Protest and Request for Clarification of the American Clean Power Association and Southern Renewable Energy Association
The American Clean Power Association and Southern Renewable Energy Association protest MISO's LARS filing as unduly discriminatory against independent power producers, a permanent uncapped expedited queue, and unlike the service described in the show cause order. They ask FERC to reject it or clarify the same-LRZ test.
Asks FERC to: Reject LARS; if any part is accepted, direct MISO to clarify that the same-LRZ test turns on the point of interconnection, not the generator's physical location.
Protests MISO's LARS filing as a departure from the interim, output-limited service for electrically proximate large loads that the E-8 show cause order described.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- The trades say LARS goes further than ERAS: permanent, uncapped, untethered to a resource adequacy need, and run through the load-serving entity.
It is permanent and uncapped. It is untethered to any identified resource adequacy need. PDF p. 2
- They say making the LSE the applicant gives LSEs gatekeeper control over a jurisdictional interconnection process.
LARS is unduly discriminatory because it makes the LSE the gatekeeper of a Commission-jurisdictional generator interconnection process PDF p. 6
- They contend the show cause order did not call for a permanent expedited queue and described interim service until ERIS or NRIS.
The Show Cause Order did not direct MISO to create a separate, permanent, expedited generator interconnection queue. PDF p. 14
- They cite bounded precedents: PJM RRI at 50 projects and MISO ERAS at 68 requests ending by August 31, 2027.
The revised MISO ERAS process is capped at 68 requests and sunsets no later than August 31, 2027 PDF p. 15
- They argue same-LRZ pairing grants broad injection rights to generators that need not be operationally tied to the load.
its same-LRZ pairing grants broad priority injection rights to generators that need not be operationally tied to the load. PDF p. 18
- They note LARS studies exclude DPP requests lacking executed GIAs, which they say shifts capacity and costs away from DPP customers.
exclude DPP Interconnection Requests that lack an executed Generator Interconnection PDF p. 6
- They say MISO has not shown LARS meets the independent entity variation standard.
MISO has not shown that LARS satisfies the independent entity variation standard. PDF p. 6
- As a fallback, they request clarification that the same-LRZ test uses the point of interconnection.
the relevant location is the applicable POI to the MISO Transmission System rather than the physical location of the Generating Facility PDF p. 30
Contents · 11 sections
- I. BACKGROUND
- A. MISO’s Initial and Revised ERAS Proposals
- B. The Show Cause Order
- C. The LARS Proposal
- II. PROTEST
- A. LARS Would Unduly Discriminate Against Independent Power Producers and
- B. LARS Is Not Just and Reasonable.
- C. The Commission’s Orders on MISO’s ERAS Proposals Confirm That LARS Is
- D. MISO Has Not Demonstrated That LARS Satisfies the Independent Entity
- III. REQUEST FOR CLARIFICATION
- IV. CONCLUSION
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
What the document says
PDF p. 21
LARS and the queue use different assumptions, so both can claim the same headroom.
LARS projects will therefore be studied as if the only other generation on the system is generation that already holds a GIA. PDF p. 21Filed comments: Connecting load and generation
PDF p. 21
Queued generators say overallocation raises their upgrade costs and curtails their output.
resulting in more constraints and higher Network Upgrade costs for DPP projects when they are finally studied against a system that LARS projects have already used. PDF p. 21Filed comments: Cost allocation
PDF p. 6
Utility gatekeeping of LARS applications is undue discrimination against independent generators.
LARS is unduly discriminatory because it makes the LSE the gatekeeper of a Commission-jurisdictional generator interconnection process PDF p. 6Filed comments: Connecting load and generation
PDF p. 2
LARS is a permanent, uncapped fast lane untethered to any identified resource adequacy need.
It is permanent and uncapped. It is untethered to any identified resource adequacy need. PDF p. 2Filed comments: Reliability and curtailment
PDF p. 27
Unlike ERAS, LARS has no cap, sunset, independent-producer carve-out, or regulator check.
LARS contains no scoring criteria, no carve-outs, no regulatory verification, no cap, and no sunset. PDF p. 27Filed comments: Connecting load and generation
PDF p. 14
Same-LRZ pairing is not the two-substation test the Show Cause Order described.
LARS does the opposite: it grants permanent NRIS through a parallel process PDF p. 14Filed comments: Connecting load and generation
PDF p. 24
Clean energy groups say LARS adds a fifth path onto the grid and breaks planning.
MISO has now twice prioritized separate, one-off expedited processes that not all market participants can feasibly access on a comparable, not unduly discriminatory basis PDF p. 24
PDF p. 29
ACP and SREA: MISO has not met the independent entity variation standard.
