ER27-25-000 · 2026-10-23 · Geronimo Power, LLC

Motion to Intervene and Comments of Geronimo Power, LLC concerning the Midcontinent Independent System Operator, Inc.’s Large Load Addition Resource Study…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
Operator, Inc.
)
)
)
)

Docket No. ER27-25-000

MOTION TO INTERVENE AND COMMENTS OF
GERONIMO POWER, LLC

Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Rules of Practice and Procedure1 and the Commission’s October 2, 2026 Combined Notice of Filings #1,2 Geronimo Power, LLC (“Geronimo Power”) hereby submits this motion to intervene and comments in the above-captioned proceeding concerning the Midcontinent Independent System Operator, Inc.’s (“MISO”) Large Load Addition Resource Study Process (“LARS”) proposal.3

I. COMMENTS
Geronimo Power appreciates MISO’s efforts to develop interconnection processes that facilitate the integration of large loads and respond to the directives included in the Commission’s Show Cause Order.4  At a time when the MISO region is experiencing “significant growth in electricity demand”5 and is “[t]he region with the fastest data center capacity growth” in the country,6 it is imperative that MISO have processes that ensure large loads and generation capacity

1 18 C.F.R. §§ 385.212 and 385.214. 2 Midcontinent Indep. Sys. Operator, Inc., et al., Docket Nos. ER27-25-000, et al., Combined Notice of Filings #1 (Oct. 2, 2026).
3 Midcontinent Indep. Sys. Operator, Inc., Docket No. ER27-25-000, Large Load Addition Resource Study Process (Oct. 2, 2026) (“LARS Filing”).
4 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at P 2 (2026) (“Show Cause Order”).
5 LARS Filing, Transmittal Letter at 2.
6 FERC, 2025 State of the Markets Report at 7 (Mar. 2026), available at: https://www.ferc.gov/news- events/news/report-3-state-markets-report-2025.

PDF page 2

2

serving these customers may interconnect to the grid in an efficient, timely, and non-discriminatory manner.

Geronimo Power supports the creation of efficient and non-discriminatory procedures that provide for the coordinated study of new generation capacity and large load customers.  Evaluating paired generation capacity and large load can provide a more accurate picture of the net impact of these customers on the transmission system and reduce the need for costly network upgrades that can unnecessarily drive up costs and delay energization timelines.  By reducing barriers to entry to new generation and large load customers, interconnection procedures that provide for the coordinated evaluation of generation and large loads can play a critical role in providing large loads a pathway to power that maintains America’s economic competitiveness while simultaneously mitigating impacts to the grid and avoiding cost shifts to existing customers. Nevertheless, any proposal that provides certain customers with a separate path to interconnection service must comply with the Federal Power Act’s (“FPA”) prohibition on undue discrimination and preference and open access requirements.7  Historically, the Commission has been skeptical of any proposals that create a separate or expedited path for certain resources to obtain interconnection service.8  But the Commission has approved expedited processes in limited circumstances where such processes were narrowly tailored to meet a demonstrated reliability need and “aligned with . . . open access principles in an objective and transparent manner.”9

7 Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131, at PP 201-02 (2025).  See also Cal. Indep. Sys. Operator Corp., 180 FERC ¶ 61,143, at P 41 (2022); PJM Interconnection, L.L.C., 190 FERC ¶ 61,084, at P 248 (2025).
8 Xcel Energy Operating Co., 106 FERC ¶ 61,260, at PP 22-23 (2004); Sw. Power Pool, Inc., 147 FERC ¶ 61,201, at P 124 (2014); Midcontinent Indep. Sys. Operator, Inc., 185 FERC ¶ 61,200, at PP 176-177 (2023).
9 Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131, at PP 201-03 (2025).  See also Cal. Indep. Sys. Operator Corp., 180 FERC ¶ 61,143, at P 41 (2022); PJM Interconnection, L.L.C., 190 FERC ¶ 61,084, at P 248 (2025).

