ER27-529-000 · 2026-11-16 · New York Independent System Operator, Inc., Central Hudson Gas & Electric Corporation and 5 others
Att F Pro Forma LL Security Agreement
PDF page 1
Attachment F
Pro Forma Large Load Security Agreement
PDF page 2
44.16.10 Appendix 10 to Attachment LL – Pro Forma Security Agreement
PRO FORMA LARGE LOAD SECURITY AGREEMENT
BETWEEN
[NEW YORK TRANSMISSION OWNER]
(Transmission Owner)
AND
[CUSTOMER NAME]
(Customer)
PDF page 3
TABLE OF CONTENTS
Recitals
Article I: Definitions
Article II: Security
Article III: Term
Article IV: Notices
Article V: Miscellaneous
• Schedule 1: Project Security Amount and Posting Schedule
• Attachment A: Form of Irrevocable Standby Letter of Credit
• Attachment B: Related Agreement
PDF page 4
PRO FORMA
LARGE LOAD SECURITY AGREEMENT
This LARGE LOAD SECURITY AGREEMENT (this “Agreement”) is made and entered into as of the [___] day of [_______], 20[__] (the “Effective Date”) by and between:
• [NEW YORK TRANSMISSION OWNER] (“Transmission Owner” or “Connecting
Transmission Owner” or “Affected Transmission Owner”), a [corporation] organized and existing under the laws of the State of New York, having an office and place of business at [_________]; and
• [CUSTOMER NAME] (“Customer”), a [corporation/ limited liability company] organized under the laws of the State of [_____], having an office and place of business at [______], and owning a Large Load Facility with an expected peak demand at the Point of Interconnection.
Transmission Owner and Customer are collectively referred to as the “Parties,” and each individually as a “Party.”
RECITALS
WHEREAS, Customer has submitted a Large Load Integration Request to interconnect or serve a Large Load Facility with an aggregate demand equal to or exceeding fifty megawatts (50 MW) at a transmission-system interconnection point with the Transmission Owner’s service territory or affecting the Affected Transmission Owner’s transmission facilities in New York State; WHEREAS, New York Independent System Operator, Inc. (“NYISO”) and/or Transmission Owner have performed [system reliability impact studies, facility studies, and/or engineering assessments] pursuant to the NYISO Open Access Transmission Tariff (“OATT”), identifying that the interconnection and commercial operation of Customer’s Large Load Facility will necessitate the construction and placement into service of certain Network Upgrades and/or TO Attachment Facilities on the Transmission Owner’s transmission system to maintain electric system reliability and system adequacy; and
WHEREAS, Customer has received the initial cost allocation estimate for Network Upgrades and/or TO Attachment Facilities identified by System Impact Studies and any applicable Facilities Studies under Attachment LL of the NYISO OATT or successor tariff provisions needed to interconnect Customer’s Large Load Facility;
WHEREAS, Customer is required to post security to Transmission Owner in the initial amount of [ ] Dollars ($[ ]), (the “Initial Project Security Amount”), consistent with Attachment LL of the NYISO OATT;
WHEREAS, the Initial Project Security Amount is subject to adjustment in accordance with the Interconnection Cost Allocation Process as set forth in Section [__] of Attachment LL of the NYISO OATT (the “Project Security Amount”);
WHEREAS, the Project Security Amount may thereafter be adjusted pursuant to the Large Load Cost Recovery Agreement (“CRA”), into which Customer has entered or will enter and pursuant
PDF page 5
to which it will agree to pay for all of Transmission Owner’s costs associated with the development of Network Upgrades and/or TO Attachment Facilities;
WHEREAS, Customer’s obligations to post Security under this Agreement shall be set forth in Schedule 1;
WHEREAS, Customer may also enter into a Large Load Interconnection Agreement or other applicable agreement(s) governing, among other things, the construction of the Network Upgrades and/or TO Attachment Facilities; and
WHEREAS, the Parties desire to set forth in this Agreement the terms governing the posting, maintenance, adjustment, application and release of such Security.
