ER27-25-000 · 2026-10-23 · WPPI EnergySouthern Minnesota Municipal Power Agency

Motion to Intervene and Limited Protest of Southern Minnesota Municipal Power Agency and WPPI Energy re Midcontinent Independent System Operator, Inc.’s…

Text extracted from the eLibrary original (SHA-256 8aaf04935a9a4ec6…). Download the original from the official source.

Contents · 8 sections
  1. I. MOTION TO INTERVENE p. 3
  2. II. LIMITED PROTEST p. 4
  3. A. MISO does not show that its proposed geographic scope for p. 4
  4. B. Additional cost allocation issues must be addressed in future p. 9
  5. CONCLUSION p. 10
  6. ATTACHMENT A p. 12
  7. ATTACHMENT A: DESCRIPTION OF MIDWEST TDUS p. 13
  8. Attachment A p. 14

Read topic-matched comments in ER27-25

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

Finally, Midwest TDUs appreciate that MISO’s LARS proposal requires that the LARS Interconnection Customer remain responsible for identified Generator Interconnection Project (“GIP”) Network Upgrades, and the LARS Associated Transmission Customer remain responsible for any identified Baseline…
Read this passage Filed comments: Connecting load and generation

I. MOTION TO INTERVENE

printed heading

MOTION TO INTERVENE Each Midwest TDU (described in Attachment A hereto) moves to intervene with full rights as parties to this proceeding.
Read this passage

II. LIMITED PROTEST

printed heading

II.
Read this passage

A. MISO does not show that its proposed geographic scope for

printed heading · Topic match: Connecting load and generation

Moreover, MISO’s LARS construct already contains numerous elements that broaden the scope of what should be a streamlined study process, e.g.: 14 Transmittal Letter at 21. - 7 - • allowing generation at multiple Points of Interconnection for a single LARS Associated Load, with separate Applications…
Read this passage Filed comments: Connecting load and generation

B. Additional cost allocation issues must be addressed in future

printed heading · Topic match: Connecting load and generation

Additional cost allocation issues must be addressed in future proceedings.
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading · Topic match: Connecting load and generation

Bayne Attorneys for Midwest TDUs Law Offices of: Spiegel & McDiarmid LLP 1818 N Street, NW 8th Floor Washington, DC 20036 (202) 879-4000 October 23, 2026
Read this passage Filed comments: Connecting load and generation

ATTACHMENT A

printed heading

ATTACHMENT A A-1
Read this passage

ATTACHMENT A: DESCRIPTION OF MIDWEST TDUS

printed heading

ATTACHMENT A: DESCRIPTION OF MIDWEST TDUS Southern Minnesota Municipal Power Agency (“SMMPA”) is a joint action agency composed of seventeen member municipalities in Minnesota that own and operate municipal electric systems.
Read this passage

Attachment A

printed heading

Attachment A A-2 its members from generation resources owned by WPPI and through purchased power contracts.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated on this 23rd day of October, 2026. /s/ Jeffrey M.