ER27-529-000 · 2026-11-16 · New York Independent System Operator, Inc., Central Hudson Gas & Electric Corporation and 5 others
Att E Pro Forma LL CRA
PDF page 1
Attachment E
Pro Forma Large Load Cost Recovery Agreement
PDF page 2
44.16.9 Appendix 9 to Attachment LL – Pro Forma Cost Recovery Agreement
PRO FORMA LARGE LOAD COST RECOVERY AGREEMENT
BETWEEN
[NEW YORK TRANSMISSION OWNER] (Transmission Owner)
AND
[CUSTOMER NAME] (Customer)
PDF page 3
TABLE OF CONTENTS
Recitals and Regulatory Context
Article 1: Definitions
Article 2: Jurisdictional Harmonization
Article 3: Scope and Construction of Network Upgrades and TO Attachment Facilities Article 4: Recovery of Network Upgrade and TO Attachment Facility Costs Article 5: Customer Payments
Article 6: Financial Security, Creditworthiness, and Exit Protection Article 7: Breach, Default, and Remedies
Article 8: Term and Termination
Article 9: Miscellaneous and Regulatory Reservations
•
Appendix A: Description and Engineering Specifications of Network Upgrades and Transmission Owner Attachment Facilities
•
Appendix B: Revenue Requirement Breakdown
•
Appendix C: True-Up and Annual Revenue Crediting Accounting Protocols
•
Appendix D: Addresses for Notices and Billing
PDF page 4
PRO FORMA LARGE LOAD COST RECOVERY AGREEMENT
This PRO FORMA LARGE LOAD COST RECOVERY AGREEMENT (the “Agreement”)
is entered into as of this [___] day of [___], 20[__], by and between:
•
[NEW YORK TRANSMISSION OWNER] (“Transmission Owner” or “Connecting
Transmission Owner” or “Affected Transmission Owner”), a [corporation] organized and existing under the laws of the State of New York, having an office and place of business at [___________]; and
•
[CUSTOMER NAME] (“Customer”), a [corporation / limited liability company] organized under the laws of the State of [______], having an office and place of business at [______], and owning a Large Load Facility with an expected peak demand of [__] MW at the Point of Interconnection.
Transmission Owner and Customer are collectively referred to as the “Parties,” and each individually as a “Party.”
RECITALS
WHEREAS, Customer has submitted a Large Load Integration Request to interconnect or serve a Large Load Facility with an aggregate demand equal to or exceeding fifty megawatts (50 MW) [at a transmission-system interconnection point within the Transmission Owner’s service territory] or [affecting the Affected Transmission Owner’s transmission facilities in New York State];
WHEREAS, New York Independent System Operator, Inc. (“NYISO”) and/or Transmission Owner have performed system reliability impact studies, facility studies, and engineering assessments pursuant to the NYISO Open Access Transmission Tariff (“OATT”), identifying that the interconnection and commercial operation of Customer’s Large Load Facility will necessitate the construction and placement into service of certain Network Upgrades and/or TO Attachment Facilities on the [Transmission Owner’s] [Affected Transmission Owner’s] transmission system to maintain electric system reliability and system adequacy; and WHEREAS, Customer has received the cost allocation for Network Upgrades and/or TO Attachment Facilities identified by System Impact Studies and Facilities Studies under Attachment LL of the NYISO OATT or successor tariff provisions and has entered into, and posted Financial Security for the benefit of [Transmission Owner] [Affected Transmission Owner] in accordance with, the Large Load Security Agreement;
NOW, THEREFORE, in consideration of the mutual covenants and agreements herein contained, the Parties agree as follows:
ARTICLE 1: DEFINITIONS
Wherever used in this Agreement, capitalized terms not defined herein shall have the meanings assigned to them in the NYISO OATT or NYISO Market Services Tariff.
PDF page 5
1.1 “Affiliate”: means, with respect to a person or entity, any other person or entity directly or indirectly controlling, controlled by, or under common control with such person or entity. “Control” means the possession, directly or indirectly, of the power to direct the management or policies of a person or entity; a voting interest of ten percent (10%) or more creates a rebuttable presumption of control.
1.2 “Assessment Period”: A term of 15 years commencing on the Commencement Date. 1.3 “Commercial Operation Date” (COD): The date on which Customer’s Large Load Facility has achieved energization and begins taking firm electric service pursuant to [the applicable Tariff] or [the Large Load Interconnection Agreement] at or above its designated minimum capacity commitment, as confirmed by notice delivered under the Large Load Interconnection Agreement.
1.4 “Commencement Date”: The date upon which the Network Upgrade and/or TO Attachment Facility is placed in service, as reflected in the In-Service Date under the Large Load Interconnection Agreement [or other applicable agreement].
1.5 “Cure Date”: The last day of the applicable cure period under Section 7.2. 1.6 “FERC”: The Federal Energy Regulatory Commission or its regulatory successor. 1.7 “Large Load Facility”: A newly interconnecting or expanded end-use electric load, co- located arrangement, or data center facility with an anticipated peak electrical demand equal to or exceeding 50 MW connecting at a voltage of 69 kV or higher.
1.8 “Large Load Upgrade Charge”: The monthly charge billed to Customer under Article 4 to recover the revenue requirement for the Network Upgrades and the TO Attachment Facilities specified in Appendix B.
1.9 “Net Present Value Residual Charge”: A lump sum payment equal to the net present value of the Customer’s obligations under the remaining term of this Agreement at the time of termination that would have been collected over the remaining term of the Assessment Period, plus any cost of removal if applicable, calculated using the inputs set forth in Appendix B for each Identified Upgrade set forth in Appendix A. The discount rate shall be equal to the interest rate pursuant to Section 35.19a of FERC’s regulations, or successor regulation, effective at the time of termination. To the extent the calculation of the Net Present Value Residual Charge requires estimates of the Customer’s remaining obligations, such estimates shall be determined by the Transmission Owner in its reasonable discretion.
1.10 “Network Upgrades”: Additions, modifications, enhancements, or replacements (other than TO Attachment Facilities) to the [Transmission Owner’s] [Affected Transmission Owner’s] electric transmission system required at or beyond the Point of Interconnection to accommodate the Customer’s Large Load Facility reliably under NERC, NPCC, NYSRC, and Transmission Owner [Affected Transmission Owner] reliability criteria and identified through the Large Load Integration Procedures contained at Attachment LL of the NYISO OATT and set forth in [Appendix A, the Large Load Interconnection Agreement, and/or other applicable agreement]. 1.11 “NY PSC”: The New York State Public Service Commission or its regulatory successor. 1.12 “Reimbursable Costs”: Costs and expenses incurred by the Transmission Owner in planning, designing, engineering, permitting, procuring, project managing, constructing, testing, and commissioning the Network Upgrades and the TO Attachment Facilities, including any
PDF page 6
incremental costs resulting from a Customer-requested suspension or a Customer delay under Section 3.3, consistent with Good Utility Practice.
