Comments of Maven Solutions on the Commission's Show Cause Order regarding large-load interconnection tariff provisions
Maven Solutions comments on the E-7 show cause order, scoring PJM's large-load tariff posture Conditional under its own Civic Bankability Rating Standard and recommending tariff revisions for each of the five reform categories.
Asks FERC to: Require PJM to file tariff revisions or a detailed evidentiary showing on all five reform categories, including time-bounded study commitments, a large-load cost-causation method and a flexible large-load tariff class.
Comments on the E-7 show cause order in EL26-67 that map Maven's recommendations to the order's five reform categories: study process, cost shifting, co-location, flexible load service and proximate generation.
E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7) E-7 PJM: Cost-recovery agreement (P 77, p. 28) E-7 PJM: Service for flexible loads (P 85, p. 56) E-7 PJM: Application / study process (P 6(a), p. 7)
Key points
- Maven rates PJM's posture Conditional with two keystone flags, Ratepayer Protection and Financial Surety, which it says warrant Commission intervention.
PJM's current tariff posture on large-load interconnection scores CONDITIONAL under the Civic Bankability Rating Standard with two active keystone flags PDF p. 3
- Maven cites the 2027/28 auction as the first to miss the reliability requirement, 6,516.6 MW UCAP short at a 14.4% reserve margin.
which PJM reported as 6,516.6 MW UCAP below the RTO Reliability Requirement. PDF p. 4
- Maven says large-load study processes lack a bounded time-to-service commitment or public reporting of completion times.
proceed without a bounded time-to-service commitment, without public reporting on median or 90th-percentile completion timelines, and without a customer-facing remedy mechanism for delayed studies. PDF p. 8
- Recommendation 2 asks that upgrade and capacity costs caused by large loads go to the responsible load class, with per-upgrade disclosure.
attributes transmission upgrade costs and capacity procurement costs caused by large-load interconnection to the responsible load class, not to Load Serving Entities or residential rate classes PDF p. 12
- Recommendation 4 asks for flexible large-load tariff classes with defined compensation, reliability crediting and financial surety.
provide for curtailable or interruptible service with defined compensation; (ii) include contribution-to-reliability crediting PDF p. 12
- Maven says this is one of six coordinated comments across dockets EL26-67 through EL26-72.
These Comments are one of six substantive Comments Maven files this cycle across the six Show Cause dockets initiated on June 18, 2026 (EL26-67 through EL26-72). PDF p. 5
Contents · 34 sections
- I. Introduction and Statement of Interest
- II. Executive Summary
- III. Record Background: The PJM System in Documented Distress
- IV. Methodology: The Civic Bankability Rating Standard
- V. Analysis Against FERC's Five Reform Categories
- VI. CBRS Findings for PJM
- VII. Recommendations to the Commission
- VIII. Companion Filings and Stage 2 Supplement Notice
- IX. Conclusion
- X. Sources and Notes
- I. INTRODUCTION AND STATEMENT OF INTEREST
- II. EXECUTIVE SUMMARY
- III. RECORD BACKGROUND: THE PJM SYSTEM IN
- A. Emergency Authorities in Force
- B. Capacity Market Trajectory
- C. The 2027/28 Footprint Shortfall
- D. July 1–3, 2026 Emergency Event
- E. Estimated Ratepayer Impact
- F. Companion Proceedings
- IV. METHODOLOGY: THE CIVIC BANKABILITY RATING
- A. Overview of CBRS
- B. Jurisdictional Application to Commission Proceedings
- C. Mapping the Jurisdictional Subset to FERC's Five Reform Categories
- V. ANALYSIS AGAINST FERC'S FIVE REFORM CATEGORIES
- A. Category (1) — Efficient Transmission Service Application and Study
- B. Category (2) — Preventing Cost Shifting and Requiring Transparency
- C. Category (3) — Accommodating Co-Location and Behind-the-Meter
- D. Category (4) — New Transmission Services for Flexible Large Loads
- E. Category (5) — Process to Study Generation Serving Electrically
- VI. CBRS FINDINGS FOR PJM
- VII. RECOMMENDATIONS TO THE COMMISSION
- VIII. COMPANION FILINGS AND STAGE 2 SUPPLEMENT
- IX. CONCLUSION
- X. SOURCES AND NOTES
Read topic-matched comments in EL26-67
Topics in the text: Cost allocation · Reliability and curtailment · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
