ER27-25-000 · 2026-10-22 · Northern Indiana Public Service Company
Motion to Intervene and Comments of Northern Indiana Public Service Company in support of the Midcontinent Independent System Operator, Inc’s Large Load…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
Operator, Inc.
)
)
)
)
Docket No. ER27-25-000
MOTION TO INTERVENE AND COMMENTS IN SUPPORT OF
NORTHERN INDIANA PUBLIC SERVICE COMPANY LLC
Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission (“FERC” or the “Commission”) Rules of Practice and Procedure,1 Northern Indiana Public Service Company LLC (“NIPSCO”), a subsidiary of NiSource Inc., moves for leave to intervene in this proceeding and submits these Comments in support of the Midcontinent Independent System Operator, Inc’s (“MISO”) filing in the above-captioned docket to establish a Large Load Addition Resource Study (“LARS”) process.2 MISO’s LARS Proposal is designed to be a permanent study process that optimizes the MISO generator and load interconnection processes by providing expedited review of the requested addition of 200 MW or greater loads together with new generation resources that are electrically proximate to those loads. The LARS Proposal is just and reasonable and not unduly discriminatory. Therefore, the Commission should approve MISO’s filing, effective December 2, 2026, as requested by MISO.
I. COMMUNICATIONS
NIPSCO requests that all communications in this proceeding be served on the following representatives:
1 18 C.F.R. §§ 385.212, 214 (2026).2 Midcontinent Independent System Operator, Inc., Revisions to the Open Access Transmission, Energy and Operating Reserves Tariff Large Load Addition Resource Study Process, Docket No. ER27-25 (filed Oct. 2, 2026) (“LARS Filing” or, generally, “LARS Proposal”).
PDF page 2
2
Karl E. Stanley
Vice President, Supply and Optimization
NiSource Corporate Services
801 East 86th Avenue
Merrillville, IN 46410
(219) 647-4810
kestanley@nisource.com
M. Bryan Little
Assistant General Counsel
NiSource Corporate Services
150 West Market Street
Indianapolis, IN 46204
(301) 704-5757
BLittle@nisource.com
Evan C. Reese III
Margaret Czepiel
Dina A. Goldman
Day Pitney LLP
555 11th Street NW
Washington, DC 20004
202-218-3917
ereese@daypitney.com
mczepiel@daypitney.com
dgoldman@daypitney.com
II. MOTION TO INTERVENE
A. Description of NIPSCO
NIPSCO is an Indiana limited liability company headquartered in Merrillville, Indiana, and is a subsidiary of NiSource Inc. NIPSCO serves more than 877,800 natural gas customers and 492,700 electric customers across Northern Indiana. NIPSCO owns and operates approximately 3,880 megawatts of electric generating capacity and 2,981 miles of electric transmission lines. NIPSCO is an electric load-serving entity and a transmission-owning member of MISO. NIPSCO has transferred functional control of its transmission system to MISO, which serves as NIPSCO’s Reliability Coordinator.
B. Grounds for Intervention
NIPSCO is a transmission-owning member of MISO and owns and operates generation facilities in the MISO footprint. NIPSCO also serves loads across Northern Indiana and expects to serve the type of loads that are at issue in the LARS Proposal. NIPSCO therefore has a direct and
PDF page 3
3
substantial interest in this proceeding that cannot be adequately represented by another party. Pursuant to Rule 214, NIPSCO moves to intervene with full rights as a party in this proceeding.3
III. BACKGROUND
Recent projections of electricity demand growth and the Commission’s recent Show Cause Order related to large load interconnections underscore the need for MISO to develop a process for studying large loads and the generation intended to serve them.4 Specifically, MISO’s 2026 Reliability Imperative Report found that data centers, manufacturing expansion, and electrification will drive annual load growth by 1% to 2% through 2044. To address long-term resource adequacy issues, the fast connection of new resource additions is paramount for supporting large load growth and ensuring reliability as reflected in MISO’s 2026 Planning Resource Auction Results. The Department of Energy’s (“DOE”) Speed to Power Initiative, likewise reflects the need to accelerate the development of generation and transmission infrastructure to serve growing load. In the Show Cause Order issued by the Commission on June 18, 2026, the Commission identified potential gaps in the MISO Tariff concerning study procedures and services for the interconnection of generation with electrically proximate large loads.5 The Commission directed MISO to provide
3 18 C.F.R. § 385.214 (2026).4 MISO, 2026 Reliability Imperative Report at 4 (Feb. 2026) (finding that data centers, manufacturing expansion, and electrification are driving annual load growth of approximately 1% to 2% through 2044) https://cdn.misoenergy.org/2026%20Reliability%20Imperative%20Report744320.pdf; see also, MISO, 2026 Planning Resource Auction Results at 2 (May 22, 2026) (“faster resource additions are still needed to support large-load growth and ensure resource adequacy”) https://cdn.misoenergy.org/2026%20PRA%20Results%20Posting%2020260522%20- %20Corrections754715.pdf; see also DOE, Speed to Power Initiative (Sept. 18, 2025) (describing the initiative as a federal effort to accelerate development for large-scale transmission and generation projects and improve reliability.) https://www.energy.gov/oe/speed-power-through-accelerated-reconductoring- and-other-key-advanced-transmission-technology; Midcontinent Independent System Operator, Inc., et al., Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).5 Show Cause Order at P 113 (2026).