1.13 “Related Agreements”: Collectively, this Agreement, the Large Load Interconnection Agreement, the Large Load Security Agreement, and any other applicable agreement referenced in Section 3.4.
1.14 “TO Attachment Facilities”: All facilities and equipment owned or controlled by Transmission Owner between the Point of Interconnection and the Point of Change of Ownership that are constructed or modified for the purpose of interconnecting the Large Load Facility, including line taps, breakers, disconnect switches, bus work, metering instrument transformers (if owned by Transmission Owner), System Protection Facilities at a Transmission Owner substation, and associated civil and structural works, as described in [Appendix A, the Large Load Interconnection Agreement, and/or other applicable agreement].
ARTICLE 2: JURISDICTIONAL HARMONIZATION
2.1 Jurisdictional Harmonization. Nothing in this Agreement shall be construed as:
(a) An assertion by the Parties of FERC jurisdiction over bundled retail transmission and distribution rates established by the NY PSC; or
(b) A waiver by Transmission Owner or Customer of any rights, claims, or defenses under the Federal Power Act (“FPA”) or the New York Public Service Law concerning the jurisdictional boundary between wholesale and retail ratemaking.
ARTICLE 3: SCOPE AND CONSTRUCTION OF NETWORK
UPGRADES AND TO ATTACHMENT FACILITIES
3.1 Identification of Upgrades. Transmission Owner shall engineer, design, procure, construct, install, commission, own, operate, and maintain the Network Upgrades and the TO Attachment Facilities detailed in Appendix A and the Large Load Interconnection Agreement, or other applicable agreement, which were, in turn, identified through the process contained within Attachment LL of the NYISO OATT.
3.2 Milestones and Construction Schedule. Transmission Owner shall use commercially reasonable efforts to engineer, design, procure, and construct the Network Upgrades and the TO Attachment Facilities in accordance with the milestone schedule set forth in [the Large Load Interconnection Agreement and/or other applicable agreement]. All such milestones, other than the In-Service Date of the Network Upgrades and TO Attachment Facilities, are good faith estimates, and a change to any such milestone shall not require an amendment of this Agreement. Customer acknowledges that environmental review, Article VII and Article VIII permitting, and all property acquisitions are subject to New York State regulatory approvals and external contingencies.
3.3 Suspension and Customer Delays. If Customer requests a suspension of construction or delays its commercial in-service milestone, Customer shall remain liable for all carrying costs, re-sequencing and re-mobilization costs, and cancellation fees incurred by Transmission Owner under Good Utility Practice during such suspension or delay. Transmission Owner reserves the
PDF page 7
right to notify Customer if such suspension or delay is expected to increase the total estimated cost of the Network Upgrades or the TO Attachment Facilities and to require additional Financial Security in accordance with the Large Load Security Agreement.
3.4 Related Agreements. This Agreement is entered into in connection with, and shall be read together with, [the Large Load Interconnection Agreement between Transmission Owner and Customer dated [●] (the “Large Load Interconnection Agreement”)] [and/or other applicable agreement] and the Large Load Security Agreement between Transmission Owner and Customer dated [●] (the “Large Load Security Agreement”). Customer shall be the same legal entity as the customer under the Large Load Interconnection Agreement (or other applicable agreement) and the Large Load Security Agreement. In the event of any conflict between this Agreement and any Related Agreement regarding the costs of, or charges for, the Network Upgrades or the TO Attachment Facilities, this Agreement shall control; and in the event of any conflict between this Agreement and any Related Agreement regarding Financial Security, the Large Load Security Agreement shall control.
ARTICLE 4: RECOVERY OF NETWORK UPGRADE AND TO
ATTACHMENT FACILITY COSTS
4.1 Customer Responsibility for Allocated Network Upgrade and TO Attachment Facilities Revenue Requirement. Customer shall be responsible for and shall pay to the Transmission Owner the revenue requirement associated with the cost allocation to Customer for required Network Upgrades and TO Attachment Facilities identified in the Facilities Study specified at Section 44.12.1.8 of Attachment LL of the NYISO OATT, or successor provisions as set forth in Appendix A. The revenue requirement shall include, without limitation, appropriate depreciation or amortization, return, income and property taxes, operation and maintenance expenses, metering installation, administrative costs, and other costs as specified in Appendix B. The revenue requirement breakdown is specified herein at Appendix B.
4.2 Large Load Upgrade Charge. The revenue requirement specified at Appendix B shall be recovered through a Large Load Upgrade Charge. This Agreement shall be specific to a single Large Load Facility, as determined by the Transmission Owner in its reasonable discretion. Transmission Owner shall calculate a separate charge for each Identified Upgrade (as defined in Appendix B) for which Customer is responsible, as set forth in Section 3 of Appendix B, and the monthly Large Load Upgrade Charge shall be the sum of all such Identified Upgrade-specific monthly charges. The monthly Large Load Upgrade Charge is specified at Section 4 of Appendix B for each month of years one (1) through the final year of the Assessment Period. The Transmission Owner shall follow the true-up procedures set forth in Section 6 of Appendix
B. 4.3 Early Termination. If, prior to the expiration of the Assessment Period, this Agreement is terminated, or Customer is in default under this Agreement or the Large Load Security Agreement and fails to timely cure the default, Customer shall be liable to the Transmission Owner for the Net Present Value Residual Charge, and the Transmission Owner shall be entitled to draw upon the Financial Security and apply it toward the Net Present Value Residual Charge. If any other outstanding charges or payments are due, Customer shall pay them within thirty (30) days of the termination date or the Cure Date, as applicable.
PDF page 8
4.4 TO Attachment Facilities. Customer shall be responsible for and shall pay to the Transmission Owner (a) all actual costs incurred by Transmission Owner for studies, engineering, design, procurement, construction, oversight, testing, and commissioning of the TO Attachment Facilities, including applicable overheads, taxes, and line outage costs, to the extent not covered by any study cost reimbursement agreement or allocated otherwise under the NYISO OATT; and (b) Transmission Owner’s reasonable and prudent costs, including, without limitation, overheads, of operating, maintaining, repairing, and replacing the TO Attachment Facilities, except to the extent such costs are paid by a third party using such facilities. Unless otherwise agreed to by Transmission Owner and Customer in Section 7 of Appendix B, such costs shall be [included in the revenue requirement specified at Appendix B and recovered through the Large Load Upgrade Charge] [billed as a separately stated component of the Large Load Upgrade Charge] [, at Transmission Owner’s election, paid by Customer as a contribution in aid of construction in advance of or as incurred during construction], and Sections 4.3 and 6.2 and Appendix C shall apply to the TO Attachment Facilities in the same manner as to the Network Upgrades. Customer’s responsibility for, and the recovery of, the costs of the TO Attachment Facilities shall be governed exclusively by this Agreement.
