ER26-3515-000 · 2026-09-04 · Equinix Inc.

Protest, Request for Clarification, and Comments of Equinix Inc. on the Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy…

PDF page 1

Equinix.com     © 2026 Equinix, Inc.

September 3, 2026
The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E., Room 1A
Washington, D.C. 20426
Re:  Submission 1788574 - Protest, Request for Clarification and Comments of EQUINIX INC. under ER26-3515

Dear Ms. Reese:
After difficulties with interactions of our internal filing system and the FERC online system, I have learned that I inadvertently uploaded and filed the original submission made by PJM Interconnection, L.L.C. (“PJM”) initiating Docket ER26-3515, instead of the “Protest, Request for Clarification and Comments of EQUINIX INC. under ER26-3515.”

I only became aware of this issue when I received the attached notice from FERC Online Support, requesting removal of the FERC watermark from the submission that I made at 4:20:02 PM today, as shown in the attached copy of the receipt of filing. I found this confusing, as I did not insert any watermarks on the document I had prepared, which has a time signature of 4:13 PM today, and as I saw none when I checked the document. I then looked at the online summary of filing, and realized the file name was for the original PJM filing rather than our document. Clearly, after several failed attempts to upload the correct document, I inadvertently attached the wrong document. I am filing a copy of this letter and its two attachments, along with the proper document with the 4:13 PM time stamp. I hope that the original document can be accepted for the Commission’s consideration in this proceeding.

Respectfully submitted,

   /s/ Arthur Haubenstock

Arthur Haubenstock

Sr. Counsel, Global Regulatory
Equinix Inc.
700 “K” Street, N.W., Suite 600
Washington DC, 20001
(202) 322-9073
ahaubenstock@equinix.com
Attachments

PDF page 2

1 of 1
Caution:
Caution:
Caution:
Caution: This email is from an external source. Please take care when clicking links, scanning QR codes, or opening attachments. When in doubt, use the Report Button

Report Button
Report Button
Report Button.
Thursday, September 3, 2026 at 9:12:07
Thursday, September 3, 2026 at 9:12:07
Thursday, September 3, 2026 at 9:12:07
Thursday, September 3, 2026 at 9:12:07 PM Eastern Daylight Time
PM Eastern Daylight Time
PM Eastern Daylight Time
PM Eastern Daylight Time
Subject:
Subject:
Subject:
Subject: [EXTERNAL] SCTASK0170495 - Submission 1788574
Date:
Date:
Date:
Date:
Thursday, September 3, 2026 at 4:56:46 PM Eastern Daylight Time
From:
From:
From:
From:
FERCOnlineSupport@ferc.gov
To:
To:
To:
To:
Arthur Haubenstock
You don't often get email from ferconlinesupport@ferc.gov. Learn why this is important Good afternoon

We are reaching out about Submission 1788574 - Protest, Request for Clarification and Comments of EQUINIX INC. under ER26-3515.

We are requesting that you remove the FERC's watermarks and refile. Or attach a cover letter and refile your submission.

Once you have refiled, please reply with your new submission number
Thank you
FERC Online Support

Ref:MSG2238124_hdVIK0RW32zK62uRPTkc

PDF page 3

1 of 1
Thursday, September 3, 2026 at 9:14:44
Thursday, September 3, 2026 at 9:14:44
Thursday, September 3, 2026 at 9:14:44
Thursday, September 3, 2026 at 9:14:44 PM Eastern Daylight Time
PM Eastern Daylight Time
PM Eastern Daylight Time
PM Eastern Daylight Time
Subject:
Subject:
Subject:
Subject:
[EXTERNAL] FERC Receipt of Filing in ER26-3515-000
Date:
Date:
Date:
Date:
Thursday, September 3, 2026 at 4:22:11 PM Eastern Daylight Time
From:
From:
From:
From:
eFiling@ferc.gov
To:
To:
To:
To:
Arthur Haubenstock, efilingacceptance@ferc.gov
Priority:
Priority:
Priority:
Priority:
High
Category:
Category:
Category:
Category: Red category
Caution: This email is from an external source. Please take care when clicking links, scanning QR codes, or opening attachments. When in doubt, use the Report Button.

Confirmation of Receipt
-----------------------
This is to confirm receipt by the FERC Office of the Secretary of the following electronic submission: -Submission ID: 1788574

-Docket(s) No.: ER26-3515-000
-Filed By: EQUINIX INC.
-Signed By: Arthur Haubenstock
-Filing Desc: Protest, Request for Clarification and Comments of EQUINIX INC. under ER26-3515-000. -Submission Date/Time: 9/3/2026 4:20:02 PM

-Projected Filed Date/Time: 9/3/2026 4:20:02 PM (Subject to Change based on OPM/FERC Closure) Additional detail about your filing is available via the following link:

https://nam11.safelinks.protection.outlook.com/?
url=https%3A%2F%2Fferconline.ferc.gov%2FSubmissionStatus.aspx%3Fhashcode%3DPV4f5QQOUD7 ocDMSiLfdJA&data=05%7C02%7Cahaubenstock%40equinix.com%7C9e7abcf8368d4fa19a7008df09f9 0616%7C72adb2712fc74afea5ee9de6a59f6bfb%7C0%7C0%7C639240637312358818%7CUnknown%7 CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIj oiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=YBzm7Colmk4NsEeS%2FMmsk%2BlS

mH%2FeORX83Qch8IG46l4%3D&reserved=0
Thank you for participating in the FERC Electronic Filing System.  If you have any questions, or if you detect errors in your submission or the FERC-generated PDF, please contact FERC at: E-Mail: ferconlinesupport@ferc.gov mailto:ferconlinesupport@ferc.gov (do not send filings to this address)

Voice Mail: 866-208-3676.