PDF page 3

3

MISO’s LARS proposal does not meet this standard.  As currently conceived, LARS would provide incumbent utilities with undue influence over the ability of interconnection customers to access the process.  Notably, an interconnection customer will not be able to participate in LARS unless the interconnecting transmission owner “pre-approves” its proposed point of interconnection and a MISO transmission customer—which typically will be a transmission owner and load-serving entity (“LSE”)—submits an application into the LARS process.10  The result is a framework that will provide incumbent utilities with new opportunities to discriminate against competing suppliers and secure preferential access to interconnection service for their own generation resources.  Ultimately, this will provide incumbent utilities with a powerful tool that they can use to pressure large load customers to rely on their generation resources, which will be eligible to receive interconnection service more quickly and at lower cost than competing resources that have been relegated to the standard interconnection queue.

At the same time, certain aspects of MISO’s proposed framework appear to arbitrarily exclude from LARS generation resources that are being developed to meet the demand of large load customers in a manner that supports resource adequacy and protects ratepayers.  For instance, the requirement that an interconnection customer provide an offtake agreement demonstrating that its facility will be used to provide energy to large load customers would appear to prevent a generation resource that has entered into a virtual power purchase agreement (“PPA”) with a large load customer from participating in LARS.  Additionally, MISO’s description of the scope of LARS could be interpreted as prohibiting co-located generation and load from accessing the LARS

10 Midcontinent Indep. Sys. Operator, Inc., 170 FERC ¶ 61,215, at P 13 (2020) (“[A]pproximately 90% of the load in MISO is served by vertically integrated LSEs[.]”); Entergy Ark., LLC v. Webb, Case No. 24-1074, Brief of Amicus Curiae the MISO Transmission Owners Supporting Petitioner at 1, 9 (U.S. Supreme Court, May 14, 2025) (explaining that the MISO transmission owners include vertically integrated utilities and that “vertically integrated utilities with load serving obligations take transmission service under the MISO Tariff to serve their retail (state- regulated) customers.”).

PDF page 4

4

process which would undermine an effective means for large loads to achieve speed to power while simultaneously mitigating the operational impact and reliability concerns that MISO claims its LARS proposal is intended to address.

At a time when large load customers are being asked to take a greater role in identifying and funding the construction of new generation capacity to offset their demand,11 it is critically important that the frameworks adopted by MISO and other transmission providers do not create barriers to large loads pursuing supply options that best align with their needs and that support the objectives of ensuring speed to power and protecting retail customers.  A generation developer that enters into an agreement with a large load customer under which the customer assumes the financial risk of the generation resource should be able to submit a request into LARS without the blessing or involvement of the incumbent utility.  Although a large load customer and generation developer may need to coordinate their supply arrangement with an LSE to comply with applicable state law, those issues can be resolved by the large load customer, generation developer, and applicable LSE outside of the context of the MISO market.

Geronimo Power does not question MISO’s intent in proposing LARS and appreciates MISO’s efforts to come up with frameworks that address the concerns expressed in the Show Cause Order.  But the effect of MISO’s proposal would be to create new opportunities for undue discrimination and arbitrarily limit the availability of LARS to certain interconnection customers. LARS should remove barriers to the entry of new capacity to serve large load customers; it should not protect the market position of incumbent utilities within the region.

11 See, e.g., The White House, Ratepayer Protection Pledge (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/ (stating that “[c]ompanies will build, bring, or buy the new generation resources and electricity needed to satisfy their new energy demands, paying the full cost of those resources whether by building, or buying from, new or otherwise additive power plants”).

PDF page 5

5

Accordingly, Geronimo Power urges the Commission to reject LARS on the basis that it has not been shown to be just, reasonable, and not unduly discriminatory or preferential.  The Commission’s order rejecting LARS should make clear that it is without prejudice to MISO making a future filing to establish a coordinated study process for generation and large load customers that aligns with open access requirements, the goals of the Show Cause Order, and the Commission’s policies aimed at efficiently integrating large loads.

A. MISO’s Proposal To Allow Incumbent Utilities To Determine Access To
LARS Is Unduly Discriminatory And Will Undermine The Objective Of
Efficiently Integrating Large Loads

The current design of LARS will create opportunities for undue discrimination by providing incumbent utilities with the ability to control which interconnection customers are able to participate in, and obtain service through, the process.  Even if a generation resource has entered into an agreement to serve large load and otherwise meets the criteria to participate, an interconnection customer will be unable to access LARS without the cooperation and support of incumbent utilities within the MISO region.

