”) proposed Interim Resource Adequacy Service (“IRAS”) and Large Load Registry.
Introduction
Virginia’s central priority is straightforward: the Commonwealth must be able to meet growing electricity demand with an affordable, reliable, and clean energy system, while protecting households and businesses from costs driven by the rapid growth in large load demand. Achieving that outcome requires that large-load customers pay their fair share for the capacity and infrastructure needed to serve them, and that PJM’s market rules provide strong incentives for those customers to reduce their impact on the grid.
PJM’s proposal is an important step, but the current IRAS design does not yet establish sufficiently clear, robust, technology-neutral pathways for large loads to pursue and receive credit for beneficial grid investments. We support refinements that ensure the program adequately rewards measurable peak-demand reductions, enables demand-side and distributed-energy resources to participate fully, and appropriately assigns curtailment risk to the loads associated with the identified resource adequacy concern.
Areas of Support
Virginia supports several important elements of PJM’s proposal.
PDF page 2
First, large load customers that drive new system needs should bear an appropriate share of associated costs and reliability obligations. This principle is essential to protect households, small businesses, and existing customers in Virginia and throughout PJM from cost shifting as large load electricity demands grow.
Second, Virginia supports PJM’s proposed approach to curtailment priority. In an emergency, curtailment risk should fall first on new large loads that have not adequately secured capacity or reduced their contribution to system peak demand, rather than on residential customers, small businesses, or demand-response participants that have already made firm and compensated reliability commitments.
Third, Virginia supports PJM’s recognition that large loads can contribute to reliability by bringing new capacity, reducing peak demand, or deploying distributed and demand-side solutions. Distributed energy resources (“DERs”), demand response, energy storage, and other demand- flexibility tools can be deployed more quickly and cost-effectively than traditional infrastructure. PJM should maintain and continue to enhance its technology-neutral rules that allow all resources capable of providing measurable reliability value to compete on fair terms.
Areas of Concern
The Commission should ensure that PJM’s final IRAS framework better reflects these principles. In particular, there are two areas that we encourage the Commission to address:
1. Credit verified peak shaving
PJM’s proposal does not reduce a large load’s IRAS curtailment exposure when that customer has secured verified demand reductions, including through the Peak Shaving Adjustment mechanism. Similarly, the proposal does not establish a clear mechanism through which measurable load reductions can reduce a large load’s allocated RBP costs. These gaps should be
PDF page 3
corrected so that large loads receive appropriate credit for actions that reduce their impact on the grid. Properly valuing verified demand-side reductions will help address PJM’s resource adequacy needs, mitigate capacity-cost pressures, and advance regional reliability and affordability. A large load that secured verified demand reductions to reduce its impact on peak demand should receive a corresponding reduction in its IRAS curtailment exposure. Large loads that take measurable steps to reduce their impact on the grid—whether through verified demand reductions or by bringing new capacity online—should receive a corresponding reduction in curtailment exposure and be curtailed only after other large loads that have not taken such steps. This should also apply to reduction in Reliability Backstop Procurement (RBP) cost allocations, with large loads that secure verified demand reductions (such as through the Peak Shaving Adjustment) being appropriately credited for their reduction in impacts on the grid. Virginia has already acted to establish pathways for voluntary demand-flexibility programs that enable large loads to secure measurable and verifiable load reductions (see Virginia Code § 56-596.7). PJM’s rules should provide a clear, timely, and administrable process through which these state-supported arrangements can be recognized in IRAS as well as the RBP cost allocation, with such reductions accounted for in a customer’s curtailment exposure and related obligations. This is an essential area for PJM to clarify to enable demand-side programs to be viable and valuable in supporting PJM’s capacity needs.
2. Enable meaningful DER participation
As we previously shared with the PJM Board,1 Virginia supports PJM’s effort to create pathways for DERs and demand-side resources to participate through peak-shaving mechanisms and through opportunities for large loads to bring new capacity. But eligibility on paper is not
1 Virginia Chief Energy Officer Letter to PJM Interconnection in re: Integrating DERs and Demand Response in Reliability Backstop Auction. June 29, 2026.
PDF page 4
enough. The rules must work in practice for the resources that can provide reliability value most quickly.
PJM should avoid requirements that arbitrarily limit or disadvantage demand-side resources relative to traditional generation. In particular, PJM should ensure that its definitions of qualifying or “new” capacity recognize incremental capacity additions, including upgrades and reactivations, new investments at existing sites, or returning sites that have not recently participated.
A technology-neutral structure that evaluates resources based on their demonstrated reliability contribution—not the particular technology or business model used to deliver it—will expand competition, strengthen reliability, and reduce costs for consumers.
Conclusion
Virginia is committed to continuing its leadership in addressing resource adequacy, protecting ratepayers, and advancing cost-effective energy solutions. Just this year, the Commonwealth acted to dramatically expand energy storage requirements for utilities,2 ease the path for large load customers to fund new zero-carbon dispatchable resources,3 support fair cost allocation,4 create a voluntary demand flexibility program for large loads,5 and other tools needed to meet this moment responsibly.
PJM must now do its part. The Commission should ensure that the IRAS framework fairly assigns responsibility to new large loads, prioritizes those loads for curtailment when they have not sufficiently addressed their reliability obligations, and provides meaningful credit for verified peak shaving, DERs, and other demand-side resources in addition to bring-your-own-new-capacity
2 2026 Va. Acts Ch. 695.3 2026 Va. Acts Ch. 43.4 Comments of the Chief Energy Officer of the Governor, Case No. PUR-2026-00056.5 2026 Va. Acts Ch. 378.
PDF page 5
frameworks. With these improvements, IRAS can better support the shared goals of reliability, affordability, fairness, and a resilient energy system for Virginia and the PJM region.
Respectfully submitted,
Josephus M. Allmond, Chief Energy Officer
Louise G. White, Deputy Energy Officer
Office of the Governor of Virginia
1111 East Broad Street
Richmond, Virginia 23219
September 3, 2026