The Pennsylvania Office of Consumer Advocate submits Request for Clarification or, in the alternative, Rehearing of the 06/18/2026 Order
The Pennsylvania Office of Consumer Advocate asks FERC to clarify, or on rehearing to require, that parties in EL26-67 can build a record on regional cost allocation for Network Upgrades caused by large loads, beyond the order's pro forma cost recovery agreements.
Asks FERC to: Clarify that the cost recovery agreements are a partial fix and that parties may develop an actionable record on regional wholesale cost allocation for large-load Network Upgrades, or else grant rehearing.
Rehearing and clarification request on the E-7 order's cost-shifting findings, seeking to widen the record beyond the pro forma cost recovery agreement directive to regional cost allocation.
E-7 PJM: Cost-recovery agreement (P 77, p. 28) E-7 PJM: Cost transparency (P 71, p. 51)
Key points
- OCA says the proposed cost recovery agreements secure revenue under existing allocation methods and do not fix cost shifts to customers not serving large loads.
Agreements guaranteeing the collection of a revenue contribution from Eligible Customers for Network Upgrades needed to serve large loads is untethered from review or consideration of the actual cost of providing transmission service induced by individual large loads. PDF p. 2
- OCA reads paragraph 81 as ambiguous on whether parties may build a record on existing regional cost allocation methods.
Order creates ambiguity whether parties can develop an actionable record on PJM’s wholesale cost allocation methods for Network Upgrades caused by large loads. PDF p. 6
- Commissioner Chang's concurrence is quoted for the point that revenue contributions untethered from actual cost may not protect other customers.
bilateral agreements that simply provide transmission revenue contributions untethered from any assessment of the actual cost of providing transmission service induced by individual large loads may be insufficient to adequately protect other customers against unjustified cost shifts. PDF p. 5
- Seven multi-state PJM zones carry 52 percent of peak load, so state retail sub-allocation cannot undo cost shifts across them.
These seven multi-state Zones comprise 52 percent of PJM’s peak load. PDF p. 12
- For regional facilities, PJM splits zonal cost responsibility 50/50 between load factor and distribution factor.
using a hybrid methodology involving a 50/50 split of each zone’s load factor and distribution factor (DFAX). PDF p. 13
Contents · 9 sections
- I. Summary of Request for Clarification or Rehearing
- II. Statement of Issues
- III. Request for Clarification
- A. FERC should clarify that PJM’s existing regional cost allocation results in
- B. FERC should clarify that the Order allows parties to develop a robust,
- IV. Request for Rehearing
- A. FERC’s Order violates the Federal Power Act and Administrative Procedure
- B. FERC’s Order violates the Federal Power Act and Administrative Procedure
- V. Conclusion
Read topic-matched comments in EL26-67
Topics in the text: Cost allocation · Filing procedure · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
EL26-67 et al. ) ) Request for Clarification Or—in the Alternative—Rehearing of the Pennsylvania Office of Consumer Advocate Before the Federal Energy Regulatory Commission (Commission or FERC), the Pennsylvania Office of Consumer Advocate (PA OCA)1 respectfully requests clarification—or, in the…Read this passage
I. Summary of Request for Clarification or Rehearing
printed heading · Topic match: Cost allocation
Pennsylvania statute empowers the PA OCA to represent the interest of utility consumers before the Pennsylvania Public Utility Commission, FERC, and state and federal courts. 71 P.S. § 309-1 et seq. 2 16 U.S.C. § 825l(b) (providing for FPA rehearing requests); 18 C.F.R. § 385.713 (providing FERC…Read this passage Filed comments: Cost allocation
II. Statement of Issues
printed heading · Topic match: Cost allocation
The PA OCA further requests that FERC disavow the second reading because that reading would result in unjust and unreasonable cost allocation among transmission customers by ignoring wholesale cost shifts for Network Upgrades that these customers neither caused nor commensurately benefit from.Read this passage Filed comments: Cost allocation
III. Request for Clarification
printed heading
III.Read this passage
A. FERC should clarify that PJM’s existing regional cost allocation results in
printed heading · Topic match: Cost allocation
As Commissioner Chang identified in her concurrence, “bilateral agreements that simply provide transmission revenue contributions untethered from any assessment of the actual cost of providing transmission service induced by individual large loads may be insufficient to adequately protect other…Read this passage Filed comments: Cost allocation
B. FERC should clarify that the Order allows parties to develop a robust,
printed heading · Topic match: Cost allocation
But there is a source of confusion: in the Order, FERC stated that its “preliminary finding [to prevent unjust and unreasonable cost shifting among transmission customers] is not intended to alter or call into question existing regional cost allocation methods for Network Upgrades, but 18 Id. at P…Read this passage Filed comments: Cost allocation
IV. Request for Rehearing
printed heading · Topic match: Filing procedure
Request for RehearingRead this passage
A. FERC’s Order violates the Federal Power Act and Administrative Procedure
printed heading · Topic match: Cost allocation
Moore, 487 U.S. 354, 371 (1988) (“States may not alter FERC-ordered allocations . . . by substituting their own determinations of what would be just and fair.”). 51 16 U.S.C. § 824(b)) (providing that the FPA “shall apply to the transmission of electric energy in interstate commerce and to the sale…Read this passage Filed comments: Cost allocation
B. FERC’s Order violates the Federal Power Act and Administrative Procedure
printed heading · Topic match: Cost allocation
To the extent that FERC does not clarify, or denies, that parties in EL26-67 may develop an actionable record on regional wholesale cost allocation methods for Network Upgrades caused by large loads—the Order violates the Federal Power Act and Administrative Procedure Act.54 FERC should grant…Read this passage Filed comments: Cost allocation
V. Conclusion
printed heading · Topic match: Registry access
Co., 463 U.S. 29, 43 (1983) (holding federal administrative agency must “examine the relevant data and articulate a . . . rational connection between the facts found and the choice made”); see also Ill.Read this passage Filed comments: Cost allocation
CERTIFICATE OF SERVICE
printed heading · Topic match: Registry access
Harrisburg, Pennsylvania; July 17, 2026. /s/ Josiah Harmar Josiah Harmar Assistant Consumer Advocate PA Attorney ID # 338426 JHarmar@paoca.orgRead this passage