Answer of Morongo Transmission LLC: no tariff amendment required, a non-load-serving participating transmission owner
Morongo Transmission LLC, a non-load-serving CAISO Participating Transmission Owner, answers the show cause order. It says its tariff needs no amendment and that it will stay in the proceeding as a party.
Asks FERC to: Find that the Morongo Tariff is just and reasonable and needs no amendment; Morongo will make compliance filings if FERC directs residual changes.
Answers the E-10 CAISO show cause order, which named every Participating Transmission Owner as respondent, by arguing that a non-load-serving owner with no end-use customers needs no tariff change.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- Morongo Transmission has no end-use customers, so the load interconnection reforms do not reach its tariff.
Morongo Transmission LLC is a Non-Load-Serving Participating [Transmission Owner] and has no End-Use Customers. PDF p. 3
- Morongo holds a 30-year lease of part of the transfer capability of SCE's West of Devers facilities.
Morongo Transmission holds a 30-year lease of a portion of the transfer capability of Southern California Edison Company’s (“SCE”) upgraded West of Devers transmission facilities PDF p. 2
- The Morongo Tariff defers its load interconnection sections (Sections 8 to 10) to SCE's TO Tariff, so SCE's reforms would cover them.
SCE could implement those reforms to its own tariff without Morongo Transmission needing to take further action to amend the Morongo Tariff. PDF p. 4
- Morongo offers compliance filings if FERC finds residual changes are needed.
to the extent that the Commission determines any residual or conforming amendments are required to the Morongo Tariff, Morongo Transmission will make compliance filings as directed. PDF p. 4
- Morongo stays a party because resource adequacy and large load interconnection matter to the Tribe.
Morongo Transmission nevertheless intends to continue participating as a party in this proceeding PDF p. 2
Contents · 4 sections
Topics in the text: Cost allocation · Reliability and curtailment
What the document says
PDF p. 2
Morongo says its tariff needs no change: it is a non-load-serving owner.
Morongo Transmission respectfully submits that the Morongo Tariff is just and reasonable and that no amendment is required in response to the issues identified in the Commission’s Order PDF p. 2
PDF p. 4
Morongo says its tariff needs no change: it is a non-load-serving owner.
SCE could implement those reforms to its own tariff without Morongo Transmission needing to take further action to amend the Morongo Tariff. PDF p. 4
PDF p. 4
Morongo will file compliance changes if FERC finds residual amendments to its tariff are required.
to the extent that the Commission determines any residual or conforming amendments are required to the Morongo Tariff, Morongo Transmission will make compliance filings as directed. PDF p. 4
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
Morongo Transmission nevertheless intends to continue participating as a party in this proceeding due to the numerous important issues raised in the Order to Show Cause, including resource adequacy and large load interconnection reform.Read this passage
I. DESCRIPTION OF MORONGO TRANSMISSION
printed heading
DESCRIPTION OF MORONGO TRANSMISSION Morongo Transmission is a Participating Transmission Owner in CAISO.Read this passage
II. ANSWER OF MORONGO TRANSMISSION
printed heading · Topic match: Cost allocation
The Order to Show Cause nonetheless targets a range of issues of great importance to Morongo Transmission and the Tribe, including resource adequacy and reform of large load interconnection processes.Read this passage
III. SERVICE, COMMUNICATIONS, AND CORRESPONDENCE
printed heading · Topic match: Cost allocation
Reg’l Transmission Planning and Cost Allocation, Order No. 1920, 187 FERC ¶ 61,068 at PP 409, 482, 528 (2024), on reh’g, Order No. 1920-A, 189 FERC ¶ 61,126 (2024), reh’g denied, Order No. 1920-B, 191 FERC ¶ 61,026 (2025); see also CAISO, Tribal Engagement on Long- term Transmission Planning 67…Read this passage
IV. CONCLUSION
printed heading
CONCLUSION For the reasons given above, the Morongo Tariff is just and reasonable and does not require amendment in light of the Order to Show Cause.Read this passage