ARTICLE 5: CUSTOMER PAYMENTS
5.1 Commencement Date. Customer’s responsibility to make monthly payments shall begin as of the Commencement Date.
5.2 Monthly Billing and Payments. The Large Load Upgrade Charge shall be billed monthly by Transmission Owner with Customer payment due within thirty (30) days. Monthly bills and payments shall be transmitted electronically in accordance with the information contained at Appendix D, or through paper copies, as the Parties may specify, using the addresses contained at Appendix D. The Parties shall cooperate in good faith to effectuate efficient billing and payment.
5.3 Late Payments. Customer shall pay all invoices on or before their due date, regardless of whether Customer disputes the same in good faith. Any balances that remain unpaid when due shall accrue interest at the interest rate specified at 18 C.F.R. § 35.19a or successor regulation. Transmission Owner may include unpaid balances, with any accrued interest, on the next monthly bill. Any disputes shall be addressed in accordance with Section 9.11. ARTICLE 6: FINANCIAL SECURITY, CREDITWORTHINESS,
AND EXIT PROTECTION
6.1 Obligation to Post Financial Security. To protect other retail and wholesale customers against stranded asset risk in the event Customer fails to achieve the Commercial Operation Date, downscales its capacity requirements, or abandons installation of the Large Load Facility, Customer shall post and maintain security in favor of [Transmission Owner] [Affected Transmission Owner] in the amount and manner specified in the separate Large Load Security Agreement (“Financial Security”). Subject to the determination of obligations under Appendix B of this Agreement, nothing in this Agreement limits in any way the obligations of Customer under the Large Load Security Agreement.
PDF page 9
6.2 Stranded Cost Recovery Upon Abandonment (Exit Protection). If Transmission Owner or Customer terminates this Agreement prematurely or otherwise defaults on its financial obligations:
(a) To the extent that Transmission Owner determines within its reasonable discretion that the Network Upgrade is no longer needed, including based on written confirmation from NYISO that completion of the Network Upgrade is not required and that no other interconnection request, NYISO interconnection or transmission planning study (including any Reliability Needs Assessment or Short-Term Assessment of Reliability), or base case relies on completion of the Network Upgrade, Transmission Owner shall promptly cease incurring uncommitted costs and make reasonable efforts to mitigate losses, except in the case of actions necessary to preserve system reliability, avoid injury or loss of human life, or prevent environmental degradation. If NYISO informs Transmission Owner in writing that the Network Upgrade must be completed, Transmission Owner may continue to engineer, procure, and construct the Network Upgrade, and Customer shall remain responsible for all Reimbursable Costs of completing the Network Upgrade in accordance with Section 6.2(b).
(b) Transmission Owner shall be entitled to draw upon the Financial Security as specified in the Large Load Security Agreement to recover all Reimbursable Costs, including without limitation engineering costs, committed equipment cancellation fees, environmental remediation costs, the costs to restore the bulk electric system to safe and reliable condition, including necessary expediting and acceleration fees, any non- salvageable construction expenditures, the costs of removal, relocation, retirement, or other disposition of any facilities already installed, and, where the Network Upgrade remains needed under Section 6.2(a), the costs of completing the Network Upgrade. Customer shall remain liable for any such costs remaining unpaid after application of the Financial Security.
(c) Any excess security remaining after full recovery and true-up shall be promptly refunded to Customer.
6.3 Reduction in Maximum Load Facility Peak Demand. Any reduction of the Maximum Load Facility Peak Demand under Section 3.6 of the Large Load Interconnection Agreement shall not reduce the Large Load Upgrade Charge, the Net Present Value Residual Charge, or the Financial Security, unless otherwise agreed in writing by the Parties. ARTICLE 7: BREACH, DEFAULT, AND REMEDIES
7.1 Events of Default. An Event of Default shall occur if Customer:
(a) Fails to pay any amount when due;
(b) Fails to provide, maintain, renew, replace, or increase the Financial Security as required under Article 6 and the Large Load Security Agreement;
(c) Becomes insolvent, files for bankruptcy, or undergoes dissolution;
(d) Abandons or materially repudiates its development or interconnection obligations; or
PDF page 10
(e) Is in default under the Large Load Interconnection Agreement (or other applicable agreement) or the Large Load Security Agreement and any applicable cure period thereunder has expired.
7.2 Notice and Opportunity to Cure. Upon the occurrence of an Event of Default, the non- defaulting Party shall provide written notice. The defaulting Party shall have (i) five (5) Business Days after receipt of notice to cure any failure to pay any amount when due or to provide, maintain, renew, replace, or increase Financial Security, and (ii) thirty (30) days after receipt of notice to cure any other default that is capable of cure; provided that a cross-default under Section 7.1(e) shall arise only after expiration of the cure period in the applicable Related Agreement, and no additional cure period shall apply under this Agreement.
7.3 Remedies. If an Event of Default is not remedied by the Cure Date, the non-defaulting Party may:
(a) Terminate this Agreement upon written notice;
(b) Draw upon the Financial Security to satisfy outstanding liabilities;
(c) Suspend engineering, procurement, and construction of the Network Upgrades and the TO Attachment Facilities; and
(d) Pursue any legal or equitable remedies available under New York State law or the FPA.
ARTICLE 8: TERM AND TERMINATION
8.1 Effective Date. This Agreement shall become effective upon execution by all Parties within the timeframe set forth in Attachment LL of the NYISO OATT[, subject to any filing with FERC that may be required under Section 205 of the FPA].
8.2 Term. This Agreement shall remain in full force and effect until all Large Load Upgrade Charge obligations and other payment obligations under Articles 4 and 5, including any Net Present Value Residual Charge, have been fully satisfied.
8.3 Regulatory Modification. Without creating any additional regulatory filing obligations, if FERC or the NY PSC issues an order requiring a material modification, including termination or rejection, of this Agreement, the Parties shall negotiate in good faith for sixty (60) days to conform the Agreement. If agreement cannot be reached, Transmission Owner may terminate this Agreement and draw upon the Financial Security for all incurred, unrecoverable Reimbursable Costs.
8.4 Cross-Termination. Termination of the Large Load Interconnection Agreement (or other applicable agreement) for any reason other than Transmission Owner’s Default (including Customer’s termination for convenience or non-renewal) shall constitute early termination of this Agreement for purposes of Section 4.3, and the Net Present Value Residual Charge shall become due.
ARTICLE 9: MISCELLANEOUS AND REGULATORY
RESERVATIONS
PDF page 11
9.1 Governing Law. This Agreement shall be governed by, construed, and enforced in accordance with the laws of the State of New York, without regard to its conflict of law principles, except to the extent that matters fall within the exclusive jurisdiction of FERC, the FPA, or federal common law.
