ER27-25-000 · 2026-11-18 · Geronimo Power, LLC

Motion for Leave to Answer and Answer of Geronimo Power, LLC to the answer of Midcontinent Independent System Operator, Inc. filed on 11/09/2026

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
Operator, Inc.
)
)
)
)

Docket No. ER27-25-000

MOTION FOR LEAVE TO ANSWER AND ANSWER OF
GERONIMO POWER, LLC

Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“FERC”
or “Commission”) Rules of Practice and Procedure,1 Geronimo Power, LLC (“Geronimo Power”) hereby moves for leave to answer2 and files this answer to the answer3 of the Midcontinent Independent System Operator, Inc. (“MISO”) regarding its Large Load Addition Resource Study Process (“LARS”) proposal.4

I. ANSWER
Geronimo Power agrees with MISO’s assessment that the significant load growth that
MISO is experiencing requires MISO to adopt new processes to integrate new large loads and serve their demand.5  Geronimo Power’s comments in this proceeding commended MISO for its

1 18 C.F.R. §§ 385.212 and 385.213.
2 Geronimo Power acknowledges that the Commission’s Rules of Practice and Procedure do not typically allow answers to answers.  However, the Commission has accepted answers in the past when they have (i) assisted the Commission in understanding the issues presented, (ii) provided additional information for the Commission’s decision-making process, and (iii) helped ensure a complete and accurate record.  See, e.g., PJM Interconnection, L.L.C., 181 FERC ¶ 61,162, at P 29 (2022); Canal Generating LLC, 181 FERC ¶ 61,157, at P 14 (2022); Equitrans, L.P., 134 FERC ¶ 61,250, at P 6 (2011); Cal. Indep. Sys. Operator Corp., 132 FERC ¶ 61,023, at P 16 (2010).  In this proceeding, Geronimo Power’s answer will help the Commission understand the issues presented by MISO’s filing and provide further information related to the issues in this proceeding to inform the Commission’s decision-making process.  Geronimo Power therefore respectfully requests leave to file this answer and asks the Commission to consider this answer in its deliberations in this proceeding.
3 Midcontinent Indep. Sys. Operator, Inc., Docket No. ER27-25-000, Motion for Leave to Answer and Answer of the Midcontinent Independent System Operator, Inc. (Nov. 9, 2026) (“MISO Answer”).
4 Midcontinent Indep. Sys. Operator, Inc., Docket No. ER27-25-000, Large Load Addition Resource Study Process (Oct. 2, 2026) (“LARS Filing”).
5 MISO Answer at 3.

PDF page 2

2

efforts to address this challenge, but raised critical questions regarding whether MISO’s proposed LARS process would in fact achieve MISO’s goals while remaining consistent with open access principles.6  MISO’s Answer fails to meaningfully respond to the concerns raised by Geronimo Power.  Accordingly, Geronimo Power urges the Commission to reject LARS without prejudice to MISO submitting a revised proposal that addresses the significant issues identified by Geronimo Power and other parties in this proceeding.

A. MISO Has Not Addressed The Arbitrary And Unduly Discriminatory
Limitations LARS Places On Eligible Agreements And Co-Location
Arrangements

Geronimo Power demonstrated that the current design of LARS appears to limit the use of this process by large loads and generation resources that are pursuing certain supply arrangements that support resource adequacy and protect ratepayers.  For instance, Geronimo Power noted that MISO’s proposed tariff language appears to preclude interconnection customers that have entered into a virtual power purchase agreement (“PPA”) from submitting an application into the LARS process.7  Geronimo Power’s comments also questioned whether co-location arrangements would be eligible for LARS given MISO’s statements suggesting that co-location arrangements could only be pursued through MISO’s Zero Injection Generator Interconnection Agreement framework.8  MISO’s Answer provides no response or clarification to these issues. The only response offered in MISO’s Answer is a generic assertion that the agreement requirement is “flexible enough for projects with commercial certainty to participate” and that the “agreement requirement should not be made more flexible to allow in projects that do not meet the

6 Midcontinent Indep. Sys. Operator, Inc., Docket No. ER27-25-000, Motion to Intervene and Comments of Geronimo Power, LLC at 2-5 (Oct. 23, 2026) (“Geronimo Comments”).
7 Id. at 14-16.
8 Id. at 16-17.