MISO cannot satisfy the independent entity variation standard, and LARS does not accomplish the purposes of Order No. 2003 PDF p. 29Filed comments: Connecting load and generation
PDF p. 30
Protesters ask FERC to reject LARS outright; Clean Energy Advocates offer a deficiency letter instead.
the Clean Energy Trades respectfully request that the Commission reject MISO's LARS proposal. PDF p. 30Filed comments: Connecting load and generation
PDF p. 30
If FERC accepts LARS, ACP wants the same-LRZ test applied at the point of interconnection.
the relevant location is the applicable POI to the MISO Transmission System rather than the physical location of the Generating Facility PDF p. 30
Elsewhere in the record
Other parties on the same questions, in their own documents.
- MISO says independent generators can negotiate before applying Midcontinent Independent System Operator
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
ER27-25-000 (Oct. 7, 2026). 2 members include independent power producers (“IPPs”) that develop generation to serve large loads and that would be directly affected by both the access rules LARS establishes and the effect of LARS on the transmission capacity and Network Upgrade costs available to…Read this passage Filed comments: Connecting load and generation
I. BACKGROUND
printed heading
I.Read this passage
A. MISO’s Initial and Revised ERAS Proposals
printed heading · Topic match: Reliability and curtailment
The accepted ERAS process is capped at 68 interconnection requests, with ten reserved for IPPs that have agreements with entities other than LSEs and eight reserved for requests serving retail- choice load; it requires verification by a Relevant Electric Retail Regulatory Authority (“RERRA”) of a…Read this passage Filed comments: Reliability and curtailment
B. The Show Cause Order
printed heading · Topic match: Connecting load and generation
P 112. 5 obtains Energy Resource Interconnection Service (ERIS) or Network Resource Interconnection Service (NRIS).”15 Separately, the Commission directed MISO to file an informational report on proposals under consideration to address resource adequacy for new large loads.16Read this passage Filed comments: Connecting load and generation
C. The LARS Proposal
printed heading · Topic match: Connecting load and generation
The LARS Proposal MISO proposes LARS as a new, permanent study process under which a large load of at least 200 megawatts (“MW”) and one or more new Generating Facilities are studied in parallel, with the generator receiving a Large Load Generator Interconnection Agreement (“LLGIA”) for NRIS in…Read this passage Filed comments: Connecting load and generation
II. PROTEST
printed heading · Topic match: Connecting load and generation
PROTEST Because MISO filed LARS under FPA section 205, MISO bears the burden of demonstrating that its proposal is just and reasonable and not unduly discriminatory or preferential.23 MISO has not carried that burden.Read this passage Filed comments: Connecting load and generation
A. LARS Would Unduly Discriminate Against Independent Power Producers and
printed heading · Topic match: Connecting load and generation
While it is reasonable for LSEs to initiate and oversee LARS requests on the load side, given state jurisdiction over retail service and LSEs’ obligations to serve load, that logic does not 36 See Order No. 888, FERC Stats. & Regs. ¶ 31,036 at 31,682; Order No. 2003, 104 FERC ¶ 61,103 at P 827. 37…Read this passage Filed comments: Connecting load and generation
B. LARS Is Not Just and Reasonable.
printed heading · Topic match: Connecting load and generation
LARS studies “will not include Interconnection Requests currently in the generator interconnection queue that do not have an executed GIA.”84 LARS projects will therefore be studied as if the only other generation on the system is generation that already holds a GIA.Read this passage Filed comments: Connecting load and generation
C. The Commission’s Orders on MISO’s ERAS Proposals Confirm That LARS Is
printed heading · Topic match: Connecting load and generation
The Commission found that the initial, rejected MISO ERAS proposal did “not sufficiently describe how the ERAS process is sufficiently targeted to study only interconnection requests needed to meet the anticipated shortfall in generating capacity,” and that it was “difficult to determine whether…Read this passage Filed comments: Connecting load and generation
D. MISO Has Not Demonstrated That LARS Satisfies the Independent Entity
printed heading · Topic match: Connecting load and generation
Operator, Inc., 185 FERC ¶ 61,084, at P 11 (2023)); see also ERAS Acceptance Order, 192 FERC ¶ 61,064 at P 259 (applying standard to ERAS). 114 See pro forma LGIP § 3.1. 115 Tab A, Attachment X, §§ 3.12.1, 3.12.2. 29 the basis of queue position and, following Order No. 2023, in clusters on a…Read this passage Filed comments: Connecting load and generation
III. REQUEST FOR CLARIFICATION
printed heading · Topic match: Connecting load and generation
Proposed Attachment X, Section 3.12.2 appears to apply the same-LRZ requirement based on the Generating Facility’s POI for an individual LARS Interconnection Customer, providing that “[t]he Point of Interconnection specified in a LARS Application must be located in the same Local Resource Zone as…Read this passage Filed comments: Connecting load and generation
IV. CONCLUSION
printed heading · Topic match: Connecting load and generation
CONCLUSION For the reasons stated above, the Clean Energy Trades respectfully request that the Commission reject MISO’s LARS proposal.Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Dated this 23rd day of October, 2026. /s/ Brett White Brett White Vice President, Markets & Transmission American Clean Power Association 1299 Pennsylvania Ave.Read this passage