ER27-25-000 · 2026-10-23 · MISO Transmission Owners

Motion to Intervene and Comments of MISO Transmission Owners in support of the 10/02/2026 filing by the Midcontinent Independent System Operator, Inc

Text extracted from the eLibrary original (SHA-256 43db776f7f4454ad…). Download the original from the official source.

Contents · 4 sections
  1. I. MOTION TO INTERVENE p. 3
  2. II. COMMENTS IN SUPPORT p. 4
  3. A. The LARS Proposal Is Just and Reasonable Given It Is Narrowly p. 5
  4. III. CONCLUSION p. 10

Read topic-matched comments in ER27-25

Topics in the text: Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

ER27-25-000 Operator, Inc. ) MOTION TO INTERVENE AND COMMENTS IN SUPPORT OF THE MISO TRANSMISSION OWNERS Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure,1 the MISO Transmission Owners2 submit this motion to intervene and…
Read this passage Filed comments: Connecting load and generation

I. MOTION TO INTERVENE

printed heading · Topic match: Connecting load and generation

MISO’s LARS proposal specifically identifies MISO Transmission Owners as one of the four primary types of 8 LARS Filing at 2-3. 9 Id. at 4. 10 18 C.F.R. § 385.214(b)(2)(ii). 4 entities involved in implementing LARS, aside from MISO.11 Consequently, each of the MISO Transmission Owners has a direct…
Read this passage Filed comments: Connecting load and generation

II. COMMENTS IN SUPPORT

printed heading · Topic match: Connecting load and generation

The Commission should accept 11 LARS Filing at 6. 5 the LARS Filing, finding the LARS proposal to be a just and reasonable and not unduly discriminatory or preferential solution to addressing a specifically regional problem.12
Read this passage Filed comments: Connecting load and generation

A. The LARS Proposal Is Just and Reasonable Given It Is Narrowly

printed heading · Topic match: Connecting load and generation

This limited window will allow for MISO to meet its stated goal of studying and completing the ten competition (i.e., Illinois and Michigan) have played an active role in ensuring resource adequacy.”). 23 LARS Filing at 6. 24 Id. 7. 25 Id. 7. 26 Id. 8. 9 generation/load pairs in one model.27 Third,…
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION

printed heading · Topic match: Connecting load and generation

CONCLUSION For these reasons, the MISO Transmission Owners request that the Commission grant this motion to intervene and accept the LARS Filing as just and reasonable, effective December 2, 2026.
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, DC, this 23rd day of October 2026. /s/ Stefan A.