Motion to Intervene and Comments of Invenergy Transmission LLC on the Midcontinent Independent System Operator, Inc.’s Large Load Addition Resource Study filing
Text extracted from the eLibrary original (SHA-256 a2d35665f0a7803b…). Download the original from the official source.
Contents · 8 sections
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
ER27-25-000 MOTION TO INTERVENE AND COMMENTS OF INVENERGY TRANSMISSION LLC Pursuant to Rules 212 and 214 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”),1 Invenergy Transmission LLC (“Invenergy”) hereby submits this motion to intervene and…Read this passage Filed comments: Connecting load and generation
I. MOTION TO INTERVENE
printed heading · Topic match: Connecting load and generation
Accordingly, Invenergy requests that the Commission grant this motion, consistent with the public interest.Read this passage Filed comments: Connecting load and generation
II. COMMUNICATIONS
printed heading
COMMUNICATIONS Please address all notices and communications regarding this proceeding to the following persons who are also designated for service in this proceeding.Read this passage
III. INTRODUCTION
printed heading · Topic match: Connecting load and generation
INTRODUCTION On October 2, 2026, MISO submitted its LARS Filing, proposing a new study process under Section 3.12 of Attachment X of MISO’s Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”) “to facilitate the cost effective, timely and reliable integration of new…Read this passage Filed comments: Connecting load and generation
IV. COMMENTS
printed heading · Topic match: Connecting load and generation
COMMENTS Invenergy respectfully submits the following comments regarding eligibility for participation in the LARS process.Read this passage Filed comments: Connecting load and generation
A. The Commission Should Direct MISO To Revise Its Proposed Tariff To
printed heading · Topic match: Connecting load and generation
MISO’s existing Tariff thus treats these requests similarly, and there is no basis for departing from that equivalent treatment in the context of LARS.Read this passage Filed comments: Connecting load and generation
B. MHVDC Participation in LARS Advances the Goals of MISO, DOE and
printed heading · Topic match: Connecting load and generation
MISO recognizes that “the challenge presented by new large load growth is not limited to connecting the load itself” and “[s]ignificant new demand must be accompanied by sufficient resources to maintain reliability and resource adequacy.”15 The proposed revisions would advance this mandate by…Read this passage Filed comments: Connecting load and generation
V. CONCLUSION
printed heading · Topic match: Connecting load and generation
CONCLUSION For the foregoing reasons, Invenergy respectfully requests that the Commission consider these comments in acting on MISO’s proposed LARS process. 17 Id. at P 117. 18 Id. 19 See Speed to Power Initiative.Read this passage Filed comments: Connecting load and generation
Attachment A
printed heading · Topic match: Connecting load and generation
No changes shall be made to the LARS Application after submission and prior to the execution or the unexecuted filing of the LLGIA or LLTCA and MTEP approval for the LARS Associated Load except that a LARS Application that is deferred to the next available LARS Study Period will be allowed to…Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that on this 23rd day of October, 2026, a copy of the foregoing document has been electronically served upon each person designated on the official service list in this proceeding. /s/ Kathy Lowrey_ Kathy Lowrey 600 Fifth St NW Washington, D.C. 20001…Read this passage