Permitting reform timeline

Dated legislative, legal and agency events, with source records for each event.

Bipartisan American Affordability and Jobs Act of 2026 · Updated 2026-11-18 · Open interactive view

The four sponsors file a managers' amendment, SA 7022

Sen. Lee, for the four sponsors, filed SA 7022 to the substitute. Besides technical corrections it adds landowner notice, land restoration and conduct rules for transmission permits, makes federal permits public, and raises the Historic Preservation Fund from $200 million to $300 million a year.

Text of Amendments, SA 7022

Senate votes 70 to 27 to end debate on the sponsors' substitute, SA 6883

The Senate agreed, 70 to 27, to end debate on the Capito substitute amendment, SA 6883, to H.R. 2347 (roll call vote 264). Three senators did not vote. Sixty votes were needed. Adopting the substitute and passing the bill are separate votes.

Roll Call Vote 119th Congress - 2nd Session, Vote 264 · Monday, November 16, 2026

Thune files cloture on SA 6883 and on H.R. 2347

At 12:29 p.m. Majority Leader Thune filed motions to end debate on the substitute, SA 6883, and on H.R. 2347, the Senate Press Gallery reported.

Wednesday, November 11, 2026

House passes H.R. 5549 and H.R. 9084 by voice vote under suspension of the rules

The House passed H.R. 5549, and H.R. 9084 as amended, by voice vote under suspension of the rules. Both were on the majority leader's November 9 schedule with three nuclear bills passed that day.

H.R. 5549: all actions · H.R. 9084: all actions

All Pueblo Council of Governors restates its opposition after the Senate vote

The All Pueblo Council of Governors, which represents 19 New Mexico Pueblos, said it remains opposed to the bill after the November 9 vote.

All Pueblo Council of Governors condemns US Senate vote advancing permitting reform bill

Senate votes 62 to 21 to take up H.R. 2347

The Senate agreed, 62 to 21, to the motion to proceed to H.R. 2347 (roll call vote 258). Seventeen senators did not vote. The vote was not on passage.

Tuesday, November 10, 2026 · Roll Call Vote 119th Congress - 2nd Session, Vote 258

Thune offers the sponsors' substitute as SA 6883, with amendments SA 6884 to SA 6890

The Senate floor record shows Majority Leader Thune proposed SA 6883, a full substitute, for Sen. Capito, and proposed SA 6884 through SA 6890. He also moved to commit H.R. 2347 to the Finance Committee with instructions to report it back with SA 6888.

Senate Floor Activity - Tuesday, November 10, 2026

House passes H.R. 3978, H.R. 9612 and H.R. 9614 under suspension of the rules

The House passed H.R. 3978, 397 to 2 (roll call 315), and H.R. 9612, 394 to 3 (roll call 316), both as amended and each needing two-thirds. It passed H.R. 9614 by voice vote. The majority leader's schedule had listed these with H.R. 5549 and H.R. 9084; BPC says four bills on the list are incorporated in the Senate bill.

Roll call 315, H.R. 3978 · Roll call 316, H.R. 9612 · H.R. 9614: all actions · Majority Leader weekly schedule · Explaining the Senate Permitting Bill

Senate votes 73 to 25 to end debate on taking up H.R. 2347

The Senate agreed, 73 to 25, to end debate on the motion to proceed to H.R. 2347, the vehicle for the permitting bill (roll call vote 257). Two senators did not vote. Sixty votes were needed.

Monday, November 9, 2026 · Roll Call Vote 119th Congress - 2nd Session, Vote 257

White House issues a Statement of Administration Policy on S. 5653

The Office of Management and Budget's statement on S. 5653, dated November 9, says the administration strongly supports passage and that the President's advisors would recommend he sign the bill.

S. 5653 - Bipartisan American Affordability and Jobs Act of 2026 (Statement of Administration Policy)

Trump says he backs the bill and will not approve wind turbines

President Trump told reporters he was 100 percent behind the permitting bill. Asked about its wind provisions, he said he would not approve wind turbines.

Trump Backs Energy Bill '100%' Before Balking at Wind Turbines · Senate Advances Permitting Overhaul But Roadblocks Loom

Trump posts endorsement of the bill on Truth Social

Per Heatmap, President Trump posted on Truth Social the night before the vote urging all senators to vote for the bill on Monday.

The Senate Prepares for First Vote on Permitting Reform

Sponsors release a 494-page substitute amendment

Sens. Capito, Lee, Whitehouse and Heinrich released an amendment in the nature of a substitute to H.R. 2347, the vehicle for the permitting bill. It edits 43 sections of the September 30 text, adds 13 and drops one; the sponsors' release calls the changes clarifying, conforming and technical edits.

Lee, Capito, Heinrich, and Whitehouse Release Substitute Amendment to Bipartisan American Affordability and Jobs Act of 2026

U.S. Chamber-led coalition letter urges Congress to pass BAAJA

A coalition letter led by the U.S. Chamber of Commerce urges Congress to pass the Bipartisan American Affordability and Jobs Act of 2026 and send it to the President.

Coalition in Support of the Bipartisan American Affordability and Jobs Act of 2026

White House official says Defense Department is advancing nine wind projects

A White House official told Punchbowl News the Defense Department was advancing nine more wind projects held up at the Pentagon, including two in New Mexico, two in Wyoming, two in Texas, and one each in Illinois, Indiana and Kansas.

White House counters Jeffries on permitting

Rep. Sharice Davids issues statement on tribal sovereignty and the bill

Rep. Sharice Davids (D-Kan.) urged lawmakers to advance reform while strengthening tribal protections, in a Nov. 5 statement.

Senators revise permitting bill ahead of Monday vote; tribal concerns remain

Jeffries spokesperson says he will not rubber-stamp the Senate permitting bill

A spokesman for House Minority Leader Hakeem Jeffries said Thursday night that he will not rubber-stamp legislation from the Senate without more constructive involvement with the House Democratic Caucus. A spokesperson for Sen. Whitehouse replied that the committees had solicited input from many House members.

White House counters Jeffries on permitting

Transit association backs the bill over repair delays

The American Public Transportation Association endorsed the bill, citing shorter reviews for repairs to existing transit and passenger rail facilities.

Transit association endorses S. 5653

Four senators seek restored grants ahead of Senate motion to take up permitting reform

Tammy Duckworth, Ron Wyden, Jeff Merkley and Ed Markey asked the bill’s sponsors to secure the release of canceled Energy Department grants before the Senate decides on November 9 whether to end debate on taking up the permitting bill. They did not commit to supporting that motion.

Four senators ask for energy grants to be restored before the vote

Protesters march to Heinrich’s Albuquerque office

Students walked out in Santa Fe and Albuquerque. More than 100 protesters marched to Sen. Martin Heinrich’s Albuquerque office, where speakers objected to the bill’s treatment of Tribal consultation.

New Mexico students walk out over data centers and permitting

Rep. Leger Fernández says she cannot support the bill as written

The New Mexico Democrat, a former vice chair of the Advisory Council on Historic Preservation, cited the bill's changes to the National Historic Preservation Act and Tribal sovereignty.

Statement on X

People's Environmental Justice Caucus opposes the bill

The House caucus founded by Reps. Tlaib, Summer Lee and Grijalva came out against the bill, citing data centers, pipelines and limits on court challenges.

People's Environmental Justice Caucus opposes Senate permitting reform bill

Speaker Johnson says he supports the Senate bill

Asked by Punchbowl News whether he supports the Senate's bipartisan permitting bill, House Speaker Mike Johnson said yes.

