EL26-71-000 · 2026-08-12 · Morongo Transmission

Answer of Morongo Transmission LLC: no tariff amendment required, a non-load-serving participating transmission owner

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
California Independent System Operator Corporation
Citizen S-Line Transmission LLC
Citizens Sunrise Transmission LLC
Citizens Sycamore-Penasquitos Transmission LLC
City of Anaheim, California
City of Azusa, California
City of Banning, California
City of Colton, California
City of Pasadena, California
City of Riverside, California
DCR Transmission, L.L.C.
DesertLink, LLC
GridLiance West LLC
Horizon West Transmission, LLC
LS Power Grid California, LLC
Morongo Transmission LLC
Pacific Gas and Electric Company
San Diego Gas & Electric Company
Southern California Edison Company
Startrans IO, L.L.C.
SunZia Transmission, LLC
Trans Bay Cable LLC
Valley Electric Association, Inc.
Viridon Path 15, LLC
Western Area Power Administration

   Docket No. EL26-71-000

ANSWER OF MORONGO TRANSMISSION LLC

Morongo Transmission LLC (“Morongo Transmission”) submits this answer pursuant to Rules 206 and 213 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure in response to the Commission’s Order to Show Cause in the above- captioned proceeding.1  Morongo Transmission respectfully submits that no amendments to its tariff are required in response to the Order to Show Cause because Morongo Transmission is a

1 18 C.F.R. §§ 385.206(f), 385.213(a); Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 at P 3 (2026) (“CAISO”) (directing Participating Transmission Owners to respond to the Order to Show Cause).

PDF page 2

2
non-load-serving Participating Transmission Owner under the California Independent System Operator (“CAISO”) tariff with no end-use customers.  Morongo Transmission nevertheless intends to continue participating as a party in this proceeding due to the numerous important issues raised in the Order to Show Cause, including resource adequacy and large load interconnection reform.

I. DESCRIPTION OF MORONGO TRANSMISSION

Morongo Transmission is a Participating Transmission Owner in CAISO.  It is wholly owned by the Morongo Band of Mission Indians (“Tribe”), a federally recognized American Indian Tribe exercising jurisdiction over the Morongo Indian Reservation (“Reservation”), which spans roughly 40,000 acres in the San Gorgonio Pass, near Banning, California.  Morongo Transmission holds a 30-year lease of a portion of the transfer capability of Southern California Edison Company’s (“SCE”) upgraded West of Devers transmission facilities, which cross the Tribe’s Reservation. 2  Morongo Transmission recovers its transmission revenue requirement through a Commission-approved formula rate under its tariff (“Morongo Tariff”), paid by CAISO’s collection of Transmission Access Charge (“TAC”) rates.3

II. ANSWER OF MORONGO TRANSMISSION

Morongo Transmission respectfully submits that the Morongo Tariff is just and reasonable and that no amendment is required in response to the issues identified in the Commission’s Order

2 Morongo Transmission LLC, Docket No. ER21-669-000, Transmittal Letter (Dec. 17, 2020) (“Morongo Transmittal Letter”); Morongo Transmission LLC, 178 FERC ¶ 61,062 at P 5 (2022) (approving uncontested settlement establishing transmission revenue requirement for Morongo Transmission).

3 E.g., Morongo Transmission LLC, Docket No. ER26-642-000 (Jan. 23, 2026) (delegated order) (accepting revisions to the Morongo Tariff reflecting updates to annual operating cost revenue requirement); Morongo Transmittal Letter at 2.

PDF page 3

3
to Show Cause.  In this proceeding, the Commission has preliminarily ordered CAISO to reform its tariff to take jurisdiction over, and facilitate, interconnection of large loads, including by:

• Developing an efficient application and study process for Eligible Customers seeking transmission service for large loads;

• Increasing transparency regarding network upgrade costs to provide transmission service for large loads, establishing mechanisms to mitigate cost shifting to other transmission customers, and creating a pro forma cost recovery agreement between CAISO, the relevant transmission owner, and the Eligible Customer;

• Developing new transmission services to accommodate flexible large loads willing to accept interruptible service and/or contracts for less than their peak demand; and

• Developing processes to efficiently study generation facilities serving electrically proximate large loads (i.e., not more than two substations apart) or co-located large loads, with the goal of avoiding unnecessary network upgrades.4

These areas of reform do not implicate the Morongo Tariff, which expressly provides that “Morongo Transmission LLC is a Non-Load-Serving Participating [Transmission Owner] and has no End-Use Customers.”5  This language reflects the arrangement between Morongo Transmission and SCE, where Morongo Transmission holds a 30-year lease of a portion of the transfer capability of SCE’s West of Devers line across the Tribe’s Reservation.6  The Morongo Tariff is therefore different from the tariffs of other CAISO Participating Transmission Owners that do serve load and have end-use customers and whose tariffs may be subject to the Order to Show Cause.