9.2 FPA Sections 205 and 206 Reservations. Nothing contained in this Agreement shall limit the statutory right of Transmission Owner to unilaterally file with FERC, under Section 205 of the FPA and FERC’s regulations, for modifications in rates, charges, classifications, or terms of service; nor shall it restrict the rights of Customer or the NY PSC under Section 206 of the FPA. 9.3 Severability. If any provision of this Agreement is held invalid, illegal, or unenforceable by a court or regulatory agency of competent jurisdiction, the remaining provisions shall continue in full force, provided the core economic and jurisdictional balance intended by the Parties remains intact.
9.4 Execution in Counterparts. This Agreement may be executed in two or more counterparts, each of which shall be deemed an original, but all of which together shall constitute one and the same instrument.
9.5 Notice. Unless otherwise provided in this Agreement, any required notice shall be made in writing, and shall be effective when delivered by recognized national courier, certified or registered mail, personal delivery, electronic mail, or another method permitted by this Agreement, addressed to the Party at the address set forth in Appendix D.
9.6 Amendment; Waiver. This Agreement may be amended, superseded, or modified by a written instrument executed by both Parties, subject to any required filing with and acceptance by FERC and any required approval of the NY PSC. No waiver shall be effective unless in writing and signed by the Party against whom it is sought to be enforced. The failure of a Party to insist on strict performance on any occasion shall not be a waiver, and no waiver of any breach shall be a continuing waiver or a waiver of any other or subsequent breach. 9.7 Assignment. No Party may assign this Agreement without the prior written consent of the other Party, which consent shall not be unreasonably withheld, conditioned, or delayed; provided that Transmission Owner may assign this Agreement on notice, without consent, to an Affiliate or in connection with a sale, merger, restructuring, or transfer of all or substantially all of its assets, so long as the assignee assumes in writing all rights and obligations under this Agreement. Any assignment by Customer (other than a collateral assignment) and any change of control of Customer shall require Transmission Owner’s prior written consent, not to be unreasonably withheld, conditioned, or delayed, and shall be conditioned on (i) the assignee assuming in writing all obligations under this Agreement, the Large Load Interconnection Agreement, and the Large Load Security Agreement, each of which shall be assigned to the same assignee at the same time; and (ii) Customer reimbursing Transmission Owner’s reasonable costs of administering the assignment or performing due diligence with respect to a change of control. Customer may assign this Agreement on notice, without consent, as collateral security in connection with financing of the Large Load Facility. Any assignment in violation of this Section is void. No assignment relieves the assigning Party of its obligations. No assignment shall be effective unless the assignee provides and maintains Financial Security satisfying the requirements of Article 6 and the Large Load Security Agreement, and no assignment by Customer shall release Customer or any existing Financial Security until the assignee’s replacement Financial Security has been posted and accepted.
PDF page 12
9.8 Limitation of Liability. In no event, whether as a result of breach of contract, tort (including negligence and strict liability), or otherwise, shall any Party be liable in connection with this Agreement for any special, indirect, incidental, penal, punitive, or consequential damages of any nature, including delays, lost profits, business interruptions, and claims of suppliers and customers, whether or not such damages were reasonably foreseeable or such Party was advised that such damages might be incurred; provided that this Section shall not limit Customer’s obligation to pay the Large Load Upgrade Charge, the Net Present Value Residual Charge, costs recoverable under Sections 3.3, 4.3, 6.2, and 8.3, or other amounts due under this Agreement. TRANSMISSION OWNER MAKES NO WARRANTIES, REPRESENTATIONS, OR
GUARANTEES IN CONNECTION WITH THIS AGREEMENT, THE NETWORK
UPGRADES, THE TO ATTACHMENT FACILITIES, OR ANY WORK PERFORMED BY
TRANSMISSION OWNER, WHETHER WRITTEN OR ORAL, STATUTORY, EXPRESS OR
IMPLIED, INCLUDING, WITHOUT LIMITATION, THE IMPLIED WARRANTIES OF
MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE, ALL OF WHICH
ARE HEREBY EXPRESSLY EXCLUDED AND DISCLAIMED.
9.9 Force Majeure. No Party shall be considered in default of any obligation under this Agreement to the extent its performance is prevented or delayed by an event of Force Majeure, provided that such Party gives prompt written notice and uses reasonable efforts to resume performance. “Force Majeure” means any act of God, labor disturbance, act of the public enemy, war, terrorism, insurrection, riot, fire, storm, flood or other unusually severe weather, earthquake, epidemic, explosion, breakage or accident to machinery or equipment, any order, regulation, or restriction imposed by a governmental, military, or lawfully established civilian authority (including any delay by a governmental authority), or any other cause beyond the reasonable control of the Party claiming Force Majeure. Force Majeure does not include acts of negligence or intentional wrongdoing by the Party claiming Force Majeure, or the lack of funds or financing. Force Majeure shall not include, with respect to Customer: (a) economic hardship, changes in market conditions, or the cost or unavailability of financing; (b) delays in Customer’s procurement of equipment or failure of Customer’s suppliers or contractors, unless caused by an independent Force Majeure event; (c) labor disputes involving only Customer’s or its contractors’ workforce; (d) Customer’s failure to obtain required permits or approvals, unless it has diligently and timely pursued them; or (e) changes in the demand for, or the business case of, the Large Load Facility’s end use. Force Majeure shall not excuse any obligation to make payments or to post and maintain Financial Security.
9.10
Effect of Force Majeure. A Party shall be excused from performance (other than the obligation to pay money when due or to timely post and maintain Financial Security) to the extent prevented by Force Majeure, provided it gives prompt notice with full particulars (confirming any telephone notice in writing), keeps the other Party informed, and exercises due diligence to remedy the effects with reasonable dispatch. A Party shall not be required to settle a labor dispute on terms unsatisfactory to it.
9.11 Dispute Resolution.
(a) Notice and Informal Resolution. A Party asserting a dispute arising out of or relating to this Agreement (a “Dispute”) shall give written notice (a “Notice of Dispute”). The Dispute shall be referred to designated senior representatives of the Parties for good-faith negotiation.
PDF page 13
(b) Arbitration by Agreement. If the Dispute is not resolved within [thirty (30) / sixty (60)] days after receipt of the Notice of Dispute, the Parties may, by mutual agreement, submit it to arbitration under Section 9.11(c). Absent such agreement, either Party may pursue any remedy available at law or in equity, including proceedings before FERC, the NY PSC, or a court of competent jurisdiction. Any court proceeding arising out of or relating to this Agreement shall be brought exclusively in the courts identified in Section 14.3 of the Large Load Interconnection Agreement. EACH PARTY KNOWINGLY,
VOLUNTARILY, AND IRREVOCABLY WAIVES ANY RIGHT TO TRIAL BY JURY
OF ANY DISPUTE ARISING OUT OF OR RELATING TO THIS AGREEMENT, TO
THE FULLEST EXTENT PERMITTED BY APPLICABLE LAW. Notwithstanding this
Section 9.11, (i) either Party may at any time seek temporary, preliminary, or injunctive relief, or specific performance, from a court of competent jurisdiction or from FERC or the NY PSC to prevent irreparable harm, protect system reliability or safety, or preserve the status quo, without first complying with Section 9.11(a); and (ii) the informal resolution and arbitration procedures shall not delay or limit Transmission Owner’s exercise of its rights under Article 6, Section 7.3, and Section 8.3, or Customer’s payment obligations under Article 5 or its obligation to provide and maintain Financial Security under Article 6 and the Large Load Security Agreement.
