Motion to Intervene and Comments of Invenergy Transmission LLC on the Midcontinent Independent System Operator, Inc.’s Large Load Addition Resource Study filing
PDF page 1
DCACTIVE-89594348.41
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator, Inc. )
Docket No. ER27-25-000
MOTION TO INTERVENE AND COMMENTS OF
INVENERGY TRANSMISSION LLC
Pursuant to Rules 212 and 214 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”),1 Invenergy Transmission LLC (“Invenergy”) hereby submits this motion to intervene and comments on the Midcontinent Independent System Operator, Inc.’s (“MISO”) proposed Large Load Addition Resource Study (“LARS”) process, filed in the above-captioned proceeding on October 2, 2026,2 pursuant to Section 205 of the Federal Power Act (“FPA”).3 For the reasons set forth below, Invenergy respectfully requests that the Commission direct MISO to clarify that Merchant High Voltage Direct Current (“MHVDC”) facilities and generating facilities interconnected to MHVDC are eligible to participate in LARS, thereby ensuring entities capable of providing capacity to large load customers seeking interconnection to the MISO system are able to do so through the LARS process.
I. MOTION TO INTERVENE
Invenergy respectfully moves to intervene in this proceeding.4 Invenergy and its affiliates develop generation and MHVDC transmission lines, including the 800-mile MHVDC Grain Belt Express transmission line, throughout the Midwest region. MHVDC transmission lines are capable
1 18 C.F.R. §§ 385.212, 385.214. 2 Midcontinent Independent System Operator, Inc., Large Load Addition Resource Study Process, Docket No. EL27-25-000 (filed Oct. 2, 2026) (“LARS Filing”).3 16 U.S.C. § 824d.4 18 C.F.R. § 385.214.
PDF page 2
DCACTIVE-89594348.42
of serving the large load customers whose interconnection needs are at issue in this proceeding, and Invenergy is in fact in advanced commercial negotiations to serve data center load in MISO, giving the company a substantial and direct interest in its outcome that cannot be adequately represented by any other party. Accordingly, Invenergy requests that the Commission grant this motion, consistent with the public interest.
II. COMMUNICATIONS
Please address all notices and communications regarding this proceeding to the following persons who are also designated for service in this proceeding.
Will Borders, Chief Compliance Officer
Nicole Luckey, Senior Vice President, Regulatory
Affairs
Invenergy LLC
One South Wacker Drive, Suite 1800
Chicago, IL 60606
Tel: 312-224-1400
NLuckey@invenergy.com
Ferccompliance@invenergy.com
Tyler O’Connor
Kathy Lowrey
Kathryn Douglass
Crowell & Moring LLP
600 Fifth St NW
Washington, DC 20001
Tel: 202-624-2500
toconnor@crowell.com
klowrey@crowell.com
kdouglass@crowell.com
III. INTRODUCTION
On October 2, 2026, MISO submitted its LARS Filing, proposing a new study process under Section 3.12 of Attachment X of MISO’s Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”) “to facilitate the cost effective, timely and reliable integration of new large loads into the system.”5 Under the proposed framework, MISO would coordinate the study of paired generation and new large loads on an expedited, parallel basis, enabling both to be brought online more efficiently than under existing interconnection procedures.6 With projected annual load growth of approximately 1-3% through 2044,7 new processes to facilitate the orderly
5 LARS Filing at 2.6 See id. at 5-7, 11-18 (describing the LARS study process). 7 Id. at 4.
PDF page 3
DCACTIVE-89594348.43
interconnection of large loads while safeguarding system reliability for all customers on the MISO system are necessary. The LARS Filing advances these objectives and is well-aligned with the goals of the Department of Energy’s (“DOE”) Speed to Power Initiative,8 which supports efforts to expedite large-scale transmission and generation infrastructure to address rapidly increasing electricity demand while keeping costs affordable and supporting the United States’ AI competitiveness. The Commission’s Show Cause Order likewise preliminarily found that MISO’s existing Tariff provisions may be unjust and unreasonable to the extent it fails to adequately address the integration of new large loads paired with generation.9 To fully achieve MISO’s stated purpose for the filing and to satisfy the objectives of both DOE and the Commission, MHVDC and associated generation should be eligible for the LARS process.
