SPP corrects the Upper Missouri rate sheet for conditional large-load service
SPP amends its November 6 CHILLS tariff filing to add the omitted Schedule 14 and Incremental Market Efficiency Use revenue references to the Upper Missouri Zone rate sheet, keeping the February 1, 2027 effective date.
Asks FERC to: Accept the November 6 filing as amended, with an effective date of February 1, 2027.
Technical amendment in SPP's ER27-432 docket extending CHILLS, its conditional large-load service, to the West Region; E-9 directs new services for flexible loads building on that framework.
E-9 SPP: New services for flexible loads (Ordering (B)(1)(d), p. 22)
Key points
- SPP may amend because no FERC or delegated order has issued on the November 6 filing.
Amendment of the November 6 Filing is permitted because no Commission or delegated order has been issued in the docket. PDF p. 1
- SPP says it inadvertently omitted revisions to the Upper Missouri Zone rate sheet.
SPP inadvertently omitted revisions to the rate sheet for the Upper Missouri Zone to add references to Schedule 14 and Incremental Market Efficiency Use revenues. PDF p. 2
- SPP keeps Attachment AU references on this sheet because the zone includes SPP East Region utilities.
because the Upper Missouri Zone includes utilities in the SPP East Region. PDF p. 3
- SPP requests no other changes and the same effective date.
SPP is not requesting any other amendments or modifications to the November 6 Filing. PDF p. 4
Contents · 6 sections
What the document says
Regional rates · PDF pp. 1–2
What the November 6 filing covered
The original proposal added CHILLS provisions to SPP’s western pricing zones. The November 10 amendment changes the Upper Missouri rate sheet.
to add provisions for Conditional High Impact Large Load Service (“CHILLS”) for pricing Zones in the SPP West Region PDF p. 2
Cost allocation · PDF pp. 2–3
Which revenue credits were missing?
The proposed correction restores two references: Schedule 14 DC tie revenues and Incremental Market Efficiency Use revenues. The latter compensates western tie owners for increased use.
omitted revisions to the rate sheet for the Upper Missouri Zone PDF p. 2
Procedural status · PDF pp. 4–5
Effective date requested
SPP asked FERC to accept February 1, 2027 as the effective date. Its letter requests no other changes to the November 6 proposal.
with an effective date of February 1, 2027 PDF p. 4