(c) Arbitration Procedures. Any arbitration shall be conducted before a single neutral arbitrator, or, if the Parties cannot agree on one within ten (10) days, a three-member panel (one appointed by each Party and a third selected by the two party-appointed arbitrators), each knowledgeable in electric utility matters and without substantial business relationships with either Party, under the Commercial Arbitration Rules of the American Arbitration Association, except as modified herein. The arbitrator(s) shall render a written, reasoned decision within ninety (90) days of appointment, shall have no authority to modify this Agreement, and the decision shall be final, with judgment enterable in any court of competent jurisdiction, subject to appeal only on grounds permitted by the Federal Arbitration Act. Each Party shall bear its own costs, the cost of its appointed arbitrator, and one-half of the cost of the single or third arbitrator.
(d) Continued Performance; Termination. Pending resolution, each Party shall continue to perform its obligations, including by paying disputed amounts, and Customer shall continue to provide and maintain Financial Security as required under Article 6 and the Large Load Security Agreement. The pendency of a Dispute shall not suspend or toll any cure period under Article 7 or limit Transmission Owner’s rights described in Section 9.11(b)(ii). Whether a termination is proper shall not be subject to arbitration unless the Parties agree otherwise.
9.12 Confidentiality. Subject to any reporting or posting obligations under the NYISO OATT and any directives or requirements of FERC, the NY PSC, or NYISO, information exchanged under this Agreement that is designated confidential by the disclosing Party, including Critical Energy/Electric Infrastructure Information, shall be held in confidence and used only for purposes of this Agreement, subject to the confidentiality provisions of the NYISO OATT, applicable laws and regulations, and any non-disclosure agreements between the Parties; provided that nothing in this Section shall restrict the disclosure of cost information required under the NYISO OATT or any filing with FERC or the NY PSC. Critical Energy/Electric Infrastructure Information shall be protected and disclosed only as permitted by 18 C.F.R. §
PDF page 14
388.113, the NYISO OATT, applicable NYISO procedures, and any FERC order. Transmission Owner may require Customer and its contractors, subcontractors, vendors, or agents to execute a separate non-disclosure agreement as a condition of receiving confidential information or Critical Energy/Electric Infrastructure Information, and nothing in this Agreement shall limit, modify, or supersede any such non-disclosure agreement.
9.13 Representations and Warranties. As of the date of execution, each Party represents and warrants to the other Party that: (i) it is duly organized, validly existing, and in good standing under the laws of its jurisdiction of formation; (ii) it has all regulatory authorizations necessary to perform its obligations under this Agreement, other than any FERC [or NY PSC] acceptance that may be required; (iii) its execution, delivery, and performance of this Agreement are within its powers, have been duly authorized, and do not violate its governing documents or, in any material respect, any contract to which it is a party or any applicable law; and (iv) this Agreement is its legal, valid, and binding obligation, enforceable against it in accordance with its terms, subject to applicable bankruptcy, insolvency, and similar laws and to general principles of equity. Each Party further represents that the signatory identified beneath its name has full authority to execute this Agreement on its behalf.
9.14 No Third-Party Beneficiaries; No Partnership. This Agreement does not create rights, remedies, or benefits in favor of any person other than the Parties and their successors in interest and, where permitted, their assigns. This Agreement shall not be construed to create an association, joint venture, agency relationship, or partnership among the Parties, and no Party shall have authority to bind any other Party.
9.15 Entire Agreement; Related Agreements. This Agreement, including its Appendices, together with the Large Load Interconnection Agreement, the Large Load Security Agreement, and any other applicable agreements, constitutes the entire agreement among the Parties with respect to its subject matter and supersedes all prior discussions and understandings with respect thereto.
9.16 Survival. Articles 4, 5, and 6, Sections 3.3, 7.3, 8.3, 9.8, 9.11, and 9.12, Section 6 of Appendix B, and any other provisions that by their nature are intended to survive, shall survive the expiration or termination of this Agreement to the extent necessary to complete the recovery of amounts owed, including any Net Present Value Residual Charge and any final annual true- up, and the application or return of Financial Security.
9.17 Rules of Interpretation. Unless a contrary intention clearly appears: the singular includes the plural; references to any agreement, tariff, or law mean it as amended from time to time; references to Articles, Sections, and Appendices are to this Agreement; “including” means including without limitation; “hereunder,” “herein,” and similar words refer to this Agreement as a whole; and “from” means “from and including,” “to” means “to but excluding,” and “through” means “through and including.” This Agreement, the Large Load Interconnection Agreement, and the Large Load Security Agreement are intended to operate together and shall be interpreted consistently with one another and according to the terms of Section 3.4 of this Agreement in the event of a conflict between or among the Related Agreements. Headings are for convenience only and do not affect interpretation.
PDF page 15
SIGNATURES
IN WITNESS WHEREOF, the Parties hereto have caused this Agreement to be duly executed by their authorized officers as of the day and year first written above. [NEW YORK TRANSMISSION OWNER]
By: ______________________________
Name: ____________________________
Title: ___________________________
Date: ____________________________
[CUSTOMER NAME]
By: ______________________________
Name: ____________________________
Title: ___________________________
Date: ____________________________
PDF page 16
APPENDIX A: REFERENCE TO NETWORK UPGRADES AND
TO ATTACHMENT FACILITIES
[Reference to Network Upgrades and TO Attachment Facilities as specified in Exhibit B of the Large Load Interconnection Agreement[, as amended from time to time] [and/or other applicable agreement].]
PDF page 17
APPENDIX B: LARGE LOAD UPGRADE CHARGE
1. Cost Transparency and Engineering Estimates
[Identified Upgrade:]
Component Category
Estimated Direct
Costs
Estimated
Indirect Costs
Total Estimated
Capital Cost
[Substation Expansion &
Breakers]
$[___________]
$[___________]
$[___________]
[Line Re-conductoring &
Towers]
$[___________]
$[___________]
$[___________]
[Protection, Metering &
Telemetry]
$[___________]
$[___________]
$[___________]
[Engineering, Permitting &
ROW]
$[___________]
$[___________]
$[___________]
[Overhead]
$[___________]
$[___________]
$[___________]
[AFUDC]
$[___________]
$[___________]
$[___________]
[ ]
$[___________]
$[___________]
$[___________]
[ ]
$[___________]
$[___________]
$[___________]
[ ]
$[___________]
$[___________]
$[___________]
TOTAL ESTIMATED
EXPENDITURE
$[___________]
$[___________]
$[___________]
Customer’s allocated share of the Total Estimated Capital Cost of each Identified Upgrade set forth in the table(s) above, inclusive of Estimated Direct Costs and Estimated Indirect Costs, shall constitute the initial Estimated Network Upgrade Book Value for purposes of this Appendix B, subject to replacement by the actual Reimbursable Costs of such Identified Upgrade in accordance with Section 6(c) of this Appendix B and Section 1 of Appendix C. The Transmission Owner shall provide a separate table for each Identified Upgrade allocated to Customer in connection with the Large Load Facility.
