Appendix C - Attachment A - GridLiance West CRA FINAL
PDF page 1
APPENDIX C
Pro Forma Cost Recovery Agreement
PDF page 2
ATTACHMENT A
FORM OF COST RECOVERY AGREEMENT
PDF page 3
1
COST RECOVERY AGREEMENT
This Cost Recovery Agreement (“Agreement”) is made and entered into as of __________ (the “Execution Date”) between GridLiance West LLC (“GridLiance West” or “Participating Transmission Owner”) and ________________, a [corporation/limited liability company/other] organized and existing under the laws of the State/Commonwealth of _____________________ (the “Eligible Customer”). The Eligible Customer is requesting Interconnection service to serve a Large Load, as those terms are defined in the Participating Transmission Owner’s tariff. The Participating Transmission Owner and Eligible Customer may be referred to herein individually as a “Party” or collectively as the “Parties.”
RECITALS
WHEREAS, Participating Transmission Owner is a Non-Load-Serving Entity Participating Transmission Owner within the California Independent System Operator, Inc. (“CAISO”) Balancing Authority Area that does not provide retail electric service;
WHEREAS, Participating Transmission Owner owns the [Facility Name], which is under CAISO’s Operational Control and within the CAISO Controlled Grid;
WHEREAS, Participating Transmission Owner’s Transmission Owner Tariff (the “Tariff”) controls the interconnection of load to [Facility Name], subject to compliance with the CAISO tariff;
WHEREAS, Eligible Customer is requesting interconnection to Participating Transmission Owner’s [Facility Name] for the purpose of serving [describe Large Load requesting service, physical location, and MW];
WHEREAS, the Parties have entered into this Agreement to establish the teams and conditions for the Interconnection in order to enable the Eligible Customer to serve the Large Load and for the Participating Transmission Owner to fully recover from the Eligible Customer the costs associated with serving the Large Load.
NOW, THEREFORE, in exchange for good and valuable consideration of the premises and mutual covenants herein, the Parties agree as follows:
ARTICLE 1: DEFINITIONS
1.1
Definitions
Capitalized terms used in this Agreement that are not otherwise defined herein shall have the meaning provided in the Participating Transmission Owner Tariff, as may be amended from time-
PDF page 4
2
to-time. In the event of a difference in a defined term between this Agreement and the definition in Module A of the Tariff, the defined term in this Agreement shall control.
1.2
Annual Required Revenue Commitment
Annual Required Revenue Commitment means the Eligible Customer’s Total Required Revenue Commitment divided by twenty (20) years.
1.3
Cost Recovery Payment
Cost Recovery Payment means the amount the Eligible Customer must pay in addition to the Large Load Annual Received Revenue to meet its Annual Required Revenue Commitment.
1.4
Large Load Annual Received Revenue
Large Load Annual Received Revenue means revenue that is received by the Participating Transmission Owner from CAISO through the Access Charges during a specific Rate Year and that is directly attributable to the Eligible Customer’s Large Load.
1.5
Large Load Network Upgrade
Large Load Network Upgrade shall mean any Network Upgrade attributable to an Eligible Customer interconnecting on behalf of a Large Load. Large Load Network Upgrades shall be specified in the Eligible Customer’s applicable Interconnection Agreement.
1.6
Monthly Cost Recovery Payment
Monthly Cost Recovery Payment means the Cost Recovery Payment divided by twelve (12) months.
1.7
Total Required Revenue Commitment
Total Required Revenue Commitment means the incremental revenue requirement for any Large Load Network Upgrade(s) to serve the Eligible Customer’s Large Load, calculated in accordance with Section 3.2.
ARTICLE 2: EFFECTIVE DATE, TERM AND TERMINATION, FILING
2.1
Effective Date
This Agreement shall be effective as of the date specified herein (“Effective Date”), subject to acceptance by FERC. If FERC accepts this Agreement subject to a different effective date,
PDF page 5
3
including in the event the Agreement is filed unexecuted, this Agreement shall become effective on the date accepted by FERC.
2.2
Term and Termination
Unless terminated earlier by mutual consent of the Parties, the term of this Agreement begins on the Effective Date and shall continue for twenty (20) years after the final Large Load Network Upgrade goes in-service or until, as applicable, the Eligible Customer has satisfied its Total Required Revenue Commitment in full pursuant to Article 3 hereof.
2.3
Filing
The Participating Transmission Owner shall file this Agreement with FERC and/or the appropriate Local Regulatory Authority, if applicable. Either Party may request that this Agreement be filed unexecuted at FERC.