Indeed, from the beginning of the process, incumbent utilities within MISO would have the ability to create barriers to competing suppliers.  As an initial matter, an interconnection customer would be ineligible to participate in LARS unless the transmission owner that owns the facilities that the customer is planning to interconnect to agrees to the proposed point of interconnection.12  If the interconnection customer and the transmission owner are unable to jointly agree on a point of interconnection at least ten business days prior to the next LARS application deadline, then the interconnection customer would be ineligible for the LARS.13  A transmission-

12 LARS Filing, Transmittal Letter at 8.
13 Id., Proposed Tariff, Att. X § 3.12.1.

PDF page 6

6

owning utility can limit access to LARS by competing suppliers simply by withholding approval for a customer’s proposed point of interconnection.14

The requirement that transmission owners approve a proposed point of interconnection is
particularly problematic given MISO’s proposal to require an interconnection customer to
demonstrate 100% site control for a customer’s generation facility and interconnection customer interconnection facilities.15  In practice, an interconnection customer seeking to enter LARS could obtain site control over the land necessary to reach its proposed point of interconnection only to have the transmission owner propose an alternative point of interconnection that does not align with the customer’s land acquisition strategy.  Even if an interconnection customer is willing to shift to the transmission owner’s point of interconnection, an interconnection customer is unlikely to have sufficient time to establish site control for a new location given that MISO’s process contemplates that transmission owners will render a decision on a proposed point of

interconnection immediately prior to the deadline for submitting a request into LARS.
Notably, an interconnection customer that clears these hurdles still would be ineligible to
participate in LARS unless it is able to identify an LSE willing to submit an application into the

14 It also appears that a transmission owner could “run out the clock” on an interconnection customer while remaining in compliance with applicable rules.  Proposed Section 3.12.1 of Attachment X requires the interconnection customer to notify the transmission owner 45 calendar days prior to the LARS application deadline and states that the interconnection customer and transmission owner must reach agreement on the point of interconnection at least ten business days prior to the application deadline.  This means that there will be approximately 31 calendar days between the deadline for notifying the transmission owner and when the parties must reach agreement.  However, Section 3.12.1 also states that (1) the transmission owner has up to ten business days (approximately 14 calendar days) after receiving notice from the customer to meet with the interconnection customer and request any information necessary to agree on the point of interconnection and (2) that the transmission owner must be given at least 15 business days (approximately 21 calendar days) to approve a point of interconnection.  If the 15-business day period does not begin running until the transmission owner meets with the interconnection customer (or after the interconnection customer provides any required information), the 15-business day period would not run until after the deadline for the interconnection customer to reach agreement on the point of interconnection to enter the LARS process (i.e., ten business days prior to the application deadline).  In fact, since Section 3.12.1 states that the transmission owner must have at least 15 business days, the transmission owner could delay a decision well beyond this period without violating the applicable tariff language.  MISO has not demonstrated that this timeline is workable or reasonable.
15 LARS Filing, Transmittal Letter at 28.

PDF page 7

7

LARS process.  A LARS Application “may only be initiated by the LARS Associated
Transmission Customer,”16 which MISO describes as the “entity that procures Transmission
Service for load and has a direct relationship with the load” and that “is often a Load Serving Entity.”17  As a practical matter, this means that a generation resource being developed to serve a large load cannot enter LARS unless the transmission customer, typically an LSE and transmission owner, elects to sponsor the LARS application.  This limitation on access to LARS applies even where the generator has site control, an executed agreement with the large load, and is prepared to satisfy all other LARS requirements.