Post on Johnson's answer

Pueblo governors meet Heinrich over the historic preservation changes

POLITICO reported a tense meeting between Sen. Heinrich and Pueblo governors; one governor said afterward that the goal is to stop the bill now.

Post on the meeting

API and 137 other organizations ask Congress to pass S. 5653 this year

A coalition from energy, labor, manufacturing, housing and transportation asked House and Senate leaders to bring S. 5653 to the floor and pass it before the end of the year.

Broad coalition of 130+ groups urge Congress to pass permitting reform

Defense Department advances two onshore wind projects

A White House official said the Defense Department advanced wind projects in Maine and South Dakota, with more to come, and that the administration is clearing the way for the bill. Whitehouse called it a start; Heinrich pointed to hundreds of projects still waiting.

Post on the Defense Department wind approvals · Whitehouse reaction

Nine Democratic attorneys general raise concerns about state authority

Attorneys general led by California, Massachusetts and Washington wrote Senate leaders about provisions affecting state authority under the Clean Water Act and the National Historic Preservation Act, and asked for a meeting.

Report of the attorneys general letter

More than 100 groups ask Congress to reject the bill over public lands

A coalition letter asked Congress to reject the bill because of its effects on public lands.

DOJ moves to kill offshore wind permits as Congress weighs permitting bill

Columbia's energy policy center estimates months saved under the bill

Columbia's Center on Global Energy Policy replayed past project reviews under the bill's deadlines and found the largest savings for transmission, while leaving state siting and the FERC backstop out of its replays.

Project timeline savings under BAAJA

Clean energy trade groups endorse the bill in a joint letter

CEBA, ACORE, Advanced Energy United, the American Clean Power Association and SEIA wrote congressional leaders to endorse the bill.

Post on the joint letter

Administration files against New England Wind; Whitehouse warns the deal is at risk

A late filing by the administration targeting the New England Wind offshore project followed similar motions on Revolution Wind and Maryland Offshore Wind. Sen. Whitehouse said it is how to blow up a permitting deal.

Post on the New England Wind filing · Trump administration asks courts to revoke permits for offshore wind farms

All Pueblo Council of Governors adopts a resolution against S. 5653

The council of New Mexico's 19 Pueblo nations unanimously adopted a resolution opposing the bill and said Sen. Heinrich did not consult them before negotiating changes to the National Historic Preservation Act.

APCG Resolution 2026-15 (PDF, posted by NATHPO) · Post on the APCG resolution

19 former economic and national security officials urge passage

A letter to Thune, Schumer, Johnson and Jeffries from 19 former officials who served six presidents, including four Treasury secretaries, asks Congress to pass the bill.

Letter to congressional leaders (PDF)

13 preservation groups ask the sponsors to revise or remove the Section 106 provisions

A coalition including NATHPO, NCSHPO and the National Trust wrote the four sponsors objecting to the historic preservation title and proposing to revisit it next session.

Coalition letter

NCAI's president says the bill needs to be killed over Section 106

Mark Macarro, president of the National Congress of American Indians, called the Section 106 changes an existential threat. Defenders, including Thomas Hochman, answered the October 16 paper the same day.

NCAI calls for the Senate permitting deal to be killed · Thread answering the Cultural Heritage Partners fact check

Tribal groups publish a claim-by-claim rebuttal of the bill's Section 106 defenders

A 17-page paper under the logos of NATHPO, NCAI, AAIA, NARF and Cultural Heritage Partners checks nine claims from the Searchlight memo, IFP and Chairman Lee's office against the bill text. The same day NATHPO told senators that Tribal heritage is not a bargaining chip.

BAAJA's Empty Promises to Tribal Nations: Claim vs. Fact · NATHPO to Senators: “Our Heritage Is Not a Bargaining Chip”

106 Strong coalition launches with 1,000 organizations and asks Congress to reject S. 5653

On the 60th anniversary of the National Historic Preservation Act, the 106 Strong coalition launched with 1,000 organizations and Tribal Nations, by its own count, and delivered a letter urging Congress to reject the Senate bill.

On Historic Preservation Law's 60th Anniversary, 1,000 Organizations Launch Campaign to Defend America's Heritage

U.S. Chamber of Commerce writes the four sponsors to support the bill

Neil Bradley, the Chamber's chief policy officer, wrote Sens. Capito, Lee, Whitehouse and Heinrich, with copies to Thune and Schumer, to say the Chamber supports the bill and wants it sent to the President as soon as possible.

Letter in support of the Bipartisan American Affordability and Jobs Act of 2026

NPR reports on the bill's Section 106 changes; advocates it quotes call them the biggest threat in 60 years

NPR reports on the bill's Section 106 changes on the law's 60th anniversary. It quotes Greg Werkheiser and the National Association of Tribal Historic Preservation Officers' Ira Matt in opposition and says Tribal groups sent Senate leaders a letter the week before.

U.S. historic preservation law faces the most serious threat in its 60-year history

Senate schedule: November 9 decision on ending debate over taking up the permitting bill

The October 15 floor log lists pro forma sessions on October 19, 22, 26, 29, November 2 and November 5. The Senate returns November 9 at 3:00 p.m. and decides whether to end debate on taking up H.R. 2347 at about 5:30 p.m. The log calls H.R. 2347 the legislative vehicle for the permitting reform bill.

Thursday, October 15, 2026

NAM and more than 100 business groups ask Thune and Schumer to bring S. 5653 to the floor

The National Association of Manufacturers and more than 100 manufacturing and business groups wrote Majority Leader Thune and Minority Leader Schumer in support of S. 5653 and asked for immediate floor consideration. The American Supply Association says it signed on.

100+ Manufacturing, Business Groups Urge Congress to Pass Bipartisan Permitting Deal · ASA Supports Bipartisan Permitting Reform to Strengthen U.S. Manufacturing

Rep. Stansbury says she cannot support the bill in its current form

Rep. Melanie Stansbury (D-N.M.) said Tribal sovereignty and consultation are her line in the sand and that she cannot support the bill as written. The day before, she had told Punchbowl she could oppose it.

Rep. Stansbury comes out against the bill

185 groups ask congressional leaders to oppose the bill as a back-door deal for data centers

A coalition of 185 community, labor, climate and environmental justice groups urged congressional leaders to oppose the bill. The Center for Biological Diversity release calls it a back-door deal to build hyperscale AI data centers and fossil fuel infrastructure. The Washington Sun reports the letter went to House Democratic leadership.

185 Groups Slam Permitting Bill's Sweetheart Deal for Data Centers · Permitting Reform Is Scrambling the Left

Trump administration asks a court to re-examine the Revolution Wind permit

The Trump administration asked a court to re-examine a key permit for the Revolution Wind offshore project in Rhode Island. Heatmap reports the move as a risk to the bipartisan permitting deal.

Is Trump Trying to Blow Up the Permitting Deal?

Huffman expects Congress to wait until after the election to consider the permitting bill

In an interview with Heatmap, Rep. Jared Huffman said Congress would wait until after the election to consider the permitting bill. He said its judgment-fund provision could pay developers without approving their projects.

Jared Huffman Wants to See Some Changes to the Senate's Permitting Bill

Capito says the White House made wind and solar concessions to advance permitting reform

Capito told WV MetroNews the White House has made some tremendous concessions on wind and solar projects. She said leaders promised to put permitting reform first when the Senate reconvened.

