ER27-25-000 · 2026-10-23 · MISO Transmission Owners

Motion to Intervene and Comments of MISO Transmission Owners in support of the 10/02/2026 filing by the Midcontinent Independent System Operator, Inc

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

Midcontinent Independent System
)

Docket No. ER27-25-000

Operator, Inc.

)

MOTION TO INTERVENE AND COMMENTS IN SUPPORT OF
THE MISO TRANSMISSION OWNERS

Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure,1 the MISO Transmission Owners2 submit this motion to intervene and comments in support of the October 2, 2026 Filing by the Midcontinent Independent System Operator, Inc. (“MISO”) in which MISO proposes

1 18 C.F.R. §§ 385.212, 385.214.
2 For purposes of this filing, the MISO Transmission Owners for this filing consist of: Ameren Services Company, as agent for Union Electric Company d/b/a Ameren Missouri, Ameren Illinois Company d/b/a Ameren Illinois and Ameren Transmission Company of Illinois; Big Rivers Electric Corporation; Central Minnesota Municipal Power Agency; Citizens Electric Corporation; City Water, Light & Power (Springfield, IL); Cleco Power LLC; Cooperative Energy; Dairyland Power Cooperative; Duke Energy Business Services, LLC for Duke Energy Indiana, LLC; East Texas Electric Cooperative, Inc.; Entergy Arkansas, LLC; Entergy Louisiana, LLC; Entergy Mississippi, LLC; Entergy New Orleans, LLC; Entergy Texas, Inc.; Great River Energy; GridLiance Heartland LLC; Hoosier Energy Rural Electric Cooperative, Inc.; Indiana Municipal Power Agency; Indianapolis Power & Light Company d/b/a AES Indiana; International Transmission Company d/b/a ITCTransmission; ITC Midwest LLC; Lafayette Utilities System; Michigan Electric Transmission Company, LLC; MidAmerican Energy Company; Minnesota Power (and its subsidiary Superior Water, L&P); Missouri River Energy Services; Montana-Dakota Utilities Co.; Northern Indiana Public Service Company LLC; Northern States Power Company, a Minnesota corporation, and Northern States Power Company, a Wisconsin corporation, subsidiaries of Xcel Energy Inc.; Northwestern Wisconsin Electric Company; Otter Tail Power Company; Prairie Power, Inc.; Southern Illinois Power Cooperative; Southern Indiana Gas & Electric Company (d/b/a CenterPoint Energy Indiana South); Southern Minnesota Municipal Power Agency; Wabash Valley Power Association, Inc.; and Wolverine Power Supply Cooperative, Inc.

PDF page 2

2
revisions to its Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”) to establish a Large Load Addition Resource Study (“LARS”) process.3  As detailed in the LARS Filing, the LARS process provides a streamlined and flexible process whereby MISO is able to expedite the study of load interconnection requests of 200 megawatts (“MW”) or greater that are paired with electrically proximate new generation resources.  LARS provides an accelerated framework that will “facilitate the cost effective, timely and reliable integration of new large loads into the system.”4 As MISO explains, MISO’s LARS proposal is built upon MISO’s existing

Expedited Project Review (“EPR”) for load integration and the Expedited Resource Additions Study (“ERAS”) for accelerated generation interconnection and positions the region to meet the significant increase in electricity demand and support critically important industries.5  LARS is aligned with initiatives such as the Department of Energy’s (“DOE”) Speed to Power Initiative6 and is responsive to the Commission’s June 18, 2026 Show Cause Proceeding that called on MISO to address potential bottlenecks limiting the ability of new generation and electrically proximate large loads to be studied for their combined impacts on the transmissions system.7

3
Midcontinent Independent System Operator, Inc.’s Large Load Addition Resource Study Process, Docket No. ER27-25-000 (October 2, 2026) (“LARS Filing”).  All capitalized terms in this pleading that are not otherwise defined herein have the same meaning they are given in the current Tariff.

4
LARS Filing at 2.
5
Id. at 2.
6
Speed to Power Initiative, U.S. Dep’t of Energy, https://www.energy.gov/oe/speed- power [https://perma.cc/X4CX-DFER] (last visited Oct. 23, 2026).

7
Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at P 113 (2026) (“Show Cause Order”).

PDF page 3

3
As noted in the LARS Filing, the addition of new large loads to the system has the potential to strain the region’s resource adequacy needs, with new large load additions coming online faster than the generation needed to support them.8  By studying the generation and load in a parallel, coordinated, and streamlined manner, MISO’s LARS proposal can reduce study times for both load and generation, and identify cost-effective solutions for interconnection that are more efficient than if load and generation were studied separately.9

The MISO Transmission Owners support MISO’s LARS proposal.  As explained in the LARS Filing, the Commission should accept the proposed Tariff revisions, effective December 2, 2026, to ensure new large loads paired with generation can be studied in streamlined, efficient, and expedited manner.