MISO has not demonstrated that allowing incumbent utilities to act as gatekeepers to the
LARS process is just, reasonable, not unduly discriminatory or preferential, and consistent with open access principles.  The Commission and courts have recognized that utilities that own

generation have an incentive to favor their own generation facilities in providing access to the electric grid.18  Indeed, the Commission’s concern that incumbent utilities might favor their own generation over that of competitors in the interconnection process led the Commission to require transmission providers to adopt a standard set of interconnection procedures to limit the ability of

16 While MISO states that a LARS application may only be initiated by the LARS Associated Transmission Customer and certain proposed tariff provisions reflect that it is the LARS Associated Transmission Customer that “is responsible for submitting the LARS Application,” proposed Section 3.12.1 of Attachment X states that “[p]rior to the applicable Transmission Owner submitting a LARS Application, the potential LARS Interconnection Customer and the Transmission Owner shall meet and agree on a definitive Point of Interconnection for the LARS Generating Facility.” (emphasis added).  MISO should, at minimum, be required to revise this proposed tariff language to make clear that the LARS Associated Transmission Customer is responsible for submitting the LARS application rather than the transmission owner.

17 LARS Filing, Transmittal Letter at 6, 7 (“[T]he LARS Application process may only be initiated by the LARS Associated Transmission Customer.”).
18 E.ON Climate & Renewables North Am., 137 FERC ¶ 61,076, at P 38 (2011), order on reh’g, 142 FERC ¶ 61,048 (2013), order on reh’g, 151 FERC ¶ 61,264 (2015) (explaining that when discretion in the interconnection process rests with transmission owner rather than independent system operator it “creates unacceptable opportunities for undue discrimination by affording a transmission owner the discretion to increase the costs of interconnection service.”); PacifiCorp, 171 FERC ¶ 61,112, at P 101 (2020); Cal. Pub. Util. Comm’n v. FERC, 29 F.4th 454, 458-59 (9th Cir. 2022) (noting that “the transmission-system owner has natural gatekeeping powers and an incentive to favor its own generation facilities in providing access to the electricity grid”); Xcel Energy Servs. v. FERC, 41 F.4th 548, 561 (D.C. Cir. 2022).

PDF page 8

8

incumbent utilities to provide preferential treatment to their affiliates and erect barriers to the entry of competing resources.19  These standardized procedures were intended to limit the discretion of incumbent utilities to preference their own generation resources or “delay[] entry into the market by new generators.”20

In this case, incumbent utilities will have a strong economic incentive to use the discretion afforded to them to limit the access of competing suppliers to LARS.  Independent power producers (“IPP”) and incumbent utilities are competing to construct generation within the MISO region necessary to meet the growing demand from large load customers.21  As designed, the LARS process will provide incumbent utilities with a new tool that they can use to provide their own resources with preferential access to interconnection capacity and bolster their ability to corner the new and significant market for serving data centers and other large loads.  Because interconnection customers that are studied through the standard interconnection queue are likely to be processed more slowly and incur higher network upgrade costs than customers processed through LARS, large loads will have a strong incentive to enter into contracts with resources that are able to access the LARS process.  And by using their gatekeeper role in the process to limit

19 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ 61,103, at P 12 (2003), order on reh’g, Order No. 2003‐A, 106 FERC ¶ 61,220 (2004), order on reh’g, Order No. 2003‐B, 109 FERC ¶ 61,287 (2005), order on reh’g, Order No. 2003‐C, 111 FERC ¶ 61,401 (2005), aff’d sub nom., Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007).
20 ESI Energy, LLC v. FERC, 892 F.3d 321, 324 (D.C. Cir. 2018).
21 See, e.g., Mich. Pub. Serv. Comm’n, MPSC Approves DTE Electric Energy Contracts For Google Data Center, Protects Other Customers From The Project’s Costs (Oct. 1, 2026), https://www.michigan.gov/mpsc/commission/news-releases/2026/10/01/mpsc-approves-dte-electric-google-data- center-and-contracts-protects-customers-from-project-cost; N. States Power Co., Minn. PUC Docket No. M-26-170, Petition Requesting Approval of New Large Load Customer Project (Apr. 14, 2026) (petition filed by incumbent utility seeking approval of agreements to provide Google subsidiary with 1,900 MWs of power); Verified Joint Petition of Northern Indiana Public Service Company LLC (“NIPSCO”) and NIPSCO Generation LLC (“GenCo”) for Approval of (1) A Customer-Specific Contract Between NIPSCO and Data Center Customer #2 Pursuant to Ind. Code §§ 8-1-2-24 and 8-1-2-25; (2) A Power Purchase Agreement between NIPSCO and GenCo; and (3) Alternative Regulatory Plans for Both NIPSCO and GenCo pursuant to Ind. Code §§ 8-1-2.5-5 and 8-1-2.5-6, Cause No. 46393, Order of the Commission (July 23, 2026) (approving agreements for NIPSCO and its generation affiliate to provide power to Alphabet, Inc. subsidiary).

