ER26-3380-000 · 2026-09-17 · PJM Power Providers Group
Answer of PJM Power Providers Group in response to PJM Interconnection, L.L.C.'s 09/10/2026 Motion for Leave to Answer and Answer
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
ANSWER1 OF THE PJM POWER PROVIDERS GROUP
The PJM Power Providers Group2 (“P3”) submits these comments in response to a
specific response and justification offered by PJM Interconnection, L.L.C. (“PJM”) in its
September 10, 2026, Motion for Leave to Answer and Answer (“Answer”) in the above
proceeding.3 On page 47 of its Answer, PJM attempts to justify Reliability Backstop
Procurement (“RBP”) resources offering into capacity auctions as price-takers by arguing that
1 This Answer is in response to PJM’s Motion for Leave to Answer and Answer filed last week on September 10, 2026. Although the Commission’s procedural rules do not provide for answers to answers as a matter of right, the Commission has allowed answers where, as here, the answer provides further explanation or otherwise helps ensure a full and complete record. See, e.g., Empire Pipeline, Inc., 164 FERC ¶ 61,076 P 9 (2018), PJM Interconnection, L.L.C., 104 FERC ¶ 61,154, at P 14 (2003), on reh’g, 109 FERC ¶ 61,236 (2004); Williams Energy Mktg. & Trading Co. v. Southern Co. Servs., Inc., 104 FERC ¶61,141, at P 10 (2003); Ameren Servs. Co., 100 FERC ¶ 61,135, at P 15 (2002), on reh’g, 103 FERC ¶ 61,178 (2003).
2 P3 is a non-profit organization dedicated to advancing federal, state and regional policies that promote properly designed and well-functioning electricity markets in the PJM Interconnection, L.L.C. (“PJM”) region. Combined, P3 members own over 108,000 MWs of generation assets and produce enough power to supply over 63 million homes in the PJM region covering 13 states and the District of Columbia. For more information on P3, visit www.p3powergroup.com. The comments contained herein represent the position of P3 as an organization, but not necessarily the views of any particular member with respect to any issue. On August 4, 2026, P3 filed a doc-less Motion to Intervene in this proceeding.3 Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. ER26-3380-000, September 10, 2026 (“PJM September 10, 2026 Answer”).
PDF page 2
2
FERC has “consistently rejected the position that requiring resources that are procured outside of a capacity market to offer into the capacity market as price takers would unjustly and unreasonably distort or suppress capacity market clearing prices.”4
P3 is baffled by this logic. PJM should know and understand that Reliability Must Run (“RMR”) contracts that are short term and only executed with the intention that they will go away as soon as possible are fundamentally different than RBP capacity commitments which will be actively serving resources in the PJM region for at least 15 years and most likely beyond. Moreover, PJM is asking FERC to buy into “two wrongs make a right” logic by asking the Commission to repeat a policy that is not part of a properly designed market and that PJM historically opposed (only changing positions recently). This is not sound logic or reasoned decision-making, and the Commission should specifically reject it or replace it with an alternative that is less damaging to the long-term health of the market and resource adequacy in the region.
The Commission cannot turn a blind eye to the long-term implications of increasing the volume of megawatts that PJM would require to offer into the auction at zero. It only stands to reason that each additional MW that is required to participate as a price taker will only drive more megawatts to demand out of market support or leave PJM as markets are increasingly undermined by regulatory interventions into a market that aspires to be competitive. As resources continue to be driven from PJM’s markets, resource adequacy issues will worsen in PJM, and consumers will pay more overall. If the Commission is serious about having a functionally competitive market in PJM that will deliver on the vision of reliability at the least
4 PJM September 10, 2026 Answer at page 47.
PDF page 3
3
cost to consumers, as P3 believes it is, it should send a message to PJM in this proceeding that out of market revenues from RBP-support should not be a vehicle to undermine the competitive capacity market upon which 67 million consumers rely.
P3 members have taken various positions on the underlying filing in this proceeding5; however, the organization wholly rejects the idea that because FERC approved certain RMRs as price-takers in PJM that the Commission should require that RBP capacity resources must be offered into capacity auctions as price takers. PJM’s argument relies on highly limited precedent6, conflates fundamentally distinct reliability mechanisms, and ignores the severe, long- term market degradation to ongoing resource adequacy that PJM’s proposal will inflict on the PJM footprint and the overall consumer cost impacts that it will have.
