Request for Rehearing of the Indicated PJM Transmission Owners of the September 29, 2026 backstop order (TO exit amendment)
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
Docket No. ER26-3380-000
REQUEST FOR REHEARING OF THE
INDICATED PJM TRANSMISSION OWNERS
Pursuant to Federal Power Act (“FPA”) section 313(a)1 and Rule 7132 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”),3 the Indicated PJM Transmission Owners4 respectfully request rehearing of the Commission’s September 29, 2026 order in this proceeding (the “Order”).51 16 U.S.C. § 825l(a). 2 See 18 C.F.R. § 385.713 (2026).3 18 C.F.R. § 385.211 (2026).4 The Indicated PJM Transmission Owners are American Transmission Systems, Inc., Mid- Atlantic Interstate Transmission, LLC, Trans-Allegheny Interstate Line Company, Keystone Appalachian Transmission Company, Jersey Central Power & Light Company, Monongahela Power Company, and The Potomac Edison Company (collectively, “The FirstEnergy Transmission Companies”) and Duquesne Light Company. The FirstEnergy Transmission Companies are separately filing a rehearing request raising other issues.5 See PJM Interconnection, L.L.C., 196 FERC ¶ 61,245 (2026) (“Order”).
PDF page 2
2
The Indicated PJM Transmission Owners are hopeful that PJM6 will submit a revised section 205 filing that supersedes its earlier section 205 filing and may moot the need for rehearing of the Order. The Indicated PJM Transmission Owners submit this rehearing request out of an abundance of caution to preserve their rights in this fast-moving and dynamic proceeding.
As discussed below, the Commission should grant rehearing of the Order as follows:
• The Order is erroneous, arbitrary and capricious, fails to engage in reasoned decision- making, and is unsupported by substantial evidence because it did not definitively reject PJM’s Exit Amendment on cost-causation grounds.
• The Order is erroneous, arbitrary and capricious, fails to engage in reasoned decision- making, and is unsupported by substantial evidence because it did not definitively reject PJM’s Exit Amendment on the basis that PJM exceeded its FPA section 205 filing authority.
I. BACKGROUND
On July 31, 2026, after a truncated CIFP review process and without proper notice to the TOs, PJM filed its RBP proposal with the Commission under FPA section 205, with a proposed effective date of September 29, 2026. The RBP proposal included an Exit Amendment that would establish new prerequisites to a TO exiting PJM and impose new fees on exiting TOs. The Indicated PJM Transmission Owners submitted a Protest opposing this Exit Amendment. This Protest was not brought on by any present desire to exit PJM; rather,
6 Defined terms used herein shall have the same meaning as in the Indicated PJM Transmission Owners’ Protest. See Protest of the Indicated PJM Transmission Owners, PJM Interconnection, L.L.C., No. ER26-3380-000 (filed Aug. 21, 2026).
PDF page 3
3
it challenged PJM’s deviation from agreed-upon CTOA processes and relevant Commission precedent in how PJM adopted the Exit Amendment and with respect to its substance. On September 29, 2026, the Commission issued its Order, accepting PJM’s RBP proposal for filing, “suspended for five months, effective February 28, 2027, subject to refund and the outcome of the further procedures ordered in this proceeding.”7 The Commission identified three aspects of PJM’s proposal that may be unjust and unreasonable—“cost allocation, [TO] exit rules, and LSE collateral requirements”8—but “f[ound] that the other aspects of PJM’s RBP proposal are just and reasonable.”9 The Commission ordered further briefing and a paper hearing pertaining to the aspects identified as potentially unjust and unreasonable, and suggested that, “following the paper hearing, the Commission may need to direct significant modifications to certain aspects of PJM’s proposal.”10 As to the Exit Amendment in particular, the Commission found that PJM “fails to explain why Transmission Owners—who are not the buyers for which PJM procures capacity under the RBP—should be responsible for RBP Charges,”11 and that the Exit Amendment “may be inconsistent with the cost causation principle.”12 But the Order did not reject the concept of an exit fee outright, and instead proposed that “a just and reasonable approach could require LSEs in an exiting Transmission Owner’s zone to pay RBP exit fees commensurate with their cost allocation under the RBP, to prevent cost shifts to other LSEs in the PJM
7 Order, 196 FERC ¶ 61,245 at P 215(A). 8 Id. P 24.9 Id. P 23.10 Id. PP 24–25. 11 Id. P 178.12 Id. P 179.
PDF page 4
4
Region.”13 The Commission did not address the Indicated PJM Transmission Owners’ argument that PJM’s Exit Amendment was not the sort of matter that PJM could unilaterally file with the Commission under PJM’s governing agreements.
As explained herein and for the reasons set forth below, the Commission should grant rehearing and definitively reject the Exit Amendment both as violative of cost-causation principles and as an ultra vires submission filed in excess of PJM’s unilateral filing authority.
