Letter order granting the SPP Joint Movants' abeyance motion for 95 days, to November 20, 2026
FERC grants the Joint Movants' motion and holds the EL26-68 SPP show cause proceeding in abeyance for 95 days, to November 20, 2026, with answers due December 21, 2026. SPP plans a section 205 filing after its November 17 Board vote.
Moves the E-9 SPP 60-day show cause response from August 17 to November 20, 2026, accepting SPP's stakeholder schedule for a section 205 filing.
E-9 SPP: Show cause or propose tariff changes in 60 days (p. 5) E-9 SPP: 30-day report on serving large loads with adequate generation (p. 7)
Key points
- FERC grants the August 3 motion of SPP and a group of transmission owners for 95 days.
we grant the Abeyance Motion filed by Joint Movants and hold this proceeding in abeyance for 95 days, until November 20, 2026. Source text
- Joint Movants describe SPP's planned work on alternative technologies, cost shifting protections, co-location and flexible-load services.
SPP anticipates developing revisions to its High Impact Large Load (HILL) process that will incorporate the evaluation of alternative transmission technologies into the study process. Source text
- SPP expects stakeholder approval of its Price Adaptive Load proposal for non-firm service on November 17, 2026.
SPP anticipates final stakeholder approval of the proposal on November 17, 2026. Source text
- The five days beyond the usual 90 reflect a Board meeting moved from November 3 to November 17.
the date of the SPP Board meeting was originally scheduled on November 3, 2026 but was changed to accommodate upcoming elections Source text
- The Regional State Committee, Missouri Commission and CEBA filed answers supporting the motion.
The RSC, Public Service Commission of the State of Missouri, and Corporate Energy Buyers Association filed timely answers in support of Joint Movants' Abeyance Motion. Source text
- Responses are due November 20 and answers December 21, 2026; a timely section 205 filing suspends the response duty.
responses to the Show Cause Order will be due on November 20, 2026, and answers to responses will be due on December 21, 2026. Source text
Read topic-matched comments in EL26-68
Topics in the text: Filing procedure · Cost allocation
What the document says
Unpaginated filing
SPP gets 95 days instead of 90, so its response is due November 20.
we grant the Abeyance Motion filed by Joint Movants and hold this proceeding in abeyance for 95 days, until November 20, 2026 Source textFiled comments: Filing procedure
Unpaginated filing
SPP gets 95 days instead of 90, so its response is due November 20.
Therefore, responses to the Show Cause Order will be due on November 20, 2026, and answers to responses will be due on December 21, 2026. Source text
Unpaginated filing
SPP's extra five days exist because its Board vote moved to November 17 around elections.
the date of the SPP Board meeting was originally scheduled on November 3, 2026 but was changed to accommodate upcoming elections and a National Association of Regulatory Utility Commissioners conference Source text
Unpaginated filing
A timely section 205 filing suspends that respondent's duty to answer the show-cause order.
then the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text
Unpaginated filing
FERC invites each respondent to say which tariff revisions justify ending the show-cause case.
we encourage SPP and/or Transmission Owners to explain, with specificity, which of their proposed Tariff revisions they believe resolve all or some of the Commission’s preliminary findings in the Show Cause Order Source text
Unpaginated filing
FERC wants the tariff changes in fast, with an effective date that respects existing deals.
we encourage SPP and/or Transmission Owners to propose an effective date that takes into account the necessary time to implement the proposed Tariff revisions and accommodate existing commercial arrangements Source text
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Why SPP asked for five more days than other operators Southwest Power Pool
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
Electric Cooperative, Inc., and Xcel Energy Services, Inc. (collectively, Joint Movants) filed a motion to hold the above-referenced show cause proceeding in abeyance, in full, for 95 days, up to and including November 20, 2026, pending completion of SPP’s stakeholder proceedings and submittal of…Read this passage Filed comments: Filing procedure
Footnotes
Word notes · Topic match: Filing procedure
Abeyance Motion at 1 n.1. [fn:8] Show Cause Order, 195 FERC ¶ 61,213 at P 33. [fn:9] Id. [fn:10] Abeyance Motion at 4. [fn:11] Id. at 8-10. [fn:12] Id. at 11-12. [fn:13] Id. at 13-14. [fn:14] Id. at 14-15. [fn:15] Id. at 16-17. [fn:16] Id. at 17. [fn:17] Id. at 7, 17-18. [fn:18] Notice Establishing…Read this passage Filed comments: Filing procedure