EL26-70: the filed comments

Positions read for this site

Each is a plain summary of one filing, checked against its pages. Where a stance is given, it is what the filing asks FERC to do with the proposal.

AMP wanted an enforceable route back to the show cause case

American Municipal Power · EL26-70-000 · 2026-08-14

AMP opposed an unconditional delay and asked FERC to require a compliance filing. The order says FERC would return to the section 206 case for any preliminary finding MISO’s tariff filings did not address.

What MISO’s regional report leaves out

Organization of MISO States · EL26-70-000 · 2026-08-14

OMS said the report does not fully reflect state proceedings on resource planning, retail rates and utility approvals because MISO is not a party to those proceedings. It wanted regional planning to complement, rather than displace, state responsibility for adequacy.

Support for more time came with a reservation

Organization of MISO States · EL26-70-000 · 2026-08-07

OMS supported time for a coordinated sequence of filings but said granting abeyance should neither narrow the inquiry nor prejudge that the coming tariff changes would settle every issue.

Eolian wants nearby generation considered for permanent service

Eolian · EL26-70-001 · 2026-09-21

Eolian sought clarification that generation located electrically close to a large load could qualify for permanent limited service if it could constrain grid withdrawals over the long term. FERC dismissed the request because the preliminary order was not final.

Other passages, matched by topic

These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.

Connecting load and generation

Individual No Affiliation

EL26-70-000 · 2026-11-20

I respectfully ask the Commission to (i) recognize the value of those defined timelines, (ii) ensure the paired- generation study is open to, and workable for, financed solar and storage, (iii) confirm that a paired generator's interconnection service does not depend on the load remaining in place, and (iv) protect the interconnection service of existing generators. PDF p. 2

Cost allocation

Individual No Affiliation

EL26-70-000 · 2026-06-24

As a local concerned citizen regarding the Viridon WISE project in Wisconsin, I formally asked ATC to evaluate upgrading their existing infrastructure (such as reconductoring) as a cheaper, ratepayer-protective alternative to Viridon's $350 million greenfield transmission line. PDF p. 1

US HOUSE OF REPRESENTATIVES

EL26-70-000 · 2026-09-10

Request for Independent Review and Concrete Data: I respectfully request that the Departments coordinate with FERC and other appropriate federal agencies to conduct an independent review addressing interstate grid reliability, water resources, infrastructure, cost allocation, and transparency. PDF p. 4

Reliability and curtailment

Organization of MISO States, Inc.

EL26-70-000 · 2026-08-14

state and local regulators play a central role in ensuring reliable, affordable electric service and should remain active participants in discussions regarding resource adequacy. PDF p. 2

Retail and wholesale authority

Organization of MISO States, Inc.

EL26-70-000 · 2026-08-14

OMS remains committed to working constructively with MISO and stakeholders to strengthen the existing framework while preserving state authority over resource adequacy and ensuring that reforms continue to support reliable service, efficient markets, and reasonable customer costs. PDF p. 2