II. REQUEST FOR REHEARING
A. Statement of Issues and Specification of Errors
The Indicated PJM Transmission Owners submit the following Statement of Issues and Specification of Errors pursuant to Rule 713(c)(1)-(2) of the Commission’s Rules of Practice and Procedure.14
• The Order is erroneous, arbitrary and capricious, fails to engage in reasoned decision- making, and is unsupported by substantial evidence because it did not definitively reject PJM’s Exit Amendment on cost-causation grounds. 16 U.S.C. § 824d(a)–(b) (all rates and charges “shall be just and reasonable,” and no public utility shall “subject any person to any undue prejudice or disadvantage”); KN Energy Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992) (rates must “reflect to some degree the costs actually caused by the customer who must pay them”); Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476–77 (7th Cir. 2009) (“FERC is not authorized to approve a pricing scheme that requires a group of utilities to pay for facilities from which its members derive no benefits, or benefits that are trivial in relation to the costs sought to be shifted to its
13 Id. P 181 (emphasis added).14 18 C.F.R. § 385.713(c)(1)–(2) (2026).
PDF page 5
5
members.”); Duquesne Light Co., 122 FERC ¶ 61,039 at PP 89–94 (2008) (holding the withdrawing entity responsible for capacity PJM had procured because it “understood that PJM was procuring capacity on its behalf and therefore should be obligated to pay for that capacity”).
• The Order is erroneous, arbitrary and capricious, fails to engage in reasoned decision- making, and is unsupported by substantial evidence because it did not definitively reject PJM’s Exit Amendment on the basis that PJM lacked authority under its governing documents to file the Exit Amendment unilaterally. See CTOA § 8.5.1 (amending the CTOA requires a two-thirds majority vote of the TOs); id. § 7.5.1(iv) (TOs hold “unilateral and exclusive” rights to make an FPA section 205 filing concerning “any provisions governing the recovery of transmission-related costs incurred by the [TOs]”); id. (requiring detailed advance notice to the TOs of any filing that “relates to or affects . . . [the] provisions governing the recovery of transmission-related costs”); New England Power Generators Ass’n v. FERC, 881 F.3d 202, 210 (D.C. Cir. 2018) (Commission must “respond meaningfully to the arguments raised before it”) (quoting TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir. 2015)).
B. Argument
1. The Exit Amendment Violates Cost-Causation Principles
The Order’s preliminary conclusion that the Exit Amendment may violate cost- causation principles should have been stated finally and definitively, instead of being left open for decision after a paper hearing. Under cost-causation principles, rates must “reflect to some degree the costs actually caused by the customer who must pay for them,” and costs must be
PDF page 6
6
allocated in a manner at least roughly commensurate with benefits.15 As the Order recognized, PJM proposes to procure RBP capacity “on behalf of LSEs,” and “the beneficiaries of the RBP are the LSEs on whose behalf PJM will procure capacity through the RBP.”16 TOs “are not the buyers for which PJM procures capacity under the RBP,” and PJM “fails to explain why” they “should be responsible for RBP Charges.”17 The Commission’s precedent points the same way: the Commission has found it just and reasonable to impose generation capacity costs on LSEs located within an exiting TO’s zone, not on the TO as such.18
Although the Commission expressed preliminary agreement with the argument that the Exit Amendment violates cost-causation principles, the Commission should not have left the issue open, but instead should have definitively and finally ruled that the Exit Amendment violates cost-causation principles. The Commission should grant rehearing and issue that final ruling now.
2. PJM Lacked Authority To File The Exit Amendment
The Order summarized the Indicated PJM Transmission Owners’ filing-rights challenge, and PJM’s brief response, but the Order did not resolve this issue.19 The Indicated PJM Transmission Owners respectfully request that the Commission address that challenge now and sustain it. PJM lacked filing authority for three independent reasons.
15 Order, 196 FERC ¶ 61,245 at P 179 (quoting KN Energy Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992), and citing Ill. Com. Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009)).16 Id. PP 178–79.17 Id. P 178; see Protest of the Indicated PJM Transmission Owners at 8–10.18 Order, 196 FERC ¶ 61,245 at P 178 (citing Duquesne Light Co., 122 FERC ¶ 61,039 at PP 89–94); see also id. P 169 (summarizing Indicated PJM Transmission Owners’ showing that, in Duquesne, the Commission found Duquesne responsible for capacity charges “only in the context of Duquesne’s role as an LSE”).19 Id. PP 166–67.