ARTICLE 3: ELIGIBLE CUSTOMER PAYMENT OBLIGATIONS
3.1
Performance Obligations
The Eligible Customer shall be responsible for the Total Required Revenue Commitment, as is calculated under this Agreement pursuant to the Participating Transmission Owner’s formula rate in Appendix III of the Participating Transmission Owner Tariff. The Eligible Customer shall be responsible for the timely payment of all applicable invoices assessed herein. This Agreement does not relieve Eligible Customer from paying any charges or amounts assessed by the CAISO or any other governmental or regulatory authority to the Eligible Customer.
3.2
Total Required Revenue Commitment
3.2.1 Calculation of Total Required Revenue Commitment
The Total Required Revenue Commitment shall be calculated through the Participating Transmission Owner’s formula rate in Appendix III of the Participating Transmission Owner Tariff, as further set forth in Section 3.2.2, including the full return on the capital cost, depreciation, operations and maintenance, and taxes of the Large Load Network Upgrade(s).
3.2.2 Initial and Adjusted Total Required Revenue Commitment
The initial Total Required Revenue Commitment will be based on the estimated costs of the Large Load Network Upgrade(s) and shall be stated in Exhibit A to this Agreement. The Total Required Revenue Commitment shall be subject to adjustment by the Participating Transmission Owner the to reflect the actual costs of the Large Load Network Upgrade(s), and as necessary to reflect changes to the Participating Transmission Owner’s formula rate in Appendix III of its Tariff.
PDF page 6
4
Adjustments to the Total Required Revenue Commitment to reflect actual costs shall be initially calculated within one (1) year of the in-service date of the Large Load Network Upgrades, with a true-up adjustment as a credit or charge and including interest. For each year thereafter adjustments and any true-up shall be provided consistent with the Participating Transmission Owner’s True-up Adjustment and Annual Update under the Participating Transmission Owner’s formula rate. Interest associated with any initial true-up adjustment will begin to accrue the first day of the month following the in-service date of the Large Load Network Upgrades, in accordance with 18 C.F.R § 35.19a.
3.3
Required Cost Recovery Payments
Each Rate Year following the Large Load Network Upgrade’s in-service date and continuing throughout the term of this Agreement, the Participating Transmission Owner shall:
(a) determine whether the Large Load Annual Received Revenue for that Rate Year meets the Annual Required Revenue Commitment; and, if not,
(b) calculate the Cost Recovery Payment, payable by the Eligible Customer, equal to the difference between (i) the Annual Required Revenue Commitment for the applicable Rate Year and (ii) the Large Load Annual Received Revenue for that Rate Year, plus any applicable interest calculated in accordance with 18 C.F.R § 35.19a.
3.4
Invoice for Monthly Cost Recovery Payments
Within thirty (30) days of the end of each month of any Rate Year in which a Cost Recovery Payment is owed, the Participating Transmission Owner shall invoice the Eligible Customer for the Monthly Cost Recovery Payment as determined under Article 8. The Eligible Customer shall timely pay such invoice in accordance with Article 8.
3.5
Treatment of Cost Recovery Payments in the Formula Rate
For each Rate Year during the Term of this Agreement, the Participating Transmission Owner shall treat any Cost Recovery Payments required to be paid by the Eligible Customer as a credit against the Participating Transmission Owner’s Transmission Revenue Requirement in its formula rate in Appendix III of its Tariff, and shall include a separate workpaper in the Participating Transmission Owner’s annual informational filing detailing such crediting and rate treatment.
3.6
Payment in Event of Termination, Cancellation, or Withdrawal
Upon termination, disconnection, suspension, or abandonment of the Large Load project, or should the Eligible Customer terminate, cancel, or otherwise withdraw or terminate this Agreement, the Interconnection Agreement, or its Interconnection service for any reason, the Eligible Customer shall remain obligated to pay to the Participating Transmission Owner all costs incurred or committed by the Participating Transmission Owner associated with serving the Large Load,
PDF page 7
5
including Network Upgrades, prior to the effective date of any such termination or change. In the event the Eligible Customer fails to make such payment, this Agreement shall not be Terminated until such payment is made and payments shall continue to be due under Article 3. The Participating Transmission Owner may draw upon the Required Security to satisfy the Eligible Customer’s obligations under this Agreement. This Section 3.6 is without prejudice to any other remedy available to the Participating Transmission Owner.
