EL26-70-000 · 2026-11-20 · Individual No Affiliation

Comments of Olabanji John Ogunyemi on the Midcontinent Independent System Operator, Inc.’s 11/16/2026 Large Load filing and the 06/18/2026 Show Cause Order

Text extracted from the eLibrary original (SHA-256 61133000c8d5f286…). Download the original from the official source.

Contents · 8 sections
  1. I. INTEREST OF THE COMMENTER p. 1
  2. II. SUMMARY p. 2
  3. III. COMMENTS p. 2
  4. A. The Filing's defined review periods are valuable, because federal law now fixes a p. 2
  5. B. The paired-generation study should be workable for financed solar and storage. p. 3
  6. C. Cost certainty for the large load supports the financing of the generation that serves p. 4
  7. D. The interconnection service of existing generators should be protected. p. 4
  8. IV. CONCLUSION p. 4

Read topic-matched comments in EL26-70

Topics in the text: Connecting load and generation · Cost allocation · Credit and exit

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

The Filing proposes Tariff provisions responding to the Commission's June 18, 2026 order finding that MISO's Tariff appears to lack provisions on large loads, co-located loads and generation serving electrically proximate large load.
Read this passage

I. INTEREST OF THE COMMENTER

printed heading

INTEREST OF THE COMMENTER I am a project finance professional based in Saint Paul, Minnesota.
Read this passage

II. SUMMARY

printed heading · Topic match: Connecting load and generation

I respectfully ask the Commission to (i) recognize the value of those defined timelines, (ii) ensure the paired- generation study is open to, and workable for, financed solar and storage, (iii) confirm that a paired generator's interconnection service does not depend on the load remaining in place,…
Read this passage Filed comments: Connecting load and generation

III. COMMENTS

printed heading

III.
Read this passage

A. The Filing's defined review periods are valuable, because federal law now fixes a

printed heading · Topic match: Connecting load and generation

The Filing establishes the Large Load Project Review as the core study process, run in three study cycles each year with application deadlines posted at least 90 days in advance, and with stated periods for each step, including a fifteen-Business-Day review of applications and a defined cure…
Read this passage Filed comments: Connecting load and generation

B. The paired-generation study should be workable for financed solar and storage.

printed heading · Topic match: Connecting load and generation

As described in the Filing, LARS is available to large loads of 200 MW or more that are formally paired with the generation that will serve them, with a commercial agreement of at least five years and a pairing of at least fifteen years.[3] Generation serving load at the same substation may instead…
Read this passage Filed comments: Connecting load and generation

C. Cost certainty for the large load supports the financing of the generation that serves

printed heading · Topic match: Cost allocation

The Filing proposes pro forma cost recovery agreements under which the large load customer provides security and makes revenue commitments for Large Load Network Upgrades, together with a Large Load Transparency Dashboard reporting the location and estimated costs of large loads.[10] I support this…
Read this passage Filed comments: Cost allocation

D. The interconnection service of existing generators should be protected.

printed heading · Topic match: Connecting load and generation

The interconnection service of existing generators should be protected.
Read this passage Filed comments: Connecting load and generation

IV. CONCLUSION

printed heading · Topic match: Connecting load and generation

CONCLUSION I respectfully ask the Commission, in acting on the Filing and in the show cause proceeding, to preserve the Filing's defined review periods; to ensure the paired-generation study is open to, and workable for, financed solar and storage, including clear treatment of the generator's…
Read this passage Filed comments: Connecting load and generation