2. Defined Terms and Variables
For purposes of this Appendix B, the following terms and variables shall have the meanings set forth below. Capitalized terms used but not defined in this Appendix B shall have the meanings set forth in Article 1 of the Agreement.
(a) [“Annual Deferred Revenue” means, for each Billing Year, the amount by which the Estimated Accelerated Annual Revenue Requirement exceeds the Estimated Annual Revenue Requirement for such Billing Year.]
PDF page 18
(b) “Annual On-going Charge Factor” or “OCF” means the annual percentage calculated by dividing the Transmission Owner’s applicable transmission and distribution operations and maintenance expenses, administrative and general expenses, property taxes, payroll taxes, and other applicable expenses, excluding depreciation and amortization expense, return on investment, and associated income taxes, by the Transmission Owner’s total transmission and distribution gross plant in service for the applicable period.
(c) “Average Service Life” or “ASL” means the dollar weighted average composite service life, expressed in years, of the property units comprising the Identified Upgrade, determined by weighting the service life associated with the depreciation rate approved for the Transmission Owner for each applicable plant account by the portion of the Estimated Network Upgrade Book Value recorded to that plant account, consistent with Section 3 of this Appendix B.
(d) “Billing Year” means each consecutive twelve (12) month period during the Assessment Period, the first of which shall commence on the Commencement Date and each subsequent one of which shall commence on the anniversary of the Commencement Date.
(e) “Contract Term” or “CT” means the number of years in the Assessment Period, as specified in Section 1.2 of the Agreement.
(f) “Estimated Accelerated Annual Revenue Requirement” or “EAARR” means, for each Billing Year, the annual revenue requirement payable by Customer under this Agreement, determined in accordance with Section 3(e) of this Appendix B.
(g) “Estimated Annual Revenue Requirement” or “EARR” means, for each Billing Year, the estimated annual revenue requirement associated with the Estimated Network Upgrade Book Value, determined in accordance with Section 3(c) of this Appendix B.
(h) “Estimated Network Upgrade Book Value” or “ENUBV” means, for each Identified Upgrade, the Total Estimated Capital Cost set forth in Section 1 of this Appendix B, as such amount will be replaced by actual Reimbursable Costs in accordance with Section 6(c) of this Appendix B and adjusted annually for deduction of accumulated depreciation and amortization.
(i) “Identified Upgrade” means each Network Upgrade and each TO Attachment Facility for which Customer is responsible, in whole or in an allocated share, as identified in the applicable Facilities Study and set forth in a table in Section 1 of this Appendix B. An Identified Upgrade may consist of more than one component.
(j) “Large Load Upgrade Gross Plant in Service” or “LLGP” means the capital cost of the Identified Upgrade in service allocated to Customer under this Agreement, initially estimated and subsequently replaced by actual Reimbursable Costs under Section 6(c) of this Appendix B, before deduction of accumulated depreciation and amortization.
(k) “Large Load Upgrade-Specific Capital Revenue Requirement” or “LLCRR” means, for each Billing Year, the sum of (i) depreciation and amortization expense attributable to the Identified Upgrade, calculated using the applicable approved depreciation and amortization rates, and (ii) the authorized return on the Identified Upgrade-specific investment balance, including associated income taxes. The
PDF page 19
investment balance used to calculate return shall reflect accumulated depreciation and amortization and any other applicable rate-base adjustments specified in this Agreement. This amount excludes expenses recovered through the Annual On-going Charge Factor.
(l) “Rate Data Sources” has the meaning set forth in Section 5(b) of this Appendix B.
(m) “T/D” means the transmission and distribution functions of the Transmission Owner’s electric utility operations, as such functions are classified and functionalized in the Rate Data Sources.
(n) “Total T/D Investment Base” has the meaning set forth in Section 5(d) of this Appendix B.
(o) “Total T/D Plant” or “TTDP” has the meaning set forth in Section 5(c) of this Appendix B.
(p) “Total T/D Revenue Requirements Allocable” or “TRRA” has the meaning set forth in Section 5(e) of this Appendix B.
3. Calculation of the Estimated Accelerated Annual Revenue Requirement
For each Billing Year during the Assessment Period, Transmission Owner shall calculate the Estimated Accelerated Annual Revenue Requirement, which shall constitute the annual Large Load Upgrade Charge, by performing the following steps in sequence:
(a) Step One – Estimated Network Upgrade Book Value. Transmission Owner shall determine the Estimated Network Upgrade Book Value for each Identified Upgrade, which shall equal the total estimated capital cost of such Identified Upgrade, inclusive of direct costs, applicable indirect costs (including overheads and allowance for funds used during construction (“AFUDC”)), as set forth in Section 1 of this Appendix B and as recorded in accordance with FERC’s Uniform System of Accounts, 18 C.F.R. Part 101.
(b) Step Two – Annual On-going Charge Factor and Large Load Upgrade-Specific Capital Revenue Requirement. Transmission Owner shall determine the Annual On- going Charge Factor in effect for the Billing Year in accordance with Sections 5 and 6 of this Appendix B. Transmission Owner shall also determine the LLCRR for the applicable Billing Year using the applicable approved inputs and Identified Upgrade-specific investment balances.
(c) Step Three – Estimated Annual Revenue Requirement. Transmission Owner shall add the LLCRR to the product of the Large Load Upgrade Gross Plant in Service and the Annual On-going Charge Factor, and round the sum to the nearest [rounding increment to be specified by Transmission Owner], as follows:
EARR = LLCRR + (LLGP × OCF)
The Estimated Annual Revenue Requirement represents the estimated annual cost of owning, operating, and maintaining the Identified Upgrade.
(d) Step Four – Average Service Life and Contract Term. Transmission Owner shall determine the Average Service Life of the Identified Upgrade and the Contract Term, each
PDF page 20
expressed in years, in accordance with the definitions set forth in Section 2 of this Appendix
B. (e) Step Five – Estimated Accelerated Annual Revenue Requirement. Transmission Owner shall multiply the Estimated Annual Revenue Requirement by the Average Service Life and divide the product by the Contract Term, as follows:
EAARR = (EARR × ASL) ÷ CT
The resulting Estimated Accelerated Annual Revenue Requirement provides for the recovery within the Contract Term of the aggregate Estimated Annual Revenue Requirements that would otherwise be recovered over the Average Service Life of the Identified Upgrade.
