ER26-3515-000 · 2026-09-28 · Vistra Corp.

Motion for Leave to Answer and Answer of Vistra Corp. in response to certain pleadings and answers filed

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
)
)
)
)

Docket No. ER26-3515-000

ANSWER OF VISTRA CORP.

Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 Vistra Corp. (“Vistra”) hereby moves to answer certain pleadings and answers filed in the above-captioned proceeding.  As the timely-filed comments in this proceeding nearly universally agree, IRAS has not been shown to be just and reasonable and not unduly discriminatory or preferential.  Although PJM stakeholders may disagree about the best way to address resource adequacy concerns in PJM, there is nearly unanimous consensus— amongst Load Serving Entities (“LSE”), independent power producers, vertically integrated utilities, end-use customers, state public utility commissions, individual retail ratepayers, and PJM’s Independent Market Monitor—that PJM’s Interim Resource Adequacy Service (“IRAS”) proposal is not the way forward.

It should be no surprise that IRAS has elicited such strong opposition.  Nor should it be a surprise that its defenders have not put forth a convincing case in support of the proposal.  To start, PJM has misdiagnosed the root cause of the region’s resource adequacy issues.  PJM blames large loads rather than recognizing a combination of exaggerated load forecasts and capacity auction and interconnection delays that contribute significantly to the resource adequacy gap.  To the

1 18 C.F.R. § 385.211 (2026).

PDF page 2

-2-
extent a market participant is contributing to the resource adequacy gap, it is LSEs and Electric Distributors (“EDs”) that commit to load that they do not have the capacity to support. Addressing PJM’s resource adequacy quandary by penalizing large loads under IRAS’s discriminatory and ill- fitting framework is fraught with risk.   From there, PJM compounds its initial error by offering a solution that is illegal for several independent reasons.  Finally, IRAS threatens to have the exact opposite effect PJM intends.  It will make the resource adequacy situation more dire because its failure to include common-sense transition mechanisms and grandfathering provisions will upend investments made in reliance on the existing market rules, thereby chilling additional investment in the PJM region.

I. MOTION FOR LEAVE TO ANSWER
Although the Commission’s procedural rules generally do not allow answers to answers, the Commission may permit them for good cause.2  The Commission frequently accepts answers that clarify the issues before the Commission, ensure a complete record, or otherwise assist the Commission in its decision-making.3   Vistra therefore respectfully requests that the Commission accept this answer, which will assist the Commission with its decision-making by contextualizing the record, responding to answers, and explaining why the scant support for IRAS is misplaced.

2 18 C.F.R. § 385.213(a)(2) (“An answer may not be made to a protest, an answer, a motion for oral argument, or a request for rehearing, unless otherwise ordered by the decisional authority.”).
3 See, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting answers to answers that “provided information that assisted us in our decision-making process”); New Fortress Energy LLC, 174 FERC 61,207, at P 7 (2021) (accepting answers because they provided information that assisted the Commission’s decisionmaking process); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that “clarify the concerns raised and provide information that has assisted in our decision making”); Saltville Gas Storage Co., L.L.C., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in understanding the issues raised, and will ensure a complete record”).

PDF page 3

-3-
II. ANSWER
As the record clearly demonstrates, IRAS has myriad fatal flaws.  An order accepting the IRAS proposal will not be upheld in court and, in the meantime, will cast a pall of uncertainty over the PJM market, stymying investments in both new capacity and the maintenance of existing capacity.  That, in turn, will further harm PJM’s resource adequacy outlook.

A. PJM Has Misdiagnosed the Cause of the Region’s Resource Adequacy Issues

Perhaps the most fundamental of IRAS’s many flaws is that it attempts to solve the wrong problem.  As parties in this proceeding have now demonstrated in several different ways, the source of PJM’s resource adequacy woes is the incentive structure that PJM’s capacity market creates:  incentivizing LSEs to agree to serve more load than they have generation to cover or can realistically procure through the capacity market.4  When the PJM system had excess generation and the capacity price was clearing at or below $50/MW-day, this was an entirely rational and efficient strategy.  That became particularly problematic in this period of rapid load growth because LSEs currently have every incentive to sign up as much load as possible without regard to whether they have sufficient supply to serve that load, and that dynamic is only made worse in today’s supply-constrained environment.  “Net-short LSEs” signing up unlimited customers without a plan to adequately supply them is a recipe for both resource adequacy shortfalls and reliability problems.

4 See Dominion Comments at 3-4 (the resource shortfall stems in part from “LSEs relying solely on the BRA” rather than bilateral contracting, and that “LSEs should have an affirmative obligation to procure new capacity to cover any new Large Loads they seek to interconnect and serve”); East Kentucky Power Cooperative Comments at 14-15 (“PJM does not propose to evaluate whether an LSE’s supply resource portfolio is sufficient to satisfy aggregate load and reliability requirements. . . . PJM does not address whether the LSE is causing the resource adequacy concern that IRAS is intended to address. However, it is not just and reasonable to subject to IRAS curtailment the load of an LSE that has prudently planned its power supply portfolio to include sufficient resources to meet its load-serving obligations, including for New Large Load.”).