NOW, THEREFORE, in consideration of the premises and for other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, and with the intent to be legally bound, the Parties agree as follows:
ARTICLE I: DEFINITIONS
1.0
Defined Terms. Capitalized terms used but not defined in this Agreement have the meanings given in the NYISO OATT, NYISO Market Services Tariff, or, if not defined therein, in the CRA or applicable Large Load Interconnection Agreement, if those agreements are in effect.
1.1
“Abandon” means Customer’s (i) failure to issue a notice to proceed for Transmission Owner to commence construction of the Project Facilities within [six (6)] months after the applicable construction commencement milestone set forth in Exhibit D of the Large Load Interconnection Agreement, or (ii) suspension of, or causing the suspension of, construction of the Project Facilities for a period of [three (3)] years, which, in either case, is not due to an event of Force Majeure; provided that if Force Majeure causes such failure or suspension, Customer shall nevertheless be deemed to have abandoned construction if it fails to commence or resume construction within [six (6)] months after the end of the Force Majeure event (unless Customer has elected to continue such suspension for a total suspension period not exceeding [three (3)] years in accordance with the Large Load Interconnection Agreement or CRA).
1.2
“Affiliate” means, with respect to a person or entity, any other person or entity directly or indirectly controlling, controlled by, or under common control with such person or entity. “Control” means the possession, directly or indirectly, of the power to direct the management or policies of a person or entity; a voting interest of ten percent (10%) or more creates a rebuttable presumption of control.
1.3
“Business Day” means any day except Saturday, Sunday, a U.S. federal legal holiday, or a day on which banking institutions in the State of New York are authorized or required by law or other governmental action to close.
1.4
“Cash” means readily available United States dollars delivered by wire transfer in accordance with Transmission Owner’s written instructions. Transmission Owner’s written instructions can be delivered via email or other means of electronic communication. 1.5
“CRA” means the Large Load Cost Recovery Agreement.
PDF page 6
1.6
“Credit Rating” means, with respect to an entity on any date of determination, the rating assigned to that entity’s unsecured, senior long-term debt (not supported by third-party credit enhancement) or its corporate credit rating, whichever is lower, by S&P or Moody’s. If the entity is rated by both S&P and Moody’s, the lower rating controls; if it is rated by only one, that rating controls. For a financial institution that is the issuer of a letter of credit hereunder, the applicable rating is its long-term deposit rating or senior unsecured, unsubordinated long-term debt rating, as applicable.
1.7
“Creditworthy Rating” means a Credit Rating of at least the threshold selected in Schedule 1: [as acceptable to the Transmission Owner].
1.8
“Cure Period” means the applicable notice and cure period under the relevant Related Agreement and, with respect to this Agreement, five (5) Business Days after Transmission Owner’s written notice.
1.9
“Event of Default” means an Event of Default under the CRA or a Default under the Large Load Interconnection Agreement.
1.10 “FERC” means the Federal Energy Regulatory Commission.
1.11
“Force Majeure” means any event or circumstance beyond a Party’s reasonable control that prevents the Party from performing an obligation, is not the result of the negligence or intentional wrongdoing of such Party, and could not have been prevented or mitigated by the exercise of Good Utility Practice (in the case of the Transmission Owner) or due diligence (in the case of Customer), including acts of God, fire, flood, storm, lightning, explosion, breakage of or accident to machinery, epidemic or pandemic, cyber-attack (except to the extent caused by or resulting from Customer’s failure to comply with its obligations under this Agreement), sabotage, terrorism, war, civil disturbance, strikes and labor disturbances, acts or orders of any Governmental Authority, and curtailment or interruption directed by NYISO for reliability reasons. Force Majeure shall not include, with respect to Customer: (a) economic hardship, changes in market conditions, or the cost or unavailability of financing; (b) delays in Customer’s procurement of equipment or failure of Customer’s suppliers or contractors, unless caused by an independent Force Majeure event; (c) labor disputes involving only Customer’s or its contractors’ workforce;
(d) Customer’s failure to obtain required permits or approvals, unless it has diligently and timely pursued them; or (e) changes in the demand for, or the business case of, the Large Load Facility’s end use. Interruptions resulting from the Single Contingency Design shall not be treated as Force Majeure. Force Majeure shall not excuse the failure to make payments when due or to timely post or maintain the Security.