Capito says permitting bill would blast away delays and protect approved projects

NARF and eight other Tribal organizations ask Senate leaders to remove sacred-places provisions

In an October 9 letter, the Native American Rights Fund and eight other Tribal organizations asked Senate leaders to remove provisions that weaken protections for sacred places and to consult Tribal Nations. NARF's alert says that, as it understands it, input must be received by October 23. It names no official source for that date.

ACT NOW: Senate Permitting Reform Bill Negatively Impacts Tribes · U.S. historic preservation law faces the most serious threat in its 60-year history

Lee says he is confident the Senate will pass the bill in a November lame-duck session

The Daily Caller News Foundation, citing the AP, reports that Sen. Mike Lee is confident the Senate will pass the bill in a lame-duck session in November.

Senators Want To Make AI Data Centers Pay For The Grid Upgrades Driving Up Your Electric Bill

House Energy and Commerce Chair Guthrie says he wants changes to the bill's grid section

Speaking at the Punchbowl Tech Summit, Rep. Brett Guthrie said he would love to see changes to the grid section of the Senate bill. Punchbowl reporter Joshua Siegel posted the remark on X.

X post by Joshua Siegel quoting Brett Guthrie

More than 200 conservation groups ask Congress to oppose the bill over its Endangered Species Act title

More than 200 conservation groups sent a letter urging Congress to oppose the bill. The Center for Biological Diversity and Friends of the Earth issued the release, which objects to the bill's changes to best available science and to state-run Section 7 consultations.

Hundreds of Organizations Oppose Endangered Species Attacks in Permitting Legislation

More than 200 environmental and local groups ask Democratic leaders to hold the bill until next Congress

A letter to Schumer and Jeffries, published by Punchbowl News, argues the environmental cost of the rollbacks outweighs the emissions benefits and that a better package is likely after the midterms. Signers include the Center for Biological Diversity, Food & Water Watch, Friends of the Earth Action and Greenpeace USA.

Broad Environmental Coalition Urges Opposition to Permitting Reform Package

Blue Dog Coalition asks both chambers to pass the permitting bill in November

The House Blue Dog Coalition backed the Senate-negotiated bill, citing the parts that came from the SPEED Act, and asked House and Senate leaders to bring the permitting bill to the floor in November. The statement names no individual member.

Blue Dog Statement on Bipartisan Permitting Reform Agreement

Blunt Rochester and Curtis introduce two Senate bills on data center disclosure

Senate version of the transparency bill, plus a DOE technical-assistance program for communities. House companion led by Rep. Menendez.

Senators Blunt Rochester, Curtis Introduce Bills to Help Public Understand Impacts of Data Centers

Markey says he is still reviewing the text and takes no position

Sen. Edward Markey issued a statement saying he was still reviewing the text and would look closely at the details. He warned against locking in more fossil fuels and locking out communities.

Senator Markey Statement on Bipartisan Permitting Reform Proposal

22 Republican governors urge Congress to pass the permitting bill

Montana Gov. Greg Gianforte and 21 other Republican governors issued a joint statement asking Congress to pass permitting reform and send the legislation to President Trump. The statement names the Bipartisan American Affordability and Jobs Act. The Senate EPW majority's October 7 roundup describes it as a statement from 21 governors.

Gianforte urges Congress to pass federal permitting reform · What They're Saying: Bipartisan Permitting Reform Will Deliver Cheaper Energy, More Jobs, Responsible Growth

Senate sets November 9 decision on ending debate over taking up permitting reform

The Senate's floor schedule set November 9 for a decision on whether to end debate on taking up H.R. 2347, the Survivor Justice Tax Prevention Act, which the Senate Press Gallery describes as the legislative vehicle for the permitting reform bill. The procedural decision is scheduled for about 5:30 p.m.; passing the bill would require a separate vote.

Thursday, October 1, 2026

Huffman says most House Democrats oppose the Senate permitting deal as written

House Natural Resources ranking member Jared Huffman said most House Democrats will not back the Senate bill as written. He urged resuming talks after the midterms, expecting a better negotiating position. POLITICO reported that Energy and Commerce Chair Brett Guthrie had not endorsed it either.

Senate bipartisan permitting deal faces a House buzz saw

Senate leaders release the 417-page Bipartisan American Affordability and Jobs Act

Sens. Capito, Lee, Whitehouse and Heinrich released the 417-page bill at a press conference. It sets a 150-day limit for NEPA claims, bars agencies from revoking issued permits except in listed cases (Sec. 1401), and requires data centers to pay their transmission costs. Wind and solar 'regular order' terms remain under negotiation with the White House, with amendment work in parallel and sponsors hoping the Senate would take up the bill in November. In the House, Natural Resources ranking member Jared Huffman said most Democrats would not support the bill as written, and Energy and Commerce Chair Brett Guthrie had not endorsed it.

Bipartisan American Affordability and Jobs Act of 2026 (bill text, 417 pages) · Senate unveils bipartisan deal tackling energy and data centers, but wind and solar questions remain · Senate bipartisan permitting deal faces a House buzz saw

Senate falls three votes short of ending debate on taking up the Ratepayer Protection Act

The Senate voted 57-43 to end debate on whether to take up H.R. 9340, the Ratepayer Protection Act. The motion needed 60 votes and failed. The Senate did not vote on passage. Sen. Jon Husted (R-Ohio) had sought unanimous consent on September 17, when Sen. Martin Heinrich objected, arguing that Congress needs legislation that requires, not merely asks states to consider, that data centers pay for grid upgrades. Democratic Sens. Ossoff, Warnock, Klobuchar and Hassan voted yes with all Republicans.

Roll Call Votes, 119th Congress, 2nd Session (Vote 254, September 30, 2026) · Senate Fails To Advance GOP-Led Data Center Bill That Had No Teeth · Capitol agenda: One day more? (Inside Congress live updates)

FERC accepts but suspends PJM reliability backstop procurement for five months

FERC found cost allocation, transmission owner exit rules and load-serving entity collateral may be unjust and unreasonable and suggested fixes. New effective date 2027-02-28. PJM pulled its 2026-09-30 auction.

FERC Suspends PJM's Backstop Procurement Five Months and PJM Pulls Its September 30 Auction · FERC chair slams PJM 'mess' as country's largest grid operator delays power auction · FERC Accepts PJM Reliability Backstop Proposal

Wind developers tell the Oregon court the Pentagon can clear projects as part of the permitting deal

In the Oregon case over the Defense Department's hold on wind airspace reviews, developers filed a response saying that if the Pentagon could approve projects with mitigation agreements awaiting countersignature in a permitting deal, it was unclear why it could not approve them to comply with the court's order.

The Senate's Big Bipartisan Permitting Deal, Explained

Senate permitting talks stall; senators expect to take up a deal after the midterms

Roll Call and Deseret News reported that Senate permitting talks had stalled and the Senate would likely wait until after the midterms to consider a permitting deal. Whitehouse said negotiators were 'over the hump on the deal-break issues' and that colleagues' feedback could go into a manager's amendment, but wanted clarity on 'regular order' for wind and solar; Thune and Barrasso accused Democrats of backing away. POLITICO reported that Democrats wanted strong interstate transmission measures and limits on the administration's power to cancel projects, and Republicans wanted to limit state reviews under Clean Water Act section 401.

Permitting reform talks fall apart in the Senate, deal punted until after midterms · Permitting bill off until after midterms even as talks close in · Permitting won't get vote ahead of election

Trump tells advisers he will direct Defense to clear its wind queue to close a permitting deal

POLITICO Pro reported that Trump told Burgum, Wright and other advisers on Sept. 21 he would direct the Defense Department to start clearing its queue of delayed onshore wind projects to strike a deal. Thune had set a Tuesday deadline for a deal. Heatmap reported on Sept. 25 that Wright would not confirm the report, and that the White House had signaled the concession might lapse after November.

