ER26-3515-000 · 2026-09-03 · Microsoft Corporation

Comments of Microsoft Corporation to the proposal of PJM Interconnection, L.L.C. to establish Interim Resource Adequacy Service and Large Load Registry

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
)
)
)

Docket No. ER26-3515-000

COMMENTS OF MICROSOFT CORPORATION

Pursuant to the Federal Energy Regulatory Commission’s (“Commission’s”) notices in this proceeding,1 Microsoft Corporation (“Microsoft”) respectfully submits these comments regarding PJM Interconnection, L.L.C.’s (“PJM’s”) proposal to establish Interim Resource Adequacy Service (“IRAS”) and a Large Load Registry.2 Microsoft, an original signatory of the Ratepayer Protection Pledge,3 supports measures to promote reliability and fair cost allocation, but urges the Commission to modify IRAS to align capacity charges with reliability benefits, recognize and protect existing retail utility contracts and project load ramp schedules, provide transparent project-level information and correction rights, and preserve accurate investment signals and workable pathways for large retail customers like

1 PJM Interconnection L.L.C., Notice Denying Extension of Time, Docket Nos. ER26-3515- 000 (Sept. 2, 2026); PJM Interconnection L.L.C., Combined Notice of Filings #1, Docket Nos. ER26- 3515-000 et al. (Aug. 14, 2026); PJM Interconnection L.L.C., Combined Notice of Filings # 2, Docket Nos. ER26-3515-000 et al. (Aug. 13, 2026).
2 PJM Interconnection, L.L.C., FPA Section 205 Filing of PJM Interconnection, L.L.C., Docket No. ER26-3515 (Aug. 13, 2026) (“IRAS Filing”).
3 See Ratepayer Protection Pledge, The White House (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/.

PDF page 2

2
Microsoft to procure new resources. Microsoft supports the Protest filed by the Data Center Coalition in this docket.4

The U.S. economy increasingly depends on an electric grid capable of serving the growing requirements of the digital economy, advanced manufacturing, and the expansion of electrification across domestic transportation, heating/cooling, and industrial sectors. As set out in Microsoft’s Community First AI Infrastructure Investment Principles,5 Microsoft recognizes that the expansion of datacenters performing cloud storage, cloud computing, and artificial intelligence operations requires significant investment in electric transmission and generation capacity, support for domestic supply chains, and innovative new tools and technologies that optimize grid operations. Microsoft itself is investing substantially in the electric power sector. For example, Microsoft has entered into a 20-year power purchase agreement with Constellation Energy for the Crane Clean Energy Center, which is expected to deliver more than 800MWs of new carbon-free capacity and energy to the PJM grid.6 Microsoft supports regulatory and tariff reforms that facilitate timely infrastructure

4 PJM Interconnection, L.L.C., Motion to Intervene and Protest of the Data Center Coalition, Docket No. ER26-3515 (Sept. 3, 2026).
5 See Brad Smith, Building Community-First AI Infrastructure, MICROSOFT ON THE ISSUES (Jan. 13, 2026), https://blogs.microsoft.com/on-the-issues/2026/01/13/community-first-ai- infrastructure/.
6 Bobby Hollis, Accelerating the addition of carbon-free energy: An update on progress, MICROSOFT (Sept. 20, 2024), https://www.microsoft.com/en-us/microsoft- cloud/blog/2024/09/20/accelerating-the-addition-of-carbon-free-energy-an-update-on-progress/ (linking Constellation to Launch Crane Clean Energy Center, Restoring Jobs and Carbon-Free Power to the Grid, CONSTELLATION (Sept. 20, 2024), https://www.constellationenergy.com/news/2024/Constellation-to-Launch-Crane-Clean-Energy- Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html).

PDF page 3

3
development, improve coordination, and provide durable and transparent market signals to enable new supply to meet the growing demand within the PJM region.

Microsoft commends PJM’s efforts to address ongoing resource adequacy challenges in the region. Microsoft also supports reforms that promote efficient investment, advance the development of new generation and transmission infrastructure, and allocate costs consistent with cost-causation principles. Microsoft recognizes that improved coordination among PJM, electric distribution companies, load-serving entities, state regulators, and large retail customers is a necessary first step as the region works to enhance load forecasting transparency and accommodate projected load growth.

I. COMMENTS
Microsoft submits these comments to highlight concerns with several aspects of PJM’s IRAS proposal and to encourage the Commission to consider modifications that better advance regional objectives.  First, PJM’s proposal requires certain large retail customers to pay for capacity while exposing them to curtailment before compensated capacity resources are called upon to perform. Second, the proposal interferes with service expectations underlying binding utility agreements and may substantially impair investments made under existing retail and wholesale rules. Third, large retail customers currently lack sufficient visibility into the load forecasts and project-level assumptions necessary for PJM to determine their exposure under IRAS and the Reliability Backstop Procurement (RBP). Microsoft therefore urges the Commission to direct modifications that preserve the connection between customer capacity payments and associated reliability benefits, protect existing binding agreements for new load that has yet to ramp to the contracted-for capacity, and provide transparent and verifiable treatment of affected large retail loads. Additionally,

PDF page 4

4
Microsoft respectfully requests that PJM, the Commission, or both explain if RBP Unforced Capacity (UCAP) Offset MW under RBP can also serve a Bring Your Own New Capacity (BYONC) under IRAS.