1.12
“Customer’s Obligations” means Customer’s obligations commencing with the facility study estimated costs assigned to the Large Load subject to adjustment through the Interconnection Cost Allocation Process until the execution of the CRA, at which point the security amount and adjustments thereto shall be based on the Customer’s remaining payment obligations under the CRA.
1.13
“Draw Event” has the meaning given in Section 2.4.
PDF page 7
1.14
“Interconnection Cost Allocation Process” means the process by which the final estimated costs are allocated to Customer, as may be incorporated into NYISO’s or Transmission Owner’s procedures.
1.15
“Large Load Facility” has the meaning given in the CRA and is the “Load Facility” under the Large Load Interconnection Agreement.
1.16
“Letter of Credit” means an irrevocable standby letter of credit substantially in the form of Attachment A, issued by a U.S. commercial bank, a U.S. branch of a foreign commercial bank, or the U.S. subsidiary of a foreign commercial bank, in each case with counters in New York, that (i) is subject to the jurisdiction of the New York federal or state courts, (ii) if a foreign bank, is compliant with 12 C.F.R. Part 252 (Regulation YY), (iii) has assets of at least [$1,000,000,000], and (iv) has a Credit Rating of at least [“A-” from S&P and “A3” from Moody’s] (the “Minimum Issuer Rating”); provided that if the bank is rated by only one of those agencies and the bank is approved in writing by an authorized representative of Transmission Owner, only the Minimum Issuer Rating for that agency must be satisfied. Each Letter of Credit shall have an expiration date at least twelve (12) months after its date of issuance or renewal and shall be renewed, replaced, extended and maintained until the Security Release Date. All Letter of Credit costs shall be borne by Customer. 1.17
“Moody’s” means Moody’s Investors Service, Inc. or its successor.
1.18
“Network Upgrades”: Additions, modifications, enhancements, or replacements to the Transmission Owner’s electric transmission system required at or beyond the Point of Interconnection to accommodate the Customer’s Large Load Facility reliably under NERC, NPCC, NYSRC, and Transmission Owner reliability criteria and identified through the Large Load Interconnection Procedures contained at Attachment LL of the NYISO OATT (or successor tariff provisions) and set forth in [the CRA, the Large Load Interconnection Agreement, and/or other applicable agreement], for which Customer is providing Security under this Agreement.
1.19
“Project Facilities” means the Network Upgrades and TO Attachment Facilities for which Customer is providing Security under this Agreement.
1.20
“Related Agreements” means, collectively, the CRA, the Large Load Interconnection Agreement, and any other agreements listed in Attachment B.
1.21 “S&P” means S&P Global Ratings or its successor.
1.22
“Security” means (a) Cash, (b) one or more Letters of Credit, or (c) any combination of the foregoing, provided and maintained in accordance with this Agreement; and, with respect to any increase or decrease in the Security Amount, Cash, a substitute Letter of Credit, or an amendment to a previously delivered Letter of Credit, unless otherwise agreed in writing by Transmission Owner.
1.23
“Security Amount” means, on any date, the Initial Project Security Amount or Project Security Amount, as increased or reduced in accordance with Sections 2.6 and 2.7. 1.24
“Security Posting Date” means each date set forth in Schedule 1 and each other date on which Customer is required to post, replace or increase Security, or on which a reduction in the Security Amount becomes effective under this Agreement.