PDF page 4

-4-
Yet PJM has entirely ignored that issue, and the reform that PJM proposes—i.e., assigning curtailment obligations based on whether an individual retail load offsets its demand with new capacity—will exacerbate the region’s resource adequacy challenge.  Notably, under PJM’s proposal, an LSE would be curtailed because a new large load in its footprint did not bring new capacity online even if that LSE planned ahead and has sufficient resources to meet its load-serving obligations.  And, conversely, an LSE that has not procured enough capacity for the load it is obligated to serve will avoid curtailment as long as the large load in its footprint brought its own new capacity.  Thus, in the name of solving a resource adequacy shortfall, PJM could simultaneously curtail entities that have done nothing to cause that shortfall in the first place while rewarding entities that have signed up more load than they have planned to serve.  This problem will only get worse as resources reach the end of their useful lives and state and federal environmental regulations begin to bind.  The likely wave of resource retirements is the next significant challenge the PJM system will face. By misidentifying the source of the current resource shortfall, PJM will hinder the ability to address the next resource adequacy challenge. In defending IRAS, Governor Shapiro’s filing claims that “PJM is appropriately aligning IRAS with existing practices that generally limit curtailment signals to zones with real-time capacity shortfalls.”5  But IRAS does not limit curtailments to zones with real-time capacity shortfalls.  Instead, IRAS directs curtailments based on individual retail customers’ contracting decisions, which is not necessarily indicative of whether a zone or area is resource adequate. Indeed, a zone or area with a 100 MW capacity surplus that adds a 50 MW Eligible New Large Load to its footprint would nevertheless be called to curtail 50 MW whenever an IRAS event is

5 Gov. Shapiro Answer at 9.

PDF page 5

-5-
triggered.  The notion that the “aggregate MW limitations on service imposed [through IRAS] at the zonal transmission system-level[] is appropriate and commensurate with the risks posed to the bulk power system”6 is misinformed.  An ED or LSE that poses no risk to reliability could still be called to curtail because IRAS is not keyed to wholesale zonal conditions.  This, in turn, means that PJM will curtail LSEs or EDs that are resource adequate while not curtailing LSEs or EDs that are not resource adequate.  That, by definition, will jeopardize reliability in the operational time horizon and make it more difficult to ensure resource adequacy in the planning horizon.  A “solution” that misidentifies the problem, rewards entities that are causing the problem, and punishes entities that are not causing the problem is definitionally unjust, unreasonable, and unduly discriminatory and preferential.

The most frustrating element of PJM’s IRAS proposal is that PJM could have designed a curtailment protocol similar to IRAS but focused on short LSEs.  Rather than develop a large load registry, PJM could have designed a registry where LSEs identify their supply arrangements. Instead of designating LSEs with large loads for curtailments, PJM could have required short LSEs to identify loads that would be curtailed when PJM is in an operational emergency.  If PJM had simply targeted the IRAS infrastructure at short LSEs instead of large loads it could have addressed its near-term challenges in a just and reasonable, not unduly discriminatory, and jurisdictionally durable fashion.

B. IRAS Exceeds the Commission’s Jurisdiction
The record resoundingly demonstrates that IRAS is jurisdictionally impermissible. Numerous parties have echoed Vistra’s arguments that the proposal targets retail customers, in

6 Gov. Shapiro Answer at 4.

PDF page 6

-6-
violation of the FPA’s jurisdictional boundaries.7  Although a small handful of parties take the opposite view, their arguments are flawed, self-defeating, or lack support altogether.

PJM’s jurisdictional defense stalls in the garage because it fundamentally misunderstands the controlling Supreme Court precedent.  PJM myopically insists that the Supreme Court’s “targeting” inquiry turns only on the utility’s stated justification for the rate it is proposing. Specifically, in PJM’s telling, EPSA instructs that “[w]hether [] a rule ‘targets’ retail or wholesale customers turns on the justification for the rule, not on whether or the extent to which the rule affects or even compels action of retail or wholesale customers.”8  This is wrong.  While the Court in EPSA considered the Commission’s justification for Order No. 745, it did so only after considering how the rule “work[ed]” and concluding that “whatever the effects at the retail level, every aspect of the regulatory plan happens exclusively on the wholesale market and governs exclusively that market’s rules.”9  So while PJM argues that language in its transmittal confirms that IRAS is “targeted to PJM’s wholesale market and enhancing the reliable operation of the bulk electric power system”10 that is beside the point because, in practice, every aspect of IRAS does not happen exclusively at the wholesale level.  In other words, PJM’s stated target does not match its reforms’ actual target.

Contrary to PJM’s position, the jurisdictional inquiry required by the FPA does not turn on how a utility characterizes a rate in a transmittal letter.  If it did, any utility could bend the FPA’s jurisdictional bright line to its liking based on how it characterized its proposal in the transmittal

7 See, e.g., Constellation Comments at 13; Corporate Energy Buyers Association Comments at 7.
8 PJM Answer at 19-20 (citing FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 264 (2016) (“EPSA”)).
9 EPSA, 577 U.S. at 282.
10 PJM Answer at 21.

PDF page 7

-7-
letter.  Claiming that up is down does not make it so.  The FPA’s jurisdictional divide cannot turn on how a filer describes its intent in a transmittal letter.  The Commission must look at the filed rate itself and determine whether it targets a matter within the states’ jurisdiction. Next, PJM and several other parties contend that, because PJM would not literally curtail individual retail customers, it cannot be targeting them.11  But that response entirely misses the point.  PJM is targeting retail customers’ capacity procurement practices and requiring those customers’ LSEs and EDs to curtail service to those retail customers based on their retail-level activity.  Despite PJM’s argument to the contrary, the stated intent of a regulatory action is not what matters from a jurisdictional perspective.  If PJM were correct, it would have been completely unnecessary for the Supreme Court to “consider[] ‘the target at which a law aims’” in the first place.12  The Supreme Court instead could have held that the jurisdictional inquiry turns on “the stated intent of the law.”  But that was not the holding in EPSA or Oneok.

Thus, it is simply incorrect that “protestors cannot logically claim both that PJM’s proposal unlawfully ‘targets retail customers’ and that PJM’s proposal is fatally flawed because it cannot guarantee which individual retail customers are curtailed.”13  It is true that PJM has targeted retail customers by proposing to assign load curtailments to EDs and LSEs based on the retail customers they serve.  It is also true that EDs and LSEs assigned curtailment may direct those curtailments at other end-use customers such that the incentives for large loads to BYONC are undermined. The fact that PJM’s shot may miss the target does not change where PJM aimed.  As the Supreme

11 PJM Answer at 26-28; See, e.g., Gov. Shapiro Answer at 9-10 (“[P]rotestors cannot logically claim both that PJM’s proposal unlawfully ‘targets retail customers’ and that PJM’s proposal is fatally flawed because it cannot guarantee which individual retail customers are curtailed. Both cannot be true.”); Appalachian Voices Comments at
8. 12 EPSA, 577 U.S. at 282 (quoting Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 385 (2015) (“Oneok”)).
13 Gov. Shapiro Answer at 9-10.