Trump will green-light wind energy projects to strike permitting deal · Offshore Wind's Existential Crisis at Climate Week

Capito and Whitehouse say permitting talks are in their final stages

Capito said a deal was very close and Whitehouse said talks were in final wrap-up, with the hardest issues resolved last. Capito said Senate consideration of the permitting deal could slip into the third week of the work session, later than the timeline she and Thune had set.

Permitting talks reach 'final' stages

Heinrich blocks Ratepayer Protection Act by unanimous consent; Moreno blocks Heinrich's GRID Savings Act request

Heinrich said the Husted bill falls short and asked to pass his GRID Savings Act instead. Sen. Bernie Moreno (R-OH) objected.

Senate Democrat blocks House-passed bill to shield Americans from data center energy costs, proposing alternate measure

House passes the Ratepayer Protection Act 417-3 on data-center electricity costs

The House passed the Ratepayer Protection Act, introduced by Rep. Gabe Evans (R-Colo.), by 417-3 under a fast-track procedure requiring two-thirds. The bill encourages state utility regulators to set standards so large-load customers such as data centers pay for the new generation and infrastructure they require. House Minority Leader Hakeem Jeffries called it 'a step forward' that needed more.

House passes bill to shield Americans from data center energy costs · Husted bill to protect Americans from footing the bill for new data centers blocked from passage

Energy and Commerce reports H.R. 9340 (H. Rept. 119-814)

The reported version carries the data-center-only definition and added cosponsors.

H.R. 9340 (RH) text

House passes the Protecting Domestic Mining Act 218-201, writing mining into FAST-41

The House passed H.R. 1501, sponsored by Rep. Jefferson Shreve (R-Ind.), 218-201. It writes mining and mineral processing into law as a sector eligible for FAST-41, the Permitting Council's coordinated review program, and blocks a Biden-era proposed rule that would have limited that coverage to critical minerals. Rep. Adelita Grijalva (D-Ariz.) opposed it; her amendment requiring consultation with Tribal Nations before expedited permitting was not adopted. The Senate referred it to the Homeland Security and Governmental Affairs Committee on September 14.

H.R.1501 - Protecting Domestic Mining Act of 2025: All Actions · Representatives Moore, Shreve's Protecting Domestic Mining Act Passes the House · Rep. Grijalva Slams Bill to Fast-Track Mining Permits

Oregon federal judge temporarily orders Pentagon to complete stalled onshore wind reviews

A federal judge in Oregon granted renewable energy groups' motion to temporarily force the Defense Department to finish its reviews of stalled onshore wind projects. Heatmap reported on Aug. 6 that Judge Karin Immergut had said at an Aug. 4 hearing there was strong evidence the government broke statutory and regulatory deadlines.

Senators outline future of permitting talks · Trump May Be Forced to Resume Wind Project Permits

Negotiators move their permitting deal target to September

After a Tuesday meeting of Capito, Lee, Whitehouse and Heinrich, Whitehouse said negotiators were aiming for September, when the Senate returns from a five-week recess.

It's official: Permitting deal won't happen this week

Heinrich introduces GRID Savings Act (S. 5199)

Bill would add Federal Power Act section 224, giving FERC jurisdiction over interconnection of loads of 150 MW or more and requiring a final rule within a year that assigns interconnection and direct-assignment costs to the large load and requires financial security.

Heinrich Introduces Legislation to Ensure Large Users of Electricity Pay for Grid Upgrades · One Senate Democrat's answer to Trump's 'ratepayer protection pledge' · S. 5199 (IS) text

Trump expands Ratepayer Protection Pledge to governors, legislators, developers and power providers

At EPA headquarters, the President announced the expansion; EPA says the Pledge will cover 80 percent of power delivered to homes and businesses.

President Trump Expands Historic Ratepayer Protection Pledge to Protect American Ratepayers, Lower Electricity Prices

D.C. Circuit rejects NEPA challenge to New Haven airport expansion, citing Seven County

In Save the Sound v. FAA, a D.C. Circuit panel of Chief Judge Srinivasan and Judges Wilkins and Katsas denied petitions challenging the FAA's environmental assessment and finding of no significant impact for a Tweed New Haven Airport expansion. Judge Katsas's opinion applied Seven County's call for a modest judicial role and deference to reasonable agency judgments.

Save the Sound, Inc. v. FAA, No. 24-1028 (slip opinion) · Court upholds Tweed New Haven airport expansion approval

House Energy and Commerce approves Ratepayer Protection Act 52-0, narrowed to data centers

Committee adopted an Evans substitute by voice vote that limited the definition to data centers at 100 MW or more, then approved the bill 52-0. The Data Center Coalition objected that the change singled out data centers; steel and industrial customer groups backed it.

House committee narrows data center energy bill · Data center lobby grumbles about reworked Ratepayer Protection Act · House Energy and Commerce Advances Energy Bills ... Ratepayer Protection Act Clears 52-0

Rep. Donalds introduces Protecting Ratepayers Act (H.R. 9777)

Would bar new and existing data centers of 5 MW or more from using the grid or public water and would give the Ratepayer Protection Pledge proclamation the force of law.

H.R. 9777 (IH) text · Byron Donalds, running for Florida governor, announces data center legislation

Six grid operators file large-load informational reports at FERC

Each RTO/ISO described its plan for resource adequacy for large loads, a first step under the June 18 show cause orders. Substantive responses were due August 17.

RTOs and ISOs Answer: A National Preview of How All Six Grid Operators Plan to Respond to the Large Load Surge

State ratepayer advocates say FERC's PJM show cause order leaves data center transmission costs with other customers

Advocates from Delaware, Illinois, Maryland, Ohio and Pennsylvania filed at FERC, arguing the order does not fix cost allocation of network upgrades for large loads.

FERC fails to shield PJM consumers from data center transmission costs: ratepayer advocates

Heinrich introduces connect-and-manage interconnection bill

Heinrich introduced a bill that lets new power plants of any type opt into a faster safety study and 'basic access service for energy-only delivery,' as Texas does, instead of waiting for full interconnection studies and paying for network upgrades. Plants would curtail output when the grid is congested.

Scoop: A Key Democrat Wants to Break America's Worst Energy Bottleneck

Sen. Husted introduces Senate companion S. 5028

Sen. Jon Husted (R-OH) introduced S. 5028, the Senate version of the Ratepayer Protection Act. Referred to Energy and Natural Resources.

S. 5028 (IS) text

Republicans reported to have made a broad permitting offer to Democrats before the July Fourth recess

E&E News reported on July 13, citing a Democrat close to the talks, that Republicans made a broad offer before the recess covering faster environmental and historic preservation reviews, some transmission permitting and GOP priorities. Democrats were reviewing it and pressing for transmission measures and limits on canceling approved permits.

Where the permitting talks stand

EPA draft rule would end federal public-notice requirement for minor New Source Review permits

EPA's draft rule would no longer require states and tribes to give notice and take comment before permitting 'minor' pollution sources. Advocates said it could let states permit data centers and power plants without informing nearby communities.

EPA proposal could sideline the public on data center permits

Nearly 60 groups urge Senate EPW not to limit state and tribal Section 401 reviews

National and regional groups sent a letter to the Senate Environment and Public Works Committee opposing limits on state and tribal review of water quality impacts under Clean Water Act Section 401. Republicans and the administration say blue states have used Section 401 to slow or block energy projects.