PDF page 4
4
a detailed report on any proposals under consideration to address the concerns of resource adequacy.6
For its part, NIPSCO, like many other electric utilities in MISO, is facing an unprecedented level of interest from customers that desire to locate in NIPSCO’s electric service territory. While historically, a new customer may inquire about adding a few MW of service and an inquiry for 10- 20 MW was considered a large load addition, new inquiries are now seeking to establish hundreds or in some cases thousands of MW of new load. These new customers are also emphasizing the desire for reliable and stable service to begin as soon as possible and the ability to interconnect quickly. New generation in the MISO footprint is urgently needed in order to reliably accommodate this growth, and accordingly new processes designed to expedite and integrate the study process for the interconnection of large loads and their associated new generation are critical. The LARS Proposal addresses these resource adequacy concerns and the need to streamline the MISO generator and load study process. Under the LARS Proposal, MISO would provide an expedited pathway for studying qualifying large loads together with associated new generation resources. While LARS Interconnection Customers will remain responsible for meeting the requirements of MISO’s standard Generator Interconnection Queue, generation and load studies will be conducted together under a single application.7 Also, Large Load Generator Interconnection Agreements would be executed in 120 days.8 Leveraging the successes of MISO’s existing Expedited Project Review process for new electric transmission projects (“EPS”), and Expedited Resource Addition Study process for new generation facilities (“ERAS”), this LARS
6 Id. At P 122.7 LARS Filing at 7.8 Id. at 5.
PDF page 5
5
Proposal and its expedited timeframe is expected to integrate new large loads to the MISO region in a timely and reliable manner.9 Unlike the ERAS process, which is a short-term fix to process interconnection requests for generation necessary to meet significant, near-term needs, the LARS Proposal is a permanent study process that would address MISO’s long-term need to interconnect large loads and their associated generation.
Importantly, the LARS Proposal contains several requirements that allow MISO to study the new load impacts with greater certainty and reduce the risks of speculative generation or load. These include the mandatory pre-submission coordination activities that require that the entities involved in each LARS Application are aligned on all relevant details including the point of interconnection and an agreement demonstrating the exact output the generating facility will use to serve the associated load.10 In addition, the LARS Associated Transmission Customer, or Load Serving Entity, must submit a non-refundable fee of $250,000 along with the LARS Application. Forty-five days in advance of submitting the joint LARS application, the interconnection customer must notify the transmission owner of its intentions to participate in LARS. After receiving the request, the transmission owner must meet with the interconnection customer and any impacted parties.11 These pre-submission coordination activities are designed to increase the efficiency of MISO’s review by having all of the necessary details agreed upon prior to filing the LARS Application.
The LARS Process provides further certainty because LARS applications must also include a signed agreement between the interconnection customer and owner or controller of the associated
9 LARS Filing at 2.10 Id. at 8-9.11 Id.
PDF page 6
6
load that demonstrates the commitment that the output of the new generation facility will serve the new load for at least five years.12 This minimum service period provides assurance that the load and generation will come online and all affected parties’ investments in the projects are warranted. Finally, and importantly, the generation and proximate load must remain paired for a minimum of fifteen years to ensure that resources are not reallocated to existing load and the LARS Process is not misused.13
MISO first introduced the LARS Proposal at the July 16, 2026 Large Load Working Group meeting and revised the original proposal to address mismatches between the existing MISO study processes and the LARS study processes in response to feedback from stakeholders.14
IV. COMMENTS IN SUPPORT
NIPSCO supports MISO’s LARS Proposal. By coordinating the study of qualifying large loads and associated generation, the LARS Proposal offers a mechanism to identify necessary network upgrades and bring new resources online while preserving reliability.15 It also addresses the gaps in MISO’s Tariff as identified by the Commission in the Show Cause Order. MISO’s 2026 Reliability Imperative Report, the MISO’s 2026 Planning Resource Auction Results, and DOE’s Speed to Power initiative all point to a high level of near-term reliability and resource adequacy risk brought about by large load additions.16 While MISO has made recent strides in addressing issues with its interconnection initiatives such as the existing EPR and ERAS processes, LARS presents a permanent solution to NIPSCO’s and other MISO participants’ imminent needs to bring
12 Testimony of Christina Drake at 17, 35 (“Drake Testimony”).13 See Drake Testimony at 35-36.14 See LARS Filing at 11-12.15 Show Cause Order at P 113.16 Supra at 4.