Invenergy is concerned that, as written, the LARS process inadvertently precludes certain entities—including MHVDC transmission lines and their associated generating facilities—from availing themselves of this new process, notwithstanding their ability to provide much-needed capacity to large load customers in MISO. Clarification is therefore necessary to ensure that MISO does not errantly restrict the pool of eligible participants and thereby undermine the efficacy of its proposal.
IV. COMMENTS
Invenergy respectfully submits the following comments regarding eligibility for participation in the LARS process. As discussed below, targeted clarifications to the proposed
8 Department of Energy, Speed to Power Initiative (Sept. 18, 2025) (“Speed to Power Initiative”), available at https://www.energy.gov/oe/speed-power.9 Midcontinent Independent System Operator, Inc., Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ 61,212 at P 113 (2026) (“Show Cause Order”).
PDF page 4
DCACTIVE-89594348.44
Tariff are necessary to ensure that the LARS process is available to all resource types capable of serving large load customers.
A. The Commission Should Direct MISO To Revise Its Proposed Tariff To
Clarify That MHVDC Transmission Lines and Associated Interconnected
Generation Should Be Eligible To Participate In LARS.
As currently drafted, several of the proposed Tariff definitions identify Generating Facilities10 as the sole type of resource that may be paired with a large load customer in the LARS process. The LARS Filing, however, is intended to facilitate the timely and reliable interconnection of large loads to the fullest extent practicable. Achieving this objective requires maximizing the pool of resources available to serve new large loads. Restricting LARS eligibility to Generating Facilities alone would arbitrarily exclude other resource types equally capable of delivering capacity, thereby undermining the very objectives the LARS Filing is designed to advance. In addition to Generating Facilities, two categories of resources are equally capable of serving large load customers—MHVDC transmission lines and the generating facilities interconnected to an MHVDC transmission line. These entities can deliver capacity in a manner functionally equivalent to a directly interconnected Generating Facility, and an MHVDC entity can contract with a large load customer to provide the capacity necessary to serve that customer’s load. Indeed, under Attachment X, MHVDC Connection Customers’ requests for injection rights are processed through the same study processes as Interconnection Requests submitted by Interconnection Customers seeking to interconnect Generating Facilities. MISO’s existing Tariff thus treats these requests similarly, and there is no basis for departing from that equivalent treatment in the context of LARS. The manner in which capacity is delivered to the Transmission
10 Capitalized terms not otherwise defined herein have the meaning set forth in MISO’s Tariff.
PDF page 5
DCACTIVE-89594348.45
System—whether directly or through an MHVDC transmission line—does not diminish the resource’s ability to reliably serve the paired load.
That MHVDC transmission lines and their associated generating facilities are equally able to timely serve large load customers is further supported by MISO’s own filing. MISO designed LARS to “address the electrically proximate large load portion of the [Show Cause] Order, by pairing generation with large load in the same LRZ.”11 MISO explained that it chose to “anchor” the LARS framework at the Local Resource Zone (“LRZ”) level, rather than on a more narrow geographic basis, so as not to constrain MISO’s ability to optimize transmission solutions.12 MHVDC transmission lines can satisfy this same requirement because each MHVDC transmission line maintains a designated Point of Connection at which it interconnects to the MISO system within a given LRZ.13 Accordingly, where a large load’s point of withdrawal is located in the same LRZ as an MHVDC transmission line’s Point of Connection, the large load and the MHVDC transmission line are electrically proximate under the LARS framework. MHVDC transmission lines and their associated generating facilities should therefore be eligible to participate in the LARS process on the same basis as directly interconnected Generating Facilities. Invenergy therefore respectfully requests that the Commission direct MISO, on compliance, to revise the proposed Tariff to clarify that MHVDC transmission lines are eligible to participate in the LARS process, as set forth in the redline attached hereto as Attachment A. There is no reason to exclude such resources if they are capable of satisfying all other applicable eligibility requirements of the LARS process, and their inclusion would meaningfully advance MISO’s ability to maintain resource adequacy across the region.
