ER27-25-000 · 2026-10-23 · WPPI EnergySouthern Minnesota Municipal Power Agency
Motion to Intervene and Limited Protest of Southern Minnesota Municipal Power Agency and WPPI Energy re Midcontinent Independent System Operator, Inc.’s…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
Operator, Inc.
Docket No. ER27-25-000
MOTION TO INTERVENE AND LIMITED PROTEST
OF SOUTHERN MINNESOTA MUNICIPAL POWER
AGENCY AND WPPI ENERGY
Pursuant to Rules 211, 212, and 214 of the Federal Energy Regulatory Commission’s (the “Commission”) Rules of Practice and Procedure,1 and the Commission’s October 2, 2026 Combined Notice of Filings #1,2 Southern Minnesota Municipal Power Agency (“SMMPA”) and WPPI Energy (“WPPI”) (collectively, “Midwest TDUs”) each moves to intervene in this proceeding and together submit this Limited Protest of Midcontinent Independent System Operator, Inc.’s (“MISO”) October 2, 2026 filing to revise its Open Access Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”) to establish a Large Load Addition Resource Study (“LARS”) process.3 As MISO explains, its LARS proposal is responsive to the Commission’s June 18, 2026 Show Cause Order,4 specifically the Commission’s preliminary finding “that MISO’s existing Tariff may be unjust and unreasonable because it does not provide
1 18 C.F.R. §§ 385.211, 385.212, 385.214. 2 eLibrary No. 20261002-3077.3 MISO, Large Load Addition Resource Study Process (Oct. 2, 2026), eLibrary No. 20261002-5074 (“MISO Filing”).4 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).
PDF page 2
- 2 -
generator interconnection study procedures and services that account for the operational dynamics of serving electrically proximate large loads.”5
Midwest TDUs protest one aspect of MISO’s Filing: MISO’s proposal to make paired generation and load within the same Local Resource Zone (“Zone” or “LRZ”) eligible for the LARS process. This geographic scope is materially different from what the Commission contemplated in its Show Cause Order, which defined “electrically proximate” as a large load located no more than two substations away from the generating facility. MISO’s proposed scope is both significantly overinclusive (including paired generation and load that may be hundreds of miles and multiple states apart) and underinclusive (excluding pairs that may be within two or fewer substations but in different Zones).
Finally, Midwest TDUs appreciate that MISO’s LARS proposal requires that the LARS Interconnection Customer remain responsible for identified Generator Interconnection Project (“GIP”) Network Upgrades, and the LARS Associated Transmission Customer remain responsible for any identified Baseline Reliability Projects or Other assigned Network Upgrades. While this requirement is necessary for LARS to be just, reasonable, and not unduly discriminatory, it is not sufficient. MISO states that it intends to make a future Federal Power Act (“FPA”) section 2056 filing to address additional cost allocation and transparency issues raised in the Show Cause Order. The Commission should therefore condition any acceptance on MISO’s filing in this proceeding on the Commission finding, in future proceeding(s), that MISO has
5 MISO Filing, Transmittal Letter at 3 (“Transmittal Letter”) (citing Show Cause Order P 113). 6 16 U.S.C. § 824d.
PDF page 3
- 3 -
satisfied its obligations with respect to the Show Cause Order’s discussion of cost allocation and transparency as applied to LARS. Midwest TDUs reserve all rights with respect to additional future MISO filings in response to the Show Cause Order.
I. MOTION TO INTERVENE
Each Midwest TDU (described in Attachment A hereto) moves to intervene with full rights as parties to this proceeding. As market participants, load-serving entities, and customers under MISO’s Tariff, Midwest TDUs will be directly affected by MISO’s proposed Tariff revisions. They each have clear and substantial interests in this proceeding that cannot be represented by any other party, and their participation would be in the public interest. Midwest TDUs should therefore each be granted intervention. Communications regarding this proceeding should be directed to the following:7 Cynthia S. Bogorad
Jeffrey M. Bayne
SPIEGEL & MCDIARMID LLP
1818 N Street, NW
8th Floor
Washington, DC 20036
Phone: (202) 879-4000 (Phone)
Fax: (202) 393-2866 (Fax)
Email: cynthia.bogorad@spiegelmcd.com
jeffrey.bayne@spiegelmcd.com
WPPI:
Tom Hanrahan, General Counsel
WPPI ENERGY
1425 Corporate Center Drive
Sun Prairie, WI 53590-9109
Phone: (608) 834-4556
Email: thanrahan@wppienergy.org
SMMPA:
Jeremy Sutton
Director of Operations and COO
SOUTHERN
MINNESOTA
MUNICIPAL
POWER AGENCY
500 First Avenue, SW
Rochester, MN 55902-3303
Phone: (507) 292-6444
Fax: (507) 292-6414
Email: jb.sutton@smmpa.org
Seth Koneczny
Manager of Power Delivery
SOUTHERN
MINNESOTA
MUNICIPAL
POWER AGENCY
500 First Avenue, SW
Rochester, MN 55902-3303
Phone: (507) 292-6456
Fax: (507) 292-6414
Email: st.kneczny@smmpa.org
7 Midwest TDUs request waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b)(3), so as to permit more than two entries on the official service list in order to enable Midwest TDUs to promptly receive all communications in the proceeding.