ARTICLE 4: Security Requirements
4.1
Required Security
The Eligible Customer shall provide and maintain financial security in accordance with this Article 4 (the “Required Security”). The Required Security shall be in an amount equal to the Total Required Revenue Commitment and shall take one of the following forms as reasonably acceptable to the Participating Transmission Owner:
(a) cash;
(b) an irrevocable letter of credit issued by a commercial bank that has (i) an office, branch, or place of business in the United States where claims can be presented, (ii) assets of at least $10 billion, and (iii) a Credit Rating of either “A3” or higher by Moody’s, or (b) “A-” or higher by Standard & Poor’s (“S&P”). If a commercial bank is rated by each of Moody’s and S&P, the lower rating will be the applicable standard;
(c) an irrevocable guaranty, provided that the guarantor maintain a senior unsecured credit rating of BBB- equivalent by Moody’s, S&P, or Fitch. If the guarantor is rated by one or more rating agencies, the lowest rating will be the applicable standard; or
(d) such other form of security as the Eligible Customer may propose and the Participating Transmission Owner, in its sole discretion, determines to be acceptable.
When the amount of Total Required Revenue Commitment is adjusted per Section 3.2.2, the amount of Required Security shall be adjusted accordingly. The amount of Required Security may be further adjusted in accordance with Sections 4.3 and 4.4.
4.2
Timing to Provide Required Security
The Eligible Customer shall provide the Required Security within thirty (30) Calendar Days of the later of (i) the execution of this Agreement by all parties or (ii) acceptance of this Agreement by FERC. Failure to provide the Required Security within such timeframe will result in the Large Load Interconnection Application being deemed withdrawn.
4.3
Annual Reduction of Required Security
The Required Security shall remain with the Participating Transmission Owner for the Term of this Agreement. The Participating Transmission Owner will reduce the Required Security
PDF page 8
6
following each Annual Update during the Term of this Agreement to reflect the completed payments made by the Eligible Customer pursuant to Article 3 of this Agreement. Any such reduced Required Security must be provided in a revised form of irrevocable security otherwise meeting the requirements of Section 4.1.
4.4
Use of Required Security by Participating Transmission Owner
In the event Eligible Customer fails to timely pay any invoice or any other payment due under this Agreement, the Participating Transmission Owner shall notify the Eligible Customer in accordance with Section 13.4. If the Eligible Customer fails to timely cure and provide such payment within five (5) Business Days of receiving such notice, the Participating Transmission Owner shall be entitled to draw on the Required Security in the amount of the missed payment, as well as any accrued interest charges based on FERC’s regulations at 18 C.F.R § 35.19a. Within twenty (20) Business Days of such draw on the Required Security occurring, the Eligible Customer shall be required to provide the Participating Transmission Owner with sufficient irrevocable security to maintain sufficient Required Security to meet the obligation under Section 4.1 of this Agreement.
4.5
Term of Required Security
Required Security shall remain in place until the termination of this Agreement. Any Required Security provided by Eligible Customer must be kept active, must continue to meet this Article 4’s requirements, and must be available to the Participating Transmission Owner in the event that Eligible Customer fails to make any payment required under this Agreement. Any fees or costs associated with the provision of the Required Security under this Agreement are the sole responsibility of the Eligible Customer.
ARTICLE 5: [RESERVED]
ARTICLE 6: [RESERVED]
ARTICLE 7: CONFIDENTIALITY
7.1
Confidentiality
During the term of this Agreement and for a period of five (5) years after any termination or expiration of this Agreement, each Party shall hold in confidence and not disclose to any person any Confidential Information received by a Party (“Receiving Party”) from the other party (“Disclosing Party”), and except as Disclosing Party may authorize in writing, a Receiving Party who received Confidential Information shall and shall cause its Representatives to: treat and cause to be treated as confidential all Confidential Information; not disclose any Confidential Information to any third party (other than its Representatives) or make available any reports, recommendations, extracts, summaries, analysis, or conclusions based on the Confidential Information; use or grant access to Confidential Information only in connection with the
PDF page 9
7
performance of the respective obligations as provided under this Agreement; or make copies of any tangible embodiment of Confidential Information only as necessary for the performance of respective obligations as provided under this Agreement.
