EL26-68-000 · 2026-08-07 · Missouri Public Service Commission

Comments of the Public Service Commission of the State of Missouri in support of Southwest Power Pool, Inc.'s et al. request for abeyance filed 08/03/2026

The Missouri Public Service Commission comments in support of the SPP Joint Movants' 95-day abeyance request in EL26-68, arguing good cause exists because SPP's Board meets November 17, one day outside the 90-day window.

Asks FERC to: Grant the Joint Movants' request for a 95-day abeyance of the section 206 proceeding.

Supports the E-9 SPP abeyance motion and ties the extra five days to state-regulator review of the cost-shift protections the order directs SPP to address.

E-9 SPP: Show cause or propose tariff changes in 60 days (p. 5) E-9 SPP: Cost-recovery + crediting (Ordering (B)(1)(b), p. 21)

Key points

  1. Missouri PSC says the 95 days fits SPP's November 17 Board meeting and state input to the compliance filing.
    SPP's Board of Directors meeting is scheduled for November 17, 2026—one day outside the 90-day window. PDF p. 1
  2. It cites the 12-month Order No. 1920 extension FERC gave SPP in April 2025 as precedent for good cause.
    the Commission granted SPP a 12-month extension of time to submit filings in compliance with the Commission's Order No. 1920 PDF p. 3
  3. State regulators care about transparency and cost-shift avoidance because they set retail rates that include transmission costs.
    Issues related to transparency and the avoidance of cost shifting are particularly important to the Missouri PSC and other state regulators who bear the responsibility of setting retail rates PDF p. 4
  4. The abeyance gives the CARE Team time to finish cost mitigation recommendations for the Board.
    The requested abeyance will allow the CARE Team time to complete this important work and present its recommendations to the Board. PDF p. 4
Contents · 6 sections
  1. I. Summary of Comments p. 1
  2. II. Service and Communication p. 2
  3. III. Background p. 2
  4. IV. Comments of the Missouri PSC p. 3
  5. V. Conclusion p. 5
  6. /s/ John D. Borgmeyer p. 5

Read topic-matched comments in EL26-68

Topics in the text: Filing procedure · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

EL26-68-000 ) COMMENTS OF THE PUBLIC SERVICE COMMISSION OF THE STATE OF MISSOURI IN SUPPORT OF THE JOINT MOVANTS’ REQUEST FOR ABEYANCE Pursuant to Rule 20081 and the Notice Establishing Answer Period issued in this docket on August 4, 2026, by the Federal Energy Regulatory Commission (Commission or…
Read this passage Filed comments: Filing procedure

I. Summary of Comments

printed heading · Topic match: Filing procedure

Summary of Comments The Commission should grant the Joint Movants’ request for a 95-day abeyance in order to accommodate SPP’s stakeholder process.
Read this passage Filed comments: Filing procedure

II. Service and Communication

printed heading

Service and Communication All pleadings, correspondence and other communications related to this proceeding should be directed to: Rodney Massman John D.
Read this passage

III. Background

printed heading · Topic match: Filing procedure

In the Show Cause Order, the Commission said it will consider requests from SPP and/or its transmission owners to hold this proceeding in abeyance for up to 90 days.7 The Commission said it will not grant such abeyances reflexively, and it “will look with great disfavor” upon requests for abeyance…
Read this passage Filed comments: Filing procedure

IV. Comments of the Missouri PSC

printed heading · Topic match: Filing procedure

Commission Rule 2008 provides that “the time by which any person is required… to act under any… order may be extended by the decisional authority for good cause, upon a motion made before the expiration of the period prescribed… .” On April 14, 2025, for example, the Commission granted SPP a…
Read this passage Filed comments: Filing procedure

V. Conclusion

printed heading · Topic match: Filing procedure

Conclusion The Missouri PSC respectfully submits these comments in support of the Joint Movants’ request for a 95-day abeyance of this Section 206 proceeding.
Read this passage Filed comments: Filing procedure

/s/ John D. Borgmeyer

PDF bookmark

General Counsel-Regulation Public Service Commission of the State of Missouri P.O.
Read this passage

Certificate of Service

PDF bookmark

Borgmeyer Jefferson City, Missouri
Read this passage