MISO Answer to Comments and Protests on the Large Load Addition Resource Study
MISO answers the 21 comments and protests on its LARS filing, defending the Local Resource Zone proximity test, 200 MW threshold, 15-year pairing and application role of the Transmission Customer, and says it will fold in cost reforms due November 16.
Asks FERC to: Accept the answer and accept the LARS filing as proposed, so MISO can implement LARS in the first quarter of 2027.
MISO replies in its section 205 LARS docket to protests that LARS only partly answers the E-8 show cause order on proximity and cost shifting, and points to its November 16 cost recovery agreement filing.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5) E-8 MISO: Cost-recovery agreement (P 6(b), p. 6) E-8 MISO: Minimum cost recovery / security (P 119, p. 74)
Key points
- MISO says LARS responds to the show cause order and should not wait for the large load cost reforms due November 16.
such a delay would frustrate the goals of the Show Cause Order and needlessly sacrifice the benefits of critical reforms for ratepayers and stakeholders without corresponding benefit. PDF p. 5
- MISO says the Local Resource Zone fits its system and the order invited tailoring the proximity definition.
MISO is expanding upon the Commission's definition to fit its needs and resource adequacy construct. PDF p. 9
- MISO describes its zone test as electrically proximate plus because it rewards close siting and also serves pairs farther apart.
MISO's LRZ approach thus can be considered an "electrically proximate plus" construct PDF p. 12
- MISO says LARS creates no new cost shift, and the Transmission Customer stays liable for assigned projects even if the load never starts service.
LARS does not create any new cost shift opportunities, but LARS does mitigate risks that already exist. PDF p. 14
- MISO and the Transmission Owners will file pro forma cost recovery agreements by November 16, 2026, and MISO would accept a compliance directive to fold them into LARS.
MISO is willing to accept a compliance directive requiring such a filing should the Commission deem this necessary. PDF p. 15
- MISO says LARS will not take headroom from DPP queue projects because LARS models are built on the existing MTEP model.
each LARS study cycle model will be built based on the existing MTEP model, which would not remove any available headroom from active DPP queue projects PDF p. 19
- MISO rejects the gatekeeper charge: only Transmission Customers have been able to submit EPR requests, and an unpaired generator would make LARS speculative.
LARS is a load-driven process, and an Interconnection Customer cannot require a Transmission Customer to scope their Transmission Service request around a generator they have not chosen to pair with. PDF p. 20
- MISO opposes a sunset date but commits to post pair data each cycle and to review usage regularly.
MISO commits to publicly post, at the beginning of each LARS cycle, information on each LARS generation/load pair's POI and POW PDF p. 23
- MISO defends the 200 MW floor and the 15-year pairing as ways to keep LARS for the largest, committed pairs.
The 15-year minimum pairing of the generation and load pairs in LARS is a necessary aspect of ensuring certainty for MISO PDF p. 24
Contents · 10 sections
- I. MOTION FOR LEAVE TO FILE ANSWER
- II. EXECUTIVE SUMMARY
- III. ANSWER
- A. LARS is Responsive to the Commission’s Show Cause Order
- B. Large Load Cost Allocation Framework
- C. LARS Will Not Harm the Existing Queue
- D. LARS Application and Eligibility Requirements
- E. MISO Has Met the Standard for an Independent Entity Variation
- F. Miscellaneous Clarifications and Requests.
- IV. CONCLUSION
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation · Cost allocation · Registry access
What the document says
PDF p. 3
MISO defends studying loads and nearby generation together.