PDF page 8

-8-
Court has long recognized, both federal and state regulators can nominally address a matter within their respective purview while in fact impermissibly targeting or aiming at the other.14  Doing so violates the FPA’s bright line between federal and state jurisdiction as much as if the relevant regulator exceeded its jurisdiction directly.15  For example, in Hughes, Maryland’s state- jurisdictional contract-for-differences scheme did not dictate the wholesale auction clearing price directly.  Nevertheless, the Supreme Court held that the scheme was jurisdictionally impermissible because it guaranteed the generator a rate distinct from the auction clearing price, even though it did not literally change that price.  “That Maryland was attempting to encourage construction of new in-state generation does not save its program,” because, as the Court put it, the program amounted to indirect wholesale rate setting that “invade[d] FERC’s regulatory turf.”16  So too here where PJM has proposed to differentiate customers’ wholesale service based solely on the practices of retail customers.

Although certain parties try to frame IRAS as working only at the wholesale level,17 their own pleadings prove otherwise.  For example, Governor Shapiro’s filing claims that IRAS does not “[t]arget retail customers . . . by mak[ing] the characteristics of the retail customer . . . the basis for a curtailment obligation.”18  At the same time, Governor Shapiro’s filing asserts that IRAS would “limit the total MWs of load reduction in a zone or area based on the share of new large loads . . . that have failed to meet their capacity needs through BYONC or capacity procured

14 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 164 (2016); Oneok, 575 U.S. at 385; N. Nat. Gas Co. v. State Corp. Comm’n of Kan., 372 U.S. 84, 94 (1963); Nw. Cent. Pipeline Corp. v. State Corp. Com’n of Kan., 489 U.S. 493, 514-15 (1989).
15 EPSA, 577 U.S. at 289 (“The FPA leaves no room either for direct state regulation of the prices of interstate wholesales” or for regulation that “would indirectly achieve the same result.” (internal quotation marks omitted)).
16Hughes v. Talen Energy Mktg., LLC, 578 U.S. at 163-64.
17 See, e.g., Gov. Shapiro Answer at 10; Public Interest Organizations Comments at 19 (“PIOs Comments).
18 Gov. Shapiro Answer at 7.

PDF page 9

-9-
pursuant to Reliability Backstop Procurement (RBP) rules.”19  Those two statements cannot be squared.  Indeed, as Governor Shapiro’s filing acknowledges, load reductions are based exclusively and entirely on the characteristics of retail customers in the zone—not the characteristics of the LSE or ED.  That is impermissible targeting of retail customers, plain and simple.

Nor is it correct that IRAS “focus[es] on zones or areas projected to have capacity shortfalls in real-time—through the existence of non-capacity backed large loads in the planning horizon.”20 As explained above, IRAS does not focus on zones or areas with shortfalls and instead turns solely on the characteristics of individual retail customers.  Indeed, an LSE/ED could be net long, with sufficient capacity to serve all of the loads in its footprint, but if a new large load comes online without offsetting capacity, that LSE would still receive a curtailment instruction.  In other words, the characteristics and practices of a single retail customer would dictate the wholesale service available to the LSE.

 Similarly, the Public Interest Organizations (“PIOs”) contend that “PJM will respect jurisdictional boundaries by directing IRAS Actions at the wholesale level.  PJM will never curtail individual retail customers—instead, it uses the Registry and results from the most recent BRA to designate megawatt quantities of IRAS curtailment by zone.”21  This argument actually underscores how IRAS targets retail customers.  Indeed, the Registry, in fact, helps ensure that IRAS is “aimed” at “the correct customers”—i.e., specific retail customers without Bring Your Own New Capacity (“BYONC”) arrangements.  Or, as the PIOs put it, “[b]y tracking individual

19 Gov. Shapiro Answer at 8.
20 Id. at 9.
21 PIOs Comments at 19.

PDF page 10

-10-
large loads and BYONC arrangements, the Registry helps ensure that EDs allocate interruptions to the correct customers during IRAS Actions.”22  The FPA does not allow such targeting of retail customers in a FERC tariff.

PJM tries a different approach to defend its proposal on jurisdictional grounds. Specifically, PJM skips past IRAS’s targeting of retail customers when it describes how IRAS will work in practice.  PJM states that when system conditions are tight “PJM would determine the quantity of MW that load in a zone/area would need to be reduced by to maintain system reliability in the PJM Region and provides a directive to Electric Distributors accordingly.”23  But crucially, this ignores the key fact that PJM would determine the quantity of MW that would be reduced based solely on whether individual retail customers have offset their demand with new capacity. PJM also claims that the Commission’s recent Tri-State decision shows that IRAS is jurisdictionally sound, but this comparison is inapt.  PJM argues that, because the Commission found that Tri-State’s HIL Program respected the FPA’s jurisdictional boundaries, it must find that IRAS does as well.  But the only similarity between the two programs that PJM identifies is that both address “concerns regarding the rapid growth of large loads.”24 But that is where the similarities between the HIL Program and IRAS begin and end.  Under the HIL tariff, Tri-State imposes reliability impact review and financial obligations on its Utility Members to prevent costs or operational impacts caused by serving a large load from being shifted to other Utility

22 PIOs Comments at 19.
23 PJM Answer at 26.
24 Id. at 25 (internal quotation marks omitted).

PDF page 11

-11-
Members.25  In this regard, Tri-State’s regime is more consistent with the net-short LSE- responsibility approach that Vistra supports than IRAS’s plain targeting of retail customers.  Tri- State’s regime is meaningfully distinct from IRAS’s targeting of retail customers, but would support Vistra’s proposed alternative of focusing on net-short LSEs rather than particular retail customers.  Under PJM’s proposal, the wholesale customer, unlike Tri-State’s Utility Members, is compelled to take diminished wholesale service solely to address the characteristics and practices of retail customers.  Thus, while the Commission found that Tri-State’s proposal “does not present an impermissible intrusion on retail rate regulation” even though it did “affect the quantity or terms of retail sales,”26 the same cannot be said of PJM’s proposal.