PDF page 8
1.25
“Security Release Date” has the meaning given in Section 2.5.
1.26
“TO Attachment Facilities”: All facilities and equipment owned or controlled by Transmission Owner between the Point of Interconnection and the Point of Change of Ownership that are constructed or modified for the purpose of interconnecting the Large Load Facility, including line taps, breakers, disconnect switches, bus work, metering instrument transformers (if owned by Transmission Owner), System Protection Facilities at a Transmission Owner substation, and associated civil and structural works, as described in [the Large Load Interconnection Agreement or other applicable agreement], for which Customer is providing Security under this Agreement.
ARTICLE II: SECURITY
2.1
Posting and Maintenance of Security. On or before each Security Posting Date, Customer shall provide Transmission Owner Security for Customer’s Obligations in the then-applicable Security Amount, and Customer shall maintain Security in the Security Amount at all times until the Security Release Date. Cash shall be wired to Transmission Owner in accordance with Transmission Owner’s written instructions delivered at least five (5) Business Days before the applicable Security Posting Date; if Transmission Owner delivers its instructions later, Customer’s deadline shall be extended until two (2) Business Days after receipt of the instructions. Each Letter of Credit shall be in form and substance acceptable to Transmission Owner. Customer shall provide a draft of each Letter of Credit to Transmission Owner for review at least five (5) Business Days before the applicable Security Posting Date. Transmission Owner shall have the opportunity to verify that the issuing bank satisfies the requirements of this Agreement, and the original Letter of Credit shall be delivered to Transmission Owner by hand delivery or overnight mail.
(a) The Initial Project Security Amount shall be established by reference to the initial cost estimate for Network Upgrades and/or TO Attachment Facilities identified by System Impact Studies and Facilities Studies under Attachment LL of the NYISO OATT or successor tariff provisions. This amount shall be entered at Schedule 1.
(b) The Security Amount shall be adjusted as prescribed in Sections 2.5, 2.6 and 2.7 of this Agreement and Article 6 of the CRA.
2.2
Letter of Credit Renewals and Replacements; Downgrades.
(a) Renewal. If a Letter of Credit is scheduled to expire before the Security Release Date, Customer shall renew or replace it no later than ninety (90) days before its expiration. If the issuing bank gives a non-extension notice, Customer shall provide acceptable replacement Security within five (5) Business Days after receiving that notice and in all events before the Letter of Credit expires. The renewed or replacement Letter of Credit shall expire no earlier than the later of (i) one (1) year after its issuance or renewal and (ii) the Security Release Date. Customer shall send evidence of the renewed or replaced Letter of Credit from the issuing bank to Transmission Owner within five (5) Business Days after renewal or replacement.
(b) Issuer Downgrade. If an issuing bank fails to maintain the Minimum Issuer Rating (an “Issuer Downgrade”), Customer shall deliver a substitute Letter of Credit within
PDF page 9
five (5) Business Days after the Customer knew or should have known of the Issuer Downgrade.
(c) Return of Replaced Letter of Credit. Upon receipt and acceptance of a substitute or replacement Letter of Credit, Transmission Owner shall, within five (5) Business Days after Customer’s request, return the replaced Letter of Credit to the issuing bank and notify Customer, unless Transmission Owner has drawn on it or a Draw Event is continuing.
• 2.3
Substitution of Security. If Customer replaces Cash with a Letter of Credit, or replaces a Letter of Credit with Cash or a Letter of Credit, in each case in an amount at least equal to the then-applicable Security Amount, Transmission Owner shall, within thirty (30) calendar days after receipt of the replacement Security, refund the replaced Cash or return the replaced Letter of Credit, as applicable, unless a Draw Event has occurred and is continuing. During any period in which Transmission Owner holds Security exceeding the Security Amount, Transmission Owner shall not apply, set off or draw on Security in an amount greater than the Security Amount. Cash refunds shall be made by wire in accordance with Customer’s written instructions delivered at least two (2) Business Days before the wire.