PDF page 4
- 4 -
II. LIMITED PROTEST
A. MISO does not show that its proposed geographic scope for
paired generation and load eligible for LARS is just, reasonable,
and not unduly discriminatory.
In the Show Cause Order, the Commission preliminarily found that MISO’s Tariff appears to be unjust and unreasonable because it lacks a generator interconnection study process and/or generator interconnection service applicable to generation facilities serving “electrically proximate large load[s].”8 The Commission used the term “electrically proximate large load” in the Show Cause Order to mean:9 a large load . . . sufficiently electrically close to the
interconnection
customer’s
requested
point
of
interconnection, such that the impact on the transmission
system of the combination of the generating facility and the
load, with the exception of the transmission facilities
between the two, will be effectively the same as if they were
located at the same substation (e.g., large load that is located
no more than two substations away from the generating
facility).
When paired load and generation are located close enough such that they have the same impact on the transmission system as if they were located at the same substation, the Commission preliminarily found that reliance on MISO’s current generation interconnection processes may be unjust and unreasonable because it results in “unnecessary interconnection delays, unnecessary Network Upgrades, and an otherwise
8 Show Cause Order P 113.
9 Id. P 112.
PDF page 5
- 5 -
inefficient expansion of the transmission system, imposing unnecessary delays and costs on transmission customers.”10
In response, MISO’s proposed a new LARS process that would provide
“expedited review” to “streamline the MISO generator and load interconnection process” for certain generation and large loads.11 But rather than adopting the Commission’s electrically proximate large load concept (i.e., located no more than two substations away from the generating facility), MISO proposes that its LARS process apply to paired load and generation located in the same Local Resource Zone (“Zone” or “LRZ”).12 MISO’s Filing does not come close to justifying a departing from the Show Cause Order’s approach by substituting a geographic scope that is both overinclusive and underinclusive.
MISO Zones can span hundreds of miles and cross multiple states.13 For example, MISO Zone 1 covers parts of eastern Montana, northeast South Dakota, North Dakota, most of Minnesota, western Wisconsin, and small portions of northeast Iowa and northwest Illinois. As a result, MISO’s LARS filing would treat a generator in Montana as “electrically proximate” to a large load in Wisconsin, despite the hundreds of miles and multiple states between them. MISO fails to show that such paired generation and load should be treated as electrically proximate, much less that they would have same impact on the MISO Transmission System as if located at the same substation.
10 Id. P 117.11 Transmittal Letter at 1.12 Id. at 10.13 See MISO Tariff, Attach. VV (Map of Local Resource Zone Boundaries).
PDF page 6
- 6 -
At the same time, MISO’s proposed geographic scope for LARS excludes paired generation and load that truly are electrically proximate. For example, under MISO’s Filing a generator in the portion of Wisconsin covered by Zone 2 could never be treated as electrically proximate to a large load located in the portion of Wisconsin in Zone 1, even if they are located within two substations of each other. These pairs of generation and load are completely denied access to the expedited LARS process, while much more distant generation and load pairs are eligible for the limited spots available per a LARS cycle.
The few reasons MISO gives in support for its zonal approach to LARS are unpersuasive and irrelevant to the Commission’s directive in the Show Cause Order. For example, MISO states that limiting paired generation and load to a specific number of substations—as suggested in the Show Cause Order—“could limit how MISO may optimize common transmission solutions.”14 MISO does not explain how more distant paired generation and load, or excluding paired generation and load close to each other but in different Zones, will lead to more optimal transmission solutions. Nor does MISO explain how this scope aligns with the Show Cause Order’s aim of identifying generation and load sufficiently close to each other such that they impact the transmission system as if they were located at the same substation.