11 LARS Filing at 21.12 See id. at 21.13 See Tariff, Attachment X, section 1, Definitions – Point of Connection; see also id. at sections 3.2.4, 16.1, 16.2.
PDF page 6
DCACTIVE-89594348.46
B. MHVDC Participation in LARS Advances the Goals of MISO, DOE and
FERC to Facilitate Timely and Reliable Large Load Interconnection.
Clarifying the categories of resources eligible to participate in the LARS process would directly advance the objectives of MISO, the DOE, and the Commission to facilitate the timely, cost-effective, and reliable interconnection of large loads.
As MISO explained, it “designed [the LARS process] to facilitate the reliable integration of significant new load and generation on an accelerated timeline.”14 Including MHVDC transmission lines and their associated generating facilities in the pool of resources available through LARS would afford large load customers the opportunity to contract with a wider and more diverse range of resource types to meet their capacity needs. This clarification is critical precisely because all sources of generation must be available to serve large load. MISO recognizes that “the challenge presented by new large load growth is not limited to connecting the load itself” and “[s]ignificant new demand must be accompanied by sufficient resources to maintain reliability and resource adequacy.”15 The proposed revisions would advance this mandate by clarifying the range of eligible resource types.
The proposed fix would also address the Commission’s concerns in the Show Cause Order, in which the Commission preliminarily found MISO’s Tariff unjust and unreasonable for lacking generator interconnection procedures and services designed to facilitate the integration of new generating facilities intended to serve electrically proximate large loads.16 The Commission emphasized that this deficiency “will result in MISO’s current generator interconnection process failing to keep pace with the new large loads seeking to be integrated onto MISO’s transmission
14 LARS Filing at 5.15 Id.16 See Show Cause Order at PP 113-119.
PDF page 7
DCACTIVE-89594348.47
system,”17 and warned that it would produce “unnecessary interconnection delays, unnecessary Network Upgrades, and an otherwise inefficient expansion of the transmission system, imposing unnecessary delays and costs on transmission customers.”18 Ensuring LARS is available to all resources capable of satisfying its eligibility criteria would more fully address these concerns by mitigating the delays and inefficiencies identified in the Show Cause Order.
Finally, the proposed adjustments complement the goals of DOE’s Speed to Power
Initiative, which aims to “dramatically accelerate development timelines for large-scale transmission and generation projects . . . [and] ensure sufficient power to support American competitiveness in artificial intelligence while meeting rising demand for affordable, reliable and secure energy.”19 Ensuring that all capable resource types are eligible to participate in the LARS process is squarely aligned with these objectives and may, in some circumstances, identify sources of capacity that can be brought online more rapidly to meet rising demand.
V. CONCLUSION
For the foregoing reasons, Invenergy respectfully requests that the Commission consider these comments in acting on MISO’s proposed LARS process.
17 Id. at P 117.
18 Id.19 See Speed to Power Initiative.
DCACTIVE-89594348.410
Proposed Revisions: Attachment X
Definitions
Interconnection Customer shall mean any entity, including Transmission Provider, Transmission Owner or any of the Affiliates or subsidiaries of either, that proposes to interconnect its Generating Facility with the Transmission System. For the purposes of Large Load Addition Resource Study (LARS), Interconnection Customer shall refer to the entity developing the Generating Facility, or MHVDC Connection Customer, that will execute the LLGIA or Large Load Transmission Connection Agreement, as applicable, which may be a different entity from the LARS Associated Transmission Customer that submitted the LARS Application.
Interconnection Request shall mean (1) an Interconnection Customer’s request, in the form of Appendix 1 to the Generator Interconnection Procedures, to interconnect a new Generating Facility, or a request for the Expedited Resource Addition Study for a new generation capacity, or a request for the processing of a proposed Generating Facility or an MHVDC Connection Customer’s request as part of a Large Load Addition Resource Study, or to increase the capacity of, or make a Material Modification to the operating characteristics of, an Existing Generating Facility that is interconnected with the Transmission System, or to interconnect an Existing Generating Facility that is external to the Transmission System, or to change Energy Resource Interconnection Service to Network Resource Interconnection Service for an Existing Generating Facility; or (2) an MHVDC Connection Customer’s request, in the form of Appendix 1 to the Generator Interconnection Procedures, to obtain Injection Rights.