7.2
Scope
Confidential Information shall include, without limitation, all information relating to a Party’s technology, research and development, business affairs, and pricing, and any information supplied by a Party to another Party prior to the execution of this Agreement. Information is Confidential Information only if it is clearly designated or marked in writing as confidential on the face of the document, or, if the information is conveyed orally or by inspection, if the Party providing the information orally informs the Party receiving the information that the information is confidential. The Parties shall maintain as confidential any information that is provided and identified by a Party as Critical Energy/Electric Infrastructure Information (“CEII”), as that term is defined in 18 C.F.R. § 388.113(c). Such confidentiality will be maintained in accordance with this Article 7. If requested by the receiving Party, the disclosing Party shall provide in writing, the basis for asserting that the information referred to in this Article warrants confidential treatment, and the requesting Party may disclose such writing to the appropriate Governmental Authority. Each Party shall be responsible for the costs associated with affording confidential treatment to its information. Confidential Information shall not include information that the receiving Party can demonstrate:
(a) is generally available to the public other than that which is a result of a disclosure by the Receiving Party;
(b) was in the lawful possession of the Receiving Party on a non-confidential basis before receiving it from the Disclosing Party;
(c) was supplied to the Receiving Party without restriction by a third party, who, to the knowledge of the Receiving Party, after due inquiry, was under no obligation to the Disclosing Party to keep such information confidential;
(d) was independently developed by the Receiving Party without reference to Confidential Information of the Disclosing Party;
(e) is, or becomes, publicly known, through no wrongful act or omission of the Receiving Party or breach of this Agreement; or
(f) is required to be disclosed by any Governmental Authority or is otherwise required to be disclosed by law or subpoena or is necessary in any legal proceeding establishing rights and obligations under this Agreement.
PDF page 10
8
Information designated as Confidential Information shall no longer be deemed confidential if the Party that designated the information as confidential notifies the other Party that it no longer is confidential.
7.4
Release of Confidential Information
No Party shall disclose Confidential Information to any other person, except to its Representatives (limited by FERC’s Standards of Conduct requirements) without the prior written consent of the disclosing Party. A receiving Party may disclose Confidential Information to its Representatives provided that such Representatives have first been advised of the confidentiality provisions of this Article 7. Notwithstanding the foregoing, a Party providing Confidential Information to a Representative shall remain primarily responsible for any release of Confidential Information by such Representative in contravention of this Article 7.
7.5
Rights
Each Party retains all rights, title, and interest in the Confidential Information that it discloses to the other Party. A Party’s disclosure to the other Party of Confidential Information shall not be deemed a waiver by such Party or any other person or entity of the right to protect the Confidential Information from public disclosure.
7.6
No Warranties
By providing Confidential Information, neither Party makes any warranties or representations as to its accuracy or completeness.
7.7
Standard of Care
Each Party shall use at least the same standard of care to protect Confidential Information it receives as such Party uses to protect its own Confidential Information from unauthorized disclosure, publication or dissemination. Confidential Information may be used solely to fulfill a Party’s obligations to the other Party under this Agreement or to comply with Applicable Laws, Regulations, and Standards.
7.8
Order of Disclosure
If a Governmental Authority with the right, power, and apparent authority to do so requests or requires a Party, by subpoena, oral deposition, interrogatories, requests for production of documents, administrative order, or otherwise, to disclose Confidential Information, that Party shall provide the Party that provided the Confidential Information with prompt notice of such request(s) or requirement(s) so that the providing Party may seek an appropriate protective order or waive compliance with the terms of this Agreement. Notwithstanding the absence of a protective order or agreement, or waiver, the Party that is subjected to the request or order may
PDF page 11
9
disclose such Confidential Information which, in the opinion of its counsel, the Party is legally compelled to disclose. Each Party shall use reasonable efforts to obtain reliable assurance that confidential treatment will be accorded to any Confidential Information so furnished.
7.9
Return or Destruction of Confidential Information
Each Party shall, within ten (10) Business Days of receipt of a written request from the other Party, use reasonable efforts to destroy, erase, or delete (with such destruction, erasure and deletion certified in writing to the requesting Party) or to return to the requesting Party, without retaining copies thereof, any and all written or electronic Confidential Information received from the requesting Party, provided that (i) the non-requesting Party shall not be required to purge any historical backup media, and (ii) if the non-requesting Party elects to delete, destroy or erase all such Confidential Information, it shall certify such deletion, destruction, or erasure to the requesting Party in writing.
7.10
Remedies
Monetary damages would be inadequate to compensate a Party for the other Party’s Breach of its obligations under this Article 7; therefore, a Party shall be entitled to injunctive or other equitable relief, without bond or proof of damages, if the other Party Breaches or threatens to Breach its obligations under this Article 7, and the Party that Breaches or threatens to Breach its obligations under this Article 7 shall not plead in defense that there would be an adequate remedy at law. Injunctive relief shall not be deemed to be an exclusive remedy for the Breach of this Article 7 and shall be in addition to all other remedies available at law or in equity. The covenants contained herein are necessary for the protection of legitimate business interests and are reasonable in scope.
