Positions read for this site
Each is a plain summary of one filing, checked against its pages. Where a stance is given, it is what the filing asks FERC to do with the proposal.
Mississippi and Louisiana Public Service Commissions · Supports · ER27-25-000 · 2026-10-23
The commissions backed a 120-day joint study. They said studying the load and its generator together could avoid duplicating network upgrades; the limit of ten pairs per period made it manageable. They wanted a permanent process so projects could plan and finance construction.
The Southern Regulators support MISO’s filing to establish the LARS process and respectfully request that the Commission accept it. PDF p. 1
Arkansas Public Service Commission · Supports · ER27-25-000 · 2026-10-23
Arkansas expressly agreed with the Mississippi and Louisiana commissions’ comments and asked FERC to accept MISO’s tariff changes. It did not offer its own numerical estimate of costs or queue delays.
The APSC supports MISO’s filing to establish the LARS process, and agrees with the comments made by the Mississippi Public Service Commission and the Louisiana Public Service Commission. PDF p. 1
Iowa Office of Consumer Advocate, Illinois and Michigan attorneys general, Minnesota Department of Commerce and co-protesters · Opposes in part · ER27-25-000 · 2026-10-23
The joint protesters asked how the study would prevent costs shifting to other customers. They warned that related MISO proposals could exempt about 30 GW of existing load from some reliability requirements; 30 GW was not the size of the proposed LARS study queue.
the Joint Protestors pray the Commission reject MISO’s proposed Tariff grandfathering exemptions to ensure Large Load customers bear the cost and risk of all costs PDF p. 11
Google · Asks FERC to reject · ER27-25-000 · 2026-10-23
Google supported studying a load and its paired generation together, but said MISO filed LARS ahead of its cost-shifting protections. It asked FERC to reject LARS with guidance to refile alongside those protections or, in the alternative, accept and suspend it until they can be weighed together. It also wanted independent generators able to participate without discrimination by the serving utility.
the Commission should either reject LARS with guidance indicating that it needs to be filed concurrently with procedures to prevent cross-subsidization PDF p. 3
Bloom Energy · Supports with changes · ER27-25-000 · 2026-10-23
Bloom backed the study but challenged its 200 MW entry threshold. It proposed letting transmission-connected loads of at least 50 MW participate and asked FERC not to delay the requested start date.
LARS should therefore apply to loads of 50 MW or more that connect to the Transmission System. PDF p. 4
American Clean Power Association and Southern Renewable Energy Association · Asks FERC to reject · ER27-25-000 · 2026-10-23
The trade associations said studying accelerated projects without other generators already waiting could leave later studies with fewer feasible connections and higher costs. They objected to a permanent parallel route without a cap on total capacity.
the Clean Energy Trades respectfully request that the Commission reject MISO’s LARS proposal. PDF p. 30
Solar Energy Industries Association and Advanced Energy United · Asks FERC to reject · ER27-25-000 · 2026-10-23
The protesters asked FERC to reject the proposal or clarify that an applicant meeting all published requirements could not lose access at the transmission customer’s discretion.
SEIA and United respectfully request that the Commission reject the LARS proposal, on the grounds that the proposal is unduly discriminatory PDF p. 2
Clean Energy Advocates · Asks FERC to reject · ER27-25-000 · 2026-10-23
The advocates warned that two study tracks using different assumptions could count the same unused transmission capacity twice. They challenged assigning upgrade costs to existing customers based on agreements whose terms FERC had not seen.
For the reasons explained below, the Commission should reject the LARS proposal. PDF p. 1
Alliant Energy and Consumers Energy · Supports · ER27-25-000 · 2026-10-23
The utilities backed the readiness requirements because a speculative project could occupy one of a limited number of study slots. They argued the joint model could identify cheaper combined upgrades.
AECS and Consumers Energy respectfully request that the Commission accept the LARS Proposal. PDF p. 2
Entergy and Cleco · Supports · ER27-25-000 · 2026-10-23
The utilities said some ordinary MISO study cycles had taken four years or more. They supported the 120-day path and argued that its cap of ten load-generator pairs per study period would keep it workable.
the Entergy Operating Companies and Cleco Power respectfully request that the Commission accept MISO’s LARS filing. PDF p. 6
DTE Electric · Supports · ER27-25-000 · 2026-10-23
DTE supported the pairing rules and minimum commitment as evidence of a lasting commercial relationship. It also said the tariff allowed the interconnection customer to participate even though the transmission customer submits the application.
DTE Electric supports the LARS filing and respectfully requests that the Commission accept the filing as proposed. PDF p. 2
Midcontinent Independent System Operator · ER27-25-000 · 2026-10-02
MISO proposed LARS in a separate section 205 docket. It argued that modeling a matched pair could identify upgrades for the combination instead of each project separately. This was one proposed response to the June concerns. The full show cause case is still open.
Midcontinent Independent System Operator · ER27-25-000 · 2026-11-09
MISO said the transmission customer submits an application for an already matched pair. It argued that an independent generator remains free to bring a proposal to that customer before the application, and that the eligibility rules are nondiscretionary.