PDF page 9

9

IPP access to LARS, incumbent utilities can increase the pressure for large loads to enter into contracts with their own resources or those of their affiliates.

The risk of undue discrimination is not limited only to incumbent utilities vetoing a proposed point of interconnection or declining to submit an application into the LARS process for a competing supplier.  Because LARS applications are processed on a serial, time-stamped basis and only a limited number of projects may participate in each study period,22 an incumbent utility also can favor its own generation through more subtle means.  For example, an LSE could submit a LARS application for its own generation capacity and an associated large load in advance of submitting a LARS application for a large load customer that has agreed to contract with a competing supplier to ensure that the application for its own resource is higher in the queue and processed more quickly than the application for a competing supplier.

While IPPs will continue to have access to the legacy interconnection queue, this does not mean that LARS is not unduly discriminatory or preferential or consistent with open access.  The prohibition on undue discrimination mandates that LARS be designed in a manner that provides all interconnection customers with comparable access to interconnection service.  A structure that provides incumbent utilities with the ability to discriminate and erect barriers to competing suppliers is inconsistent with this requirement.  And the fact that LARS would be a permanent feature of the MISO market—rather than a one-time process similar to ERAS or similar processes that have been adopted by other markets—only increases the need to scrutinize the proposal to ensure that it does not create opportunities for undue discrimination.

MISO has not demonstrated that the features of LARS described above are necessary to address the reliability needs that LARS seeks to address.  Indeed, expedited large load and paired

22 LARS Filing, Transmittal Letter at 9.

PDF page 10

10

generator interconnection processes adopted by other transmission providers demonstrate that there is no reason why access to LARS must be conditioned on sponsorship by an incumbent

utility.  For example, Southwest Power Pool, Inc.’s (“SPP”) High Impact Large Load Generation Assessment (“HILLGA”) process—which the Commission has cited as a model process for

efficiently integrating new large loads with paired generation23—provides customers developing generation to support a large load the ability to submit a request for interconnection service directly.  Specifically, under SPP’s HILLGA process a generator supporting one or more high impact large loads (i.e., a “HILL”) is permitted to submit its HILLGA request so long as it is able to demonstrate that it is supporting a large load being studied through SPP’s High Impact Large Load Study process.24  MISO has provided no explanation as to why LSEs must play a

23 Show Cause Order at PP 17-19, 115.  See also id. (Comm’r Rosner, concurring at P 14) (“SPP has been a leader in showing how to push beyond the status quo.  With its innovative HILLGA proposal, approved by the Commission in January, SPP leveraged the opportunity for speed and efficiency by studying load and generation together, and by creating a limited, expedited interconnection service to connect faster.  By matching the generator’s output to the electrically proximate large load’s demand, the impacts to the grid are less than they otherwise would be, minimizing the need for time-consuming and costly Network Upgrades needed to connect.  HILLGA is one solution that works for SPP, but today’s orders direct other regions to follow SPP’s lead in ways that work for them.”).