7.11
Disclosure to Federal or State Commissions or their Staff
Notwithstanding anything in this Article 7 to the contrary, and pursuant to 18 C.F.R. § 1b.20, if FERC or its staff, during the course of an investigation or otherwise, requests information from a Party that is otherwise required to be maintained in confidence pursuant to this Agreement, such Party shall provide the requested information to FERC or its staff, within the time provided for in the request for information. In providing the information to FERC or its staff, the Party must, consistent with 18 C.F.R. § 388.112, request that the information be treated as confidential and non-public by FERC and its staff and that the information be withheld from public disclosure. To the extent permitted by law, each Party shall notify the other Party prior to the release of the other Party’s Confidential Information to FERC or its staff. A Party shall promptly notify the other Party when it is notified by FERC or its staff that a request to release the other Party’s Confidential Information has been received by FERC, at which time either of the Parties may respond before such information would be made public, pursuant to 18 C.F.R. § 388.112.
PDF page 12
107.12
General Disclosure
Notwithstanding any other provisions of this Article 7, a Party may disclose the Confidential Information provided by the other Party to the extent disclosure is: (i) reasonably deemed by the disclosing Party to be required in connection with a dispute between the Parties, or the defense of litigation or dispute; (ii) otherwise permitted by written consent of the Party that provided such Confidential Information; (iii) necessary to fulfill its obligations to an RTO or ISO or to a regional or national reliability organization; or (iv) is required to be disclosed pursuant to any Governmental Authority or is otherwise required to be disclosed by law or subpoena. Prior to any disclosures of another Party’s Confidential Information under this Section 7.12, the Disclosing Party shall promptly notify the other Party in writing and shall assert confidentiality and cooperate with the other Party in seeking to protect the Confidential Information from public disclosure by confidentiality agreement, protective order, or other reasonable measures.
7.13
Audit Rights
Subject to the requirements of confidentiality under Article 7 of this Agreement, (1) the accounts and records related to the adjustment provided for in Section 3.2.2 shall be subject to audit for a period of twenty-four (24) months following the date the adjustment; and (2) the accounts and records related to the determination of whether the Eligible Customer satisfied its Annual Required Revenue Commitment shall be subject to audit for a period of twelve (12) months following each year’s determination in accordance with this Article 7. Eligible Customer at its expense shall have the right, during normal business hours, and upon prior reasonable notice to the other Parties, to audit such accounts and records. Any audit authorized by this Article 7 shall be performed at the offices where such accounts and records are maintained and shall be limited to those portions of such accounts and records that relate to obligations under this Agreement.
ARTICLE 8: INVOICING AND PAYMENT; TAXES
8.1
Purpose of Invoicing
Any invoice that is issued pursuant to this Agreement shall be for the purposes set forth in this Agreement.
8.2
Timeliness of Payment
Unless otherwise agreed upon, any invoices issued pursuant to this Agreement shall be rendered within thirty (30) Calendar Days of the end of the calendar month in which expenses were incurred and shall be due and payable, unless otherwise agreed upon, within thirty (30) Calendar Days of receipt of such invoice. Payment shall be made by electronic transfer or such other means as shall cause such payment to be available for the use of the payee. Interest on unpaid amounts shall be determined based on FERC’s regulations at 18 C.F.R § 35.19a.
PDF page 13
118.3
Disputed Invoices
In the event that a Party disputes an invoice, the disputing Party shall pay the invoice in full in accordance with Section 8.2 of this Agreement, subject to the refund of any amounts found to have been incorrectly invoiced plus interest on such amount from the date of payment to the date of the refund at the rate stated in Section 8.2. In the event of a billing dispute, the disputing Party shall provide written notice of the dispute to the billing Party as set out in Section 13.4. In response to the notice, the billing Party will promptly provide all documentation that is reasonably required in support of its bill and confer with the disputing Party. If these good faith efforts fail to resolve the issue, the matter may, by mutual agreement of the Parties, be settled through the dispute resolution process described in Article 10.
8.4
Invoice Adjustments
Other than as required by law, regulatory action or metering test adjustments, invoice adjustments shall be made within six (6) months of the rendition of the initial invoice.