1. RMR Contracts Are Fundamentally Distinct from RBP Capacity
Importantly, PJM misreads its own precedent. For example, the case PJM cites on pages 47 and 48 clearly limited the applicability of the RMR zero offer rule to only two BRAs.7 While, that ruling was extended by two years to accommodate a known transmission issue, PJM’s suggestion that all RMRs are required to offer as price takers for all time is simply not true based on PJM’s tariff or FERC orders.
But even if PJM’s preferred reading of FERC’s orders and its tariff were correct, its reliance on RMR precedent is misplaced because RMR contracts and RBP resources serve
5 See Motion to Intervene and Request for Clarification of Talen Energy Corporation, Docket No. ER26-3380-000, August 21, 2026; See Limited Protest of the NRG Companies, Docket No. ER26-3380-000, August 21, 2026; See Limited Protest of Vistra Corp., Docket No. ER26-3380-000, August 21, 2026; See Limited Protest of Constellation Energy Generation, LLC, See Motion to Intervene and Comments of CPV Power Holdings, Docket No. ER26-3380- 000, August 21, 2026.
6 PJM cites PJM Interconnection, L.L.C., 190 FERC ¶ 61,088, at P 50 (2025) for the proposition that RMR resources should be included in capacity auctions as price takers, but does not mention that the Commission limited that price taker participation to two auctions.
7 PJM September 10, 2026 Answer at pages 47 and 48 (notes 136-138).
PDF page 4
4
completely different structural functions. RMR resources are localized, short-term, stop-gap measures designed to keep retiring, uneconomic generators online temporarily to resolve immediate transmission or operational reliability constraints. RBP capacity is a multi-year, forward procurement mechanism involving long-term commitments (up to 15 years) intended to bring significant volumes of new generation online to satisfy steep, multi-gigawatt load growth (largely driven by data centers).
Conflating short-term retention of legacy units to resolve transmission constraints with long-term, multi-gigawatt new entry ignores the difference in scale and market impact. RMR contracts are designed to be short-term propositions for relatively small amounts of power (about 2 GWs in the case of Brandon Shores and Wagner), RBP resources are not. RBP resources are designed to be on-going and can be significantly larger, potentially over 6.8 GWs. Dumping potentially thousands of megawatts of long-term RBP capacity into RPM auctions as price takers will severely distort market-clearing signals at a regional scale, far beyond the hyper-local impact of a typical RMR contract – which is time bound and will result in the unit leaving the market. Apples and oranges come to mind.
2. "Two Wrongs Don't Make a Right": RMR Precedent Is Limited and Should Not Be Expanded
PJM’s primary defense for price-taker treatment rests on the Commission’s precedent regarding RMR resources. However, doubling down on a historically flawed policy does not make it just and reasonable. P3 extensively protested PJM’s policy reversal to include RMR units in capacity auctions as price takers. As P3 offered at the time, “While P3 appreciates the desire to address the concerns raised by state and consumer interests, if approved, the proposed changes will further send PJM down a road that will only prolong the successful resolution of the
PDF page 5
5
issues that created the RMR in the first instance while unnecessarily compromising reliability.”8 P3 regrets this prognostication being accurate and fears that PJM is pushing the Commission further down this reliability-threatening and more costly path.