Groups urge lawmakers to protect state water reviews in permitting talks

CEQ withdraws 18 NEPA guidance documents, including Forty Questions and 1997 EJ memo

A Federal Register notice signed by CEQ Chairman Katherine Scarlett withdrew nine previously published guidance documents and nine agency memoranda, effective June 29, 2026, as obsolete after CEQ's rescission of its NEPA regulations, NEPA amendments, revoked executive orders and case law. They include the 1981 'Forty Most Asked Questions,' the 1997 environmental justice guidance and the June 2024 memo on the Phase 2 rule; CEQ will review whether any should be reissued.

Notification of Withdrawal of Guidance Documents (91 FR 39086) · CEQ Rescinded Rule Implementing NEPA

EPA proposes changes to its NEPA procedures

EPA proposed to conform its NEPA procedures to the 2023 Fiscal Responsibility Act (two-year, 150-page limits on impact statements), add the 2025 fee for expedited reviews, and apply last year's Supreme Court ruling narrowing the scope of review.

EPA floats changes to NEPA implementation rules

Pallone calls for a national data center moratorium

Energy and Commerce ranking member Frank Pallone called for a nationwide moratorium on new data centers, saying the bills before the committee were 'not nearly enough.' Castor did not support a moratorium; Chair Guthrie's office called it 'not the answer.' AOC formally introduced a moratorium bill.

Data center energy bill hits speed bump

FERC issues show cause orders to all six RTOs on large-load interconnection

In place of a single national rule, FERC voted unanimously on June 18, 2026 to issue Section 206 show cause orders to PJM, MISO, SPP, CAISO, ISO-NE and NYISO, preliminarily finding their tariffs may be unjust and unreasonable for lacking clear large-load and co-location provisions. Responses were due in 60 days, with generation-adequacy reports due in 30 days; DOE had asked for final action on its October 2025 proposal by April 30. All five commissioners backed the orders. The orders cover five areas: study rules, safeguards against cost shifts, co-location, flexible service and generation near load.

FERC Issues Large Load Interconnection Show Cause Orders to Each RTO/ISO · FERC Targets Large Load Interconnection Rules Across All Regional Grid Operators · FERC Has a New Plan for Data Centers

Reps. Evans and Castor introduce the Ratepayer Protection Act (H.R. 9340)

H.R. 9340 would add a PURPA 111(d) standard for large loads of 100 MW or more: full incremental upgrade costs recovered from the customer, with financial assurances. Referred to Energy and Commerce.

H.R. 9340 (IH) text

Senate Armed Services releases NDAA with King amendment on Pentagon wind reviews

The committee released its fiscal 2027 defense bill with an amendment by Sen. Angus King to curb the Pentagon's delay in processing wind project permits. Chair Roger Wicker said the dispute needed to be resolved and that there was bipartisan support.

Senate releases NDAA with permitting amendment

Cortez Masto and Cotton release Senate FREEDOM Act on permit certainty

Sens. Catherine Cortez Masto (D-Nev.) and Tom Cotton (R-Ark.) released a Senate version of the FREEDOM Act. It would keep future presidents from interfering with permitted energy projects. Unlike the House bill it drops the de-risking compensation program, lets a court appoint a contractor to finish a stalled permit, and covers projects on the Outer Continental Shelf.

Freedom (It Won't Slow You Down)

Interior drops appeal of ruling voiding the wind freeze; First Circuit dismisses case

The Justice Department moved on June 10 to voluntarily dismiss its appeal of the December 8 New York v. Trump ruling, and the First Circuit granted the request on June 15. Interior gave no explanation in its filing; the attorneys general in the 18-member coalition led by New York called the outcome a win.

States claim victory as Trump admin ends wind court fight · Trump Administration Abandons Fight Against Wind Energy As Clean Energy Output Surges

Capito and Whitehouse tell the White House at POLITICO's Energy Summit to stop attacking renewables

Both EPW leaders said the administration's moves against offshore wind and clean energy approvals put a permitting deal at risk. Whitehouse said it was hard to ask his caucus to trust the administration. The White House energy council's director said Democrats were blocking gas pipelines.

Special edition: POLITICO's Energy Summit kicks off hot permitting summer

E&E News reports Lee's push to change the preservation law is tripping up permitting talks

E&E News reported that Lee wanted to change the National Historic Preservation Act to speed energy projects on federal land, prioritizing limits on lawsuits. Some Democrats were wary because the law matters to tribes and preservation groups. Heinrich said he wanted to keep the law's intent while making reviews more predictable.

Debate over preservation law tripping up permitting talks

Wright dines with Republican lawmakers on permitting after a dinner of the four Senate negotiators

A Monday dinner organized by Sen. Hickenlooper brought together Capito, Lee, Whitehouse and Heinrich; on Tuesday Energy Secretary Chris Wright dined with Republican lawmakers. Whitehouse said Democrats would decide within their caucus whether to back a permitting deal before bringing one to the floor.

Wright meets with Republicans on permitting, but deal remains elusive as ever

Burgum says Interior will appeal wind/solar injunction; Democrats link July memo to deal

Testifying to the House Natural Resources Committee, Interior Secretary Burgum said the administration would appeal Judge Casper's April injunction, rejecting its 'whole premise.' Rep. Susie Lee (D-Nev.) told him that rescinding the July 15 memo would let Congress pass permitting reform this Congress, and Latitude Media reported that two key senators had made their support conditional on Interior approving wind and solar projects after the ruling.

Burgum: DOI will fight judge's ruling lifting renewable energy blockade

Judge Casper preliminarily enjoins five directives on federal wind and solar permitting

Chief Judge Denise Casper of the U.S. District Court for the District of Massachusetts preliminarily enjoined five agency actions as likely violating the Administrative Procedure Act: Interior's July 15, 2025 secretary-review memo, a Fish and Wildlife Service database restriction, Secretarial Order 3438's capacity-density standard, an Army Corps memo and an Interior offshore order. Regional clean energy trade groups brought the case; the relief is limited to the plaintiffs and their members.

A judge blocked Trump's clean energy blockade. Are projects out of limbo? · Federal Court Blocks Trump Administration Policies Restricting Wind and Solar Permitting

CEQ issues new categorical exclusion guidance, replacing its 2010 guidance

CEQ's April 9, 2026 memorandum on establishing, revising, adopting and applying categorical exclusions replaced the December 2010 guidance, which had rested on CEQ's now-removed 1978 regulations. It tells agencies to create categorical exclusions for categories of actions that normally lack significant effects, adopt other agencies' exclusions where appropriate, and consider exclusions before developing an EA or EIS.

Implementation of the National Environmental Policy Act Guidance (categorical exclusions, notice of availability)

Tonko introduces House companion H.R. 8241

Rep. Paul Tonko introduced the House version of the Power for the People Act with Rep. Kathy Castor and others.

H.R. 8241 (IH) text

Senate ENR hearing on the bulk power system takes up transmission and data centers

The Energy and Natural Resources Committee, chaired by Mike Lee with Martin Heinrich as ranking member, held a hearing on the state of the grid. Heinrich questioned witnesses from the Niskanen Center, the Cato Institute and the Electric Power Supply Association on interregional transmission and data-center costs, shortly after Democrats floated draft legislation to speed new transmission lines.