PDF page 7
7
First, the Exit Amendment amends the CTOA, which already addresses an exiting TO’s obligations,20 and which may be amended only with the supporting vote of the TOs.21 The Exit Amendment adds new obligations to exit that have no counterpart in PJM’s governing documents, which “do not contain an exit fee.”22 And the Exit Amendment makes those obligations preconditions to exit: each payment obligation must be satisfied “prior to” the TO’s exit from PJM.23 Thus, the Exit Amendment constitutes an amendment of the CTOA—the existing version of which permits an exit only once the preconditions in sections 3.2 and 3.4 have been met.24 PJM cannot avoid the CTOA’s amendment procedures by casting a change to the core terms of the CTOA as an amendment to the OATT, rather than to the CTOA. Second, to the extent the Exit Amendment imposes costs on TOs in their capacity as TOs, this is a matter of recovery of transmission-related costs—which falls within the TOs’ exclusive filing rights.2520 Id. P 166 (noting “the existing CTOA requirements in sections 3.2 and 3.4 governing an exiting Transmission Owner’s obligations”). 21 CTOA § 8.5.1; Protest of the Indicated PJM Transmission Owners at 5–6; see Order, 196 FERC ¶ 61,245 at P 166.22 Id. P 168.23 Proposed Tariff, attach. DD, § 18.7(a)–(b).24 Pursuant to CTOA section 3.2, “[a]ny Party may withdraw from” the CTOA if it meets three preconditions: (1) securing alternative arrangements for comparable transmission service; (2) obtaining FERC approval to withdraw; and (3) “if its Transmission Facilities do not comprise an entire Control Area,” satisfying all applicable NERC and Applicable Regional Reliability Council standards for operating a Control Area or being included within an existing one. CTOA § 3.2 (“Withdrawal From This Agreement”). Pursuant to section 3.4, a withdrawing TO remains liable for obligations it incurred, that were incurred on its behalf, or that arose under the CTOA before the withdrawal’s effective date. Id. § 3.4 (“Obligations After Withdrawal, Transfer, or Assignment”).25 CTOA § 7.5.1(iv); Protest of the Indicated PJM Transmission Owners at 6–7; see Order, 196 FERC ¶ 61,245 at P 166.
PDF page 8
8
Third, even if the Exit Amendment somehow does not concern recovery of
transmission-related costs, at a minimum it “relates to or affects” provisions governing recovery of transmission-related costs, and PJM therefore was required to provide the TOs with 45 days’ notice before filing the Exit Amendment.26 PJM did not do so, opting instead for a truncated CIFP review process that provided a constantly moving target and no adequate notice.27
Because PJM failed to fulfill any of these procedural prerequisites, PJM exceeded its authority in unilaterally submitting the Exit Amendment as a section 205 filing. The sole mechanism by which PJM could have filed this proposal would have been pursuant to section 206—but PJM failed to do so, or to carry the associated burden of showing that the current exit provisions are unjust and unreasonable.
The Order’s suggestion that exit obligations might instead be placed on LSEs28 does not moot this challenge. The Order did not adopt that modification; rather, it accepted the Exit Amendment as filed, anticipated that modifications may be directed after the paper hearing, and encouraged PJM to submit a new filing.29 The Commission should grant rehearing and hold that PJM lacked authority under section 205 to file the Exit Amendment.
26 CTOA § 7.5.1(iv); Protest of the Indicated PJM Transmission Owners at 7–8; see Order, 196 FERC ¶ 61,245 at P 166.27 Protest of the Indicated PJM Transmission Owners at 8. 28 Order, 196 FERC ¶ 61,245 at P 181.29 Id. PP 25, 28, 215(A).
PDF page 9
9
III. CONCLUSION
For the foregoing reasons, the Indicated PJM Transmission Owners respectfully request that the Commission grant rehearing of the Order and definitively reject PJM’s proposed Exit Amendment.
Dated: October 29, 2026
Respectfully submitted,
/s/ Evan K. Dean
Evan K. Dean
Managing Counsel, Transmission Rates &
Services
FirstEnergy Service Company
341 White Pond Drive
Akron, Ohio 44320
Telephone: 330-620-9585
edean@firstenergycorp.com
/s/ Sanford I. Weisburst
Sanford I. Weisburst
Matthew Meyer
Madeleine Fleming
QUINN EMANUEL URQUHART
& SULLIVAN, LLP
295 Fifth Avenue, Ninth Floor
New York, New York 10016
Telephone: 212-849-7000
sandyweisburst@quinnemanuel.com
matthewmeyer@quinnemanuel.com
madeleinefleming@quinnemanuel.com
/s/ Anthony Alden
Anthony Alden
QUINN EMANUEL URQUHART
& SULLIVAN, LLP
865 S Figueroa St, 10th Floor
Los Angeles, CA 90017
Telephone: 213-443-3000
anthonyalden@quinnemanuel.com
Counsel for the FirstEnergy Transmission Companies
/s/ Michael Brechlin
Michael Brechlin
Manager Asst GC - Regulatory Law State
Regulatory
Duquesne Light Company
Nova Place
100 South Commons, Suite 118
Mail Drop OGC-L1
Pittsburgh, PA 15212
Telephone: 412-393-6431
mbrechlin@duqlight.com
Counsel for Duquesne Light Company
PDF page 10
10
CERTIFICATE OF SERVICE
I hereby certify that I have caused the foregoing document to be served upon all the parties listed on the official service list for the above-referenced proceedings, pursuant to the requirements of Rule 2010 of the Commission's Rules of Practice and Procedure. Dated at New York, N.Y., this 29th day of October, 2026.
/s/ Sanford I. Weisburst
Sanford I. Weisburst
QUINN EMANUEL URQUHART
& SULLIVAN, LLP
295 Fifth Avenue, Ninth Floor
New York, New York 10016
Telephone: 212-849-7000
sandyweisburst@quinnemanuel.com