PJM itself previously recognized the market-distorting impacts of injecting zero-priced RMR offers into the supply stack and the long-term resource adequacy and cost impacts that such an action could have. Forcing out-of-market supported resources to offer as price takers creates artificial supply at a $0 price point which will push existing resources out of PJM exacerbating the current resource adequacy shortfall and consumer cost issues. Adopting this approach for RBP capacity expands a limited construct, compounding market disruption and undermining market efficiency and resource adequacy across the RTO. As PJM offered prior to its policy reversal, “requiring participation of a deactivating unit in the capacity auction under the existing RMR agreements could distort the price signal and fail to incent the new build …… suppressing this price signal now is likely to result in greater reserve shortfalls in the future. Additionally, suppressing this price signal now could discourage other forms of resources, such as Demand Response and other resources that may be available on shorter notice from increasing their market participation precisely at the time they are most needed.”9
Since PJM is clearly aware of the damage that mandated price taking capacity has on the markets, resource adequacy and ultimately consumer costs, it is troubling that it is asking FERC to yet again endorse and significantly expand a policy that is antithetical to sound market design. Moreover, and importantly, the Commission’s 2025 decision to require RMR units to participate
8 See Comments and Request to Sever of the PJM Power Providers Group, Docket No. ER25-682-000, January 6, 2025, at page 6.9https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2024/20240919-pjm-board- response-consumer-advocates-letter-re-urgent-reforms-pjm-capacity-market-re-reliability-must-run- units.ashx?_sp=0238a5f6-837e-4142-a86f-f8b8f54cd74a.1789491722754
PDF page 6
6
in capacity auctions as price takers was specifically time-limited to two auctions when it was approved so as to avoid sustained disruption to the market.10 The Commission and commenters relied heavily on the fact that PJM was making a limited exception and not creating an ongoing expectation that RMR resources would participate in auctions as price takers. Yet, here, PJM is seeking to expand this limited exception to a full on market principle as significant amounts of capacity could be offered into the auction for up to 15 years at zero – at the very time PJM is seeking to send price signals to encourage new entry. This tortured logic must be rejected.
4. Long-Term Price Suppression Destroys Market Performance and Reliability
P3 echoes and supports the arguments raised by NRG Energy and Constellation: price-taker treatment for out-of-market capacity destroys the long-term integrity and performance of the capacity market; resource adequacy will suffer and costs will increase as a result. When RBP supply is forced into RPM auctions at $0/MW-day, it artificially shifts the supply curve to the right without a corresponding shift in auction demand, crashing RPM clearing prices. The long-term ramifications of this artificial suppression are severe:
Premature Exits: Depressed clearing prices prevent existing, uncontracted merchant generators from recovering their avoidable costs, forcing premature retirements or exits of needed capacity.
Deterrence of Unsubsidized New Entry: Investors will not commit merchant capital to new supply if the capacity market signals are systematically suppressed by multi- gigawatt backstop procurements offered at zero.
Perpetual Backstop Dependence: By chilling competitive investment and accelerating retirements, PJM creates a self-fulfilling crisis where the competitive market continually clears short, forcing PJM to rely indefinitely on administrative backstop procurements.
Resource Adequacy Issues in PJM will be Exacerbated: Reliability will most
certainly be compromised as existing resources are incented to exit, and new capacity
10 In FERC Docket no. ER25-682, the Commission required that PJM make changes in its compliance to clarify the time-limited nature of RMR units participating in capacity auctions as price takers. See Order at paragraph 54.
PDF page 7
7
resources will struggle with the decision to participate in capacity auctions or backstop procurements.
Consumers will Pay more for Resource Adequacy. Over the long term, reliance on out of market supported resources offering as price takers will drive overall prices higher as the ability to garner out of market support replaces efficiency as a capacity resource’s primary motivation.
5. A Just and Reasonable Path Forward
Most concerning, PJM is asking FERC to take a further step down what is an
extraordinarily slippery slope. Resources that are receiving out of market financial support need to be appropriately recognized in the capacity market if the capacity market is going to remain the engine for reliability at the least cost for consumers in PJM. This is the same challenge that was presented in MOPR where the Commission had to wrestle with the question of state subsidies distorting wholesale market pricing. In the instant case, the question is how to handle the participation of resources that PJM is procuring to meet system load outside of the capacity market.
Fortunately, unlike the MOPR, there are easy answers to this question. For example, NRG and Constellation include proposed paths forward in their pleadings in this docket. Another simple to implement path forward would be to have RBP resources offer at their contract prices. Specifically, RBP resources will have an easily identified contracted price that is reflective of the capacity cost necessary to support the resource. That price will also be at or below a price cap set by the Commission in this proceeding. The Commission can maintain the fidelity of the market by having the capacity participate in the market at its contract price.11 The Commission could easily direct PJM to make this change as part of its compliance filing and in
11 If the contracted RBP price happens to be above the BRA price cap, P3 would support the BRA price cap as the RBP offer price.