8.5
Tax Reimbursement
If, as part of any compensation to be paid under this Agreement, any transaction tax, including, but not limited to sales, excise, or similar taxes (other than taxes based on or measured by net income) is levied and/or assessed against either Party by any taxing authority on the power and/or energy manufactured, generated, produced, converted, sold, purchased, transmitted, interchanged, exchanged, exported or imported by the supplying Party to the other Party, then such supplying Party shall be fully compensated by the other Party for such direct taxes.
ARTICLE 9: INDEMNITY
To the extent permitted by law, each Party (the “Indemnifying Party”) shall indemnify, save harmless, and defend the other Party from and against any losses, liabilities, costs, expenses, suits, actions, claims, and all other obligations arising out of injuries or death to persons or damage to property (each a “Loss” and each suffered by or asserted by a third party) arising out of, in connection with, or resulting from the Indemnifying Party’s (or its Contractor’s) performance or non-performance of its obligations under this Agreement; provided, however, that a Party’s obligation to indemnify the other Party shall not apply to any Losses arising from the other Party’s negligence or intentional misconduct. Promptly after receipt by a Party entitled to indemnity (“Indemnified Party”) of any claim or notice of the commencement of any action, administrative or legal proceeding, or investigation as to which the indemnity provided for in this Article 9 may apply, the Indemnified Party shall notify the Indemnifying Party of such fact. Any failure of or delay in such notification shall not affect an Indemnifying Party’s indemnification obligation unless such failure or delay is materially prejudicial to the Indemnifying Party.
PDF page 14
12
The Indemnifying Party shall, at the Indemnified Party’s option and at the Indemnifying Party’s expense, defend the Indemnified Party against any and all suits, actions, or claims arising out of, connected with, or resulting from the performance or non-performance by the Indemnifying Party or any of its Contractors of its obligations under this Agreement. The Indemnifying Party shall not settle or make a plea with respect to any suit, action or claim without the Indemnified Party’s prior written consent.
A Party’s obligations to another Party under this Article 9 shall not be limited in any way by any provision of any workers’ compensation, disability benefits, payroll, or other employee benefits laws; provided, however, that nothing herein shall limit or restrict any defense a Party may be entitled to assert with respect to a Loss, including a defense based on the status of such Party as a statutory employer. EACH PARTY HEREBY SPECIFICALLY AND EXPRESSLY WAIVES
ANY AND ALL DEFENSES IT MAY HAVE TO AN INDEMNIFICATION OBLIGATION TO
THE OTHER PARTY PURSUANT TO THIS AGREEMENT BASED ON ANY IMMUNITY TO
WHICH SUCH PARTY MAY BE ENTITLED UNDER ANY WORKERS’ COMPENSATION,
DISABILITY BENEFITS, PAYROLL, OR EMPLOYEE BENEFITS LAWS.
For the purposes of this Article 9 only, the term “Party” shall include the Party’s Affiliates and the directors, officers, employees, and agents of the Party and its Affiliates.
ARTICLE 10: DISPUTES
10.1
Dispute Resolution
The Parties shall attempt, in good faith, to resolve or cure any dispute, controversy or claim (a “Dispute”) before initiating any formal legal action at law or in equity to resolve the same. If either Party believes that a Dispute has arisen, such Party shall give written notice thereof to the other Party, which notice shall describe in reasonable detail the basis and specifics of the claimed Dispute (the “Dispute Notice”). Within five (5) Business Days after delivery of the Dispute Notice, each Party shall appoint a senior level executive. Each designated executive shall meet (in person or via telephone) to discuss and attempt to resolve or cure such Dispute.
Each senior level executive shall negotiate for a reasonable period of time to settle the Dispute after the Dispute Notice is referred to them; provided that such reasonable period shall not, unless otherwise agreed by the Parties in writing, exceed twenty (20) Business Days from the time of receipt of the Dispute Notice by the senior level executive of each Party, or longer period of time if agreed to by the Parties. Notwithstanding anything to the contrary herein, in no event will the executive officer to whom the matter is referred be a person who is an attorney without the express written permission of the chief legal counsel of the other Party.
If the Dispute has not been resolved pursuant to this Section 10.1 within thirty (30) Business Days from the time of receipt of the Dispute Notice by the applicable individual, either Party may
PDF page 15
13
proceed to take any and all actions available to it under this Agreement to resolve such dispute and to obtain any remedies available under this Agreement.
10.2
Not Usable As Evidence
Nothing said or disclosed, nor any document produced, in the course of any negotiations, conferences and discussion in connection with efforts to settle a Dispute that is not otherwise independently discoverable shall be offered or received as evidence or used for impeachment or for any other purposes in any suit, but shall be considered to have been disclosed for settlement purposes.