Large Load Addition Resource Study (LARS) shall mean the procedure as set forth in Section 3.12 of this GIP for studying an Interconnection Customer’s proposed Generating Facility or MHVDC Connection Customer’s request in parallel with the study of a LARS Associated Load Customer’s proposed load.
Large Load Addition Resource Study (LARS) Period shall mean the period of time in which Interconnection Requests for proposed Generating Facility or MHVDC Connection Customer’s request are studied in parallel with the study of a LARS Associated Load Customer’s proposed load. There are three LARS study periods in one year and each study period will run for approximately 120 days. All Interconnection Customers requesting to join the next Large Load Addition Resource Study (LARS) shall submit their Interconnection Request to the Transmission Provider no later than the LARS Application deadline as published on the MISO public website, which shall be at least twenty (20) Business Days prior to the scheduled kick-off of the LARS cycle published on the MISO public website.
Large Load Transmission Connection Agreement (LLTCA) shall mean the form of transmission connection agreement for merchant HVDC transmission facilities set forth in Appendix 2 to the MHCP, with modifications to reflect the Large Load Addition Resource Study Process. Unless otherwise provided, all requirements applicable to the Transmission Connection Agreement shall apply to the LLTCA. A LLTCA is a form of TCA and, where used in the Tariff, references to Transmission Connection Agreement or TCAs encompasses LLTCAs.
PDF page 11
DCACTIVE-89594348.411
LARS Application shall be a single submission consisting of the materials required for LARS processing as required by Section I.D.1.b.ii of Attachment FF to the Tariff as well as the information required for studying the Generating Facilities or the MHVDC Connection Customer’s request under this Attachment X (in the form of Appendix 1) to these generator interconnection procedures. For purposes of this GIP, a LARS Application shall be a form of Interconnection Request.
LARS Associated Load shall mean a source of electrical load that is at least 200 MW and that is formally paired with one or more Interconnection Customer(s) that have submitted an Interconnection Request to LARS proposing one or more new Generating Facility(ies) or an MHVDC Connection Customer’s request to provide energy to such load.
Section 3.2
At the time the Interconnection Request is submitted, Interconnection Customer must request NR Interconnection Service, ER Interconnection Service or Surplus Interconnection Service, as described; provided, however, any Interconnection Customer requesting NR Interconnection Service may also request that it be concurrently studied as an ER Interconnection Service, up to the expiration of Interconnection Customer Decision Point II. Interconnection Customer may then elect to proceed with NR Interconnection Service or to proceed under a lower level of NR Interconnection Service to the extent that only certain upgrades will be completed. A description of the modeling details used when studying a project as ER Interconnection Service or NR Interconnection Service can be found in Section 6 of the Generator Interconnection Business Practices Manual (BPM-015). MHVDC Connection Customer may only request Injection Rights pursuant to Section 16 or Section 3.12 of the GIP and shall not be eligible to receive any Interconnection Services specified in the GIP. Section 3.5.4
Section 3.5.4
(3) In the event that affected systems studies and cost information are not available at the time the LLGIA or LLTCA is tendered, such LLGIA or LLTCA shall include an obligation to execute any agreements for the study, construction, or funding of Network Upgrades identified by the Affected System within fifteen (15) Calendar Days after such agreement is tendered for execution to the Interconnection Customer . . .
Section 3.12.1
Prior to the applicable Transmission Owner submitting a LARS Application, the potential LARS Interconnection Customer and the Transmission Owner shall meet and agree on a definitive Point of Interconnection for the LARS Generating Facility or MHVDC Transmission Line …
The Transmission Owner will have a minimum of fifteen (15) Business Days to provide an attestation and approve a valid Point of Interconnection. The Transmission Owner and LARS Interconnection Customer shall jointly agree upon a feasible Point of Interconnection no later
PDF page 12
DCACTIVE-89594348.412
than ten (10) Business Days prior to the next LARS Application deadline as published on the MISO public website. An Interconnection Request seeking LARS Interconnection Service must include an attestation that the Transmission Owner and LARS Interconnection Customer have agreed upon the Point of Interconnection for the Generating Facility or MHVDC Transmission Line for which LARS processing is sought.