1 of 16 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
TABLE OF CONTENTS
printed heading
TABLE OF CONTENTSRead this passage
I. Introduction and Statement of Interest
printed heading
I.Read this passage
II. Executive Summary
printed heading
II.Read this passage
III. Record Background: The PJM System in Documented Distress
printed heading
Record Background: The PJM System in Documented DistressRead this passage
IV. Methodology: The Civic Bankability Rating Standard
printed heading
Methodology: The Civic Bankability Rating StandardRead this passage
V. Analysis Against FERC's Five Reform Categories
printed heading
V.Read this passage
VI. CBRS Findings for PJM
printed heading
VI.Read this passage
VII. Recommendations to the Commission
printed heading
VII.Read this passage
VIII. Companion Filings and Stage 2 Supplement Notice
printed heading
VIII.Read this passage
IX. Conclusion
printed heading
IX.Read this passage
X. Sources and Notes
printed heading
X.Read this passage
I. INTRODUCTION AND STATEMENT OF INTEREST
printed heading · Topic match: Cost allocation
Founded in 2014, Maven has developed the Civic Bankability Rating Standard (“CBRS”), a statute-grounded scoring methodology for evaluating large-load and data-center projects against the ratepayer, reliability, community-cost, and financial-surety exposures they generate.Read this passage Filed comments: Cost allocation
II. EXECUTIVE SUMMARY
printed heading · Topic match: Cost allocation
EXECUTIVE SUMMARY HEADLINE FINDING PJM's current tariff posture on large-load interconnection scores CONDITIONAL under the Civic Bankability Rating Standard with two active keystone flags — Ratepayer Protection (FERC Category 2) and Financial Surety (FERC Category 4).Read this passage Filed comments: Cost allocation
III. RECORD BACKGROUND: THE PJM SYSTEM IN
printed heading
RECORD BACKGROUND: THE PJM SYSTEM IN DOCUMENTED DISTRESSRead this passage
A. Emergency Authorities in Force
printed heading
Emergency Authorities in Force On May 18, 2026, the U.S.Read this passage
B. Capacity Market Trajectory
printed heading
Capacity Market Trajectory PJM Base Residual Auction (“BRA”) clearing prices have followed the trajectory shown below.4 Delivery Year Clearing Price ($/MW-day) Notes 2024/25 $28.92 Baseline 2025/26 $269.92 Single-auction increase 2026/27 $329.17 Constrained by PA/PJM settlement cap 2027/28 $333.44…Read this passage
C. The 2027/28 Footprint Shortfall
printed heading
The 2027/28 Footprint Shortfall PJM has reported that the 2027/28 BRA was the first RPM auction since the Reliability Pricing Model was created in 2007 that did not meet the reliability requirement.Read this passage
D. July 1–3, 2026 Emergency Event
printed heading · Topic match: Reliability and curtailment
PJM also warned utilities to prepare for possible curtailment of data centers and other large loads to backup generation, but reported that the action was ultimately not required.7 The event was contemporaneous with the intervention window for these Show Cause Comments.Read this passage Filed comments: Reliability and curtailment
E. Estimated Ratepayer Impact
printed heading · Topic match: Cost allocation
Estimated Ratepayer Impact The Natural Resources Defense Council has estimated that data-center-driven load growth could impose up to $163 billion in additional PJM consumer costs through 2033, with average household impacts reaching approximately $70 per month by 2028.9 Monitoring Analytics has…Read this passage Filed comments: Cost allocation
F. Companion Proceedings
printed heading
Companion Proceedings The Commission's Show Cause Order in this docket is one of six issued on June 18, 2026, splitting the underlying rulemaking record from Docket No.Read this passage
IV. METHODOLOGY: THE CIVIC BANKABILITY RATING
printed heading
METHODOLOGY: THE CIVIC BANKABILITY RATING STANDARDRead this passage
A. Overview of CBRS
printed heading · Topic match: Cost allocation
Overview of CBRS The Civic Bankability Rating Standard is a statute-grounded scoring methodology Maven Solutions has developed for evaluating large-load and data-center projects against ratepayer, reliability, community-cost, and financial-surety exposures.Read this passage Filed comments: Cost allocation
B. Jurisdictional Application to Commission Proceedings
printed heading · Topic match: Cost allocation