PDF page 7
7
large loads and their proximate generation online in a safe and reliable manner. The LARS Proposal provides a cost-effective tool to address the intersection of large load and generation, as well as identify more optimized Network Upgrades at an expedited rate.17
A. The LARS Proposal is Necessary to Address MISO’s Short-Term Needs
MISO’s existing interconnection process as set forth in Attachment X of MISO’s Tariff (the Definitive Planning Phase (“DPP”) process) alone is insufficient to bridge the corresponding needs of new generation and large expected load growth throughout the MISO footprint. While the DPP process is well-suited to address NIPSCO’s interconnection needs for normal load growth, the scale and timing of large load interconnections present a different challenge. NIPSCO and other MISO Market Participants are working with potential large load customers, such as data centers, that have unprecedented service needs on short timeframes. NIPSCO, for example, is considering requests to add between 3,000-8,000 MW primarily to serve megaload customers.18 The DPP process was simply not designed to process the needs for both the interconnection of new large load additions and the interconnection of new generation to supply energy to those loads in an organized, coordinated and comprehensive fashion.
Large loads present operational and reliability challenges and therefore require detailed studies that enable affected parties to plan for reliability challenges. The LARS Proposal would allow MISO to evaluate the associated load and generation using aligned assumptions and to identify the upgrades required to accommodate both, through a single process. This coordinated
17 LARS Filing at 4.18 On June 17, 2026, the Indiana Utility Regulatory Commission made several approvals that would allow NIPSCO to provide service to an Amazon data center expected to increase to 2,400 MW by the end of 2032.
PDF page 8
8
approach could reduce the time needed to bring qualifying projects online without relying solely on improvements to the broader DPP queue.
B. The LARS Proposal is a Just and Reasonable Solution
As MISO outlines in its filing, the LARS Proposal is tailored to meet a specific need identified by the Commission.19 It is self-limiting in that it is designed solely to study generation/load pairs and maintains several guardrails in order to protect the DPP process and DPP interconnection customers. MISO developed the LARS Proposal to ensure that the process works in tandem with the DPP process and existing interconnection customers are not adversely impacted. For instance, the LARS Proposal is designed to keep the transmission capacity available for LARS applications separate from the transmission capacity headroom available throughout the DPP cycle.20
Further, LARS Applicants must commit to a substantially higher financial commitment including a non-refundable $250,000 application fee. This payment will be used to fund the additional tools, staffing, and process enhancement MISO needs to support its existing process and LARS.21
Finally, LARS applications cannot be modified after submission and prior to the execution of the Large Load Generator Interconnection Agreement, ensuring that LARS Applicants avoid sudden changes causing delays and withdrawals.22 The LARS Proposal is a just and reasonable solution to MISO’s current resource adequacy dilemma.
19 LARS Filing at 20.20 Id.21 Drake Testimony at 32.22 LARS Filling at 30.
PDF page 9
9
V. CONCLUSION
WHEREFORE, and for good cause shown, NIPSCO respectfully requests that the Commission grant this Motion to Intervene and consider these Comments in support and accept MISO’s LARS Proposal, effective December 2, 2026, as requested.
October 22, 2026
Respectfully submitted,
/s/ Evan C. Reese III
Evan C. Reese III
Margaret Czepiel
Dina A. Goldman
Day Pitney LLP
555 11th Street NW
Washington, DC 20004
202-218-3917
ereese@daypitney.com
mczepiel@daypitney.com
dgoldman@daypitney.com
M. Bryan Little
Assistant General Counsel
NiSource Corporate Services
150 West Market Street
Indianapolis, IN 46204
(301) 704-5757
BLittle@nisource.com
PDF page 10
10
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon the parties designated on the official service list compiled by the Secretary for the above-captioned dockets in accordance with the requirements of Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice and Procedure, 18 C.F.R. 385.2010 (2026).
Dated at Washington, DC this 22nd day of October, 2026.
/s/ Dina A. Goldman
Dina A. Goldman
Day Pitney LLP
555 11th Street NW
Washington, DC 20004
202-218-3906