Letter order granting the PJM, Indicated PJM Transmission Owners and Silver Run Electric abeyance motions
FERC grants the abeyance motions of PJM, the Indicated PJM Transmission Owners and Silver Run, holding the E-7 show cause proceeding for 90 days. Responses move to November 16, 2026 and answers to December 16, 2026.
Postpones the E-7 60-day show cause deadline for PJM and its Transmission Owners to November 16, 2026, in exchange for section 205 filings on study, cost and flexible service topics.
E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7) E-7 PJM: Service for flexible loads (P 85, p. 56) E-7 PJM: Cost-recovery agreement (P 77, p. 28)
Key points
- FERC holds the whole EL26-67 proceeding in abeyance for 90 days, moving show cause responses to November 16 and answers to December 16, 2026.
responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text
- A section 205 filing by November 16 suspends the filer's obligation to respond to the show cause order.
then the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text
- PJM says its planned filing will cover study processes, cost shifting, services for flexible large loads, and generation serving proximate large loads.
(1) achieve efficient transmission service application and study processes, including through the consideration of alternative transmission technologies; (2) prevent cost shifting and enhance transparency into transmission costs Source text
- PJM plans an advisory stakeholder vote at the Members Committee on October 28, 2026.
with the goal of taking an advisory stakeholder vote on the proposal at the Members Committee meeting on October 28, 2026. Source text
- The Indicated Transmission Owners expect to file pro forma cost recovery agreements and penalties for exceeding contractual service limits.
pro forma cost recovery agreements and rates for new transmission services for flexible large loads and electrically proximate large loads or co-located loads Source text
- FERC encourages filers to explain which proposed revisions resolve the show cause findings and to set effective dates that respect existing commercial arrangements.
we encourage PJM and/or Transmission Owners to explain, with specificity, which of their proposed Tariff revisions they believe resolve all or some of the Commission’s preliminary findings Source text
Read topic-matched comments in EL26-67
Topics in the text: Filing procedure · Cost allocation · Connecting load and generation
What the document says
Unpaginated filing
Five of six cases go into 90-day abeyance; responses are due November 16.
Therefore, responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text
Unpaginated filing
A timely section 205 filing suspends that respondent's duty to answer the show-cause order.
then the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text
Unpaginated filing
FERC granted abeyance because each movant described its coming filing and named a filing date.
PJM, Indicated PJM TOs, and Silver Run have provided robust descriptions of the filings they anticipate making, provided a date by which they intend to make such filings Source text
Unpaginated filing
FERC wants the tariff changes in fast, with an effective date that respects existing deals.
we encourage PJM and/or Transmission Owners to propose an effective date that takes into account the necessary time to implement the proposed Tariff revisions and accommodate existing commercial arrangements Source text
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
In this order, we grant the Abeyance Motions filed by PJM, Indicated PJM TOs, and Silver Run, and hold this proceeding in abeyance for 90 days.Read this passage Filed comments: Cost allocation
Footnotes
Word notes · Topic match: Filing procedure
PP 35, 37. [fn:5] 18 C.F.R. § 385.212 (2025). [fn:6] The Indicated PJM TOs include: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power…Read this passage