(f) Annual and Monthly Large Load Upgrade Charge. Transmission Owner shall perform the calculation set forth in this Section 3 separately for each Identified Upgrade. The annual Large Load Upgrade Charge for each Billing Year shall equal the sum of the Estimated Accelerated Annual Revenue Requirements for all Identified Upgrades for that Billing Year. The monthly Large Load Upgrade Charge shall equal one-twelfth of the annual Large Load Upgrade Charge, as set forth in Section 4 of this Appendix B.
4. Monthly Large Load Upgrade Charge Schedule
[Transmission Owner to insert the monthly Large Load Upgrade Charge for each month of Billing Years one (1) through [the final Billing Year of the Contract Term], calculated in accordance with Section 3 of this Appendix B.]
The schedule set forth in this Section 4 shall be revised for each Billing Year to reflect the annual update and any true-up performed under Section 6 of this Appendix B, and Transmission Owner shall provide the revised schedule to Customer in accordance with Section 6(d) of this Appendix
B. A revision of this schedule made in accordance with this Appendix B shall not constitute an amendment of the Agreement under Section 9.6 of the Agreement.
5. Annual On-going Charge Factor: Methodology and Input Data Sources
(a) Formula. The Annual On-going Charge Factor shall equal the Total T/D Revenue Requirements Allocable divided by the Total T/D Plant, as follows:
OCF = TRRA ÷ TTDP
For purposes of calculating the OCF, the TRRA used in the numerator shall exclude depreciation and amortization expense, return on investment, and associated income taxes, and TTDP represents total transmission and distribution gross plant in service.
(b) Rate Data Sources. Each input to the Annual On-going Charge Factor shall be derived exclusively from the following sources (collectively, the “Rate Data Sources”), each as in effect or as most recently filed with, or issued or approved by, the NY PSC as of the date of the applicable annual update:
(i) the revenue requirement, rate base, depreciation rates, capital structure, cost of capital, return on common equity, and functionalization and allocation
PDF page 21
methodologies established in or approved pursuant to Transmission Owner’s most recent electric rate order issued by the NY PSC [in Case No. ______], including any joint proposal or multi-year rate plan adopted therein (the “NY PSC Rate Order”), applied to both the transmission and distribution functions comprising T/D;
(ii) Transmission Owner’s annual report filed with the NY PSC, and any
compliance, reconciliation, or earnings report submitted by Transmission Owner to the NY PSC under the NY PSC Rate Order, to the extent such filing reports actual T/D plant balances, expenses, or other inputs for the most recently completed reporting period; and
(iii) to the extent an input is not separately stated in the sources identified in clauses
(i) and (ii) above, Transmission Owner’s books and records maintained in the ordinary course of business in accordance with the uniform system of accounts prescribed by the NY PSC for electric corporations and, to the extent consistent therewith, FERC’s Uniform System of Accounts, 18 C.F.R. Part 101, and the functionalization and allocation methodologies employed in the NY PSC Rate Order.
(iv) If an input required by this Section 5 is not stated in, or cannot be derived from, the sources identified in clauses (i) through (iii) above for the applicable reporting period, Transmission Owner shall derive such input from its most recent FERC Form No. 1, using the functionalization and allocation methodologies employed in the NY PSC Rate Order, and shall identify such input in the informational statement provided under Section 6(d) of this Appendix B.
The incorporation of NY PSC-approved inputs in this Section 5 is solely for the purpose of measuring the annual carrying cost of the Identified Upgrades under this Agreement, and the Rate Data Sources are incorporated solely as inputs to the formula set forth in this Appendix B. Such incorporation shall not (A) constitute a waiver or limitation of FERC’s jurisdiction over the rates, terms, and conditions of this Agreement under Sections 205 and 206 of the FPA, as reserved in Section 9.2 of the Agreement, or (B) constitute an assertion of FERC jurisdiction over any retail rate established by the NY PSC, in each case subject to Article 2 of the Agreement. A change to an input resulting from a NY PSC order issued after the effective date of this Agreement shall be implemented through the annual update under Section 6 of this Appendix B and shall not require a filing with FERC under Section 205 of the FPA, unless such change modifies the formula set forth in this Appendix B. All inputs shall be drawn from the same reporting period and functionalized on a consistent basis. Customer may challenge the computation or application of any input in accordance with Section 6(d) of this Appendix B and Section 9.11 of the Agreement; provided that the reasonableness of any input approved by the NY PSC in the NY PSC Rate Order shall not be subject to challenge under this Agreement.
(c) Total T/D Plant (Denominator). Total T/D Plant shall equal the sum of the following, each stated at gross original cost before deduction of accumulated depreciation and amortization, and limited to plant in service:
(i) T/D Plant, consisting of transmission plant in service and distribution plant in service, as recorded in the applicable transmission and distribution plant accounts
PDF page 22
of the Uniform System of Accounts and reported in Transmission Owner’s FERC Form No. 1; and
(ii) T/D Related Intangible and General Plant, consisting of intangible plant and general plant functionalized to the transmission and distribution functions using the allocation factors employed in the Rate Data Sources.
(d) Total T/D Investment Base. The Total T/D Investment Base, which forms the basis for the return component described in Section 5(e)(i) of this Appendix B, shall be determined as follows:
(i) Net Investment, equal to Total T/D Plant, less the T/D related accumulated provision for depreciation and amortization, less the T/D related accumulated deferred income taxes (net of associated deferred tax assets), and plus or minus other regulatory assets and regulatory liabilities includable in rate base under the Rate Data Sources; plus
(ii) T/D Prepayments (Account 165) and T/D Materials and Supplies (Account 154), each as functionalized to the transmission and distribution functions; less
(iii) T/D Related Cash Working Capital, determined in accordance with the cash working capital methodology employed in the Rate Data Sources.
(e) Total T/D Revenue Requirements Allocable (Numerator). Total T/D Revenue Requirements Allocable shall equal the sum of the following components, each functionalized to the transmission and distribution functions in accordance with the Rate Data Sources:
(i) Return and Associated Income Taxes, equal to the Total T/D Investment Base multiplied by Transmission Owner’s weighted average cost of capital, reflecting the capital structure, embedded cost of long-term debt, cost of preferred stock (if any), and return on common equity most recently approved or accepted for Transmission Owner by the NY PSC, grossed up for federal and state income taxes at the applicable statutory rates;
(ii) T/D Depreciation and Amortization Expense, equal to the depreciation and amortization expense recorded for T/D Plant and T/D Related Intangible and General Plant, calculated using the depreciation rates most recently approved or accepted for Transmission Owner by the applicable regulatory authority;
(iii) T/D Related Municipal Tax Expense, equal to the real property and other municipal taxes recorded as taxes other than income taxes (Account 408.1) and attributable to the transmission and distribution functions;
(iv) T/D Related Payroll Tax Expense, equal to the payroll taxes recorded as taxes other than income taxes (Account 408.1) and allocated to the transmission and distribution functions;
(v) T/D Operation and Maintenance Expense, equal to the transmission and distribution operation and maintenance expenses recorded in the applicable expense accounts of the Uniform System of Accounts, [excluding any costs recovered through separately stated surcharges, pass-through mechanisms, or NYISO charges];
PDF page 23
(vi) T/D Related Administrative and General Expense, equal to administrative and general expenses (Accounts 920 through 935) allocated to the transmission and distribution functions, excluding any items excluded from recovery under the Rate Data Sources; less
(vii) T/D Rents Received from Electric Property, equal to rents from electric property (Account 454) attributable to the transmission and distribution functions, which shall be applied as a reduction to the revenue requirement; provided that revenues received by Transmission Owner under this Agreement shall be excluded from this component.