PDF page 8
8
doing so significantly reduce the long-term market damage that could be caused by resources with significant capacity costs participating in the market as price takers.
In the alternative, FERC could defer the question of RBP capacity participation in auctions to a future proceeding. PJM and FERC will not know how much capacity is procured through the RBP process or the location of that capacity until later this year after the auction has been completed. In addition, all RBP capacity can come online as late as June 1, 2032. Finally, and importantly, the auction that will occur in December of this year is for the 29/30 delivery year which is bound by both a cap and a floor and, by PJM’s own declaration, “...there will need to be substantial load reduction for the auction to clear at a price lower than the ‘collar cap.’”12 In other words, if any RBP capacity participates in the December auction, that capacity is highly unlikely to impact the outcome. Given all these factors, the need to resolve the significant question of how best to reflect RBP capacity in capacity auctions going forward for potentially two decades can easily be addressed in a separate, more thoughtful, context.
The Commission should provide PJM guidance that RBP resources are not sufficiently similar to the limited RMR precedent that PJM cites and direct PJM as part of its holistic resource adequacy market review to consider the question of how RBP capacity participates in capacity auctions in a way that reflects its capacity value and does not undermine the integrity of the market for the resources that are not receiving out of market support. If the Commission does not want to defer the question to that initiative, P3 would suggest that the question be addressed in a paper hearing that commences after the quantity and location of RBP capacity is known and concludes before the BRA in May 2027 for the 29/30 delivery year.
12 https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260901-pjm-president- ceo-response-to-md-office-of-peoples-counsel-letter-regarding-base-residual-auction-2029-2030.pdf
PDF page 9
9
6. At Minimum, the Commission Must Reject PJM’s Logic
In the event that the Commission is inclined to accept PJM’s proposal to include RBP capacity in the auction as price takers immediately, P3 urges the Commission to reject PJM’s assertion that the Commission is indifferent to the price suppression impacts and that RMR contracts are the same as RBP contracts. RMR contracts and RBP commitments are fundamentally different propositions and should not be subject to the same regulatory structures. The Commission recognized the importance of limiting mandated price taking capacity in 2025 – it should do so again here.
CONCLUSION
The Commission should not accept PJM’s attempt to justify zero-dollar price-taker treatment for multi-gigawatt, 15-year Reliability Backstop Procurement commitments by hiding behind short-term Reliability Must Run precedent that is explicitly very narrow and relies on fundamentally broken logic. Conflating temporary legacy unit retention with long-term new generation entry is not justified; it completely ignores market fundamentals and threatens to entrench administrative price suppression across the entire regional footprint. By systematically depressing capacity clearing prices, this proposal will accelerate premature plant retirements, chill vital merchant investment, and trap the region in a self-fulfilling crisis of perpetual resource adequacy shortfalls, backstop dependence and increased overall costs. Something the Commission should be highly motivated to avoid.
The Commission must reject PJM’s proposal to treat out-of-market backstop capacity as zero-priced supply and preserve the long-term integrity of the wholesale market. At minimum, FERC should require RBP capacity as suggested by NRG or Constellation or to offer at its actual contract price, sending a clear signal that out-of-market revenues cannot be leveraged to
PDF page 10
10
dismantle a competitive framework that 67 million consumers rely upon for cost-effective, reliable power. P3 also supports deferring the question until more information is known about the quantity, timing and location of any RBP capacity so such a significant question can be resolved more thoughtfully.
Respectfully submitted,
On behalf of The PJM Power Providers Group
By: /s/ Glen Thomas
Glen Thomas
GT Power Group
101 Lindenwood Drive, Suite 225
Malvern, PA 19355
gthomas@gtpowergroup.com
610-768-8080
Dated: September 17, 2026
PDF page 11
11
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the Official Service List compiled by the Secretary in this proceeding.
Dated at Washington, D.C., this 17th day of September, 2026.
On behalf of the PJM Power Providers Group
By: /s/ Diane Slifer
Diane Slifer