EL26-68: the filed comments

Positions read for this site

Each is a plain summary of one filing, checked against its pages. Where a stance is given, it is what the filing asks FERC to do with the proposal.

Why SPP asked for five more days than other operators

Southwest Power Pool · EL26-68-000 · 2026-08-14

SPP told FERC its board meeting had moved because of the elections. The revised November 17 vote made a November 16 filing impractical; FERC granted a November 20 response date.

Missouri supports five extra days to secure a state review

Missouri Public Service Commission · EL26-68-000 · 2026-08-07

Missouri backed the 95-day request because SPP’s November 17 board vote fell just beyond the 90-day window. It said the extra days allowed meaningful state input without materially delaying the case.

SPP’s state committee wanted time to develop a cost proposal

SPP Regional State Committee · EL26-68-000 · 2026-08-07

The committee endorsed a November 20 deadline while its cost-allocation team studied who should secure network costs if promised demand fails to arrive or leaves early. The filing endorsed the schedule only. The cost-allocation formula is still being studied.

State regulators raised the risk that a large project leaves early

SPP Regional State Committee · EL26-68-000 · 2026-08-07

In its later comments on the filing schedule, the committee said its cost team was examining security for upgrades if a large customer never arrives or leaves early. It did not approve a particular conditional-service charge.

Other passages, matched by topic

These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.

Filing procedure

Missouri Public Service Commission

EL26-68-000 · 2026-08-07

EL26-68-000 ) COMMENTS OF THE PUBLIC SERVICE COMMISSION OF THE STATE OF MISSOURI IN SUPPORT OF THE JOINT MOVANTS’ REQUEST FOR ABEYANCE Pursuant to Rule 20081 and the Notice Establishing Answer Period issued in this docket on August 4, 2026, by the Federal Energy Regulatory Commission (Commission or FERC), the Public Service Commission of the State of Missouri (Missouri PSC) hereby submits these comments in support of the request for abeyance filed by the Southwest Power Pool, Inc. PDF p. 1