6. Annual Update and True-Up
(a) Annual Update. No later than August 1 of each calendar year during the Contract Term and the year immediately following the Contract Term, Transmission Owner shall recalculate the Large Load Upgrade-Specific Capital Revenue Requirement and Annual On-going Charge Factor using the Rate Data Sources then most recently available, and shall recalculate the Estimated Annual Revenue Requirement, the Estimated Accelerated Annual Revenue Requirement, the Annual Deferred Revenue, and the monthly Large Load Upgrade Charge for the succeeding Billing Year in accordance with Sections 3 and 5 of this Appendix B. Each annual update shall reflect, without limitation, changes during the Contract Term in Transmission Owner’s approved or accepted return on common equity and depreciation rates.
(b) Annual True-Up. Because the Annual On-going Charge Factor applied in each Billing Year is derived from data for the most recently completed reporting year, the Large Load Upgrade Charge billed for each Billing Year shall be an estimate. In the Billing Year following each Billing Year, Transmission Owner shall determine the difference between
(i) the Large Load Upgrade Charge billed for the prior Billing Year and (ii) the Large Load Upgrade Charge that would have been billed for that Billing Year using the Annual On- going Charge Factor, the Large Load Upgrade-Specific Capital Revenue Requirement, and Large Load Upgrade Gross Plant in Service derived from actual data for the corresponding period. Any resulting over-recovery or under-recovery, together with interest calculated in accordance with 18 C.F.R. § 35.19a, shall be refunded to or surcharged to Customer, as applicable, in equal monthly installments over the succeeding Billing Year, in accordance with the accounting protocols set forth in Appendix C.
(c) Replacement of Estimated Costs. Upon completion of the Final Cost Reconciliation Protocol set forth in Section 1 of Appendix C, the actual Reimbursable Costs of each Identified Upgrade shall replace the Estimated Network Upgrade Book Value for all purposes of this Appendix B. Transmission Owner shall recalculate the Large Load Upgrade Charge prospectively and shall true up all amounts billed from the Commencement Date, with interest calculated in accordance with 18 C.F.R. § 35.19a.
(d) Informational Statement. Concurrently with each annual update, Transmission Owner shall provide Customer with a written statement setting forth the recalculated Annual On-going Charge Factor, Large Load Upgrade-Specific Capital Revenue Requirement, and Large Load Upgrade Gross Plant in Service, and each input used to determine those amounts, the specific Rate Data Source and account or line reference from
PDF page 24
which each input was derived, the true-up calculation for the prior Billing Year, and the revised schedule under Section 4 of this Appendix B, together with supporting workpapers. Transmission Owner may use such statement to satisfy any reporting or posting obligations under the NYISO OATT or applicable FERC or NY PSC requirements. Customer may review and challenge any annual update in accordance with Section 9.11 of the Agreement.
(e) Expiration of Contract Term. Following the final annual true-up for the last Billing Year of the Contract Term, no further updates or true-ups of the Large Load Upgrade Charge shall be performed under this Agreement. Any over-recovery or under-recovery attributable to changes in the inputs to the Annual On-going Charge Factor occurring in the year after the expiration of the Contract Term shall be addressed in Transmission Owner’s rate proceedings before FERC or the NY PSC, as applicable, and shall not be billed to or refunded to Customer.
(f) No Double Recovery. Nothing in this Appendix B shall permit Transmission Owner to recover, through FERC-jurisdictional wholesale transmission rates or NY PSC- jurisdictional retail delivery rates, any revenue requirement associated with the Identified Upgrades that has been recovered from Customer under this Agreement, consistent with the NYISO OATT.
(g) Early Termination. In the event of termination prior to the expiration of the Assessment Period, the Net Present Value Residual Charge under Section 4.3 of the Agreement shall be calculated net of the accumulated Annual Deferred Revenue collected from Customer through the date of termination.
7. TO Attachment Facilities Cost Recovery Special Provisions
Any alternative cost recovery arrangement for the TO Attachment Facilities agreed to by the Parties shall be set forth in this Section 7 and shall, at a minimum, specify: (i) the capital payment amount and schedule; (ii) the exclusion of amounts so paid from the revenue requirement and the Large Load Upgrade Charge; (iii) the income tax treatment, including any gross-up and true-up; (iv) the treatment of operation, maintenance, repair and replacement costs during and after the Term; (v) any resulting adjustments to security under the Large Load Security Agreement; and (vi) treatment upon termination. Transmission Owner shall make any such arrangement available on a non-discriminatory basis to similarly situated customers. If the Parties exercise their rights under this Section 7, Transmission Owner shall file this Agreement, or any amendment under Section 9.6 adding or changing this Section 7, with FERC, and such terms shall not take effect until accepted by FERC. If FERC does not accept such terms, the default treatment under Section 4.4 shall apply.
PDF page 25
APPENDIX C: TRUE-UP AND ANNUAL REVENUE
CREDITING ACCOUNTING PROTOCOLS
1. Final Cost Reconciliation Protocol
(a) Within one hundred eighty (180) days after the COD, Transmission Owner shall assemble all direct work orders, material invoices, internal payroll overheads, and AFUDC computations recorded in accordance with FERC’s Uniform System of Accounts (18 C.F.R. Part 101) and NY PSC accounting guidelines.
(b) A formal accounting statement detailing any variance between the preliminary estimates in Appendix B and actual Reimbursable Costs will be submitted to Customer and NY PSC Staff.
(c) Billing adjustments or refunds shall be processed within thirty (30) days thereafter.
2. Revenue Crediting and Prevention of Cost Shifting
(a) Revenue Crediting: All funds collected from Customer toward the carrying charges or capital costs of the Identified Upgrades shall be credited or otherwise reflected in Transmission Owner’s applicable wholesale transmission revenue requirement or retail rate base, as appropriate, consistent with Article 2 and the NYISO OATT, so that non- participating wholesale and retail customers are insulated from the capital and operating costs of the dedicated Identified Upgrades.
PDF page 26
APPENDIX D: PAYMENT INFORMATION AND ADDRESSES
FOR NOTICES AND BILLING
[Transmission Owner insert wire/electronic payment information and mailing address for notices]
[Customer insert wire/electronic payment information and mailing address for notices]