EL26-70-000 · 2026-08-14 · FERC

Letter order granting the MISO and MISO Transmission Owners abeyance motion over American Municipal Power's opposition

FERC grants the MISO and MISO Transmission Owners motion and holds the E-8 show cause proceeding in abeyance for 90 days, moving responses to November 16, 2026 and answers to December 16, 2026.

Moves the E-8 order's 60-day show cause deadline from August 17 to November 16, 2026 and suspends a respondent's response duty if it files section 205 tariff changes that address the preliminary findings.

E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)

Key points

  1. FERC grants the abeyance request filed August 3, 2026, for 90 days and in full.
    we grant the Abeyance Motion filed by MISO and the MISO TOs and hold this proceeding in abeyance for 90 days. Source text
  2. MISO listed six planned section 205 filings, starting with a Zero Injection Generator Interconnection Agreement by end of August.
    by the end of August, MISO expects to submit Tariff changes establishing a new Zero Injection Generator Interconnection Agreement Source text
  3. MISO described a load addition and resource study process completable within 120 days.
    a load addition and resource study process that will assess the transmission infrastructure needed to meet new large loads and new generation in an efficient study process that can be completed within 120 days. Source text
  4. AMP opposed abeyance and asked FERC to condition it on a cost-transparency and cost-shifting proposal and a compliance filing.
    AMP argues that the Abeyance Motion fails to meet the standards for abeyance established in the Show Cause Order and only superficially describes a potential future filing under FPA section 205. Source text
  5. New due dates: responses on November 16, 2026 and answers on December 16, 2026.
    responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text
  6. A section 205 filing addressing the preliminary findings by November 16 suspends that respondent's duty to respond.
    the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text
  7. FERC warns that issues not covered by the section 205 filings will be addressed in the show cause proceeding.
    should their FPA section 205 filings not address all of the Commission’s preliminary findings in the Show Cause Order, the Commission will address those issues through the show cause proceeding. Source text

Read topic-matched comments in EL26-70

Topics in the text: Filing procedure · Cost allocation · Registry access

What the document says

Unpaginated filing

Five of six cases go into 90-day abeyance; responses are due November 16.

Therefore, responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text

Unpaginated filing

A timely section 205 filing suspends that respondent's duty to answer the show-cause order.

then the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text

Unpaginated filing

FERC warns MISO that findings its 205 filings miss return to the show-cause case.

should their FPA section 205 filings not address all of the Commission’s preliminary findings in the Show Cause Order, the Commission will address those issues through the show cause proceeding Source text

Unpaginated filing

MISO plans a series of 205 filings, the first due by end of August.

MISO states that it intends to submit a series of FPA section 205 filings during the abeyance period, with the first filing by the end of August. Source text

Unpaginated filing

AMP opposed MISO's abeyance and wanted it conditioned on a compliance filing.

AMP asserts that, in the interest of expediting resolution of this matter, the Commission should condition abeyance on a future compliance filing by MISO. Source text

Unpaginated filing

FERC invites each respondent to say which tariff revisions justify ending the show-cause case.

we encourage MISO and/or Transmission Owners to explain, with specificity, which of their proposed Tariff revisions they believe resolve all or some of the Commission’s preliminary findings in the Show Cause Order Source text

Unpaginated filing

FERC wants the tariff changes in fast, with an effective date that respects existing deals.

we encourage MISO and/or Transmission Owners to propose an effective date that takes into account the necessary time to implement the proposed Tariff revisions and accommodate existing commercial arrangements Source text

Elsewhere in the record

Other parties on the same questions, in their own documents.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

Responses to the Show Cause Order are due on August 17, 2026, with answers due 30 days after the responses are filed.[fn:4] On August 3, 2026, pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure,[fn:5] MISO and the MISO Transmission Owners (MISO TOs)[fn:6] filed a motion to…
Read this passage Filed comments: Cost allocation