EL26-67: the filed comments

Positions read for this site

Each is a plain summary of one filing, checked against its pages. Where a stance is given, it is what the filing asks FERC to do with the proposal.

Pennsylvania’s consumer advocate challenges regional cost sharing

Pennsylvania Office of Consumer Advocate · EL26-67-001 · 2026-07-17

The office asked FERC to clarify that a customer agreement is only one protection. It wanted parties to be able to show that existing regional allocation methods themselves charge other customers for network upgrades needed by a large load.

Four state offices want the full upgrade cost charged to the new load

Maryland Office of People’s Counsel, Ohio Consumers’ Counsel, Delaware Division of the Public Advocate and Illinois Attorney General · EL26-67-001 · 2026-07-17

The four offices backed FERC’s transparency directives but said disclosure alone leaves existing cost shifts intact. They asked that agreements require full payment for the necessary upgrades and that other customers receive the corresponding revenue credits promptly.

An Indiana representative asks for federal review of large-load projects

Rep. Victoria Spartz (Indiana’s 5th Congressional District) · EL26-67-000 · 2026-11-05

Spartz asked FERC and DOE to scrutinize potentially duplicate load forecasts and to require developers to pay attributable generation and transmission costs. Her November letter represents a member of Congress, not Indiana’s utility commission.

Constellation supported more time with a condition

Constellation Energy Generation · EL26-67-000 · 2026-08-03

Constellation supported a partial delay but said PJM’s separate duty to comply with the co-location order could not depend on the outcome of the large-load process.

Other passages, matched by topic

These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.

Connecting load and generation

Individual No Affiliation

EL26-67-000 · 2026-07-09

PJM Should Address Maximum Net Withdrawal as Part of Any Framework for Generation Serving Electrically Proximate or Large Co-Located Load. PDF p. 3

Individual No Affiliation

EL26-67-000 · 2026-11-19

Terms for generation serving electrically proximate or co-located load should be set out in the Tariff (Show Cause Order P 3(d)). PDF p. 4

Cost allocation

MAVEN SOLUTIONS

EL26-67-000 · 2026-07-08

The Commission's five reform categories, addressed with the specific reforms recommended in Section VII, would materially strengthen PJM's tariff posture on cost causation, transparency, co-location governance, transmission service class design, and generation study reciprocity. PDF p. 13

MAVEN SOLUTIONS

EL26-67-000 · 2026-07-08

The Commission's five reform categories, addressed with the specific reforms recommended in Section VII, would materially strengthen PJM's tariff posture on cost causation, transparency, co-location governance, transmission service class design, and generation study reciprocity. PDF p. 13

Global Capacity Alliance

EL26-67-000 · 2026-07-08

Doing so ensures that the integration of large, flexible loads supports grid visibility, protects regional ratepayers, and unlocks privately funded reliability infrastructure. PDF p. 3

Individual No Affiliation

EL26-67-000 · 2026-11-19

I support the Commission's focus on transparency of Network Upgrade costs and on a pro forma cost recovery agreement to mitigate cost shifting. PDF p. 3

Reliability and curtailment

Global Capacity Alliance

EL26-67-000 · 2026-07-08

Should RTOs wish to pursue FTM-Netting, stakeholder engagement can focus on 3 key areas: • Scarcity Yield & Coordinated Curtailment: Standardizing the technical parameters and response time for a facility to execute a controlled curtailment to onsite backup generation. PDF p. 3

NATIONAL CONGRESS OF AMERICAN INDIANS

EL26-67-000 · 2026-10-26

●​ Grid reliability and impact assessment: The FERC must require rigorous, independent, and conflict-free assessments of how these facilities impact regional resource adequacy and transmission congestion, ensuring transparent economic analysis of the true costs required to support their operations. PDF p. 2