PDF page 3

3

high hurdle that LARS is designed to maintain.”9  But Geronimo Power is not arguing for MISO to relax its standards.  A long-term virtual PPA provides the same level of commercial certainty as a long-term physical PPA and allowing this arrangement to qualify for LARS would in no way lower the bar MISO has set.  MISO’s restrictions on virtual PPAs and other supply arrangements arbitrarily prevent customers that are pursuing supply arrangements that are consistent with the objectives underlying LARS and the Show Cause Order from accessing the LARS process.10

Virtual PPAs increasingly are being used by large loads to support the construction of the new generation needed to meet their demand.11  Virtual PPAs accomplish exactly what MISO says LARS is intended to encourage: they de-risk new generation, support the entry of the capacity needed to offset the resource adequacy requirements of new large loads, and place the cost of resources on the large loads they will serve rather than on retail customers.12  Indeed, MISO’s own explanation of LARS confirms that allowing physical PPAs to qualify for LARS while excluding virtual PPAs makes little sense.  Specifically, MISO concedes that LARS does not require the

9 MISO Answer at 25.
10 See Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at P 113 (2026) (“Show Cause Order”).
11 See, e.g., Zachary Skidmore, Google Signs vPPA with Cypress Creek for 2.45 GW Solar Project in Arkansas – Report, Data Center Dynamics (July 14, 2026), https://www.datacenterdynamics.com/en/news/google- signs-vppa-with-cypress-creek-for-245gw-solar-project-in-arkansas-report (reporting that Google signed a long-term virtual PPA for the full output of the Steel River Energy Center, a 2.45 GW solar plus storage facility in Mississippi County, Arkansas and that the revenue commitment allowed the developer “to commence construction of the project”); EDP Global, EDP Renewables North America Delivers Three Additional Renewable Energy Projects for Microsoft (Feb. 10, 2025), https://edp.com/en/north-america/na/media/edp-renewables-north-america-delivers-three- additional-renewable-energy (noting that Microsoft “agreed to purchase 389 MW of electricity and renewable energy credits (RECs) from the projects [in Illinois and Texas] through long-term virtual power purchase agreements (VPPAs)”); Sustainability Roundtable, Inc., Akamai Technologies, Teradyne, and Wayfair Partner to Purchase Solar Energy in Champaign County, Ill. Through the Net Zero Consortium for Buyers, GlobeNewswire (Sept. 26, 2024), https://www.globenewswire.com/news-release/2024/09/26/2953870/0/en/Akamai-Technologies-Teradyne-and- Wayfair-Partner-to-Purchase-Solar-Energy-in-Champaign-County-Ill-Through-the-Net-Zero-Consortium-for- Buyers.html (describing an “aggregated virtual power purchase agreement” for the 135 MWac Prairie Solar project in development in the MISO region of Illinois).  See also Brian Martucci, Meta-Constellation virtual PPA could be first of many deals for existing reactor output: experts, UtilityDive (June 12, 2025), https://www.utilitydive.com/news/meta-constellation-ppa-could-be-first-of-many-deals-for-existing- reactors/750567/.
12 Geronimo Comments at 15-16.

PDF page 4

4

output of the generating facility to match the demand of load because that “is not the mechanism LARS uses to create value and potential savings.”13  If the physical delivery of energy to the load is irrelevant to the goal LARS is intended to achieve, there is no basis for excluding resources that are financially, rather than physically, committed to serving that load.  And while load-serving entities (“LSE”) and Alternative Retail Electric Suppliers have the option of obtaining LARS eligibility through “other types of agreements” that would allow for a wider range of commercial arrangements, this option is not available to independent power producers (“IPP”) and large loads14—a distinction that is unduly discriminatory and for which MISO has failed to provide any justification.