Moreover, MISO’s LARS construct already contains numerous elements that broaden the scope of what should be a streamlined study process, e.g.:
14 Transmittal Letter at 21.
PDF page 7
- 7 -
• allowing generation at multiple Points of Interconnection for a single LARS
Associated Load, with separate Applications for each Point of
Interconnection;
• conducting serial studies, even when there are multiple pairs of generation and load in the same Zone and even for multiple Points of Interconnection for the
same LARS Associated Load;
• permitting generation to receive Network Resource Interconnection Service
(“NRIS”) for up to 150% of the LARS Associated Load’s peak demand; and
• permitting a LARS Generating Facility to retain NRIS for up to a year without its paired LARS Associated Load.15
LARS’ flawed geographic and study scope puts in doubt the optimality of the resulting transmission solutions that the LARS process will identify. The purpose of LARS and the Show Cause Order’s discussion of electrically proximate large loads is to identify those pairs of load and generation that can be studied “efficiently and effectively.”16 A geographic measure of eligibility for LARS that fails to address electrical proximity, however, is incompatible with that goal.
MISO also states that its zonal scope “avoids potential capacity import / capacity export limitations for the individual LRZ and also avoids price separation between the paired generation and LARS Associated Load,”17 referring to Planning Resource Auction
15 Under MISO’s proposal, termination of the LLGIA is triggered if “the LARS Associated Load or a portion of the LARS Associated Load has ceased use of Transmission Service granted through LARS for a period of one year beginning with the last date of use of such Transmission Service.” Id. at 41 (quoting revised Article 2.3.1 of MISO Filing, Tab A, Attach. X – Appendix 6 (emphasis added)). After that full year where there can be no associated load, MISO will then provide the generator an additional full year “to continue to operate under the LLGIA in order to provide time for the Interconnection Customer to enter the DPP and obtain new NR Interconnection Service,” with operations subject to MISO’s Quarterly Operating Limits and Annual ERIS process during this one-year transition period. Id. at 17.16 Id. at 18. 17 MISO Filing, Tab C, Prepared Direct Testimony of Christina Drake at 40.
PDF page 8
- 8 -
capacity prices that are set by Zone under MISO’s Resource Adequacy construct.18 These cursory references to capacity prices are a non sequitur. MISO does not explain why the geographic scope used for certain Resource Adequacy purposes is the correct scope for an expedited interconnection study process. MISO also does not explain why a desire to avoid capacity price separation should determine the geographic scope of LARS, particularly given that there can be energy price separation (based on nodes) within the same Zone.
Consistent with the Show Cause Order, the scope of LARS eligibility should instead be based on which paired generation and load are likely to either have limited impacts on the Transmission System or result in more optimal transmission solutions when paired, such that a unique, expedited study process is justified. An inappropriately broad geographic scope for LARS will likely capture more generation and load pairs, requiring more time and resources to implement, which risks detracting from MISO’s ability to improve the timing and processes for its “standard” interconnection processes. It also invites gaming by those seeking to take advantage of differences in the LARS and standard generation and load interconnection study processes. In contrast, a more targeted scope ensures that LARS is appropriately focused on generation and load pairs likely to either present fewer challenges to the Transmission System or result in more optimal transmission solutions when paired—without diverting more resources than necessary
18 See also Transmittal Letter at 10 (stating that MISO’s proposed geographic scope for LARS “aligns with MISO’s Resource Adequacy construct” and “provid[es] an incentive for Load to bring Generation in a manner that maximizes the positive impact this Generation has on Resource Adequacy”).
PDF page 9
- 9 -
away from the standard generation and load interconnection study processes that non- paired MISO loads must depend on for affordable and reliable electricity.
B. Additional cost allocation issues must be addressed in future
proceedings.