2.4
Draw Events. Transmission Owner may apply, set off and/or draw on the Security, up to the outstanding Security Amount, upon the occurrence of any of the following (each, a “Draw Event”):
(a) Customer notifies Transmission Owner in writing that it is ceasing to negotiate, or fails, within a reasonable period of time, to enter into the CRA, the Large Load Interconnection Agreement, or other applicable agreements, and either NYISO or the Transmission Owner has informed Customer in writing that the Project Facilities must be completed because they are included in the NYISO base case, Transmission Owner’s local transmission plan, or the NYISO’s Reliability Needs Assessment or Short-Term Assessment of Reliability or another interconnection request relies on completion of the Network Upgrades or TO Attachment Facilities; [(b)
Customer notifies Transmission Owner in writing that it is ceasing to negotiate, or fails, within a reasonable period of time, to enter into the CRA, the Large Load Interconnection Agreement, or other applicable agreements, and NYISO or Transmission Owner has determined that the Project Facilities are not needed, to the extent of costs to restore the New York State Transmission System to a safe and reliable condition;]
(c) An Event of Default has occurred under any Related Agreement and any applicable Cure Period has expired;
(d) Customer Abandons the Large Load Facility or a material portion of it, and the abandonment continues for thirty (30) days after Transmission Owner’s written notice to Customer;
(e) Customer fails to pay any amount, or any amount finally determined to be due, when due, under the CRA, and the failure continues beyond any applicable Cure Period;
PDF page 10
(f) The CRA has terminated prior to the expiration of the Assessment Period thereunder;
(g) A Letter of Credit will expire in thirty (30) days or less, or an earlier period required by Section 2.2(a), and Customer has not renewed or replaced it as required by Section 2.2(a);
(h) Customer fails to deliver substitute or replacement Security within the time required by Section 2.2(b);
(i) Customer fails to comply with a material term of this Agreement, or defaults under a material term of any Related Agreements, and the failure continues beyond any applicable Cure Period after Transmission Owner’s written notice describing the default; or
(j) Transmission Owner is otherwise entitled to draw on Security under any Related Agreement.
Upon a Draw Event, Transmission Owner may draw on or make demand under any or all of the Security without further notice to Customer. If Transmission Owner draws before it incurs the related costs, it shall hold the proceeds as Cash Security and apply them only to Customer’s Obligations in accordance with Section 2.5. Customer shall remain liable for all Customer’s Obligations that remain unpaid after application of the Security.
2.5
Application and Release of Security. Transmission Owner may apply any or all of the Security to Customer’s Obligations, including amounts owed by Customer to complete the Project Facilities or restore the New York State Transmission System to a safe and reliable condition. Upon a Draw Event, Transmission Owner shall apply the drawn funds (the “Funds”) to then-outstanding Customer’s Obligations and shall retain any Funds exceeding those obligations (“Excess Proceeds”) as security for future Customer’s Obligations. Within thirty (30) calendar days after the latest of the following dates (the “Security Release Date”), Transmission Owner shall refund any unapplied Cash and Excess Proceeds to Customer, and/or return any unapplied Letter of Credit to the issuing bank:
(i) the date on which all of Customer’s obligations under the Related Agreements have been satisfied;
(ii) the date on which the portions of the New York State Transmission System affected by construction of the Project Facilities have been restored to a safe and reliable condition, as confirmed in writing by NYISO or Transmission Owner, and all associated costs have been paid, as applicable, and all of Customer’s obligations under the Related Agreements have been satisfied (the “Restoration Completion Date”); or
(iii) the date on which Transmission Owner or NYISO confirms in writing that the Project Facilities are no longer required, Customer has paid all outstanding obligations, neither Party has any current or future obligation to restore the New York State Transmission System or to install or complete any Project Facilities, and all of Customer’s obligations under the Related Agreements have been satisfied (the “Obligation Termination Date”).