A. Large Retail Customers Paying for Capacity Should Receive Reliability Benefits

Microsoft supports the principle that large retail customers benefiting from grid reliability should contribute appropriately to the costs of maintaining that reliability. Microsoft also supports mechanisms that align growing demand with new resource development and provide large retail customers meaningful pathways to support the addition of new supply. Those principles must operate consistently in both the rates customers pay and the service they receive.

PJM’s proposal requires Eligible New Large Loads to be curtailed before PJM initiates certain load-management actions, including dispatch of Demand Response Resources that have been compensated through the capacity market to reduce load when needed.7 At the same time, the proposal does not clearly provide a corresponding reduction in the capacity-related charges paid by large retail customers subject to IRAS. Instead, PJM relies on a separate IRAS compensation mechanism, the implementation of which is largely left to Electric Distributors and state authorities. This creates a fundamental mismatch between cost and benefit: large retail customers may be required to pay for capacity while being interrupted before that capacity is used to preserve their service.  PJM has not demonstrated why some retail customers that contracted for firm service should be involuntarily converted to a materially different service construct. Where a customer remains

7 See IRAS Filing, at 100–01.

PDF page 5

5
responsible for capacity-related costs and transmission network service charges, the Commission should ensure that a load curtailment obligation is supported by an appropriate customer election, compensation mechanism, or corresponding adjustment in service rights and charges.

Microsoft is concerned that PJM has not demonstrated that IRAS is consistent with cost-causation principles and charges large retail customers for reliability benefits they will not receive. Further, PJM has not explained how capacity charges, IRAS credits, and any state-administered compensation will interact—information that is necessary for large retail customers to evaluate the full cost and reliability implications of the proposal.

B. The Proposal Upends Retail Contractual Commitments and Large Retail
Customers’ Reliance Interests on Those Arrangements.
Microsoft is concerned with how IRAS changes the retail service framework applicable to projects where sponsors have already entered into binding utility arrangements and made substantial investment commitments. Large-load projects like Microsoft’s investments require years of planning and involve substantial commitments for land, construction, network infrastructure, electric facilities, generation procurement, and long- term utility service. IRAS imposes requirements that could not reasonably have been anticipated when a large retail customer and utility entered into their agreement, causing abrupt, substantial impairment to the value of these long-lead time projects. Many large load projects also ramp up over time rather than entering service at their full contract demand. IRAS upsets existing commitments when some portion of its contracted load ramps after the PJM-proposed cutoff date; The cut-off date is completely arbitrary as to any particular phase of the large load project. Applying IRAS to later increments of a phased project already covered by an executed agreement could divide a

PDF page 6

6
single facility into different service categories, further undermining settled commercial expectations and imposing new retail service requirements that could not reasonably have been anticipated when the large retail customer and utility entered into their agreement. If the Commission decides to proceed with IRAS, Microsoft requests that the Commission direct changes that provide a clear and effective transition mechanism that protects large retail customers that executed binding utility agreements or made other substantial, demonstrable commitments they relied upon before PJM proposed IRAS. PJM's own proposed Large Load Registry recognizes that large load projects may have phased ramp schedules and requires reporting of each increment's in-service date, peak load and ramp schedule, and applicable contracts or service agreements.  The transition should recognize the full contracted load and reasonable ramp schedule associated with an eligible project, rather than protecting only the load energized before a single, arbitrary cutoff date without assessment of commercial implications. This approach would preserve legitimate reliance interests while maintaining appropriate obligations for genuinely new and unsupported load.

C. Transparent, Project-level Information Is Necessary for Retail Customers To Assess Their IRAS Exposure.

IRAS depends heavily on the load forecasts used to establish the relevant baseline and identify incremental load.8 Large retail customers, however, have limited visibility into how electric distribution companies incorporate individual projects, contract quantities, and ramp schedules into the forecasts underlying PJM’s proposal. Without that information, these customers are unable to assess which portions of their retail load may be considered

8 See id., at 112–113.

PDF page 7

7
incremental, whether contracted demand was fully reflected in the rolled-up load forecast, or what actions may be needed to limit curtailment and cost exposure.

