Motion for Leave to Answer and Answer of Geronimo Power, LLC to the answer of Midcontinent Independent System Operator, Inc. filed on 11/09/2026
Text extracted from the eLibrary original (SHA-256 0b429cdcee2bd78d…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
ER27-25-000 MOTION FOR LEAVE TO ANSWER AND ANSWER OF GERONIMO POWER, LLC Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Rules of Practice and Procedure,1 Geronimo Power, LLC (“Geronimo Power”) hereby moves for leave to answer2 and files this…Read this passage Filed comments: Connecting load and generation
I. ANSWER
printed heading · Topic match: Connecting load and generation
Geronimo Power therefore respectfully requests leave to file this answer and asks the Commission to consider this answer in its deliberations in this proceeding. 3 Midcontinent Indep.Read this passage Filed comments: Connecting load and generation
A. MISO Has Not Addressed The Arbitrary And Unduly Discriminatory
printed heading · Topic match: Connecting load and generation
MISO’s restrictions on virtual PPAs and other supply arrangements arbitrarily prevent customers that are pursuing supply arrangements that are consistent with the objectives underlying LARS and the Show Cause Order from accessing the LARS process.10 Virtual PPAs increasingly are being used by large…Read this passage Filed comments: Connecting load and generation
B. MISO’s Answer Fails To Meaningfully Address The Unduly Discriminatory
printed heading · Topic match: Connecting load and generation
As Geronimo Power explained in its comments, although MISO states that a LARS Application may only be initiated by the LARS Associated Transmission Customer, proposed Section 3.12.1 of Attachment X states that “[p]rior to the applicable Transmission Owner submitting a LARS Application, the…Read this passage Filed comments: Connecting load and generation
II. CONCLUSION
printed heading · Topic match: Connecting load and generation
CONCLUSION Geronimo Power respectfully requests that the Commission issue an order consistent with its filings in this proceeding and reject LARS without prejudice to MISO submitting a revised proposal that addresses the significant issues identified by Geronimo Power and other parties in this…Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 18th day of November 2026. /s/ Stephen J.Read this passage