Section 3.12.2
(i) The Interconnection Request shall be accompanied by an agreement executed by the Interconnection Customer and either the LARS Associated Transmission Customer or the entity that owns or controls the LARS Associated Load evidencing that the output of the Generating Facility or MHVDC Transmission Line for which LARS processing is sought shall be used to provide energy to the LARS Associated Load …
(iv) The Interconnection Request shall include a one-line diagram showing the Generating Facility(ies) or MHVDC Transmission Line and associated electrical equipment with appropriate rating and impedance information.
(v) The Interconnection Request shall include a detailed power flow model for the proposed Generating Facility or MHVDC Transmission Line that includes the Point of Interconnection for the Interconnection Request and any proposed system protection facilities. Such model must be submitted in a format specified by the Generator Interconnection Business Practices Manual and align with the data provided in the Interconnection Request, including the one-line diagram required in Section 3.12.2.iv of these GIP …
(vii) The Interconnection Request seeking LARS processing shall specify a Commercial Operation Date for the Generating Facility or MHVDC Transmission Line and a date by which the LARS Associated Load shall commence service for the full amount of transmission service requested in the LARS Application that is not later than three (3) years from the date such Interconnection Request is submitted …
No changes shall be made to the LARS Application after submission and prior to the execution or the unexecuted filing of the LLGIA or LLTCA and MTEP approval for the LARS Associated Load except that a LARS Application that is deferred to the next available LARS Study Period will be allowed to extend its In-Service Date or Commercial Operation Date to be no more than three calendar years from the kickoff of the LARS Study Period in which its LARS Application is studied …
Section 3.12.4
The Interconnection Study for LARS will follow the same manner of NR Interconnection Study as noted in Sections 3.2.1.2 and 3.2.2.2 needed to integrate the Generating Facility in the same manner as for any Generating Facility being designated as a Network Resource. Transmission Provider will use Reasonable Efforts to study LARS Interconnection Requests from all
PDF page 13
DCACTIVE-89594348.413
Interconnection Customers regardless of Generating Facility or MHVDC Transmission Line within sixty (60) Calendar Days after the kickoff date for such study. . . . Section 3.12.5 - Notice to Proceed to LLGIA or LLTCA.
Section 3.12.6
Transmission Provider shall tender a draft pro forma LLGIA or LLTCA, as applicable, that conforms to the pro forma GIA or pro forma TCA in effect at the time, as modified for LARS, no later than 90 Calendar Days after the date LARS studies commence for such Interconnection Request with a confirmed Notice to Proceed… Upon tender of the LLGIA or LLTCA, the LARS Interconnection Request shall be subject to the timing and procedures set forth in Sections 11.1 through 11. 4 of these GIP.
Transmission Provider shall include in the final LLGIA or LLTCA any Affected System Study results and information regarding Network Upgrades from Affected Systems provided the Affected System Study Reports are available. If Affected System analysis is not available for inclusion in the final LLGIA or LLTCA, the Transmission Provider shall provide such analysis separately when received from the applicable Affected System …
Section 3.12.7.2
Interconnection Customers are eligible to receive one hundred percent (100%) refund of the Large Load Addition Resource Study entry milestone (M2) upon withdrawal prior to execution or unexecuted filing of the final LLGIA or LLTCA. Interconnection Customers that terminate the LLGIA or LLTCA after execution or unexecuted filing are eligible to receive a refund of the remaining M2 milestone payment.
