Motion to Intervene and Protest of Tesla, Inc. et al. re the Section 206 investigation re PJM Interconnection’s Reliability Backstop Procurement framework
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. EL26-108-000
(Consolidated with
Docket No. ER26-3380-000)
MOTION TO INTERVENE AND PROTEST OF TESLA, INC., SUNRUN, INC.,
AND RENEW HOME VPP, LLC D/B/A EVERYDAY ELECTRIC
Pursuant to Rules 211 and 214 of the Federal Energy Regulatory Commission's ("Commission" or "FERC") Rules of Practice and Procedure1, Tesla, Sunrun, and Everyday Electric (collectively, "Joint Intervenors") hereby submit this Motion to Intervene and Protest in the parallel Section 206 investigation regarding PJM Interconnection, L.L.C.'s ("PJM") Reliability Backstop Procurement ("RBP") framework.
I. COMMUNICATIONS
All communications, pleadings, and orders regarding this proceeding should be directed to the following designated representative for the Joint Intervenors: Jaden D. Crawford
Tesla, Inc.
1 Tesla Road
Austin, Texas 75725
jadcrawford@tesla.com
617-872-6568
1 18 C.F.R. §§ 385.211, 385.214.
PDF page 2
2
II. MOTION TO INTERVENE
The Joint Intervenors, namely Tesla, Sunrun, and Everyday Electric, are leading developers, operators, and aggregators of advanced energy technologies, distributed energy resources (DERs), behind-the-meter energy storage, and automated Virtual Power Plants (VPPs) operating across the PJM footprint. Collectively, the Joint Intervenors maintain a coordinated technical framework delivering over 1.0 GW of fast, flexible residential and small commercial capacity committed directly to the PJM footprint, capable of alleviating regional grid congestion and support wholesale reliability:
● Tesla, Inc. ("Tesla") is an original equipment manufacturer of residential and small commercial battery energy storage, and develops and deploys energy management software, vehicle-to-grid systems, and behind-the-meter small commercial and residential battery networks across PJM states.
● Sunrun, Inc. ("Sunrun") develops residential solar-plus-storage systems in the region, managing a growing footprint of behind-the-meter battery systems capable of injecting energy back to the grid during peak events.
● Renew Home VPP, LLC d/b/a Everyday Electric ("Everyday Electric") coordinates flexible residential capacity across millions of connected devices in PJM states, orchestrating mass-scale, automated household load-shifting and advanced vehicle-grid integration.
As active market participants, technology providers, and creators of regional virtual power infrastructure, the Joint Intervenors' commercial operations, asset deployments, and multi-state investments are directly affected by PJM's wholesale
PDF page 3
3
market rules, reliability procurement targets, and forecasting structures. No other party can adequately represent the distinct commercial and technical interests of the Joint Intervenors. Accordingly, the Joint Intervenors respectfully request that they be granted full party status in this consolidated proceeding.
III. LEGAL PRECEDENT AND THE "RULE OF REASON"
The Commission has long established that a Regional Transmission Organization ("RTO") cannot shield practices that significantly affect wholesale rates or terms of service by burying them inside internal business practice manuals. Under the judicial and Commission "Rule of Reason" doctrine, provisions that "significantly affect rates, terms, and conditions of service" must be filed in the RTO's tariff.2
The Commission has consistently applied this doctrine to ensure that PJM's business practice manuals maintain regulatory transparency and conform with filed tariff obligations:
● The "Significantly Affects Rates" Standard: The Commission has explicitly held that when PJM modifies accounting, math, or crediting methodologies within its business practice manuals in a way that alters market clearing or procurement targets, those rules must be moved to the tariff.32 See City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985).3 See Energy Storage Ass'n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at PP 111–13 (2018).
PDF page 4
4
● Manuals Cannot Alter Substantive Rights: The Commission has firmly declared that "manual provisions cannot change or revise tariff obligations" or frustrate a market participant's ability to offer compliant capacity.4
Because the internal, structurally deficient forecasting metrics within PJM Manual 19 directly dictate the total Procurement Target for the multi-billion dollar Reliability Backstop Procurement framework, they directly and significantly affect wholesale rates under Docket No. EL26-108-000. Under the Rule of Reason, these practices are squarely within the Commission's Section 206 jurisdiction.