  MISO has similarly failed to justify excluding co-located load and generation from the LARS process.  Co-located load and generation supported by a long-term PPA or similar arrangement are similarly situated to electrically proximate pairs in every respect relevant to LARS: both pairings are based on a binding agreement between the two entities, are located in the same local resource zone, are studied together for their combined system impacts, and are intended to bring new generation online to serve a specific load.15  Indeed, co-location arrangements are better situated to achieve the goals of LARS because they are less likely to trigger transmission upgrades relative to generation that is merely “electrically proximate” to the load.  And the Commission’s Show Cause Order also made no distinction between these two arrangements.16  Yet MISO has refused to clarify that co-located load and generation will be eligible for LARS.

13 MISO Answer at 10.  See also id. at 24 (“MISO is not requiring a generating facility’s output to be matched to the demand of the electrically proximate large load.”). 14 LARS Filing, Proposed Tariff, Att. X § 3.12.2(i)(c); LARS Filing, Tab C, Prepared Direct Testimony of Christina Drake at 31-32.
15 See Geronimo Comments at 17-18 (citing Show Cause Order at P 113).
16 Id. at 16-18.

PDF page 5

5

MISO does not dispute Geronimo Power’s arguments that there is no reason to exclude co- location arrangements from LARS.  In fact, MISO concedes that “adjacent large loads and Generating Facilities may produce the most significant Network Upgrade optimization” and touts LARS as an “electrically proximate plus” construct that encourages generation and load to site “as close together as is practical.”17  Despite these concessions, MISO has offered no clarification that co-location arrangements are eligible for LARS.  MISO should not be permitted to design LARS around the electrical proximity of load and generation and then exclude the very pairings that have the closest electrical proximity and that it acknowledges will produce the greatest benefits.

B. MISO’s Answer Fails To Meaningfully Address The Unduly Discriminatory
Components Of LARS

Under the LARS process, a generation resource may enter into an agreement to serve a large load and otherwise meet all the criteria to participate in LARS but will nevertheless be ineligible unless a transmission customer—which MISO concedes will often be an LSE—agrees to submit a LARS application on its behalf.18  Moreover, this same generation resource and large load pairing will be ineligible for the LARS process unless the transmission owner of the system they are interconnecting to agrees to a proposed point of interconnection.19  These components of LARS effectively give incumbent utilities, in the form of LSEs and transmission owners, the ability to prevent otherwise viable generation and load pairings from accessing LARS. Although MISO says that it disagrees with commenters’ characterization of the LARS process as placing LSEs in a gatekeeper role,20 it does not offer any arguments or evidence to rebut commenters’ characterization.  MISO instead defends the gatekeeping role LSEs and transmission

17 MISO Answer at 11-12.
18 LARS Filing, Transmittal Letter at 6.
19 Id. at 8.
20 MISO Answer at 20.

PDF page 6

6

owners will be permitted to play in the LARS process on the grounds that, like its Expedited Project Review process, “LARS is a load-driven process, and an Interconnection Customer cannot require a Transmission Customer to scope their Transmission Service request around a generator they have not chosen to pair with.”21  MISO’s defense is flawed for numerous reasons.

To begin with, MISO’s argument on this point is circular.  To the extent that LARS is a load-driven process, that is only because MISO designed it as such.  It does not, however, absolve MISO of its obligation to demonstrate that the process it has designed is consistent with the Federal Power Act’s (“FPA”) prohibition on undue discrimination.  Indeed, if MISO’s rationale were to hold, public utilities would be permitted to adopt any unduly discriminatory interconnection policies so long as the design of the policies was intended to accomplish the utilities’ stated goals. MISO similarly dismisses the fact that Southwest Power Pool, Inc.’s (“SPP”) High Impact Large Load Generation Assessment (“HILLGA”) process provides generation resources with a non-discriminatory pathway to interconnect and serve electrically proximate large loads on the grounds that it is a “generator-driven process.”22  But MISO’s claim that LARS is a load-driven process ignores that LARS is not simply a load study; it is also a generator interconnection process that results in a resource obtaining a Large Load Generator Interconnection Agreement (“LLGIA”) and Network Resource Interconnection Service.23  Indeed, the key components of LARS are focused on the interconnection of a generation resource and the interconnection customer’s resulting interconnection rights.  MISO’s own filing, for instance, defines a LARS Application as “a form of Interconnection Request.”24  And under MISO’s proposal, the interconnection