Parties also contend that IRAS must be legal because “actions that would be possible under IRAS are no different from other actions” that PJM can take when carrying out its NERC responsibilities.27  Vistra does not dispute that PJM can initiate emergency procedures to maintain reliability, but that does not give PJM the authority to initiate emergency procedures in any way it chooses, as parties suggest.  For example, PJM could not decide to curtail only EDs in parts of PJM that voted for a certain political party in a particular election, regardless of how concerned it is about resource adequacy.

Finally, parties are wrong to suggest that Vistra and other protesters are arguing that “PJM must blind itself—that it is legally barred from acting on information about the characteristics of

25 Tri-State Generation & Transmission Ass’n., 196 FERC ¶ 61,127, at PP 14-16 (2026) (“Tri-State”).  PJM incorrectly points to paragraph 25 of Tri-State in support of IRAS, but paragraph 25 is a summary of Tri-State’s deficiency letter response, not part of the Commission’s determination.  See PJM Answer at 25 (citing Tri-State, 196 FERC ¶ 61,127 at P 25). 26 PJM Answer at 26 (quoting Tri-State, 196 FERC ¶ 61,127 at P 66).
27 Gov. Shapiro Answer at 7.

PDF page 12

-12-
load growth in a zone or area.”28  This glosses over how IRAS would work.  PJM can and should consider information about aggregate load growth in a zone or area to ensure reliability of the bulk power system, which is jurisdictionally appropriate and directly related to resource adequacy.  But that is not what IRAS does.  Rather, PJM is proposing to determine the quality of wholesale transmission service based on the characteristics and practices of individual retail customers within a zone, which is a bridge too far.  Similarly, the claim that “the protestors’ position would bar PJM from taking into consideration information about generating facilities—ramp rates, minimum run times, outage rates, and so on—because neither the Commission nor PJM have authority to directly regulate generation”29 suffers from the same fallacy.  The Commission can consider information about and regulate wholesale generators that sell into a Commission-jurisdictional wholesale market without running afoul of the states’ jurisdiction over those same generators.  Because those generators are participating in the wholesale market, regulation that considers how the characteristics of those generators impact their wholesale market activity is “aimed” at and “all about” wholesale market participation.30  Even if that regulation incidentally affects areas within the states’ authority, that is of no consequence because FERC’s regulation is aimed at the wholesale market.  And were the Commission to not regulate those generators in the wholesale market, that would give rise to the type of regulatory gap that cannot exist under the FPA, as states cannot set the terms and conditions governing how generators participate in federal wholesale markets.  But the same is not true of retail loads that just want to take retail service.  Unlike the generators that FERC permissibly regulates within its jurisdictional sphere, the retail customers

28 Gov. Shapiro Answer at 10.
29 Id. at 11.
30 EPSA, 577 U.S. at 282.

PDF page 13

-13-
targeted by IRAS are not participating in the FERC-jurisdictional wholesale market.  Accordingly, a rule that prohibits the Commission from conditioning jurisdictional service on the characteristics of non-jurisdictional entities would not preclude the Commission from considering ramp rates, outage rates, or anything else in that parade of horribles.

C. IRAS Unduly Discriminates Against Existing Resources
As Vistra has explained, PJM’s proposal unlawfully discriminates against existing resources in favor of new resources.  Neither PJM’s original filing nor any of the subsequent comments and answers provide record evidence that justifies that discriminatory treatment, much less render it undue.  Even IRAS’s defenders do not explain why new and existing resources are different in any respects that are material to the inquiry at hand—i.e., that they contribute differently to resource adequacy—such that discriminating against existing resources is “due.” PJM blithely asserts that IRAS is not unduly discriminatory against existing generators because “[t]he PJM Region needs new capacity.”31  Vistra agrees, but a construct designed to attract new capacity without sufficient attention to retaining existing capacity may even make matters worse.  As the Commission has explained, “[b]oth new entry and retention of existing efficient capacity are necessary to ensure reliability and both should receive the same price so that the price signals are not skewed in favor of new entry.”32  A MW of existing supply does as much to maintain resource adequacy as a MW of new supply.  That is an issue of physics, not policy, and so it is unsurprising that nothing in the record calls this fundamental fact into question.  In requiring balance between supply and demand, the system does not (and cannot) distinguish between the in-service dates of the resource providing the supply.  A single-minded focus on

31 PJM Answer at 44.
32 PJM Interconnection, L.L.C., 128 FERC ¶ 61,157, at P 102 (2009).

PDF page 14

-14-
incentivizing new entry that comes at the cost of driving existing capacity into retirement will not help PJM’s resource adequacy issues—it will exacerbate them.

Governor Shapiro’s filing attempts to distinguish new and existing generation on the basis that existing generators have previously received capacity market commitments and customers have previously contributed to the “embedded costs” of those generators.33  These arguments are contradicted by the most basic principles of PJM’s capacity market.  The use of the phrase “embedded costs” reveals the misguided focus of Governor Shapiro’s filing.  “Embedded costs” is an established term relevant to monopoly utilities to describe the combined capital, operations, and maintenance costs associated with a resource that a utility is including in its regulated rate base.  In a monopoly utility setting, captive customers are obligated to ensure full recovery of resource costs, including a guaranteed rate of return, and thus it is fair to consider generation resources as having been paid for and thus entitled to existing customers.  Competitive generators sell capacity for a specific delivery year.34  Doing so does not obligate the generator to continue to be a capacity resource after that delivery year35 nor does it obligate any captive customer to guarantee the generator fully recover its costs including a return on equity.  Nor does it entitle PJM (or any loads) to any “special equitable claim [to that capacity] in perpetuity.”36  Indeed, arguments to the contrary disregard the fact that independent generators provide services through voluntary

33 Gov. Shapiro Answer at 16.
34 PJM, Open Access Transmission Tariff, attach. DD.5.4 (Reliability Pricing Model Auctions) (10.0.0), § 5.4.
35 See Id. Common Service Provisions, Definitions C-D, (23.1.0), “Delivery Year.”
36 See BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 269 (D.C. Cir. 2014).