This uncertainty is particularly consequential where utility forecasts appear to include less load than a large retail customer has committed to under an executed service agreement with commercial obligations and firm commitments. A large retail customer should not face curtailment or new capacity obligations because of forecasting practices of others that it was never given the opportunity to verify or correct. Nor should large retail customers ever be required to make resource-procurement decisions without clear information regarding the delivery years, megawatt quantities, and facilities potentially subject to IRAS. Before IRAS is implemented, each potentially affected customer must be provided with sufficient project-level information to verify how its load is represented in the applicable load forecast and Large Load Registry, including both load reflected in executed service agreements and any additional forecasted load, and how any associated supply arrangement will be credited. PJM must put into place a process to identify and correct forecasting and registry errors. PJM must also clearly distinguish among Qualifying Reliability Backstop Procurement (“RBP”) Offset Unforced Capacity (“UCAP”) MW, allocated RBP UCAP MW, and Bring Your Own New Capacity (“BYONC”). These retail customer-specific determinations must be made sufficiently in advance of each Delivery Year so that affected large retail customers have a meaningful opportunity to procure qualifying supply, challenge errors, or adjust project plans before incurring curtailment risk. Additionally, PJM must explain whether and how the same resource may receive recognition under both frameworks, the extent to which each designation reduces customer- specific cost or curtailment exposure, and how resources with future commercial-operation

PDF page 8

8
dates will be treated during earlier Delivery Years.  For example, it is unclear from PJM’s submissions whether a resource that is used as Qualifying RBP Offset UCAP MW under RBP can also be used as BYONC under IRAS, assuming it meets all of the relevant criteria.9 This is a critically important point of clarification as Microsoft and other large load customers look to make business decisions in the coming months.  Microsoft respectfully requests that PJM and the Commission confirm that a resource may qualify and participate in both programs.  The rules must ensure that large retail customers procuring qualifying new capacity are not subject to duplicative charges.

D. Microsoft Supports Competitive Market Rules that Achieve Reliability
without Undermining Signals for New Capacity Investment
Microsoft supports reforms that maintain reliability while facilitating the development of the generation and transmission infrastructure needed to serve growing demand. A durable regulatory framework should create transparent pathways for customers to support new supply, recognize bilateral procurement and other qualifying resource commitments, and facilitate competitive market signals that encourage timely resource entry. Any exclusion of new load from capacity-market demand should be carefully evaluated to ensure that market outcomes correctly signal the region’s actual long-term need for capacity.  In Microsoft’s view, reliability reforms should align customer obligations, resource qualification rules, and capacity-market signals in a manner that supports both near- term operational reliability and long-term supply development.  PJM has not yet cogently explained why its proposal to exclude projected load from auction demand does not understate the region’s future capacity needs and mask signals necessary to attract new

9 See Proposed Tariff, Attachment DD, Section 18.2; Proposed Tariff, Attachment DD-4, Section VI.

PDF page 9

9
generation investment. Because the stated purpose of IRAS is to address resource adequacy concerns associated with load growth, PJM should demonstrate how removing that same load from capacity-market demand is consistent with encouraging the supply additions needed to maintain resource adequacy and reliability across the system over time.

II. CONCLUSION
Microsoft fully supports PJM’s objective of maintaining system reliability and agrees that large retail customers should pay their fair share of the grid costs incurred to serve them. The Commission should not, however, approve a tariff framework—and more generally, establish regulatory precedents—that disconnect customer payments from reliability benefits, disrupts binding utility arrangements and substantial investments made under existing rules, or determines large retail customer obligations through forecasts that customers cannot verify.

For these reasons, Microsoft respectfully requests that the Commission direct modifications to (1) align curtailment priority and capacity charges with the reliability benefits customers receive; (2) establish a meaningful transition to protect existing contractual commitments and project ramp schedules; (3) provide transparent, project-level information and correction rights regarding IRAS exposure; and (4) preserve accurate market signals and workable pathways for customers to support new resource development. Additionally, Microsoft respectfully requests that PJM, the Commission, or both explain if RBP UCAP Offset MW under RBP can also serve a BYONC under IRAS.

PDF page 10

10
Respectfully submitted,

Dallas Harris
Principle Corporate Counsel
Microsoft Corporation
Redmond, WA 98052
Email: dallasharris@microsoft.com
Tel: (909) 575-7320

John Greene
Senior Program Manager, Energy
Regulatory Affairs
Microsoft
901 K St NW, Washington, DC 20001
Email: john.greene@microsoft.com
Tel: (603) 620-0654

/s/ Jeffery Riles
Jeffery Riles
Senior Director of Energy Markets, Americas Microsoft Corporation

One Microsoft Way
Redmond, WA 98052
Email: jeffriles@microsoft.com
Tel: (425) 882-8080

Dated: September 3, 2026

PDF page 11

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

Respectfully submitted,
/s/ Dallas Harris
Dallas Harris
Principle Corporate Counsel
Microsoft Corporation
Redmond, WA 98052
Email: dallasharris@microsoft.com
Tel: 909-575-7320

Dated: September 3, 2026