Heinrich Questions Experts on the Power Grid, Highlighting Need to Expand Transmission and Efficiently Power Data Centers to Help Lower Costs for Consumers · Senate lawmakers debate ideas for grid upgrades

Interior and TotalEnergies sign deal to cancel two offshore wind leases; talks continue

At CERAWeek, Interior Secretary Burgum and TotalEnergies signed settlements ending its Carolina Long Bay and New York Bight offshore wind leases; TotalEnergies recovers its lease fees and invests an equal amount in U.S. gas and LNG. Sen. Whitehouse called the deal 'not good' but stopped short of declaring permitting talks off again.

United States: TotalEnergies Signs Agreements with U.S. Department of Interior to End its U.S. Offshore Wind Projects · Why Democrats aren't pulling the plug on permitting talks

Administration does not appeal ruling against the Revolution Wind stop-work order

The Justice Department let its deadline pass without appealing a federal injunction against Interior's order to stop work on Revolution Wind. Whitehouse had said any appeal would be inconsistent with progress on permitting reform; the White House said it looked forward to ultimate victory on the issue.

Permitting talks live on as DOJ declines to appeal ruling favoring Revolution Wind

Whitehouse and Heinrich reopen permitting negotiations, warning against 'further mischief'

In a joint statement, Heinrich and Whitehouse said that after talking with colleagues they had decided to reopen negotiations on permitting reform, citing positive developments from the administration. They said they expect no further interference with permitted wind projects and faster solar approvals, and warned that continued permit approvals were critical to keeping talks going.

Heinrich and Whitehouse Joint Statement on Permitting Reform · Why Democrats aren't pulling the plug on permitting talks

Seven hyperscalers sign White House Ratepayer Protection Pledge

Amazon, Google, Meta, Microsoft, OpenAI, Oracle and xAI signed. President Trump issued a proclamation saying the Pledge effectuates national policy. The Federal Register published it on 2026-03-09 (91 FR 11439).

Ratepayer Protection Pledge · Ratepayer Protection Pledge Proclamation · Ratepayer Protection Pledge

Permitting Council signs first state FAST-41 agreements with Idaho and Tennessee

Permitting Council Executive Director Emily Domenech, at an event hosted by Interior Secretary Burgum, signed memorandums of understanding with Idaho Gov. Brad Little and Tennessee Gov. Bill Lee committing the states to opt in to FAST-41 and align state and federal environmental review timelines. Iowa became the eighth such state in August 2026.

Permitting Council Announces Latest Federal-State Agreements to Streamline Permitting · Gov. Reynolds, Permitting Council announce agreement to streamline permitting

Hawley and Blumenthal introduce the GRID Act (S. 3852)

Bill would require data centers of 20 MW or more to run off the grid within 180 days, give existing sites 10 years via annual Zero Rate Effect Certificates, and set public reporting rules.

S. 3852 (IS) text · Hawley, Blumenthal Introduce Bill to Prevent Data Centers from Increasing Electricity Costs for Americans

House members introduce FREEDOM Act to bar presidents from revoking permits

Reps. Josh Harder, Adam Gray, Mike Lawler, Don Bacon and Chuck Edwards introduced the 77-page FREEDOM Act. It would bar agencies from terminating or revoking a fully permitted project except to prevent clear and immediate harm, and set up a De-Risking Compensation Fund.

Scoop: New Bipartisan House Bill Would Keep President From Yanking Permits

Senate EPW permitting hearing: Whitehouse ties progress to administration's wind policy

The Senate Environment and Public Works Committee held 'Hearing to Examine the Federal Environmental Review and Permitting Processes, Part II,' with witnesses from Business Roundtable, LIUNA, API, SEIA and NASEO. Chairman Capito said she called it to get talks back on the path to compromise; Ranking Member Whitehouse said reviving a deal depended on 'credible confidence that the nonsense will stop.'

Hearing to Examine the Federal Environmental Review and Permitting Processes, Part II · Republican, Democratic senators call for project certainty at permitting reform hearing

EPA proposes revised Clean Water Act Section 401 certification rules

EPA's proposed rule 'Updating the Water Quality Certification Regulations' (91 FR 2008, published January 15, 2026) would revise 40 CFR part 121 on the scope of certification, the contents of requests and decisions, and withdrawal and resubmittal of requests. Comments closed February 17, 2026; the proposal followed a July 2025 request for input on the 2023 rule and EPA's May 2025 memo on the limits of Section 401.

Updating the Water Quality Certification Regulations (proposed rule, 91 FR 2008) · EPA Reinforces Alignment of Clean Water Act Section 401 with 'Powering the Great American Comeback' Initiative

Van Hollen introduces Power for the People Act (S. 3682)

Bill would have FERC require data center load queues and local transmission cost allocation, and have states consider data-center rate classes. Eight Democratic cosponsors.

S. 3682 (IS) text · Van Hollen Leads New Bill to Ensure Americans Aren't Footing the Bill for Big Data Centers

Federal judges enjoin all five offshore wind stop-work orders between Jan. 12 and Feb. 2

Judge Royce Lamberth enjoined the December 22 order for Revolution Wind on January 12, Judge Carl Nichols did so for Empire Wind on January 15, and Judge Jamar Walker for Coastal Virginia Offshore Wind on January 16. Vineyard Wind won an injunction on January 27 and Sunrise Wind on February 2, so all five projects could resume construction while the suits continue.

UPDATED: Court Lifts Stop-Work Orders for Three Paused Offshore Wind Projects · Republican, Democratic senators call for project certainty at permitting reform hearing

CEQ finalizes removal of its NEPA regulations, adopting the 2025 interim rule unchanged

CEQ published a final rule (91 FR 618), effective January 8, 2026, adopting its February 2025 interim final rule without changes and responding to public comments. It confirms removal of all versions of CEQ's NEPA regulations from the CFR.

Removal of National Environmental Policy Act Implementing Regulations (final rule, 91 FR 618) · CEQ Rescinded Rule Implementing NEPA

Menendez and Casar introduce Data Center Transparency Act (H.R. 6984)

Would require EIA to collect data center energy use every 6 months and EPA to report quarterly on water and emissions.

H.R. 6984 (IH) text

Interior pauses leases for five offshore wind projects under construction

Interior announced it was pausing, effective immediately, the leases for all large-scale offshore wind projects under construction: Vineyard Wind 1, Revolution Wind, Coastal Virginia Offshore Wind, Sunrise Wind and Empire Wind 1, together about 7 GW. It cited national security risks, including radar interference, identified in classified Department of War reports.

The Trump Administration Protects U.S. National Security by Pausing Offshore Wind Leases · Senate Democrats end permitting reform talks over offshore wind freeze

Senate Democrats Whitehouse and Heinrich end permitting talks over offshore wind halt

Sens. Sheldon Whitehouse (D-R.I.) and Martin Heinrich (D-N.M.), the ranking members of the EPW and ENR committees, announced they were ending permitting reform discussions after the administration halted five offshore wind projects. They said talks could resume only if the attacks on fully permitted projects were reversed, and thanked Sens. Capito and Lee for good-faith negotiating.

Senate Democrats end permitting reform talks over offshore wind freeze · Why Democrats aren't pulling the plug on permitting talks

House passes the SPEED Act 221-196 after text changes demanded by offshore wind opponents

The House passed H.R. 4776 on Roll Call 356 by 221-196: 210 Republicans and 11 Democrats voted yes, 195 Democrats and one Republican voted no. Before the House voted on the rules for debating the SPEED Act, leaders agreed to text exempting agency decisions since January 20, 2025 to reopen permits from the bill's anti-revocation language, at the urging of offshore wind opponents including Reps. Andy Harris and Jeff Van Drew.