IV. PROTEST
The Joint Intervenors respectfully urge the Commission to direct PJM to incorporate technical modifications to its load forecasting methodologies as part of its upcoming RBP compliance framework. The Joint Intervenors offer these parameters to ensure an accurate and cost-effective resource target:
Requirement for Technical Revisions to Account for Injection-Capable and Demand- Shifting Resources: The operational target for any RBP auction relies directly on the peak load forecasting methodology governed by PJM Manual 19. As demonstrated in previous submissions in the related IRAS proceeding (Docket No. ER26-3515-000), including Tesla’s formal comments filed on September 23, 2026, Manual 19 relies on static baseline assumptions that treat large new loads as entirely flat, invariable demands. The
4 See Radford's Run Wind Farm, LLC v. PJM Interconnection, L.L.C., 165 FERC ¶ 61,121 (2018).
PDF page 5
5
current framework does not fully incorporate advanced forecasting methodologies that account for the over 1.0 GW capability of the Joint Intervenors' PJM-localized co-located energy storage networks that are capable both of serving on-site load and grid injections, and automated demand response and peak-shaving dispatch regardless of whether those behind-the-meter resources possess grid-injection capabilities5. Accounting for how these active assets are operating to reduce system peaks through state or utility programs within the PJM Manual 19 Attachment D demand-offset calculations is necessary to ensure the regional capacity target reflects actual grid conditions.
1. Need for Predictable Demand Offsets Across Resource Categories: By omitting these advanced, multi-technology metrics from the formal forecasting text, the current framework prevents injection-capable behind-the-meter battery networks and automated residential demand-response assets from being fully credited as offsets to peak wholesale demand. Updating these definitions will ensure PJM establishes its reliability procurement targets on an optimized baseline that accurately reflects the modern grid flexibility resources actively deployed by the Joint Intervenors within the PJM footprint.
2. Alignment with Advanced Technology Investment Signals: Incorporating clear Virtual Power Plant and storage capabilities within peak load forecasts supports efficient wholesale market signals. Establishing a transparent methodology prevents the unintended penalization of commercial investments in flexible, cost- effective technologies, helping to avoid unnecessary, ratepayer-funded capital expenditures for traditional backstop infrastructure.
5 See Energy Storage Ass'n, 162 FERC ¶ 61,296, at PP 111–13.
PDF page 6
6
3. Supporting the Regulatory Role of State Commissions: In its recent orders, the Commission affirmed that state utility commissions hold jurisdictional authority over retail energy delivery and large-load grid integration, noting that states play a central role in managing localized reliability dynamics.6 To effectively fulfill these responsibilities, state regulators require clear visibility into regional forecasting data and underlying methodologies. Utilizing the Joint Intervenors' proposed technology-specific adjustments to reduce baseline peak load projections provides state commissions with the necessary operational information to accurately evaluate and support local resource adequacy alongside PJM.
V. CONCLUSION AND REQUESTED RELIEF
WHEREFORE, the Joint Intervenors respectfully request that the Commission:
● Grant full party status to the Joint Intervenors in Docket No. EL26-108-000;
● Direct PJM to incorporate into its upcoming RBP compliance filing a modification to Manual 19 that transparently subtracts verified, technology- specific VPP asset pools, behind-the-meter storage grid injections, and automated demand response capacities from its baseline peak load projections regardless of whether those behind-the-meter resources possess grid-injection capabilities7; and
6 See PJM Interconnection, L.L.C., Docket No. ER26-3515-000 (Oct. 9, 2026) (rejecting IRAS and related provisions as intruding on state jurisdiction over retail customer obligations, retail curtailment, and retail rates). 7 See Energy Storage Ass'n, 162 FERC ¶ 61,296, at PP 111–13.
PDF page 7
7
● Accept PJM's subsequent compliance elements subject to the inclusion of these constructive forecasting adjustments.
Respectfully submitted,
By: /s/ Jaden D. Crawford
Jaden D. Crawford
Head of VPP Policy, North America
Tesla, Inc.
jadcrawford@tesla.com
Dated: October 20, 2026