21 Id.
22 Id. at 21.
23 LARS Filing, Tab C, Prepared Direct Testimony of Christina Drake at 12-13; id., Transmittal Letter at 6.
24 Id., Transmittal Letter at 7, n.29.

PDF page 7

7

customer—not the transmission customer or transmission owner—completes the generation portion of the application, satisfies the Attachment X requirements, posts the required security, executes the LLGIA, and bears responsibility for network upgrades.25  In contrast, MISO’s filing is largely devoid of explanation as to how a transmission customer is to obtain transmission service for a LARS Associated Load.

Even if the LARS process were accurately characterized as a load-driven process, MISO fails to justify requiring a commercially viable large load and its paired generation resource to obtain the support and consent of LSEs and transmission owners to access the process.  MISO asserts that so long as an interconnection customer and load can obtain the agreement of a transmission customer to initiate the LARS application, there is no barrier to them entering the LARS process and without such agreement “the pairing of load and generation in a coordinated study process would be premature and speculative.”26  MISO does not explain, however, why the ability of a generation resource to obtain the agreement of an incumbent utility to submit an application is a reasonable benchmark for commercial viability.  A generation developer only would be able to enter LARS if it has an executed long-term agreement with the entity that owns or controls the LARS Associated Load or the LARS Associated Transmission Customer already, 100% site control, and deposits in hand.  These measures already are sufficient to deter speculative requests and ensure the commercial viability of a proposed resource.  Requiring a generation developer and large load to obtain the agreement of the incumbent utility to submit the LARS

25 MISO has also failed to address discrepancies in its tariff that create ambiguity regarding the entity that is eligible to submit a LARS Application.  As Geronimo Power explained in its comments, although MISO states that a LARS Application may only be initiated by the LARS Associated Transmission Customer, proposed Section 3.12.1 of Attachment X states that “[p]rior to the applicable Transmission Owner submitting a LARS Application, the potential LARS Interconnection Customer and the Transmission Owner shall meet and agree on a definitive Point of Interconnection for the LARS Generating Facility.”  Geronimo Comments at 7, n.16 (emphasis added).  MISO’s Answer fails to clarify that the LARS Associated Transmission Customer is responsible for submitting the LARS application rather than the transmission owner.
26 MISO Answer at 20.

PDF page 8

8

application merely creates opportunities for undue discrimination that incumbent utilities can use to create barriers to entry without any corresponding benefit.

MISO’s defense of the requirement that the transmission owner pre-approve a project’s point of interconnection before a LARS application may be submitted is equally unsupported. MISO states that LARS “has stricter site control requirements such that the Transmission Owner must agree on the POI at the time of application submission” to ensure that only shovel-ready projects participate.27  But site control and a transmission owner veto are different things.  An interconnection customer can demonstrate site control and identify a point of interconnection without having to await the interconnecting transmission owner’s approval.  Indeed, in the generator interconnection context, no transmission owner consent to a point of interconnection is required, yet evidence of site control is still provided.28  And requiring transmission owner approval also does not provide meaningful protection against the risk that technical issues could arise that could lead the transmission owner or MISO to request a change in the point of interconnection during the study process.29

MISO also does not demonstrate that it is just and reasonable to require interconnection customers to bear the risk of a transmission owner-initiated change to the point of interconnection that occurs during the study process.  As Geronimo Power pointed out in its comments, MISO’s proposal not only requires the transmission owner to agree to the point of interconnection in order for a customer to enter the LARS process, but proposes language that would deem a customer’s request withdrawn if the transmission owner later changes its mind and proposes to modify the