ARTICLE 11: BREACH AND DEFAULT
11.1
General
A Party shall be considered in default of this Agreement (“Default”) if it fails to cure a Breach in accordance with the terms of this Section 11.1. A breach (“Breach”) shall mean the failure of a Party to perform or observe any material term or condition of this Agreement; provided that no Breach shall exist where such failure to discharge an obligation (other than the payment of money) is the result of Force Majeure as defined in this Agreement or the result of an act or omission by the other Party. Upon a Breach, the non-breaching Party shall give written notice of such Breach to the breaching Party. The breaching Party shall have thirty (30) Calendar Days from receipt of the Breach notice within which to cure such Breach; provided however, if such Breach is not capable of cure within thirty (30) Calendar Days, the breaching Party shall commence such cure within thirty (30) Calendar Days after notice and continuously and diligently complete such cure within ninety (90) Calendar Days from receipt of the Breach notice; and, if cured within such time, the Breach specified in such notice shall cease to exist.
11.2
Consequence of Default
In the event of Default, Eligible Customer shall promptly pay any remaining Total Required Revenue Commitment owed under this Agreement. In the event that Eligible Customer does not promptly such amount, the Participating Transmission Owner may draw on the Required Security. This payment or draw on the Required Security does not limit any and all rights and remedies available to the non-defaulting Parties allowed by law with respect to such default or collecting all amounts owed under this Agreement. The Defaulting Party shall indemnify non-Defaulting Parties for reasonable costs, attorney fees and/or expenses incurred with respect to a default or collecting all amounts owed, including, as applicable, any tax gross-up obligations under this Agreement.
PDF page 16
14
ARTICLE 12: GOVERNMENTAL AUTHORITIES; AMENDMENT
12.1
Governmental Authorities
This Agreement is made subject to the jurisdiction of FERC and any Local Regulatory Authority having jurisdiction over the rates, terms and conditions, or services provided under this Agreement. Nothing in this Agreement shall limit the rights of the Parties or of FERC under Sections 205 and 206 of the Federal Power Act and FERC’s rules and regulations thereunder.
12.2
Amendments to the Agreement
This Agreement may only be modified in a writing signed by the Parties. In the event that the Parties agree to amend this Agreement, the Parties shall, if required by Applicable Laws, Regulations, and Standards, file any such amendment or modification with FERC.
ARTICLE 13: GENERAL
13.1
Force Majeure
No Party shall be in Breach in respect to any obligation hereunder because of Force Majeure. if any Party’s performance under this Agreement is hindered by an event of Force Majeure, it shall make all reasonable efforts to perform its obligations under this Agreement. An event of Force Majeure means any act of God, labor disturbance, act of the public enemy, war, act of terrorism, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, order, regulation or restriction imposed by governmental military or lawfully established civilian authorities, or any other cause beyond a Party’s control. Force Majeure does not include an act of negligence or intentional wrongdoing by the Party claiming Force Majeure or economic hardship or economic conditions rendering a Party’s performance of this Agreement unprofitable or uneconomic. Any Party’s obligation to make payments or maintain the Required Security at all times shall not be suspended by Force Majeure. A Party unable to fulfill any other obligation by reason of Force Majeure shall provide prompt written notice of such Force Majeure event to the other Party and such notice shall include an estimate of the expected duration of such event. The failure of a Party to perform its obligations under this Agreement as a result of Force Majeure shall only be excused for the duration of the Force Majeure and while such Party exercises diligence to remove such disability. As soon as the non-performing Party is able to resume performance of its obligations, such Party shall resume performance and give prompt notice thereof to the other Party.
13.2
Waivers
No failure or delay on the part of either Party in exercising any of its rights under this Agreement, no partial exercise by either Party of any of its rights under this Agreement, and no course of dealing between the Parties shall constitute a waiver of the rights of either Party under this Agreement. Any waiver shall be effective only by a written instrument signed by the Party
PDF page 17
15
granting such waiver, and such shall not operate as a waiver of, or continuing waiver with respect to, any subsequent failure to comply therewith.
13.3
Liability
To the fullest extent permitted by law and notwithstanding any provision of this Agreement, in no event shall a Party, its Affiliates, or any of their respective owners, officers, directors, employees, agents, successors or assigns be liable to the other Party, its Affiliates or any of their respective owners, officers, directors, employees, agents, successors or assigns, whether in contract, warranty, tort, negligence, strict liability, or otherwise, for any special, indirect, incidental, exemplary, consequential (including, without limitation, attorneys’ fees, litigation costs, replacement power costs, lost profits or revenues, loss of good will or lost business opportunities), or punitive damages related to or resulting from performance or nonperformance of this Agreement or any activity associated with or arising out of this Agreement.
