EL26-70-000 · 2026-08-14 · Organization of MISO States, Inc.

Comments of the Organization of MISO States, Inc. on the Informational Report of the Midcontinent Independent System Operator, Inc. filed on 07/20/2026

The Organization of MISO States comments on MISO's informational report to stress that states hold primary responsibility for resource adequacy and affordability, and that state proceedings address large-load cost shifting outside FERC jurisdiction.

State regulators' comments on MISO's July 20 informational report, filed under the E-8 directive on ensuring adequate generation for existing and new large loads.

E-8 MISO: 30-day report on serving large loads with adequate generation (p. 7)

Key points

  1. OMS says many resource adequacy and affordability measures sit in state proceedings that MISO's report does not reflect.
    many important resource adequacy and affordability policy and implementation issues are being addressed through state proceedings and utility-specific processes PDF p. 2
  2. OMS says large load growth does not signal failure of the existing state and MISO resource adequacy framework.
    these challenges do not indicate a failure of the states and their collaboration with MISO’s underlying resource adequacy framework PDF p. 2
  3. OMS calls for planning that evaluates load additions with rigor comparable to new generation.
    planning processes that evaluate load additions using a level of rigor comparable to that applied to new generation resources PDF p. 3
  4. OMS cites state tariffs, special contracts and statutes that guard against cost shifting from new large loads.
    state commissions are implementing retail tariffs, approving special contracts, requiring resource adequacy demonstrations, establishing interruptible service requirements PDF p. 3
  5. OMS says existing interconnection processes should stay primary, with expedited paths narrowly tailored.
    existing interconnection processes should remain the primary pathway for connecting new resources PDF p. 4
Contents · 4 sections
  1. I. COMMENTS p. 1
  2. A. MISO and the States’ Existing Resource Adequacy Construct Provides a p. 2
  3. B. States Remain Key in Ensuring Affordability through Resource Adequacy p. 3
  4. II. CONCLUSION p. 5

Read topic-matched comments in EL26-70

Topics in the text: Reliability and curtailment · Cost allocation · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

The Organization of MISO States, Inc. (“OMS”)1 submits the following comments in response to the Midcontinent Independent System Operator, Inc.’s (“MISO”) July 20, 2026 Informational Report2 filed with the Federal Energy Regulatory Commission (“Commission”) in the above-captioned proceeding.3 OMS…
Read this passage Filed comments: Reliability and curtailment

I. COMMENTS

printed heading · Topic match: Reliability and curtailment

COMMENTS OMS submits this response to ensure that the perspectives of state and local regulators are reflected in the Commission’s consideration of resource adequacy.
Read this passage Filed comments: Reliability and curtailment

A. MISO and the States’ Existing Resource Adequacy Construct Provides a

printed heading · Topic match: Reliability and curtailment

MISO and the States’ Existing Resource Adequacy Construct Provides a Strong Foundation to Integrate New Loads.
Read this passage Filed comments: Reliability and curtailment

B. States Remain Key in Ensuring Affordability through Resource Adequacy

printed heading · Topic match: Reliability and curtailment

As MISO, states, and stakeholders continue to evolve the resource adequacy framework to address unprecedented large load growth, OMS believes that future reforms should continue to build upon the complementary roles established under the Federal Power Act, recognizing the central role states play…
Read this passage Filed comments: Reliability and curtailment

II. CONCLUSION

printed heading

CONCLUSION OMS submits these Comments because a majority of OMS members support this filing.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Pope Brad Pope Director of Legal & Regulatory Affairs Organization of MISO States 811 E.