PDF page 11
Cash refunds shall be wired to Customer in accordance with Customer’s written instructions delivered at least two (2) Business Days before the wire. Any interest earned on Cash Security or Excess Proceeds shall be for the account of Transmission Owner. Notwithstanding Section 9-207 of the New York Uniform Commercial Code and to the extent permitted by applicable law, Transmission Owner may invest, use, commingle or otherwise dispose of Cash Security and Excess Proceeds, subject to its obligations to apply or return those amounts under this Agreement. 2.6
Reduction or Increase of Security Amount as a Result of the Interconnection Cost Allocation Process and/or the CRA.
Customer must timely post Security in the Initial Project Security Amount, subject to adjustment based on the Interconnection Cost Allocation Process in effect at the time of the Facilities Study. The Interconnection Cost Allocation Process shall provide the procedures pursuant to which cost allocations are adjusted when projects fail timely to post security following the release of the Facilities Studies until all remaining projects in the Cluster have posted required security. Required Security may also be adjusted upon execution of the CRA and adjusted annually thereafter to provide security for Customer’s obligations under the CRA for the remaining term.
If Customer provided a Letter of Credit as Security, the annual adjustment may occur at the time of renewal of the Letter of Credit by amendment or replacement of the Letter of Credit. If Customer provided Cash as Security, the annual adjustment shall be effectuated through either an increase in the Cash provided by Customer or a refund of Cash held by Transmission Owner. Within ten (10) Business Days after Customer’s written request following a reduction of the Security Amount, Transmission Owner shall refund by wire any Cash exceeding the adjusted Security Amount or return any replaced Letter of Credit (provided Customer has delivered a substitute Letter of Credit or amendment in the adjusted Security Amount) to the issuing bank. Changes to Schedule 1 under this Section shall not constitute an amendment of this Agreement.
2.7
Adjustment of Security Amount as a result of Change in Scope or Extension Request. The Security Amount shall be adjusted for reasons including but not limited to the following occurrences, and in each case as may be reflected in an amendment to the Large Load Interconnection Agreement and/or CRA:
(i) Change in Scope. If the scope of the Project Facilities is modified, expanded or otherwise changed from the scope described in the Large Load Interconnection Agreement, CRA, or other applicable agreements, including as a result of a Material Modification or an Exceedance Event under the Large Load Interconnection Agreement or updated engineering or design requirements, the Security Amount shall be adjusted by the amount of the change in Customer’s allocated share of the costs of the Project Facilities attributable to that change. Transmission Owner shall provide Customer with a written calculation of the adjustment.
(ii) Extension Request; Suspension or Delay. If Customer requests an extension of any milestone date in the Large Load Interconnection Agreement, CRA, or other applicable agreements, or suspends or delays performance under Section 3.3 of the CRA, and the extension, suspension or delay results in additional costs to Transmission Owner under the Large Load Interconnection Agreement or CRA,
PDF page 12
the Security Amount shall be increased by the amount of those additional costs, as reasonably documented by Transmission Owner. Transmission Owner shall not require the increased Security Amount earlier than five (5) Business Days after delivering that documentation to Customer.
On the applicable Security Posting Date for an adjustment, Customer shall post additional Security in a form permitted by Section 2.1 if the Security Amount increases, or Transmission Owner shall take the actions described in Section 2.6 if the Security Amount decreases. Any increased Security Amount remains subject to reduction under Section 2.6.
ARTICLE III: TERM
3.1
Term. This Agreement is effective as of the Effective Date and continues until the later of
(i) the Security Release Date and (ii) the date on which Transmission Owner has returned or released all unapplied Security to Customer in accordance with Section 2.5. Rights and obligations that by their nature survive expiration or termination shall so survive. ARTICLE IV: NOTICES
4.1
Notices. Notices shall be in writing and delivered by hand, United States mail, overnight courier, or email (provided that an email notice is also delivered by one of the other methods). Notices are effective on receipt. A Party may change its address by notice given in accordance with this Section.