Roll Call 356, H.R. 4776 (SPEED Act), On Passage · How Republicans saved the 'SPEED Act' from oblivion

House passes the PERMIT Act 221-205 after unanimously passing the ePermit Act

The House passed the PERMIT Act (H.R. 3898), which makes more than a dozen Clean Water Act changes and limits states' authority to block infrastructure, by 221-205; six Democrats voted yes and one Republican voted no. Two days earlier it passed the ePermit Act (H.R. 4503) unanimously, and smaller NEPA and pipeline-review bills also passed in the preceding weeks.

Clean Water Act permitting bill clears the House · Johnson's Bipartisan Digital Permitting Bill Passes U.S. House

Heinrich, Whitehouse and Schatz publicly oppose passing the House SPEED Act

In an exclusive joint statement to Heatmap News, Senate ENR ranking member Martin Heinrich, EPW ranking member Sheldon Whitehouse and Sen. Brian Schatz (D-Hawaii) came out against passing the SPEED Act, citing how it would apply to renewable energy and transmission. Schatz also criticized American Clean Power for backing the bill without transmission provisions.

Exclusive: Key Senate Democrats Oppose Permitting Bill · Lawmakers question clean energy group's tactics on permitting

Federal judge vacates Trump's wind permitting freeze as arbitrary and capricious

In New York v. Trump, Judge Patti Saris of the U.S. District Court for the District of Massachusetts ruled the January 20 wind memorandum 'arbitrary and capricious and contrary to law' and set it aside. Seventeen states led by New York Attorney General Letitia James had sued in May 2025.

Trump ban on wind power projects overturned by federal judge · Federal Judge Vacates Trump Administration's Halt to Wind Energy Permitting

House Natural Resources Committee advances the SPEED Act 25-18

The committee advanced H.R. 4776 by 25-18 after debating dozens of amendments; only Chairman Westerman's substitute and Rep. Golden's amendment were adopted. Golden's amendment bars revocation of project authorizations except by court order or at the sponsor's request. Many Democrats cited Interior's policy requiring Secretary Burgum's personal approval of wind and solar projects as their reason for opposing the bill.

House Natural Resources Committee Passes SPEED Act · Golden's bipartisan permitting reform bill passes House Natural Resources Committee

DOE directs FERC to start a large-load interconnection rulemaking for data centers

Energy Secretary Chris Wright used Section 403 of the DOE Organization Act to send FERC an advance notice of proposed rulemaking on interconnecting retail loads above 20 MW to transmission facilities, and asked for final action by April 30, 2026. The proposal would make large loads pay for the network upgrades they trigger.

DOE Directs FERC to Take Action on Large Load Interconnection · Secretary of Energy Directs FERC to Initiate Rulemaking to Expedite Data Center and Large Load Interconnection

Whitehouse says it makes little sense to pursue permitting reform if the administration won't faithfully execute it

At an EPW hearing, Whitehouse called the administration's attacks on wind and solar 'gangster Gong Show stuff' and asked why Democrats would negotiate on permitting while it ignored congressional mandates. He cited Revolution Wind, the Energy Department's project kill list and a revoked Nevada solar approval.

Whitehouse threatens to blow up permitting talks

CEQ issues updated NEPA guidance and a template for agency NEPA procedures

CEQ's September 29, 2025 memorandum 'Implementation of the National Environmental Policy Act' updated and replaced its February 19, 2025 guidance and attached a template agencies could use to write or revise NEPA procedures. Harvard's tracker reports it tells agencies to consider only the proposed action at hand, citing Seven County, and explains the new opt-in fee process.

Implementation of the National Environmental Policy Act Guidance (notice of availability) · CEQ Rescinded Rule Implementing NEPA

Judge Lamberth enjoins the Revolution Wind stop-work order

Judge Royce Lamberth of the U.S. District Court for the District of Columbia granted Revolution Wind a preliminary injunction against the August stop-work order, finding the project likely to succeed on the merits and likely to suffer irreparable harm. Orsted said construction would resume as soon as possible.

Revolution Wind to resume construction after judge grants injunction · UPDATED: Court Lifts Stop-Work Orders for Three Paused Offshore Wind Projects

BOEM orders Revolution Wind to halt all offshore activity at about 80% completion

BOEM's Acting Director issued a Director's Order requiring Orsted's Revolution Wind to halt all ongoing outer continental shelf activities while Interior reviewed concerns under the January 20, 2025 wind memorandum, citing national security and interference with other ocean uses. The 700-MW project off Rhode Island was roughly 80% complete.

Director's Order to Revolution Wind, LLC (August 22, 2025) · Orsted's Revolution Wind Project Hit with Federal Stop-Work Order at 80% Completion

Westerman and Golden introduce the SPEED Act (H.R. 4776) to rewrite NEPA

House Natural Resources Chairman Bruce Westerman (R-Ark.) and Rep. Jared Golden (D-Maine) introduced the Standardizing Permitting and Expediting Economic Development (SPEED) Act. The bill clarifies what counts as a 'major federal action,' simplifies NEPA documents and sets judicial review limits including a 150-day deadline for filing claims.

Westerman and Golden Introduce Bipartisan Permitting Reform Legislation · Golden introduces permitting reform bill with Natural Resources Committee Chairman Westerman

EO 14318 directs faster federal permitting for data centers and their power supply

EO 14318 defined a 'Data Center Project' as a facility needing more than 100 MW of new load for AI uses and told agencies to speed environmental reviews, including by identifying existing categorical exclusions and working with CEQ on new ones. It also called for FAST-41 transparency-project status through the Permitting Council and revoked Biden's EO 14141 on AI infrastructure.

Accelerating Federal Permitting of Data Center Infrastructure (Executive Order 14318) · Accelerating Federal Permitting of Data Center Infrastructure (90 FR 35385)

Interior memo routes every wind and solar decision to the Secretary for final review

An Interior memorandum dated July 15, 2025 required all department decisions, actions, consultations and undertakings on wind and solar facilities to go through the Executive Secretariat and Regulatory Affairs, then the Office of the Deputy Secretary, with final review by the Secretary's office. Interior published it on July 17.

Department of the Interior Issues Flurry of Actions Targeting Wind and Solar Energy Projects · Trump targets solar and wind with tighter federal permitting in another blow to renewable industry

One Big Beautiful Bill Act adds a paid, faster NEPA review option (Sec. 60026)

Public Law 119-21, signed July 4, 2025, added NEPA Section 112 through Sec. 60026: a project sponsor can pay a fee of 125 percent of anticipated costs to have an environmental assessment finished within 180 days of payment or an EIS within one year of the notice of intent. Sec. 60023 rescinded unobligated environmental review implementation funds, and the law also ended key wind and solar tax incentives.

Public Law 119-21 (One Big Beautiful Bill Act), Sec. 60023 and Sec. 60026 · Trump targets solar and wind with tighter federal permitting in another blow to renewable industry

Interior, DOE, USDA, DOT and Army Corps replace NEPA rules with streamlined procedures

Following CEQ's rescission, the Departments of the Interior, Energy, Agriculture, Transportation (FHWA, FRA, FTA), Commerce and Defense, including the Army Corps, published interim final rules or new procedures on July 3, 2025; several moved most NEPA procedures into non-binding guidance. FERC's revised NEPA rules took effect August 18, 2025.

National Environmental Policy Act Implementing Regulations (Interior interim final rule, 90 FR 29498) · Agencies Significantly Narrowed NEPA Requirements, Changes Effective Immediately

Supreme Court decides Seven County v. Eagle County, 8-0 in the judgment

The Supreme Court reversed the D.C. Circuit's vacatur of the Surface Transportation Board's environmental impact statement for the Uinta Basin Railway. Justice Kavanaugh's opinion says courts must give agencies substantial deference on NEPA reviews and that agencies need not analyze effects of separate upstream or downstream projects; Justice Gorsuch took no part.