PDF page 15

-15-
participation in the markets and amount to the unprecedented and unconstitutional assertion that existing load has a property right in existing generation.37

The New Jersey Board of Public Utilities (“NJBPU”) argues that new capacity resources should be favored because they “require additional price certainty to enter PJM’s uncertain investment environment, take on risks from federal regulatory uncertainty, and undergo longer project development timelines due to supply constraints and siting and permitting delays.”38  There are at least three flaws with that argument. First, it ignores the fact that new resources have been entering the nation’s organized capacity markets for many years without “additional price certainty.”  Second, to the extent “additional price certainty” is a virtue, it is one that also benefits existing resources which need ongoing investments for maintenance and refueling in order to continue providing capacity. Third, NJBPU fails to recognize that constant tinkering with the market, including via interventions like IRAS, artificially skews prices (e.g., by removing certain new large loads from the Variable Resource Requirement (“VRR”) Curve), which undermines price certainty for all resources—new and existing.  Neither NJBPU nor any other party has attempted to quantify and compare the alleged benefits of providing “additional price certainty” to new resources with the unavoidable and well-understood costs of IRAS’s extreme market intervention, including potentially the cost of replacing the resources that IRAS could incentivize to retire. NJBPU is, therefore, wrong to suggest that the BYONC construct will help attract new resources by providing price certainty. If anything, IRAS signals to developers that the rules of the

37 U.S. Const. amend. V; Duquesne Light Co. v. Barasch, 488 U.S. 299, 299 (1989) (“If the rate does not afford sufficient compensation, the State has taken the use of utility property without paying just compensation and so violated the Fifth and Fourteenth Amendments.”).
38 NJBPU Comments at 6.

PDF page 16

-16-
game in PJM will continue to be shuffled and reshuffled with little-to-no regard for the effects on existing contracts and commercial arrangements, actually discouraging new investment.

D. IRAS Unduly Discriminates Against New Large Loads
As Vistra demonstrated in its initial comments, IRAS discriminates against New Large Loads.  Certain commenters attempt to claim otherwise using three arguments.  None of those arguments are sound.

First, some parties try to justify discrimination between new and existing large loads, arguing that New Large Loads are solely or disproportionately responsible for the region’s resource adequacy shortfall.39  But no party has explained why this is the case.  Nor could they: according to economic principles espoused by the D.C. Circuit, every user of the transmission system is economically marginal, meaning that increases in demand can be attributed to every user, both new and existing.40

Second, Governor Shapiro’s filing asserts that any differential treatment between new and existing large loads is simply due to the fact that IRAS applies on a forward-looking basis.41  That argument is contradicted by the IRAS proposal itself: the IRAS on/off switch makes clear that IRAS does not apply to all new large loads.  Under IRAS, “new” is a term of art that is dictated by variables independent of the load’s vintage or characteristics.  Whether IRAS applies to a given large load is not a function of whether it was online as of the IRAS effective date (i.e., how a

39 E.g., PJM Answer at 61 (“New, not existing load, is the reason for the shortfall, which drives the need for IRAS. Failing to make a distinction between New Large Loads and Large Loads for purposes of applying IRAS would fail to account for causation.”); NJBPU Comments at 5 (framing large loads as “those who have contributed the most to the grid’s current resource adequacy shortfall”); Joint Consumer Advocates Comments at 10 (arguing that large loads “that cause the need for network upgrades or system stress are ‘differently situated’”); Appalachian Voices Comments at 8 (“New Large Loads have caused the capacity shortfall in PJM.”).
40 See BNP Paribas, 743 F.3d at 268-69.
41 Gov. Shapiro Answer at 18.

PDF page 17

-17-
grandfathering provision would typically work) but instead depends, in large part, on the resource adequacy picture in the region in the three years immediately prior to a particular delivery year. Specifically, PJM can switch BYONC obligations off when the region is long capacity for three years, then switch them back on the moment capacity runs short.  When that happens, large loads that were once considered “new” lose that designation even though they never operated under the pre-IRAS rules.  And when the IRAS rules are toggled off, a “new” resource is not considered “new” for IRAS purposes.  Therefore, it is simply incorrect to suggest that IRAS’s differential treatment between new and existing loads is needed to “grandfather existing entities under prior rules.”42 As the IRAS on/off switch shows, IRAS treats New Large Loads differently precisely because they are “new” (as defined in reference to PJM’s ever-shifting baseline) not because they came online after IRAS went into effect.

Third, PJM appears to misunderstand the precedent it cites when it argues that the Commission has permitted differential treatment of large loads if such treatment is “tailored to the specific and unique nature of” such loads.43  In the order on which PJM relies, the Commission found that the differences between CHILLS—a new, non-firm transmission service—and existing transmission service were “narrowly tailored to reflect the interim nature of CHILLS and the unique characteristics of the CHILLS that transmission customers will serve.”44  At most, CHILLS supports the unremarkable proposition that a utility can offer different transmission services to serve differently situated loads.  That is a far cry from PJM’s proposal to diminish the network transmission service of EDs serving materially identical loads.

42 Gov. Shapiro Answer at 18.
43 PJM Answer at 60 (quoting Sw. Power Pool, 195 FERC ¶ 61,196, at PP 85, 87 (2026)).
44 Sw. Power Pool, Inc., 195 FERC ¶ 61,196 at P 85.