If to Transmission Owner: [Name], [Address], Attn: [Treasurer / Vice President], Phone: [___], Email: [___]; with a copy to: [Address], Attn: General Counsel. If to Customer: [Name], [Address], Attn: [___], Phone: [___], Email: [___]. ARTICLE V: MISCELLANEOUS
5.1
Representations and Warranties. As of the Effective Date, each Party represents and warrants to the other that: (i) it is duly organized, validly existing and in good standing under the laws of its jurisdiction of formation; (ii) it has all regulatory authorizations necessary to perform its obligations under this Agreement; (iii) its execution, delivery and performance of this Agreement are within its powers, have been duly authorized, and do not violate its governing documents or, in any material respect, any contract to which it is a party or any applicable law; and (iv) this Agreement is its legal, valid and binding obligation, enforceable in accordance with its terms, subject to bankruptcy, insolvency and similar laws and to general principles of equity.
5.2
Assignment. This Agreement may be assigned by a Party only with the other Party’s written consent, not to be unreasonably withheld, conditioned, or delayed; provided that
(a) Transmission Owner may assign without consent to an Affiliate or successor with the legal authority and operational ability to perform; (b) Transmission Owner may assign without consent in connection with a sale, merger, restructuring, or transfer of all or substantially all of its assets, including the Project Facilities, if the assignee assumes in writing all obligations hereunder; and (c) Customer may assign without consent for collateral security purposes to aid in financing the Large Load Facility, upon prompt notice to Transmission Owner. Any assignment by Customer (other than a collateral assignment) and any change of control of Customer shall require Transmission Owner’s prior written
PDF page 13
consent, not to be unreasonably withheld, conditioned, or delayed, and shall be conditioned on (i) the assignee assuming in writing all obligations under this Agreement and the Related Agreements; (ii) the assignee posting replacement Security under this Agreement before the assignment becomes effective and having a Credit Rating equal to or greater than that of Customer as of the date of assignment or providing such additional Security under this Agreement as Transmission Owner reasonably requires; and (iii) Customer reimbursing Transmission Owner’s reasonable costs of administering the assignment or performing due diligence with respect to a change in control, including reissuing invoices and amending related contracts. Any financing obtained by Customer shall require the secured party to notify Transmission Owner before exercising assignment rights and to demonstrate compliance with Section 6.2 and Article 18 of the Large Load Interconnection Agreement. Any assignment in violation of this Section is void. No assignment by Customer shall release Customer or any existing Security until the assignee’s replacement Security has been posted and accepted. No assignment shall relieve a Party of, or enlarge, its obligations. 5.3
Governing Law. THIS AGREEMENT AND THE RIGHTS AND DUTIES OF THE
PARTIES HEREUNDER SHALL BE GOVERNED BY AND CONSTRUED,
ENFORCED AND PERFORMED IN ACCORDANCE WITH THE LAWS OF THE
STATE OF NEW YORK, WITHOUT REGARD TO PRINCIPLES OF CONFLICTS OF
LAW.
5.4
FERC, the OATT, and Related Agreements Compliance. The Parties shall comply with all applicable filing, acceptance, and effectiveness requirements under Federal Power Act Section 205, the OATT, and Related Agreements. No amendment or waiver that is required to be filed with and accepted by FERC shall be effective before the required filing or acceptance, and the Parties shall cooperate in making any required filing. 5.5
Counterparts and Electronic Signatures. This Agreement may be executed in counterparts, each of which is an original and all of which together are one instrument. Counterparts and signatures delivered by email in PDF format or through an electronic- signature platform are effective as originals.
5.6
Binding Effect. This Agreement shall be binding upon and inure to the benefit of the Parties and their successors and permitted assigns.