Seven County Infrastructure Coalition v. Eagle County, No. 23-975 (opinion)

CEQ withdraws Biden-era NEPA guidance on greenhouse gas emissions and climate change

CEQ published a notice withdrawing its January 9, 2023 interim guidance on considering greenhouse gas emissions and climate change in NEPA reviews, effective May 28, 2025. It said the guidance was inconsistent with EO 14154 and cited that order's criticism of the social cost of carbon.

Withdrawal of National Environmental Policy Act Guidance on Consideration of Greenhouse Gas Emissions and Climate Change (90 FR 22472)

Interior lifts Empire Wind stop-work order; Burgum cites New York pipeline capacity

BOEM told Equinor the April 16 stop-work order had been lifted and construction could resume. New York Gov. Kathy Hochul said Burgum and President Trump had agreed to let the project proceed; Burgum said he was encouraged by Hochul's willingness to move forward on pipeline capacity, while Hochul's statement did not mention gas.

Stop work order lifted, Empire Wind project resumes construction · Trump allows New York offshore wind project after apparent gas pipeline compromise with state

Interior adopts emergency permitting procedures with 14- to 28-day energy reviews

Citing the national energy emergency, Interior announced alternative NEPA procedures for energy and critical-minerals projects, with targets of 14 days for environmental assessments and 28 days for environmental impact statements. It also set expedited ESA Section 7 consultation and a seven-day Section 106 comment window under the National Historic Preservation Act.

Department of the Interior Implements Emergency Permitting Procedures to Strengthen Domestic Energy Supply

Interior orders construction stopped on Empire Wind off New York

Interior Secretary Doug Burgum ordered Equinor to stop construction of Empire Wind 1, an 810-MW offshore wind project approved in 2024, alleging the Biden administration approved it without sufficient analysis or consultation among agencies. The project was more than 30% complete.

Trump allows New York offshore wind project after apparent gas pipeline compromise with state · Stop work order lifted, Empire Wind project resumes construction

Presidential memo orders permitting technology plan and CEQ Permitting Innovation Center

A presidential memorandum told agencies to make maximum use of technology in environmental review and permitting. It ordered the CEQ Chairman to issue a Permitting Technology Action Plan within 45 days and to establish an interagency Permitting Innovation Center within 15 days.

Updating Permitting Technology for the 21st Century (presidential memorandum) · Memorandum: CEQ Establishment of Permitting Innovation Center

FERC Order No. 1920-B affirms the long-term transmission planning rule on rehearing

FERC issued Order No. 1920-B, resolving rehearing of Order No. 1920-A (November 21, 2024), which had expanded states' role in the 20-year regional transmission planning rule first issued in May 2024. It clarified that transmission providers need not plan for unenrolled non-jurisdictional providers and kept the requirements tied to state-agreed cost allocation methods. Court challenges are consolidated in the Fourth Circuit.

Order No. 1920-B Affirms FERC's Long-Term Transmission Planning and Cost Allocation Rule · Regional Transmission Planning Rule

CEQ interim final rule removes its NEPA implementing regulations from the CFR

CEQ published an interim final rule (90 FR 10610) removing its NEPA regulations, 40 CFR parts 1500-1508, effective April 11, 2025, with comments due March 27, 2025. The rule cited EO 14154, Marin Audubon and Iowa v. CEQ.

Removal of National Environmental Policy Act Implementing Regulations (interim final rule, 90 FR 10610) · CEQ Rescinded Rule Implementing NEPA

North Dakota court vacates CEQ's 2024 NEPA rule, finds CEQ lacks rulemaking authority

In Iowa v. Council on Environmental Quality, the U.S. District Court for the District of North Dakota granted summary judgment to the plaintiff states and vacated CEQ's 2024 'Phase 2' NEPA rule. The court found that CEQ lacks statutory authority to promulgate binding rules implementing NEPA.

Removal of National Environmental Policy Act Implementing Regulations (interim final rule, 90 FR 10610) · A Hard Look at CEQ's Hard Luck: North Dakota Court Decision Accelerates NEPA Regulations' Rapid Fall

EO 14154 'Unleashing American Energy' directs CEQ to propose rescinding its NEPA rules

On his first day, President Trump signed EO 14154, which revoked Carter-era EO 11991 (the basis for CEQ's binding NEPA regulations) and ordered the CEQ Chairman to issue NEPA guidance and propose rescinding CEQ's regulations within 30 days. It also told agencies to prioritize 'efficiency and certainty' in permitting and to streamline judicial review of NEPA.

Unleashing American Energy (Executive Order 14154)

EO 14156 declares a national energy emergency and calls for emergency permitting

EO 14156 declared a national emergency under the National Emergencies Act and told agencies to use emergency and other lawful authorities to expedite energy projects. It singled out the Army Corps' emergency permitting provisions, ESA emergency consultation regulations, and the ESA Committee.

Declaring a National Energy Emergency (Executive Order 14156)

Presidential memo halts new wind leasing and orders review of wind permitting

A presidential memorandum temporarily withdrew all Outer Continental Shelf areas from new or renewed wind leasing and ordered a review of existing wind leases. It also barred agencies from issuing new or renewed approvals, rights of way, permits, leases or loans for onshore and offshore wind projects pending a review of federal wind permitting practices.

Temporary Withdrawal of All Areas on the Outer Continental Shelf from Offshore Wind Leasing and Review of the Federal Government's Leasing and Permitting Practices for Wind Projects

D.C. Circuit panel says CEQ has no authority to issue binding NEPA regulations

In Marin Audubon Society v. FAA, a divided D.C. Circuit panel vacated an air tour management plan for four Bay Area parks. In Part II, Senior Judge Randolph wrote that NEPA gives CEQ no authority to issue binding regulations; Chief Judge Srinivasan dissented from that part.

Marin Audubon Society v. FAA, No. 23-1067 (slip opinion) · D.C. Circuit Upends CEQ's NEPA Rules

Senate ENR Committee advances the Manchin-Barrasso Energy Permitting Reform Act, 15-4

The Senate Energy and Natural Resources Committee advanced S. 4753, the Energy Permitting Reform Act of 2024, by 15-4; Sens. Sanders, Wyden, Hirono and Hawley voted no. Chairman Joe Manchin and ranking member John Barrasso had released it on July 22 and introduced it July 23. It never received a floor vote and died with the 118th Congress. House Republicans rejected it, in part over provisions easing large power lines, and co-ops and public power providers lobbied against wider FERC jurisdiction.

Senate Energy & Natural Resources Committee Passes Permitting Bill · Energy Chairman Manchin's Permitting Bill Moves Through Committee in Careful Balancing Act · https://www.eenews.net/articles/where-the-permitting-talks-stand/

Fiscal Responsibility Act writes NEPA deadlines and page limits into law (BUILDER Act)

Public Law 118-5, signed June 3, 2023, added NEPA Section 107 through its Title III 'Builder Act' (Sec. 321): lead-agency rules, a two-year deadline for environmental impact statements, page limits of 150 pages (300 for extraordinary complexity) for EISs and 75 for environmental assessments, and sponsor-prepared documents. Title III also covered energy storage permitting and the Mountain Valley Pipeline.

Public Law 118-5, Fiscal Responsibility Act of 2023, Title III (Permitting Reform), Sec. 321