13.4
Written Notices
Any notice or other communication required or permitted by this Agreement may be given by personal delivery, by e-mail (with confirmation of receipt), by any courier service which guarantees overnight, receipted delivery, or by U.S. certified or registered mail, return receipt requested, addressed to the Party entitled thereto, at the following addresses. The below listed titles and addresses for a Party may be changed by written notice to all the other Parties. Such change shall not necessitate a filing under Section 205 of the Federal Power Act. Any such notice or communication will be deemed to have been given as of the date received.
If to GridLiance
West:
GridLiance West LLC
700 Universe Boulevard
Juno Beach, Florida 33408
NEET-Business-Management.SharedMailbox@nexteraenergy.com
With a copy (which shall not constitute notice) to:
GridLiance West LLC
Attn: Legal Department
700 Universe Boulevard
Juno Beach, Florida 33408
NEET-Legal.SharedMailbox@nexteraenergy.com
If to [Eligible
Customer]:
[Eligible Customer to insert]
PDF page 18
1613.5
Governing Law
The validity and meaning of this Agreement shall be governed by and construed in accordance with federal law where applicable and, when not in conflict with or preempted by federal law, the applicable law of the State of California, without application of its conflicts of law provisions.
13.6
Counterparts
This Agreement may be executed in one or more counterparts, each of which shall be deemed an original.
13.7
Entire Agreement; Superseding Effect
This Agreement, including all exhibits, schedules, appendices and other attachments hereto, sets forth the entire understanding and agreement of the Parties as to the subject matter of this Agreement, cost recovery by the Participating Transmission Owner of all costs of Large Load Network Upgrades under the applicable Interconnection Agreement, and supersedes all prior written and oral understandings, offers, agreements, commitments, representations, writings, discussions, or other communications of every kind between the Parties, pertaining to the subject matter hereof.
ARTICLE 14: ASSIGNMENT
14.1
Assignment
This Agreement shall inure to the benefit of and be binding upon the successors and assigns of the Parties. This Agreement shall not be assigned by any Party without the written consent of the other Party, which consent shall not be unreasonably withheld, conditioned, or delayed; provided that the assignee is at least as creditworthy as the assigning Party and the assignee of Eligible Customer shall provide Participating Transmission Owner with valid Security as contemplated herein. No purported assignment of this Agreement shall release or discharge any Party from current or future obligations hereunder unless all such obligations are assumed by the successor or assignee of that Party in writing and in conformity with this provision.
ARTICLE 15: SURVIVAL
15.1
Survival
The termination of this Agreement shall not discharge either Party from any obligation it owes to the other Party under this Agreement by reason of any transaction, loss, cost, damage, expense, or liability that shall occur (or the circumstances, events or basis of which shall occur or arise) prior to such termination, including but not limited to any accrued payment obligations, final cost reconciliation, ownership of the Network Upgrades or Interconnection Facilities, or provisions that
PDF page 19
17
expressly or by their nature survive the termination or expiration of this Agreement. It is the intent of the Parties hereby that any such obligation owed (whether the same shall be known or unknown at the termination of this Agreement) shall survive the termination of this Agreement, and that either Party may enforce its rights against the other Party with respect to such obligations in an action at law or in equity to the fullest extent permitted by law.
This Agreement shall continue in effect after termination to the extent necessary: (i) for final billings and payments; (ii) to permit the determination and enforcement of liability and indemnification obligations arising from acts or events that occurred while this Agreement was in effect; and (iii) to permit each Party to have access to the real property, including but not limited to leased property and easements of the other Party to disconnect, remove or salvage its own facilities and equipment.
[The remainder of this page is intentionally left blank. The next
page of this document is the signature page.]
PDF page 20
18
IN WITNESS WHEREOF, the Parties have caused their authorized representatives to execute this agreement as of the date first above written.
GRIDLIANCE WEST LLC
By:
Name:
Title:
[ELIGIBLE CUSTOMER]
By:
Name:
Title:
[ENTITY NAME]
By:
Name:
Title:
PDF page 21
19
EXHIBIT A
Initial Total and Annual Required Revenue Commitment
Estimated costs of the Large Load Network Upgrade(s) stated in the Interconnection Agreement: $
.
Initial Total Required Revenue Commitment per formula rate: $
.
Initial Annual Required Revenue Commitment: $
.