5.7
Rules of Interpretation. Unless a contrary intention clearly appears: the singular includes the plural; references to any agreement, tariff, or law mean it as amended from time to time; references to Articles, Sections, Schedules, and Attachments are to this Agreement unless otherwise indicated with respect to a Related Agreement; “including” means including without limitation; “hereunder,” “herein” and similar words refer to this Agreement as a whole; and “from” means “from and including,” “to” means “to but excluding,” and “through” means “through and including.”
5.8
Several Obligations. The obligations of the Parties are several, and not joint, and not joint and several.
5.9
Entire Agreement; Related Agreements. This Agreement and the Related Agreements are intended to operate together and shall be interpreted consistently with one another. This Agreement, including its Schedule, Attachments, and the Related Agreements, constitutes
PDF page 14
the entire agreement of the Parties with respect to its subject matter and supersedes all prior understandings, oral or written.
5.10 No Third-Party Beneficiaries; No Partnership. This Agreement does not create rights, remedies, or benefits in favor of any person other than the Parties and their successors in interest and, where permitted, their assigns. This Agreement shall not be construed to create an association, joint venture, agency relationship, or partnership among the Parties, and no Party shall have authority to bind any other Party.
5.11
Waiver. The failure of a Party to insist on strict performance on any occasion shall not be a waiver, and no waiver of any breach shall be a continuing waiver or a waiver of any other or subsequent breach.
5.12 Force Majeure. No Party shall be considered in default of any obligation under this Agreement to the extent its performance is prevented or delayed by any event of Force Majeure, provided that such Party gives prompt written notice and uses reasonable efforts to resume performance; provided that Force Majeure shall not excuse any obligation to pay money or to post, maintain, renew, replace, or increase Security.
5.13 Severability. If any provision of this Agreement is finally determined to be invalid or unenforceable by a court or Governmental Authority, the remaining provisions shall continue in full force and effect.
5.14 Order of Precedence. In the event of a conflict between this Agreement and any Related Agreement regarding Security, this Agreement controls; in the event of a conflict regarding costs or charges, the CRA controls.
5.15 Dispute Resolution; Forum. Any dispute arising out of or relating to this Agreement shall be resolved in accordance with Article 20 and Section 14.3 of the Large Load Interconnection Agreement, including the jury waiver set forth therein; provided that no dispute resolution proceeding shall delay or restrict Transmission Owner’s right to draw on or apply Security in accordance with this Agreement.
5.16 Amendment. This Agreement may be amended by a written instrument signed by both Parties, subject to any required filing with and acceptance by FERC.
IN WITNESS WHEREOF, and with the intent to be bound, the Parties have caused their duly authorized representatives to execute this Agreement with effect as of the Effective Date, which represents the date of the last signature to this Agreement.
[CUSTOMER]
By: ______________________________
Name: ______________________________
Title: ______________________________
Date:_______________________________
SCHEDULE 1
Project Security Amount and Posting Schedule
Initial posting: $[_______] on the Effective Date.
Project Security Amount: $[_______]
[Subsequent posting(s): $[_______] on or before [date or milestone].]
Total Security Amount following all scheduled postings: $[_______], subject to adjustment under Sections 2.6 and 2.7.
Creditworthy Rating threshold: [A- from S&P and A3 from Moody’s for Letter of Credit issuer]. Permitted Security form(s): [Cash] [Letter of Credit].
Project Facilities covered: [list or reference IA appendix / NYISO study].
PDF page 17
ATTACHMENT A1
Form of Irrevocable Standby Letter of Credit
[To be completed by the Transmission Owner and Customer; the Letter of Credit shall be in form and substance acceptable to the Transmission Owner]
1 Each Transmission Owner may require modifications to match its commercially reasonable requirements or standards
PDF page 18
ATTACHMENT B
[Identify CRA, Large Load Interconnection Agreement and other agreements as needed]