Answer of the Organization of MISO States, Inc. in Support of Midcontinent Independent System Operator, Inc.'s et al. 08/03/2026 Motion to Hold Proceeding in Abeyance
The Organization of MISO States answers in support of the MISO abeyance motion, on the condition that the stakeholder process and later filings fully address the issues in the E-8 order.
Asks FERC to: Grant the abeyance, without narrowing the scope of FERC's inquiry or prejudging whether MISO's filings resolve each issue.
Supports the MISO abeyance request that postponed the E-8 show cause deadline, while asking that cost-shift and transparency directives get full treatment in MISO's coming filings.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5) E-8 MISO: Cost-recovery agreement (P 6(b), p. 6)
Key points
- OMS supports abeyance because the issues are interconnected and suited to a stakeholder process followed by section 205 filings.
the issues identified by the Commission’s Show Cause Order are significant, highly interconnected, and best addressed through a coordinated stakeholder process PDF p. 1
- OMS conditions its support on full treatment of the Commission's issues and no prejudgment of resolution.
Granting abeyance should not narrow the scope of the Commission’s inquiry or prejudge whether any particular issue has been adequately resolved PDF p. 2
- OMS lists the issues it wants addressed, including cost transparency, cost shifting if load does not materialize, flexible service and alternative transmission technologies.
addressing the potential for inappropriate cost shifting when anticipated load does not ultimately materialize or materializes at a different scale or schedule than expected PDF p. 4
- OMS says MISO's stakeholder workstreams so far have favored issues supported by parties interested in developing and serving large loads.
workstreams prioritized by MISO and stakeholders to date have been limited to those issues supported by parties largely interested in developing and serving large loads. PDF p. 4
Contents · 6 sections
- I. ANSWER
- A. OMS Supports the Request to Hold this Proceeding in Abeyance.
- B. The Show Cause Order Appropriately Identifies the Core Issues Requiring
- C. OMS Intends to Participate in Developing Comprehensive Solutions.
- D. All Issues Identified in the Show Cause Order Should Remain Open Throughout
- II. CONCLUSION
Read topic-matched comments in EL26-70
Topics in the text: Filing procedure · Cost allocation · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL26-70-000 Operator, Inc., et al. ) ) ANSWER IN SUPPORT OF THE MOTION TO HOLD PROCEEDING IN ABEYANCE OF THE MIDCONTINENT INDEPENDENT SYSTEM OPERATOR, INC.Read this passage
I. ANSWER
printed heading
I.Read this passage
A. OMS Supports the Request to Hold this Proceeding in Abeyance.
printed heading · Topic match: Filing procedure
OMS Supports the Request to Hold this Proceeding in Abeyance.Read this passage
B. The Show Cause Order Appropriately Identifies the Core Issues Requiring
printed heading · Topic match: Cost allocation
The Commission’s Show Cause Order appropriately focuses attention on issues that states within the MISO region have increasingly observed as requests to interconnect and serve new large loads continue to accelerate.Read this passage Filed comments: Cost allocation
C. OMS Intends to Participate in Developing Comprehensive Solutions.
printed heading · Topic match: Cost allocation
OMS intends to participate throughout the MISO stakeholder process during the abeyance period.Read this passage Filed comments: Cost allocation
D. All Issues Identified in the Show Cause Order Should Remain Open Throughout
printed heading · Topic match: Filing procedure
While OMS supports granting the Abeyance Request, the Commission should make clear that all issues identified in the Show Cause Order remain open throughout the abeyance period.Read this passage Filed comments: Cost allocation
II. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION For the foregoing reasons, OMS respectfully requests that the Commission grant MISO and the MISO TOs’ Motion to Hold Proceeding in Abeyance.Read this passage
CERTIFICATE OF SERVICE
printed heading
Pope Brad Pope Director of Legal & Regulatory Affairs Organization of MISO States 811 E.Read this passage