Midcontinent Independent System Operator · ER27-25-000 · 2026-11-09
MISO defended 200 MW based on its experience with large-load studies. It said modeling the load and several associated plants together offered the largest potential savings where loads and upgrades were especially large.
Midcontinent Independent System Operator · ER27-25-000 · 2026-11-09
MISO said the study should go ahead before related cost-recovery reforms were complete. It promised to incorporate those protections once FERC accepted them and cited other existing tariff mechanisms.
Northern Indiana Public Service Company · Supports · ER27-25-000 · 2026-10-22
NIPSCO asked FERC to accept MISO’s proposal effective December 2, 2026. It said it is considering requests to add between 3,000 and 8,000 MW of load, that the standard queue was not designed for paired load and generation, and that LARS would yield interconnection agreements in 120 days.
NIPSCO supports MISO’s LARS Proposal PDF p. 6
Base Electron, Corp. · Supports · ER27-25-000 · 2026-10-23
Base Electron supported timely acceptance and did not ask FERC to delay or condition LARS. It asked for confirmation that the 150% limit on interconnection service is measured against the load’s full expected peak, including planned later phases, not its first phase.
Base Electron supports timely acceptance of MISO’s LARS Tariff proposal PDF p. 2
MISO Transmission Owners · Supports · ER27-25-000 · 2026-10-23
The transmission owners asked FERC to accept LARS effective December 2, 2026. They said it would yield an agreement in an estimated 120 days, is limited to three study cycles a year with ten applications per cycle, and keeps LARS requests out of the standard queue studies. The group lists Southern Minnesota Municipal Power Agency and NIPSCO among its members; both also filed separately, and SMMPA protested one part of LARS.
The MISO Transmission Owners support MISO’s LARS Filing PDF p. 4
Data Center Coalition · Supports with changes · ER27-25-000 · 2026-10-23
The coalition supported approving LARS but objected that every application must come through the load-serving entity, which keeps third-party generators from applying directly. It asked FERC to encourage MISO to let generators with demonstrated commercial pairings apply directly, or to add transparency on how utilities select applications.
DCC supports approval of the proposed LARS framework, but requests FERC encourage MISO to consider improvements for independent generator access PDF p. 7
Southern Minnesota Municipal Power Agency and WPPI Energy · Opposes in part · ER27-25-000 · 2026-10-23
The two municipal power suppliers protested one aspect of LARS, the rule that any generator and load in the same Local Resource Zone can pair. They said it departs from the Show Cause Order’s two-substation example and excludes close pairs in different zones. They asked FERC to reject that scope and to condition acceptance on a later finding that MISO addressed cost allocation and transparency.
MISO’s Filing does not come close to justifying a departing from the Show Cause Order’s approach by substituting a geographic scope that is both overinclusive and underinclusive PDF p. 5
Geronimo Power · Asks FERC to reject · ER27-25-000 · 2026-10-23
Geronimo supported coordinated study in principle but said a generator cannot enter LARS without the transmission owner’s sign-off on its point of interconnection and a utility sponsor for the application. It also said MISO’s wording could exclude generators selling under virtual power purchase agreements and co-located generation and load. It asked FERC to reject LARS without prejudice to a revised filing.
Geronimo Power urges the Commission to reject LARS on the basis that it has not been shown to be just, reasonable, and not unduly discriminatory or preferential PDF p. 5
Invenergy Transmission · Supports with changes · ER27-25-000 · 2026-10-23
Invenergy said LARS fits FERC and DOE goals but that its definitions appear to admit only generating facilities. It asked FERC to direct MISO, on compliance, to clarify that merchant high voltage direct current lines and generation connected to them can participate, and attached a tariff redline.
Invenergy therefore respectfully requests that the Commission direct MISO, on compliance, to revise the proposed Tariff to clarify that MHVDC transmission lines are eligible to participate in the LARS process PDF p. 5
Geronimo Power · Asks FERC to reject · ER27-25-000 · 2026-11-18
Geronimo said MISO’s answer gave only a generic response on virtual power purchase agreements and did not address co-location and did not justify the roles of load-serving entities and transmission owners. It said a transmission owner could also remove a project by changing the point of interconnection. It again asked FERC to reject LARS without prejudice to a revised filing.
Geronimo Power urges the Commission to reject LARS without prejudice to MISO submitting a revised proposal that addresses the significant issues identified by Geronimo Power and other parties in this proceeding PDF p. 2
Southern Minnesota Municipal Power Agency and WPPI Energy · Opposes in part · ER27-25-000 · 2026-11-19
Answering MISO’s November 9 answer, the two suppliers said MISO’s “maximum flexibility” rationale does not show the zonal scope meets the Show Cause Order. They said cost-shifting protections rest on MISO’s separate Nov 16 filings, not the LARS tariff, and repeated that FERC should reject the geographic scope and condition acceptance rather than delay LARS.
the inclusion in LARS of pairs of generation and load that do not reduce the need for Network Upgrades (e.g., those not electrically proximate) risks crowding out those pairs that do create greater efficiencies PDF p. 7
These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.