PDF page 18

-18-
E. PJM’s Proposed Curtailment Priority Scheme Is Unjust and Unreasonable
Neither PJM nor any other party defending IRAS has justified the proposal to curtail new large loads seeking firm service before demand response resources that have volunteered and are paid to be curtailable.  To start, parties argue that “the proposed order of curtailment are policy judgments that do not render the design unjust and unreasonable.” 45  But curtailing retail load before demand response is not a run-of-the-mill policy judgment—it is a choice that would be arbitrary and capricious and invert basic economic principles by interrupting would-be firm customers before deploying resources that are paid to provide capacity.  Such a design cannot be just and reasonable.

PJM and NJBPU argue that curtailing demand response resources after eligible new large loads will help avoid “fatigue” that could arise if demand response resources are called to curtail too frequently. 46  Demand response resources are paid to curtail when system conditions are tight—that is the entire reason for compensating demand response in the first place.  Demand response resources providing capacity are paid the same price as every other capacity resource and there is no explicit or implicit limit to the frequency with which they will be called to provide capacity.  It would be entirely novel to structure PJM’s curtailment regime to increase the likelihood that demand response resources will meet their contractual obligations going forward. Vistra is aware of no precedent that would permit disadvantaging one class of customers to

45 Gov. Shapiro Answer at 5.
46 PJM Answer at 36 (“The more often a load center is asked to reduce consumption the more disruptive the provision of demand response and the greater the opportunity cost. The result is load centers become less willing to provide demand response and support Demand Resources. . . . Were such Demand Resource fatigue to manifest, there would be a significant adverse effect on the reliability and resource adequacy for the PJM Region.”); NJBPU Comments at 5 (“Importantly, this proposed step will be initiated prior to calling on Pre-Emergency Load Management Reductions Actions, which will help maintain the participation of certain load management reduction resources, like DR, by minimizing ‘fatigue’ that can occur from being over-called on during stress events.”).

PDF page 19

-19-
increase the likelihood that another class will meet contractual obligations to which they have voluntarily agreed.  If PJM is concerned that demand response may not perform adequately as a capacity resource because it is called to curtail too frequently, that should be addressed through accreditation or by creating a demand response product that can only be dispatched a limited number of times, not by introducing a curtailment scheme that is unjust and unreasonable.47 PJM’s proposal is likely to be counter-productive in the long run.  By protecting demand response resources from the need to perform, PJM will encourage additional, less reliable demand resources to enter the market.  These less reliable resources could displace physical generation (or demand response that will actually perform), especially because the reduced expectation of performance will likely lead to demand response capacity offers below the cost of new entry for a new gas-fired plant.  Over time, PJM could become increasingly reliant on demand response that does not expect to need to perform.  That is a recipe for a deepening reliability crisis. PJM also claims that “[t]he Eligible New Large Loads available to provide IRAS have not satisfied their respective capacity needs through BYONC, and therefore, should not obtain the capacity benefit of Demand Resources.”48  In other words, PJM’s position is that Eligible New Large Loads will pay for capacity, including from demand response resources, but should receive no capacity benefit for those payments.  That would flagrantly violate bedrock cost causation principles, as the cost for capacity would be substantial and yet the benefit would be zero.  This is sufficient reason to reject IRAS.

PJM itself “recognized that Eligible New Large Loads would not be able to obtain the full benefit, and therefore, consistent with cost causation principles, [] proposed to compensate them

47 See Google Protest at 21-22.
48 PJM Answer at 31.

PDF page 20

-20-
for the load reduction service—both for the load reduction service provided and in exchange for the avoided capacity service not provided.”49  As a threshold matter, the issue is that Eligible New Large Loads would receive zero benefit for the capacity they paid for, not that they would be unable to obtain “the full benefit.”  More troubling still, PJM is essentially conceding that it will either (1) violate the FPA’s jurisdictional scheme by dictating how retail customers will be compensated at the retail level or (2) violate cost causation because it cannot ensure that retail customers will, in fact, be compensated for their load reduction service.  Put another way, PJM has created a construct that treats certain large loads as if they do not benefit from capacity service, while nonetheless charging them for such service.  Presumably to avoid this obviously unlawful approach, PJM has proposed a compensation scheme that it either cannot implement, or it would be unlawful for PJM to implement.  Either way, this aspect of IRAS is itself sufficient to render it unlawful.

How and whether Eligible New Large Loads are compensated for curtailing should be determined at the state level.  That means PJM has no authority to avoid a cost-benefit mismatch and instead, under IRAS, is left to hope that every large load curtailed under IRAS receives compensation for that curtailment—an uncertainty that in itself is likely to chase investment away from PJM and into other markets where large loads have the benefit of clear rules of the road governing their curtailment obligations.  The cost causation principle requires more than wishful thinking.  PJM errs again when it claims that “when viewed globally” it is just and reasonable to curtail New Large Loads before demand response but compensate them for curtailing.  Cost causation requires that an entity that pays for a service gets that service in a manner that is roughly

49 PJM Answer at 56.

PDF page 21

-21-
commensurate with the costs it incurred; it cannot be satisfied by tallying up all of a customer’s credits and debits and seeing if the ledger balances “globally.”