Under MISO’s LARS Filing, “[t]he Interconnection Customer remains
responsible for any identified GIP Network Upgrades and the LARS Associated Transmission Customer remains responsible for any identified [Baseline Reliability Projects] or Other assigned Network Upgrades.”19 Midwest TDUs support this requirement, which appropriately links cost responsibility with cost causation. MISO’s filing, however, does not purport to address all cost-related issues raised in the Commission’s Show Cause Order.20 MISO specifically notes that it is “continuing to work with stakeholders . . . to develop the pro forma cost shifting agreement and any necessary terms for transmission service for large loads, all of which will be submitted to the Commission in a FPA section 205 filing by November 16, 2026.”21 Although MISO states that “[t]he LARS structure is compatible with these agreements and MISO will incorporate them into LARS once they are accepted,” it also states that “LARS can be implemented based on the Tariff revisions filed herein and need not await these future filings.”2219 Id. at 16.20 MISO explains that its LARS filing “responds to concerns identified in the Show Cause order regarding proximity between large loads and their associated generation,” id. at 18, and that “other concerns raised by the Show Cause Order . . . will ultimately be presented to the Commission in separate FPA section 205 filings by November 16, 2026,” id. at 20. 21 Id. at 14.22 Id. n.66.
PDF page 10
- 10 -
As a result, the Commission currently has an incomplete picture of how cost allocation and transparency will work in the context of the LARS process. Midwest TDUs do not oppose MISO responding to the Show Cause Order through multiple section 205 filings, but the Commission must ensure that the end results are Tariff revisions that work together and comprehensively address the issues raised in the Show Cause Order. The Commission should therefore condition any acceptance on MISO’s filing in this proceeding on the Commission finding, in future proceeding(s), that MISO has satisfied its obligations with respect to the Show Cause Order’s discussion of cost allocation and transparency as applied to LARS.
CONCLUSION
For the reasons discussed above, the Commission should (1) reject MISO’s proposed geographic scope for paired generation and load eligible for LARS and direct MISO to revise its Tariff language consistent with the Show Cause Order; and
(2) condition any acceptance on MISO’s filing in this proceeding on the Commission finding, in future proceeding(s), that MISO has satisfied its obligations with respect to the Show Cause Order’s discussion of cost allocation and transparency as applied to LARS.
PDF page 11
- 11 -
Respectfully submitted,
/s/ Cynthia S. Bogorad
Cynthia S. Bogorad
Jeffrey M. Bayne
Attorneys for Midwest TDUs
Law Offices of:
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
Washington, DC 20036
(202) 879-4000
October 23, 2026
PDF page 12
ATTACHMENT A
PDF page 13
A-1
ATTACHMENT A: DESCRIPTION OF MIDWEST TDUS
Southern Minnesota Municipal Power Agency (“SMMPA”) is a joint action
agency composed of seventeen member municipalities in Minnesota that own and operate municipal electric systems. SMMPA is also a non-profit political subdivision of the State of Minnesota organized under Chapter 453 of the Minnesota Statutes that is not subject to the Commission’s full jurisdiction. SMMPA became a Transmission Owning Member of MISO, effective April 1, 2006.
WPPI Energy (“WPPI”) is a municipal electric company formed pursuant to Wis. Stat. § 66.0825. WPPI provides bulk power and other services to its 51 members (50 municipalities and one cooperative), each of which operates a distribution utility and sells electricity at retail to the residences, businesses, and industries in and around its municipality. These members are located within the Wisconsin, Michigan, and/or Iowa service territories of four large investor-owned utilities: Northern States Power- Wisconsin (Xcel Energy (“Xcel”)), WEC Energy Group (Wisconsin Electric Power Company (“WEPCO”) and Wisconsin Public Service Corp. (“WPS”)), Upper Peninsula Power Co., and Alliant Energy (Wisconsin Power & Light Co. (“WP&L”) and Interstate Power and Light Co.). The bulk of WPPI’s load is on the American Transmission Company LLC (“ATCLLC”), Xcel, or ITC Midwest transmission systems, although some of WPPI’s resources are located in other transmission zones in MISO, as well as in PJM Interconnection, L.L.C. WPPI supplies the bulk power and energy requirements of
PDF page 14
Attachment A
A-2
its members from generation resources owned by WPPI and through purchased power contracts.
WPPI is a longstanding member of MISO, with both generation and load within the MISO footprint, and owns portions of transmission projects. WPPI also is a participating owner of ATCLLC, a MISO Transmission Owner which was formed pursuant to 1999 Wisconsin Act 9 with WPPI’s support.
PDF page 15
CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing document to be served upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated on this 23rd day of October, 2026.
/s/ Jeffrey M. Bayne