I. MOTION TO INTERVENE
This proceeding involves revisions to MISO’s Generator Interconnection Procedures and the Tariff that are necessary to implement LARS.  Under the Commission’s rules, intervention is appropriate where “[t]he movant has . . . an interest which may be directly affected by the outcome of the proceeding.”10  As Transmission Owners within MISO that are subject to the Tariff, each of the MISO Transmission Owners may be affected by the Commission’s action in this proceeding.  MISO’s LARS proposal specifically identifies MISO Transmission Owners as one of the four primary types of

8 LARS Filing at 2-3.
9 Id. at 4.
10 18 C.F.R. § 385.214(b)(2)(ii).

PDF page 4

4
entities involved in implementing LARS, aside from MISO.11  Consequently, each of the MISO Transmission Owners has a direct interest in this case that cannot be adequately represented by any other party.  Therefore, the Commission should allow the intervention of each MISO Transmission Owner.

The MISO Transmission Owners also request that the Commission place the following individuals on the official service list for this proceeding: Wendy N. Reed

Anna Fernandez
Stefan A. Koester
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC  20005-3898
202-393-1200
reed@wrightlaw.com
fernandez@wrightlaw.com
koester@wrightlaw.com
II. COMMENTS IN SUPPORT
The MISO Transmission Owners support MISO’s LARS Filing.  The LARS Filing will provide the region with another efficient, effective, and appropriately tailored tool to address the need to expedite the interconnection of new large loads and the necessary generation to serve them.  The proposed LARS process provides a framework to a parallel, streamlined, and coordinated study process for pairing new load with much needed generation projects.  The pairing of new load with generation for large load customers is part of a broader suite of efforts on the part of MISO and MISO stakeholders to address resource adequacy and reliability needs across the MISO footprint while providing a pathway to bring new large loads online as fast as possible.  The Commission should accept

11 LARS Filing at 6.

PDF page 5

5
the LARS Filing, finding the LARS proposal to be a just and reasonable and not unduly discriminatory or preferential solution to addressing a specifically regional problem.12

A. The LARS Proposal Is Just and Reasonable Given It Is Narrowly
Tailored in Scope, Avoids Negative Impacts on the Generator
Interconnection Queue, and Facilitates Speed to Power
The LARS proposal is a narrowly tailored but valuable tool that enables the accelerated evaluation and integration of electrically proximate large load and generation pairs and the related identification of more efficient network upgrades.  As a new permanent study process, the LARS proposal will provide for a new Large Load Generator Interconnection Agreement in an estimated 120 days.13  The LARS proposal is a balanced and necessary addition to MISO’s tools for addressing exponential load growth across the region.

1. Urgent Need to Interconnect New Large Loads and Associated
Generation
MISO and MISO stakeholders, including the MISO Transmission Owners, fully agree on the need to meet the moment by facilitating the interconnection of new large loads, such as data centers, without jeopardizing resource adequacy and reliability needs.14  The urgent resource adequacy and reliability needs that led to the LARS proposal are in part due to recent, rapid changes to the MISO footprint.  Specifically, recent assessments by MISO demonstrate that a combination of factors, including, among other things, the rapid

12 See ISO New England Inc., 170 FERC ¶ 61,218, at P 26 (2020) (“[A]n RTO/ISO . . . has greater flexibility to customize its interconnection procedures and agreements to fit regional needs.”).
13 LARS Filing at 11.
14 See id. at 49-52 (detailing the robust stakeholder process used in developing the LARS proposal as well as changes made to the LARS proposal as a result of stakeholder feedback).

PDF page 6

6
growth of large energy-consuming industries (i.e., data centers and manufacturing), and early retirements of large generating units, are significantly impacting resource adequacy and reliability needs in the region just when more generation is needed to serve new large loads.15  For example, the 2025 Organization of MISO States-MISO Survey found that “[a]t least 3.1 GW of additional capacity beyond the committed capacity will be needed to meet the projected planning reserve margin forecast.”16  As noted by MISO, the LARS proposal, along with MISO’s recent generator interconnection reforms accepted by the Commission, such as ERAS, will speed up the study process for both new large loads and generation, bringing new large loads and necessary generation online faster than the status quo of studying these requests separately and in a non-coordinated manner.17 The LARS proposal builds off of the successful EPR and ERAS processes. The LARS load study process requires similar information to that required in the EPR process, while the LARS generation study process builds off of ERAS.18  LARS improves upon these two processes, however, by integrating the study and planning of new large load with generation, thereby enabling the identification of more efficient transmission Network

15 See id. at 2, n. 6 (MISO, 2026 Reliability Imperative Report at 4 (Feb. 2026) (projecting annual load growth of approximately 1% to 2% through 2044 and identifying data centers, manufacturing expansion, and electrification as drivers of sustained, concentrated load growth); see also, MISO, 2026 Planning Resource Auction Results at 2 (May 22, 2026) (stating that faster resource additions are needed to support large-load growth and ensure resource adequacy)).
16 2025 OMS-MISO Resource Adequacy Survey Results Workshop, Midcontinent Indep. Sys. Operator, Inc. & Org. of MISO States, 2 (June 6, 2025), https://cdn.misoenergy.org/20250606%20OMS%20MISO%20Survey%20 Results%20Workshop%20Presentation702311.pdf [https://perma.cc/J8AB- TUQX].
17 LARS Filing at 5.
18 Id. at 13-15.