The Organization of PJM States (“OPSI”) contends that curtailing new large loads after demand response resources would shift the consequences of the region’s shortfall “onto customers and resources that did not cause it,” which “would undermine the basic purpose of IRAS.”50  But OPSI’s argument is not a principled rationale for curtailing new large loads first and, indeed, would undermine the entire demand response construct.  As noted above, demand response resources have volunteered to be curtailed in tight conditions; so, by design, the consequences of shortfalls and tight system conditions always fall on entities that volunteer to be curtailed when conditions warrant.  Further, if PJM had to consider the causes of a shortfall or tight conditions before dispatching demand response resources, which is what OPSI’s argument implies, dispatching demand response would become a fraught and administratively infeasible exercise that would render demand response unusable.  Essentially, the implication of OPSI’s argument is that the curtailment priority that dictates the timing for dispatching demand response resources should be dependent on the general nature of system conditions.  That notion runs contrary to the demand response construct. Finally, OPSI’s argument implies that IRAS curtailments are meant to punish new loads that do not offset their demand with new capacity, but the goal of IRAS is to preserve reliability,51 and curtailing demand response resources first is the best way to do that. Finally, PJM defends the curtailment priority as a way to ensure that New Large Loads satisfy the Ratepayer Protection Pledge, but this is a repeat of a flawed argument that parties rely

50 Organization of PJM States, Inc. Comments at 5 (“OPSI Comments”).
51 See Transmittal at 7.

PDF page 22

-22-
on to defend illegal aspects of IRAS.52  Vistra believes that it is important that large loads do not shift costs onto other customers.  But the Commission cannot accept tariff provisions that violate the FPA just because they make it easier for entities to comply with voluntary commitments they made in other fora.  Whether or not IRAS is just and reasonable and not unduly discriminatory is wholly independent of whether and how entities satisfy the commitments they made under the voluntary Ratepayer Protection Pledge that is nowhere to be found in PJM’s tariff.

F. IRAS Is Unjust and Unreasonable Because it Will Undermine Market
Fundamentals and Harm Resource Adequacy
PJM and IRAS’s defenders have not justified PJM’s proposal to undermine capacity market fundamentals by excluding new large loads from the VRR Curve.  Although PJM argues that it is necessary to exclude new large loads from the VRR Curve to protect other retail customers from high capacity prices,53 PJM has provided no evidence demonstrating that this drastic market intervention is necessary, nor has PJM meaningfully analyzed the foreseeable impacts of that market intervention.  As Vistra has explained, this aspect of PJM’s IRAS proposal will leave PJM worse off than before, by divorcing the VRR Curve from the region’s actual level of demand and muddling the capacity market’s investment signals.

PJM further justifies exclusion of large load from the capacity market by arguing that “the auction will continue to produce a price signal that incents supply to meet the needs of the capacity- backed loads that are included in the demand curve.”54  This response is flawed for several reasons. First, IRAS loads are still paying for capacity, they are simply not getting the benefit of that payment.  To assert that IRAS loads are not “capacity-backed” is not a statement about what they

52 See, e.g., Ohio FEA Comments at 7.
53 PJM Answer at 50-53.
54 Id. at 52-53.

PDF page 23

-23-
have paid for, it is a statement about what they are getting.  Second, Vistra showed, and PJM does not refute, that excluding large loads from the capacity market will impair the capacity price signal for non-IRAS loads.  As the Commission has repeatedly explained, a capacity market based on rational economic theory provides price signals and an investment environment that will help ensure resource adequacy.55  That is of paramount importance to the PJM region if it is to attract the investments necessary to both satisfy the growth of large loads while also maintaining affordability.  Depending on the results of RBP, there may continue to be a resource adequacy gap that will require additional new entry.  A well-functioning market based on true supply and demand fundamentals is necessary to give developers confidence that their decision to enter the market will not destroy the price signal to which their entry was responding.  That developer confidence to enter the market is what will ultimately moderate prices for all loads.  Constant market interventions that collapse demand signals make developers and existing resource owners less likely to invest in the region, which means that the conditions that have been straining resource adequacy in PJM will continue to persist.

Critically, the desire for a well-functioning capacity market does not reflect a belief that “PJM’s only option is to procure supply for all new large loads through the capacity market.” 56 Quite the opposite.  A well-functioning market that fosters innovative commercial arrangements between large loads and generation resources (existing and new) by harnessing competition is the

55 See, e.g., ISO New England Inc., 162 FERC ¶ 61,205, at P 21 (2018) (“A capacity market should facilitate robust competition for capacity supply obligations, provide price signals that guide the orderly entry and exit of capacity resources, result in the selection of the least-cost set of resources that possess the attributes sought by the markets, provide price transparency, shift risk as appropriate from customers to private capital, and mitigate market power. Ultimately, the purpose of basing capacity market constructs on these principles is to produce a level of investor confidence that is sufficient to ensure resource adequacy at just and reasonable rates.” (footnote omitted)); Calpine Corp., 171 FERC ¶ 61,035 (2020). 56  Gov. Shapiro Answer at 24.

PDF page 24

-24-
surest path to serving historic load growth at least cost.  Indeed, Vistra showed that efforts to keep capacity market prices artificially low would ultimately undermine the incentive for large loads to BYONC because the combination of low capacity costs and curtailment risk may provide better value than paying the cost of new entry for the potential to avoid curtailment.  Furthermore, Vistra has not argued that the capacity market should be the sole mechanism for procuring capacity.  As Vistra has repeatedly emphasized, PJM should foster a range of commercial arrangements, including bilateral co-location arrangements, that allow sophisticated parties to procure capacity in ways that move the market and the economy forward at the speed of competition.  But the PJM capacity market should not be thrown by the wayside in that effort.  As PJM acknowledges, part of the role of the capacity market is to “produc[e] a forward price signal that load and generation can contract around through bilateral arrangements.”57  Without that clear price signal, PJM would be banking entirely on the gamble that IRAS sufficiently works as intended to incentivize new entry.  As Vistra previously explained, that gamble is unlikely to pay off. 58

Finally, PJM also attempts to support its proposal to exclude Eligible New Large Loads from the VRR Curve by analogizing to its practice of excluding energy-only resources from the supply curve.  That analogy illustrates the opposite point that PJM intended.  PJM excludes energy- only resources from the capacity market because they are not paid for capacity.  To contrast, the load PJM is proposing to exclude will pay for capacity.  This is the core of the cost causation problem that Vistra explained in its initial Protest:  loads will be expected to pay for a benefit that they will not receive.59  To be consistent with cost causation principles, the supply and demand