27 Id. at 21.
28 See MISO Tariff, Att. X § 7.2.1(ii).
29 Geronimo Comments at 12-13.

PDF page 9

9

point of interconnection.30  The result is that the transmission owner holds not only an up-front veto over a project’s entry into LARS but also a continuing ability to remove the project from the process after the fact, and MISO offers no justification for placing the consequences of that unilateral decision on the interconnection customer rather than on the party that made it. Ultimately, MISO’s defense of the gatekeeping role that LSEs and transmission owners

will be permitted to play for LARS appears to hinge on a fundamental misunderstanding of the FPA’s prohibition on undue discrimination and the Commission’s open access principles.  MISO appears to believe that so long as its proposal does not expressly prohibit IPPs from accessing LARS, it is not unduly discriminatory.31  But that is not how courts or the Commission evaluate whether a proposal is unduly discriminatory and consistent with open access.  The Commission has repeatedly rejected proposals that provide the mere opportunity for undue discrimination by incumbent utilities.32  Moreover, whether a proposal is facially neutral—as MISO claims LARS is—has no bearing on whether its effect is unduly discriminatory and unlawful under the FPA.33

30 Id. at 13, n.31 (citing LARS Filing, Proposed Tariff, Att. X § 3.12.9).
31 MISO Answer at 20 (“LARS does not prevent Independent Power Producers (‘IPPs’) from competing to supply energy to large loads under applicable state and or [sic] utility-led RFP processes.”).  See also id. at 22 (“If an IPP has a generation project that is better, more cost effective, or otherwise preferable to alternatives, nothing in the LARS process stops the IPP from bringing this project forward for consideration and entering into a pairing arrangement with a LARS Transmission Customer.”).
32 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ 61,103, at PP 11, 696 (2003), order on reh’g, Order No. 2003‐A, 106 FERC ¶ 61,220 (2004), order on reh’g, Order No. 2003‐B, 109 FERC ¶ 61,287 (2005), order on reh’g, Order No. 2003‐C, 111 FERC ¶ 61,401 (2005), aff’d sub nom., National Ass’n of Regulatory Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007) (“The Commission would find any policy that creates opportunities for such discriminatory behavior to be unacceptable.”).
33 See Xcel Energy Servs. v. FERC, 41 F.4th 548, 559-60 (D.C. Cir. 2022) (quoting Pub. Serv. Co. of Colo., 172 FERC ¶ 61,297, at P 13 (2020)).

PDF page 10

10

II. CONCLUSION
Geronimo Power respectfully requests that the Commission issue an order consistent with its filings in this proceeding and reject LARS without prejudice to MISO submitting a revised proposal that addresses the significant issues identified by Geronimo Power and other parties in this proceeding.

Respectfully submitted,

/s/ Stephen J. Hug
Matthew Morais
Senior Director, Policy
Kurt Rempe
Assistant General Counsel
GERONIMO POWER, LLC
8400 Normandale Lake Blvd., Ste. 1200
Bloomington, MN 55437
mmorais@geronimopower.com
krempe@geronimopower.com

Stephen J. Hug
Ben N. Reiter
AKIN GUMP STRAUSS HAUER & FELD LLP
2001 K Street, N.W.
Washington, D.C.  20006
Tel: (202) 887-4084
shug@akingump.com
breiter@akingump.com
On behalf of Geronimo Power
Dated: November 18, 2026

PDF page 11

CERTIFICATE OF SERVICE

I hereby certify that I have caused the foregoing document to be served upon the individuals designated on the Commission’s official service list for this proceeding.

Dated at Washington, D.C., this 18th day of November 2026.

/s/ Stephen J. Hug

Stephen J. Hug
AKIN GUMP STRAUSS HAUER & FELD LLP
2001 K Street, N.W.
Washington, D.C.  20006
(202) 887-4084