EL26-70-000 · 2026-11-20 · Individual No Affiliation
Comments of Olabanji John Ogunyemi on the Midcontinent Independent System Operator, Inc.’s 11/16/2026 Large Load filing and the 06/18/2026 Show Cause Order
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
Midcontinent Independent System
)
Docket Nos. ER27-526-000
Operator, Inc.
)
EL26-70-000
)
COMMENTS OF OLABANJI JOHN OGUNYEMI
Olabanji John Ogunyemi submits these comments on the November 16, 2026 filing by Midcontinent Independent System Operator, Inc. (MISO) in Docket No. ER27-526-000, titled "Large Load Review, Cost Recovery and Transmission Services Filing" (Filing). The Filing proposes Tariff provisions responding to the Commission's June 18, 2026 order finding that MISO's Tariff appears to lack provisions on large loads, co-located loads and generation serving electrically proximate large load. Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (Show Cause Order); see Midcontinent Indep. Sys. Operator, Inc., 196 FERC ¶ 61,217, at PP 5, 9 (2026). Because the Filing responds to the Show Cause Order, these comments are submitted in both dockets.
My comments address one practical question: whether the proposed provisions will leave solar and storage generation in the MISO footprint, both new projects and those already operating, with terms that lenders and investors can underwrite. In several respects the Filing moves in that direction, and I offer suggestions on where clarity would help.
I. INTEREST OF THE COMMENTER
I am a project finance professional based in Saint Paul, Minnesota. I work on the financing and asset management of solar projects in Minnesota, within the MISO footprint, and in New England. My work includes sizing construction and term debt, preparing the documentation lenders and tax credit buyers require before they commit capital, and preparing the reporting lenders rely on once projects are operating. I submit these comments in my personal capacity. They 1
PDF page 2
do not represent the views of any employer, client or counterparty, and I am not a party to either proceeding.
II. SUMMARY
Large loads in the MISO footprint will be served in part by new solar and battery storage, which can be built faster than other resources. Developers planned to add 43.4 GW of utility-scale solar and 24 GW of battery storage nationally in 2026, out of 86 GW of planned additions.[1] That generation is built only if it can be financed. The Filing's defined review periods and its expedited study for loads paired with nearby generation are steps toward financeable terms. I respectfully ask the Commission to (i) recognize the value of those defined timelines, (ii) ensure the paired- generation study is open to, and workable for, financed solar and storage, (iii) confirm that a paired generator's interconnection service does not depend on the load remaining in place, and (iv) protect the interconnection service of existing generators.
III. COMMENTS
A. The Filing's defined review periods are valuable, because federal law now fixes a completion deadline for solar.
The Filing establishes the Large Load Project Review as the core study process, run in three study cycles each year with application deadlines posted at least 90 days in advance, and with stated periods for each step, including a fifteen-Business-Day review of applications and a defined cure period.[2] It also integrates the Large Load Addition Resource Study (LARS), proposed separately in Docket No. ER27-25-000, under which very large loads and the generation paired with them are studied on a coordinated timeline.[3] Defined periods of this kind matter to capital providers. Under Public Law 119-21, the clean electricity investment and production credits are not available for wind and solar facilities placed in service after December 31, 2027, where construction begins after July 4, 2026.[4] A solar project financed against the credit cannot absorb an open-ended study. The Commission has recognized the value of a comparable expedited 2
PDF page 3
process in Southwest Power Pool's tariff.[5] I support the defined periods in the Filing and encourage the Commission to preserve them.