Section 3.12.7.3
In the event the Interconnection Customer has elected to make its milestones in the form of cash, Transmission Provider will transfer the Large Load Addition Resource Study milestone to the appropriate Transmission Owner to satisfy the initial payment requirement of the Large Load Generator Interconnection Agreement, TCA or other applicable service agreement within the timeline specified in the Appendix B of the LLGIA or Exhibit B11 of the LLTCA. Provided that the Interconnection Customer has not requested withdrawal, is deemed withdrawn, or is pending termination of its applicable service agreement, the Transmission Provider shall refund milestone cash payments exceeding the initial payment requirement to the Interconnection Customer upon Interconnection Customer’s request with Transmission Owner’s consent, within forty-five (45) Calendar Days of the later effective date of the LLGIA, or LLTCA, or other applicable construction agreements. In the event the milestone payments are less than the initial payment requirement, the Interconnection Customer shall be responsible for the remaining payment to the Transmission Owner.
Section 3.12.7.4
PDF page 14
DCACTIVE-89594348.414
In the event that the Interconnection Customer’s LLGIA or LLTCA is terminated after execution by all parties or after LLGIA or LLTCA is filed unexecuted, the Interconnection Customer will be responsible for the costs of the Network Upgrades that are classified as GIPS and documented in the LLGIA, LLTCA, and/or corresponding FCAs or MPFCAs, including those GIP Network Upgrades arising from the Affected System Study process …
In the event that the LARS Associated Load is withdrawn from LARS or ceases use of the Transmission Service granted through LARS within the first fifteen (15) Calendar Years after the LARS Associated Load commences use of the Transmission Service granted through LARS, then operations of the Generating Facility shall be subject to the Annual ERIS (“AERIS”) and Quarterly Operating Limit (“QOL”) for a one year period until termination as set forth in Article 2.3.1 of Attachment X Appendix 6 or the LLTCA. An Interconnection Customer that desires to continue injections shall be required to obtain Interconnection Service or injection rights through the DPP as described in Attachment X. The LLGIA will be terminated after the period specified in Article 2.3.1, or applicable injection rights under the LLTCA, as relevant. Following the first fifteen (15) Calendar Years after a LARS Associated Load ceases use of its Transmission Service or if the agreement required by GIP Section 3.12.2.i is terminated or otherwise ceases to be in effect, then Transmission Provider shall not terminate the Generating Facility’s Interconnection Service or the MHVDC Connection Customer’s injection rights with respect to the LARS Associated Load.
Once MTEP approval occurs for the LARS Associated Load, the LARS Associated
Transmission Customer remains responsible for the identified BRPs and Other assigned projects even if such LARS Associated Load does not commence service. In addition, if the LLGIA or LLTCA for a LARS Associated Load is terminated, the LARS Associated Transmission Customer remain responsible for the costs thereof …
Section 3.12.9
After submission of the LARS Application, no modification to the Interconnection Request or any of its parameters, including any information provided by the Transmission Owner such as the agreed-upon Point of Interconnection, is permitted under Section 4.4 or otherwise prior to the execution or unexecuted filing of the final LLGIA or LLTCA. Any modification made by the Interconnection Customer, LARS Associated Transmission Customer, or Transmission Owner prior to the execution or unexecuted filing of the final LLGIA or LLTCA shall cause the LARS Interconnection Request to be deemed withdrawn.
After entering the Large Load Addition Resource Study as defined in Section 3.12.4, no changes to the In-Service Date or Commercial Operation Date of the Generating Facility is permitted via section 4.4.4 except that a LARS Application that is deferred to the next available LARS Study Period will be allowed to extend its In-Service Date or Commercial Operation Date to be no more than three calendar years from the kickoff of the LARS Study Period in which its LARS Application is studied. At the completion of the Large Load Addition Resource Study, the
PDF page 15
DCACTIVE-89594348.415
Commercial Operation Date and Service Commencement Date for the LARS Associated Load shall be set forth in the LLGIA or LLTCA …
Section 11.1
Throughout this Section 11, the applicable Interconnection Facilities Study for a GIA shall be the Interconnection Facilities Study that was initiated for that project in DPP Phase II. For EGIAs, LLTCAs, or LLGIAs, this shall be the applicable Interconnection Facilities Study initiated through ERAS or LARS. Throughout this Section 11, the applicable Interconnection Facilities Study for a Network Upgrade that is addressed in a FCA or MPFCA or GIA shall be the Interconnection Facilities Study performed for that Network Upgrade. For Interconnection Requests initiated through LARS, the Final System Impact Study shall be the LARS System Impact Study.