study both the large load and the generation that will serve it at the same time PDF p. 3
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Geronimo says MISO’s answer leaves the discrimination concerns unaddressed Geronimo Power
- Municipal utilities say MISO’s answer does not justify the zone-wide scope Southern Minnesota Municipal Power Agency and WPPI Energy
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
ER27- 25-000 (Oct. 2, 2026) (“LARS Filing”); the GIP and Attachment FF are available at: https://www.misoenergy.org/legal/rules-manuals-and-agreements/tariff/. 2 System.4 Also, because a number of commenters misstate the intent and background of LARS, raise extraneous issues, seek clarifications,…Read this passage Filed comments: Connecting load and generation
I. MOTION FOR LEAVE TO FILE ANSWER
printed heading · Topic match: Connecting load and generation
MOTION FOR LEAVE TO FILE ANSWER Under the Commission’s rules, answers to protests generally are not permitted.5 Nonetheless, the Commission waives this requirement where an otherwise prohibited answer would clarify the issues under consideration, ensure completeness of the record or assist the…Read this passage Filed comments: Connecting load and generation
II. EXECUTIVE SUMMARY
printed heading · Topic match: Connecting load and generation
See Data Center Coalition LARS Comments at 2-3; NIPSCO LARS Comments at 2-4; MISO Transmission Owners LARS Comments at 6-9; Entergy and Cleco LARS Comments at 10-11; Mississippi Public Service Commission and the Louisiana Public Service Commission (the “Southern Regulators”) LARS Comments at 1-2;…Read this passage Filed comments: Connecting load and generation
III. ANSWER
printed heading · Topic match: Connecting load and generation
As such, MISO 17 Consumers Energy and Alliant LARS Comments at 2; Data Center Coalition LARS Comments at 4; DTE LARS Comments at 2; Electricity Customer Alliance (“ECA”) LARS Comments at 1. 18 Entergy and Cleco LARS Comments at 2. 9 respectfully asks that the Commission accept its proposal to…Read this passage Filed comments: Connecting load and generation
A. LARS is Responsive to the Commission’s Show Cause Order
printed heading · Topic match: Connecting load and generation
In developing LARS, MISO concluded that defining a maximum distance based on substations would impede the flexibility of large loads and 19 Clean Energy Trades LARS Comments at 18; the Community Organizations and Clean Energy Advocates (the “Advocates”) LARS Comments at 37-38; Consumer Advocates…Read this passage Filed comments: Connecting load and generation
B. Large Load Cost Allocation Framework
printed heading · Topic match: Connecting load and generation
With respect to cost responsibility, accountability, and cost shifting, the LARS filing includes Tariff language stating: Once MTEP approval occurs for the LARS Associated Load, the LARS Associated Transmission Customer remains responsible for the identified BRPs and Other assigned projects even if…Read this passage Filed comments: Connecting load and generation
C. LARS Will Not Harm the Existing Queue
printed heading · Topic match: Connecting load and generation
LARS Will Not Harm the Existing Queue MISO understands that many stakeholders are concerned that LARS projects will take available transmission capacity or headroom from other projects currently in the DPP queue.35 The argument is that since LARS and DPP interconnection customers are vying for the…Read this passage Filed comments: Connecting load and generation
D. LARS Application and Eligibility Requirements
printed heading · Topic match: Connecting load and generation
Specifically, LARS allows arrangements involving Interconnection Customers that are separate entities from the Transmission Customer and provides that the Interconnection Customer—and not the LARS Transmission Customer—will receive the LLGIA awarding Interconnection Service to LARS Associated…Read this passage Filed comments: Connecting load and generation
E. MISO Has Met the Standard for an Independent Entity Variation
printed heading · Topic match: Connecting load and generation
LARS advances Order No. 2003’s goal of expediting new generation while protecting reliability.49 LARS also meets Order No. 2023’s goal of insulating the DPP queue and ensuring that only truly commercially ready projects apply.50 Notably, the LARS process requires an increased non-refundable payment…Read this passage Filed comments: Connecting load and generation
F. Miscellaneous Clarifications and Requests.
printed heading · Topic match: Connecting load and generation
The applicants submitting a LARS Application must identify the LARS Associated Load’s expected peak 49 See Order No. 2003, FERC Stats. & Regs. ¶ 31,146 at PP 822-827; Order No. 2003-A, FERC Stats. & Regs. ¶ 31,160 at P 759. 50 See Improvements to Generator Interconnection Procs. & Agreements, Order…Read this passage Filed comments: Connecting load and generation
IV. CONCLUSION
printed heading · Topic match: Connecting load and generation
CONCLUSION WHEREFORE, MISO respectfully requests that the Commission: (1) accept this Answer; and (2) accept the LARS Filing as discussed herein.Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Dated at Carmel, Indiana this 9th day of November, 2026. /s/ Dawn Kaminski Dawn Kaminski Midcontinent Independent System Operator, Inc. 720 City Center Drive Carmel, Indiana 46032 Telephone: (317) 249-5400Read this passage