Furthermore, the Morongo Tariff provides that the tariff provisions governing the load interconnection process—Section Eight (Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades), Section Nine (Expansion Process (including the study process for necessary facilities)), and Section Ten (Interconnection Process)—“shall be superseded by the

4 CAISO, 195 FERC ¶ 61,214 at P 3.
5 Morongo Transmission LLC Transmission Owner Tariff (“Morongo Tariff”) § 1 (May 15, 2021) (emphases added).
6 See Part I, supra.

PDF page 4

4
corresponding sections of the TO Tariff of Southern California Edison.”7  Thus to the extent that amendments to the Participating Transmission Owners’ tariffs are necessary to implement large load interconnection reforms to CAISO’s tariff in response to the Order to Show Cause,8 SCE could implement those reforms to its own tariff without Morongo Transmission needing to take further action to amend the Morongo Tariff.9  The Morongo Tariff thus will not be impacted by reforms facilitating interconnections of large loads.  However, to the extent that the Commission determines any residual or conforming amendments are required to the Morongo Tariff, Morongo Transmission will make compliance filings as directed.

The Order to Show Cause nonetheless targets a range of issues of great importance to Morongo Transmission and the Tribe, including resource adequacy and reform of large load interconnection processes.  These topics are significant to Morongo Transmission and the Tribe as they work to expand economic opportunity on the Reservation while ensuring affordable and reliable electricity for the Tribe’s members.  Morongo Transmission accordingly looks forward to continuing to participate as a party in this proceeding and assisting the Commission as it weighs these important matters—in keeping with Order No. 1920’s recognition of the critical role that federally recognized Tribes play in developing policies affecting the interstate transmission grid.10

III. SERVICE, COMMUNICATIONS, AND CORRESPONDENCE
Morongo Transmission requests that the persons listed below be included on the official

7 Morongo Tariff § 16.12 (cross-referencing Sections 8, 9, and 10).
8 See CAISO, 195 FERC ¶ 61,214 at P 3.
9 Southern California Edison Transmission Owner Tariff §§ 8-10 (effective May 1, 2019).
10 Bldg. for the Future Through Elec. Reg’l Transmission Planning and Cost Allocation, Order No. 1920, 187 FERC ¶ 61,068 at PP 409, 482, 528 (2024), on reh’g, Order No. 1920-A, 189 FERC ¶ 61,126 (2024), reh’g denied, Order No. 1920-B, 191 FERC ¶ 61,026 (2025); see also CAISO, Tribal Engagement on Long- term Transmission Planning 67 (Apr. 9, 2026), https://www.caiso.com/documents/presentation-tribal- engagement-on-long-term-transmission-planning-apr-09-2026.pdf.

PDF page 5

5
service list for this proceeding, and respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) to permit the designation of more than two persons upon whom service is to be made in this proceeding.

Sam Cohen
Chief Legal Officer
MORONGO TRANSMISSION LLC
12700 Pumarra Road
Banning, CA 92220
(909) 454-4515
scohen@morongo-nsn.gov

Max Spivak
MORONGO BAND OF MISSION INDIANS
12700 Pumarra Road
Banning, CA 92220
(951) 755-5122
morongotransmissionllc@morongo-nsn.gov

Suedeen G. Kelly
JENNER & BLOCK LLP
1099 New York Avenue NW, Suite 900
Washington, DC 20001
(202) 639-6055
SKelly@jenner.com

IV. CONCLUSION

For the reasons given above, the Morongo Tariff is just and reasonable and does not require amendment in light of the Order to Show Cause.

Respectfully submitted,

/s/ Sam Cohen

Sam Cohen
Chief Legal Officer
MORONGO TRANSMISSION LLC
12700 Pumarra Road
Banning, CA 92220
(909) 454-4515
scohen@morongo-nsn.gov

On behalf of Morongo Transmission LLC

Dated: August 12, 2026

PDF page 6

CERTIFICATE OF SERVICE

I certify that, on August 12, 2026, I served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

/s/ Suedeen G. Kelly

Suedeen G. Kelly