Maven applies to Commission proceedings a jurisdiction-relevant subset consisting of four dimensions: Ratepayer Protection, Transparency, Co-Location and Interconnection Governance, and Financial Surety.Read this passage Filed comments: Cost allocation
C. Mapping the Jurisdictional Subset to FERC's Five Reform Categories
printed heading · Topic match: Cost allocation
Reform Focus Primary CBRS Dimension 1 Efficient transmission service application and study processes Transparency 2 Preventing cost shifting; requiring transparency Ratepayer Protection — 8 of 16 KEYSTONE 3 Co-location and behind-the-meter generation Co-Location & Interconnection Governance 4 New…Read this passage Filed comments: Cost allocation
V. ANALYSIS AGAINST FERC'S FIVE REFORM CATEGORIES
printed heading
V.Read this passage
A. Category (1) — Efficient Transmission Service Application and Study
printed heading
Category (1) — Efficient Transmission Service Application and Study Processes Primary CBRS Dimension: Transparency Score: 2 of 5 — Conditional.Read this passage
B. Category (2) — Preventing Cost Shifting and Requiring Transparency
printed heading · Topic match: Cost allocation
Category (2) — Preventing Cost Shifting and Requiring Transparency Primary CBRS Dimension: Ratepayer Protection — KEYSTONE FLAG ACTIVE Score: 1 of 5 — below the CBRS Acceptable threshold.Read this passage Filed comments: Cost allocation
C. Category (3) — Accommodating Co-Location and Behind-the-Meter
printed heading · Topic match: Cost allocation
The posture recognizes co-location as a service class but does not yet include measurable reliability-hold-harmless mechanisms, financial surety instruments backing switching-event ratepayer exposure, or reciprocity provisions between co-located generation and the load it serves. 10 of 16Read this passage Filed comments: Cost allocation
D. Category (4) — New Transmission Services for Flexible Large Loads
printed heading
Category (4) — New Transmission Services for Flexible Large Loads Primary CBRS Dimension: Financial Surety — KEYSTONE FLAG ACTIVE Score: 2 of 5 — Conditional.Read this passage
E. Category (5) — Process to Study Generation Serving Electrically
printed heading · Topic match: Connecting load and generation
The study process for such 11 of 16 generation currently proceeds on the same footing as unconstrained generation interconnection, which does not account for the specific service-and-cost relationship between the generation and the co-located load it primarily serves.Read this passage Filed comments: Connecting load and generation
VI. CBRS FINDINGS FOR PJM
printed heading · Topic match: Cost allocation
CBRS Dimension Applied Raw Score Keystone? 1 Transparency (primary) 2 / 5 — 2 Ratepayer Protection 1 / 5 KEYSTONE FLAG 3 Co-Location & Interconnection Governance 2 / 5 — 4 Financial Surety 2 / 5 KEYSTONE FLAG 5 Transparency (secondary axis) 2 / 5 — Total Four unique dimensions applied 9 / 20 TWO…Read this passage Filed comments: Cost allocation
VII. RECOMMENDATIONS TO THE COMMISSION
printed heading · Topic match: Cost allocation
Recommendation 3 — Category (3): Co-Location and BTMG Reliability and Ratepayer-Hold- Harmless Any co-location or behind-the-meter generation tariff provisions adopted in Category (3) should be consistent with the Commission's dispositions in PJM's parallel co-location and BTMG compliance…Read this passage Filed comments: Cost allocation
VIII. COMPANION FILINGS AND STAGE 2 SUPPLEMENT
printed heading
COMPANION FILINGS AND STAGE 2 SUPPLEMENT NOTICE These Comments are one of six substantive Comments Maven Solutions files in the six Show Cause dockets initiated on June 18, 2026 (Dockets EL26-67 through EL26-72).Read this passage
IX. CONCLUSION
printed heading · Topic match: Cost allocation
Maven respectfully requests that the Commission require PJM to submit tariff revisions or, in the alternative, a detailed evidentiary showing that addresses each of the five categories consistent with the recommendations set out herein.Read this passage Filed comments: Cost allocation
X. SOURCES AND NOTES
printed heading · Topic match: Reliability and curtailment
PJM Interconnection, L.L.C., post-event operations reporting on the July 1–3, 2026 heat event, including preliminary July 2, 2026 instantaneous load of approximately 162,700 MW after demand- response activation and reporting on the utility warning regarding possible curtailment of data centers and…Read this passage Filed comments: Reliability and curtailment