Section 11.3
Transmission Provider shall provide to Interconnection Customer and Transmission Owner a final GIA, and, as applicable, final JTIQ Service Agreement(s), final FCA(s) and/or final MPFCA(s) prepared for execution by the parties within fifteen (15) Business Days after the completion of the forty (40) Business Day negotiation period in accordance with Section 11.2 of this GIP. For Interconnection Requests for an ERAS, the Transmission Provider shall provide to Interconnection Customer and Transmission Owner a final EGIA within ten (10) Business Days after the completion of the negotiation period in accordance with Section 11.2 of this GIP. For LARS Interconnection Requests, the Transmission Provider shall provide to Interconnection Customer and Transmission Owner a final LLGIA or LLTCA executed by Transmission Provider, within fifteen (15) Business Days after the completion of the negotiation period in accordance with Section 11.2 of this GIP. Within forty-five (45) Calendar Days of tender of the final GIA, and within fifteen (15) Business Days for LLGIA and LLTCA, and, as applicable, final JTIQ Service Agreement(s), final FCA(s) and final MPFCA(s), Interconnection Customer and Transmission Owner shall either: (i) execute the tendered GIA or LLGIA, and, as applicable, final JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s); or (ii) request in writing that Transmission Provider file with FERC the GIA, LLGIA, LLTCA, and, as applicable, JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s) in unexecuted form.
If Interconnection Customer has neither executed the GIA, LLTCA, or LLGIA, and, as applicable, tendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s), nor requested filing of the GIA, LLGIA, or LLTCA, and, as applicable, JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s) in unexecuted form within forty-five (45) Calendar Days, or for Interconnection Requests in an ERAS ten (10) Business Days, or for Interconnection Requests in LARS fifteen
(15) Business Days, of tender of the final GIA, LLGIA, LLTCA, and, as applicable, JTIQ Service Agreement(s), final FCA(s) and final MPFCA(s), Interconnection Customer shall be deemed to have withdrawn its Interconnection Request. The Interconnection Customer’s forty- five (45) Calendar Day deadline for execution will not reset in the event that an additional change is made to the GIA, LLGIA, LLTCA, JTIQ Service Agreement(s), FCA, or MPFCA after circulation for execution.
PDF page 16
DCACTIVE-89594348.416
Within ten (10) Business Days after receiving from the Interconnection Customer(s) and the Transmission Owner either the executed tendered GIA, LLTCA or LLGIA, and, as applicable, tendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s) or the request to file an unexecuted GIA, LLTCA or LLGIA, and, as applicable, tendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s), Transmission Provider shall report or file the GIA, LLTCA or LLGIA, and, as applicable, tendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s) with FERC, together with its explanation of any matters as to which Interconnection Customer, Transmission Owner and Transmission Provider disagree and support for the costs that Transmission Owner proposes to charge to Interconnection Customer under the GIA, LLTCA or LLGIA and, as applicable, tendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s). An unexecuted GIA, LLTCA or LLGIA, and, as applicable, JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s), shall contain terms and conditions deemed appropriate by Transmission Provider for the Interconnection Request.
Section 11.4
If Interconnection Customer executes the final GIA, LLTCA, or LLGIA and, as applicable, tendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s) Transmission Provider, Transmission Owner and Interconnection Customer shall perform their respective obligations in accordance with the terms of the GIA, LLTCA, or LLGIA and, as applicable, tendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s), subject to modification by FERC. Unless otherwise agreed by all Parties, upon submission of an unexecuted GIA, LLTCA, or LLGIA, and, as applicable, unexecuted tendered JTIQ Service Agreement(s), unexecuted FCA(s) and/or unexecuted MPFCA(s), the Parties shall promptly comply with the unexecuted GIA, LLTCA, or LLGIA, and, as applicable, unexecuted JTIQ Service Agreement(s), unexecuted FCA(s) and/or unexecuted MPFCA(s), subject to modification by FERC. As applicable, compliance with the terms of such unexecuted JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s) or execution and performance under a JTIQ Service Agreement(s), FCA and/or MPFCA will be a requirement under the GIA, LLGIA or LLTCA.