57 PJM Answer at 52. 58 Vistra Protest at 20-21.
59 Id. at 16-17.

PDF page 25

-25-
curves should exclude entities that do not pay for capacity or receive capacity payments, while including entities that do pay for or receive capacity payments.  That accurate reflection of basic supply and demand dynamics is also what will, in the long run, incentivize new entry. PJM’s analogy to energy-only resources also fails because it ignores that PJM treats energy-only resources and Eligible New Large Loads differently for planning purposes.  In the planning context, PJM makes conservative assumptions as to both load and generation to ensure that it is able to meet its installed reserve margin.  Specifically, PJM excludes energy-only resources from the studies it conducts to develop the target installed reserve margin and Effective Load Carrying Capability (“ELCC”) and explicitly chooses not to rely on those resources to offset the supply needed to meet the installed reserve margin.  On the other hand, PJM would model all large loads—including Eligible New Large Loads—in the studies it uses to develop the target installed reserve margin and ELCCs.  This conservative approach to planning stands in contrast to what PJM is proposing to do with load in the VRR Curve, where it would administratively tinker with the market to ignore Eligible New Large Loads that will, nevertheless, be connected to PJM’s system.  Pulling Eligible New Large Loads out of the VRR Curve therefore creates a mismatch between PJM’s conservative planning assumptions and its market assumptions.  That is, PJM is planning its system around the same Eligible New Large Loads that it has chosen to exclude from the capacity market precisely because, in the planning context, PJM does want to account for all large loads.

G. IRAS Will Be Counterproductive and Undermine Investment
Not only do stakeholders across the industry agree that IRAS is illegal, they also agree that it will undermine the investments in new capacity that will ultimately resolve PJM’s resource adequacy shortfall.  IRAS proposes to establish a profoundly novel regulatory framework without

PDF page 26

-26-
any grandfathering mechanism for the investments made in reliance on the rules that have previously governed—and, at present, continue to govern—resource adequacy in PJM. Under IRAS, entities that have made billion-dollar investments in digital and energy infrastructure—investments that were informed by the rules in place at the time they made those investments—would be exposed to a regulatory regime that “could not reasonably have been anticipated when a large retail customer and utility entered into their agreement, causing abrupt, substantial impairment to the value of these long-lead time projects.”60  That type of dramatic regulatory change will deter companies from making those billion-dollar investments in the future—the very investments that are needed to actually resolve the resource adequacy issues that PJM faces in a durable manner.  No party appears to rebut that argument. 61

Ironically, while PJM contends that the capacity market was never intended to be the only mechanism for procuring capacity and that it was instead designed to facilitate bilateral contracting,62 its recent market interventions have thrown bilateral contracting into a tailspin. Between IRAS, the Reliability Backstop Procurement, and PJM’s ongoing failure to grandfather existing contracts when it rolls out new regulatory regimes, PJM has created profound regulatory uncertainty and shown an avowed disregard for bilateral contracting.

Governor Shapiro’s filing proffers the explanation that IRAS will, on its own, create sufficient investment incentives because “individual large loads materially decrease their likelihood of being subject to curtailment by investing in new capacity.” 63  But there is no

60 Microsoft Comments at 5. 61 See Gov. Shapiro Answer at 18 (acknowledging that “when needed,” the Commission “grandfathers existing entities,” based on “whether the disruption of settled expectations due to the new rules is significant enough to warrant a transition period to mitigate the harm to settled expectations.”).
62 PJM Answer at 51-52. 63 Gov. Shapiro Answer at 22.

PDF page 27

-27-
guarantee that bringing your own new capacity will actually “materially decrease” the likelihood of being curtailed.  PJM cannot ensure that the states will give BYONC load the benefit it hopes to purchase.  Indeed, PJM goes to great lengths to disclaim any role in curtailing individual retail customers.64  In any event, even if BYONC did “materially decrease” the likelihood of curtailment, a “material” chance is insufficient to support multi-billion-dollar investments. Finally, parties incorrectly assert that there is a logical inconsistency in the idea that “IRAS will not be effective in incenting new large loads to bring their own capacity because only retail authorities, not PJM, decide which specific retail customers are [curtailed]” while also insisting that IRAS “will disrupt expectations, and new large loads need a longer transition period[.]”65  To the contrary, it is fully consistent to point out that IRAS will fail to incentivize investments in new capacity and that existing contracts should be honored.  While these are separate issues with the IRAS proposal, they both serve to illustrate one of the critical underlying flaws in IRAS:  it will undermine the investor confidence needed to build and finance the generation that the region requires.  Under IRAS, new loads coming to the system would have no certainty that bringing their own new capacity would buy them firm service.  And if IRAS does not grandfather existing contracts, investors will have little reason to trust that PJM and the Commission will honor their next contract either.  In that way, IRAS is a recipe for a perpetual resource adequacy and reliability shortfall rather than the type of durable solution the region requires.

64 See, e.g., PJM Answer at 23. 65 Gov. Shapiro Answer at 3-4.

PDF page 28

-28-
III. CONCLUSION
The record before the Commission clearly demonstrates that IRAS is unlawful several times over and it will make PJM’s resource adequacy situation worse, not better.  The Commission should reject PJM’s proposal.

Respectfully submitted,

/s/ J. Arnold Quinn
J. Arnold Quinn
SVP of Regulatory Policy

Andrew Weinstein
Vice President, FERC Market Policy

Vistra Corp.
325 7th Street NW
Suite 520
Washington, DC 20004
arnie.quinn@vistracorp.com
andrew.weinstein@vistracorp.com

Nic Gladd
Sarah Greenberg
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
ngladd@wsgr.com
sgreenberg@wsgr.com
bshpall@wsgr.com

Counsel for Vistra Corp.

Dated:  September 28, 2026

PDF page 29

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.

Dated:  September 28, 2026
Washington, D.C.

/s/ Bryan Shpall
Bryan Shpall
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006