B. The paired-generation study should be workable for financed solar and storage. As described in the Filing, LARS is available to large loads of 200 MW or more that are formally paired with the generation that will serve them, with a commercial agreement of at least five years and a pairing of at least fifteen years.[3] Generation serving load at the same substation may instead use MISO's proposed zero injection interconnection agreement, filed in Docket No. ER26-3552-000, while MISO has said that generation serving electrically proximate load would be addressed through further work.[6] Three points would help financing:
•
Loads between 50 MW and 200 MW. MISO lowered the LARS threshold from 250 MW to 200 MW in response to stakeholder feedback.[7] Even so, a load of 50 MW to 200 MW that is served by nearby generation not at the same substation appears to have no coordinated path for studying the load and its generation together. I encourage the Commission to ask MISO whether a lower threshold, or a scaled coordinated process for smaller pairs, is feasible, since solar and storage projects sized to serve loads in that range would otherwise lack a coordinated path.
•
The generator's interconnection rights over the pairing period. Term debt for a solar or storage project typically runs longer than five years, and lenders treat the project's interconnection service as part of their collateral. The Tariff should state clearly what happens to a paired generator's interconnection service if the load is delayed, curtailed, defaults or exits before the fifteen-year period ends, so that the generator's lenders can assess that risk at financial close.
•
Storage as paired generation. I support the exclusion of load used exclusively for charging an Electric Storage Resource from the definition of Large Load,[8] and I note that the zero injection proposal allows an Electric Storage Resource to participate.[9] I encourage the Commission to confirm that battery storage, alone or with solar, may also serve as the paired resource in LARS.
3
PDF page 4
C. Cost certainty for the large load supports the financing of the generation that serves it.
The Filing proposes pro forma cost recovery agreements under which the large load customer provides security and makes revenue commitments for Large Load Network Upgrades, together with a Large Load Transparency Dashboard reporting the location and estimated costs of large loads.[10] I support this structure, which protects other customers from cost shifts. It also matters to generators: where a generator sells output to a large load, the generator's lenders look closely at the load customer's obligations. Cost estimates and true-up mechanisms that are predictable, and bounded where possible, make the load a more creditworthy counterparty and the generation serving it easier to finance.
D. The interconnection service of existing generators should be protected.
This point is drawn from the operating side of my work. An operating solar project's debt is secured on the project's revenue, and that revenue depends on the interconnection service the project holds. I urge the Commission to confirm that the provisions the Filing adds, including deferral of service, interim service and the curtailment terms applicable to large loads, do not reduce the interconnection service of, or shift new upgrade costs onto, existing generators that are not party to a large load arrangement. Uncertainty on this point would affect the financing of generation that is already serving the grid.
IV. CONCLUSION
I respectfully ask the Commission, in acting on the Filing and in the show cause proceeding, to preserve the Filing's defined review periods; to ensure the paired-generation study is open to, and workable for, financed solar and storage, including clear treatment of the generator's interconnection service over the pairing period; to support predictable cost terms for large loads; and to protect the interconnection service of existing generators.
Respectfully submitted,
4
PDF page 5
/s/ Olabanji John Ogunyemi
Olabanji John Ogunyemi
Saint Paul, Minnesota
banjiogunyemi@gmail.com
Filed in his personal capacity
Dated: November 20, 2026
Notes
[1] U.S. Energy Information Administration, Today in Energy, "New U.S. electric generating capacity expected to reach a record high in 2026" (Feb. 20, 2026).
[2] Filing, Transmittal Letter, pages 14-15 and proposed Attachment FF, Section I.D.1.c (Large Load Project Review).
[3] Filing, Transmittal Letter, pages 9-10, 13 (note 43) and 15; proposed Tariff provisions on Large Load Application study options.
[4] Pub. L. No. 119-21 (2025), amending 26 U.S.C. §§ 45Y and 48E for wind and solar facilities.
[5] See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (discussing Southwest Power Pool, Inc., 194 FERC ¶ 61,031, at P 64 (2026)).
[6] Filing, Transmittal Letter, page 9 (describing the zero injection generator interconnection agreement proposal in Docket No. ER26-3552-000).
[7] Filing, Transmittal Letter, page 10.
[8] Filing, proposed definition of Large Load.
[9] Filing, Transmittal Letter, page 45.
[10]
Filing, Transmittal Letter, page 5; proposed Attachments LLL and MMM.
5