Appendix 1
1. [The undersigned Interconnection Customer submits this request to interconnect its Generating Facility, located in ______________ County, [ State], with the Transmission System pursuant to the Tariff.] or;
[The undersigned MHVDC Connection Customer submits this request for Injection Rights for its MHVDC Transmission Line, located in ______________ County, [ State], with the Transmission System pursuant to a Tariff.];
[The undersigned Interconnection Customer submits this request to interconnect its Generating Facility, located in ______________ County, [ State], located in ____________County, [________State], with the Transmission System pursuant to the Tariff as part of a LARS Application.] [The undersigned Interconnection Customer submits this request to interconnect its MHVDC Transmission Line and/or Generating Facility, located in ______________ County, [
PDF page 17
DCACTIVE-89594348.417
State], located in ____________County, [________State], with the Transmission System pursuant to the Tariff as part of a LARS Application.]
4.j. An agreement executed by the Interconnection Customer and the entity that owns or controls the LARS Associated Load evidencing that the output of the Generating Facility or MHVDC Transmission Line for which LARS processing is sought is intended to be used to provide energy to the LARS Associated Load. Such agreement shall meet the requirements of Section 3.12.2 of the Generator Interconnection Procedures (for LARS Application);
4.l. The attestation required by Section 3.12.1 of the Generator Interconnection Procedures confirming agreement upon the Point of Interconnection for the Generating Facility or MHVDC Transmission Line (for the LARS Application).
Appendix 1, Attachment A-4
A LARS Interconnection Request seeking Interconnection Service shall include:
(1) A detailed power flow model for the proposed Generating Facility or MHVDC Transmission Line…
Proposed Revisions: Attachment FF
Section I.D.1.b.ii(c)
The anticipated Service Commencement Date for the LARS Associated Load listed in the LARS Application shall be no later than three calendar years from the submission date of the LARS Application and shall be identical to the Commercial Operation Date listed for the Generating Facility or MHVDC Transmission Line in the LARS Interconnection Request.
Section I.D.1.b.ii(g) - Termination of LLGIA, LLTCA, and/or Withdrawal of Large Load In the event that the Interconnection Customer’s LLGIA or LLTCA is terminated after execution by all parties or after LLGIA or LLTCA is filed unexecuted, the Interconnection Customer will be responsible for the costs of the Network Upgrades that are classified as GIPS and documented in the LLGIA, LLTCA and/or corresponding FCAs or MPFCAs, including those GIP Network Upgrades arising from the Affected System Study process.
Once MTEP approval occurs for the LARS Associated Load, the LARS Associated Transmission Customer remains responsible for the identified BRPs and Other assigned projects even if such LARS Associated Load does not commence service or commences service for less than the total amount of the LARS Associated Load. In addition, if the LLGIA or Large Load Transmission Connection Agreement for a LARS Associated Load is terminated, the LARS Associated Transmission Customer remain responsible for the costs thereof …
Section I.D.1.b.ii(j)
PDF page 18
DCACTIVE-89594348.418
In accordance with the LARS definitions, Section 3.3.1, and Section 3.12 of Attachment X, and notwithstanding the requirements of Section I.D.1.b.ii, a generating solution that does not yet have generator interconnection agreement filed with the Commission pursuant to Attachment X of this Tariff may be considered as an alternative transmission solution if: (1) a valid Interconnection Request for such Generating Facility has been submitted for processing under the LARS process specified by Attachment X to the Tariff . . .
PDF page 19
DCACTIVE-89594348.419
CERTIFICATE OF SERVICE
I hereby certify that on this 23rd day of October, 2026, a copy of the foregoing document has been electronically served upon each person designated on the official service list in this proceeding.
/s/ Kathy Lowrey_
Kathy Lowrey
600 Fifth St NW
Washington, D.C. 20001
klowrey@crowell.com