PDF page 7

7
Upgrade solutions.  Additionally, LARS is a permanent, rather than temporary, proposal that will provide a long-term market signal and certainty to new large loads and generation for at minimum 15 years by pairing new electrically proximate generation appropriately sized to serve new large loads.19

As shown above, the proposed LARS Filing is narrowly tailored to address speed to power and the resource adequacy and reliability needs of the region, while addressing the concerns outlined in the Show Cause Order, specifically, the need to pair new generation with new large loads.

2. LARS Is an Appropriate, Focused, and Needed Solution to Bringing
on New Large Loads and Generation in a Timely Manner
As MISO explained, the region faces the twin imperatives of bringing critically important new large loads online fast enough while not exacerbating the region’s resource adequacy concerns by failing to bring new generation to support these new large loads.20 The current separate, non-coordinated study processes of studying load interconnection requests and generator interconnection requests separately was identified by MISO as a key hurdle to speeding up the integration of large loads without compromising reliability.21 Meeting resource adequacy and reliability needs is a paramount concern for the MISO Transmission Owners and in MISO, it is the Load Serving Entities’ (“LSE”) obligation to meet the load needs for most of the region’s states.22  LSEs are also typically

19 Id. at 16.
20 Id. at 4-5.
21 Id. at 4-5.
22 See id. at 4-5; see also Midcontinent Indep. Sys. Operator, Inc., 162 FERC ¶ 61,176, at P 67 (2018) (“The vast majority (approximately 90 percent) of MISO’s load is served by vertically integrated utilities over which state and local authorities play an active role in ensuring resource adequacy.  In fact, even states with retail

PDF page 8

8
the entity responsible for interconnecting new large loads that seek to take service in their service territory.23  The LARS proposal respects the division of responsibility by establishing a single application process that is initiated by the LARS Associated Transmission Customer, typically the LSE.24  However, the Transmission Owners, Interconnection Customer, and Associated Load all have critical roles to play in the LARS Application process.25

The LARS process is also designed to avoid disrupting MISO’s existing load and generator interconnection study processes.  First, the LARS proposal includes a robust pre- submission coordination process aimed at streamlining the LARS Application process prior to submittal with specific consultation requirements and timelines baked into the process.  Transmission Owners have a distinct role to play in the LARS pre-submission coordination process by meeting with an Interconnection Customer that proposes to interconnect for participation in LARS and working jointly with that Interconnection Customer to identify a feasible Point of Interconnection (“POI”).  MISO Transmission Owners must also provide necessary attestation with regard to an agreed upon POI with the Interconnection Customer as a part of the LARS Application.26  Second, LARS is limited to three study cycles per year with ten LARS Applications per cycle.  This limited window will allow for MISO to meet its stated goal of studying and completing the ten

competition (i.e., Illinois and Michigan) have played an active role in ensuring resource adequacy.”).

23 LARS Filing at 6.
24 Id. 7.
25 Id. 7.
26 Id. 8.

PDF page 9

9
generation/load pairs in one model.27  Third, LARS projects will not impact existing customers in MISO’s generator interconnection queue (the Definitive Planning Phase process or “DPP”), with LARS requests not included in DPP studies, thereby avoiding utilizing available transmission capacity.28  Fourth, and finally, LARS includes various safeguards to deter customers from gaming the LARS process and speculative applications.29  Together, these requirements ensure “commercially viable and shovel ready projects enter LARS.”30

The LARS proposal advances key elements of the DOE’s Speed to Power Initiative and is responsive, in part, to the Commission’s Show Cause Order.  MISO Transmission Owners support the goals of the LARS proposal, with it building off of recent successful MISO efforts to expedite the study and addition of new loads and generation in a timely manner, while identifying more efficient transmission solutions.

27 Id. 13.
28 Id. 13.
29 Id. at 9-10.
30 Id. 11.

PDF page 10

10
III. CONCLUSION

For these reasons, the MISO Transmission Owners request that the Commission grant this motion to intervene and accept the LARS Filing as just and reasonable, effective December 2, 2026.

Respectfully submitted,
 /s/ Wendy N. Reed

Wendy N. Reed
Anna Fernandez
Stefan A. Koester
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC  20005
(202) 393-1200
reed@wrightlaw.com
fernandez@wrightlaw.com
koester@wrightlaw.com

Attorneys for the
MISO Transmission Owners
October 23, 2026

PDF page 11

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated at Washington, DC, this 23rd day of October 2026.

/s/ Stefan A. Koester
Stefan A. Koester
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC  20005
(202) 393-1200
koester@wrightlaw.com

Attorney for the
MISO Transmission Owners