24 See Sw. Power Pool, Inc., Docket No. ER26-247-000, Submission of Tariff Revisions to Add the High Impact Large Load Processes and High Impact Large Load Generation Assessment, Transmittal Letter at 24 (Oct. 24, 2025) (“The submission and eligibility requirements for a HILLGA Request are similar to the requirements in the DISIS process.  The HILLGA Customer must submit the following: (1) an executed HILLGA Study Agreement; (2) a nonrefundable application fee of $20,000; (3) a study deposit of $250,000 for HILLGA Requests up to 500 MW or a study deposit of $500,000 for HILLGA Requests over 500 MW; (4) demonstration of Site Control; (5) definitive POI; (6) Nameplate Capacity, Maximum Injection Capability, and Network Resource Deliverability (MW) pursuant to Appendix 1, Attachment A of Attachment BB; (7) Security deposit equal to $8,000/MW of the requested Maximum Injection Capability (‘Financial Security One’); (8) reasonable evidence of satisfaction of one of the listed development milestones; and (9) if applicable, the charging parameters of the Generating Facility that includes at least one electric storage resource, and a description of any control technologies that will limit the operation of the Generating Facility to the operating assumptions submitted by the HILLGA Customer.”).  See id., Proposed Tariff, Att. BB § 1 (Definitions – HILLGA Customer) (defining HILLGA Customer as “an Interconnection Customer that proposes to interconnect its Generating Facility with the Transmission System pursuant to the High Impact Large Load Generation Assessment”); Southwest Power Pool, Inc., Open Access Transmission Tariff, Att. BB § 8.2(g) (stating that interconnection customer must provide executed HILL delivery point study agreement or show that such an agreement has been executed).  See also Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at P 69 (2026) (“We find that SPP’s HILLGA-related revisions, taken together, accomplish these purposes because they will help ensure that HILLGA Customers seeking to serve HILLs are able to interconnect to the transmission system in a timely manner and increase the speed of interconnection queue processing.”).

PDF page 11

11

determinative role in what generation resources are allowed to access its LARS process when such role is not required under similar processes adopted by other transmission providers. MISO attempts to justify its proposal to place incumbent utilities in this gatekeeping role on the grounds that only a transmission customer can procure transmission service for a large load.25  But while that rationale may explain why the transmission customer must participate in the load-side study and obtain any necessary transmission service, it does not address why a generator—which will independently complete the generation portion of the LARS Application, satisfy the Attachment X requirements, post the required financial security, execute the Large Load Generator Interconnection Agreement, and bear responsibility for network upgrades—must rely on an LSE to initiate the LARS process.  Indeed, whether an LSE chooses to sponsor a particular application has no bearing on the claimed objectives of MISO’s proposal—i.e., whether the paired generation is commercially ready, whether it will serve the large load, or whether it will support resource adequacy.  If anything, the discretion afforded to LSEs under the LARS proposal may result in projects developed by LSEs being admitted to the LARS process over more commercially viable projects developed by IPPs given that there are no objective criteria or oversight imposed on LSEs for evaluating what projects should be admitted to LARS.

MISO also defends its proposal by arguing that “Independent Power Producers and other kinds of Interconnection Customers are not prohibited from participating in the LARS process.”26 But the fact that MISO’s proposed tariff language does not explicitly prohibit IPPs from participating in the LARS process is not determinative.  Indeed, the courts and the Commission have found that facially neutral tariff provisions that have the effect of preferencing generation of

25 LARS Filing, Transmittal Letter at 6, 9.
26 Id. at 7-8.

PDF page 12

12

incumbent utilities or providing incumbent utilities with the discretion to preference their own generation are unduly discriminatory.

For instance, the D.C. Circuit has explained that the fact that a proposal “looks like a non- discriminatory proposal on the surface,” does not excuse that “in practice its design ‘inherently favor[s]’ … existing [incumbent] generators ‘over developers or owners of third-party generation’” and is unduly discriminatory.27 Similarly, the Commission rejected a PacifiCorp proposal that would have provided LSEs with the option to demonstrate commercial readiness for their generation facilities by submitting a site-specific purchase order for generating equipment or a signed statement that the facility will be supplied with generating equipment while requiring IPPs to demonstrate that they had an executed term sheet or other reasonable evidence that the developer would sell the resource, or the resource’s output, to an LSE or large end-use customer.28 The Commission found that allowing LSEs to meet these criteria by providing a purchase order or attestation would impermissibly allow PacifiCorp’s “own generation an easier path to demonstrating readiness than other interconnection customers and could allow PacifiCorp to use the interconnection process to favor its own generation.”29

MISO also argues that requiring pre-approval of a proposed point of interconnection by the transmission owner will increase the “efficiency of reviewing the LARS Application” and “avoid future disagreements or changes, which can lead to unnecessary or late withdrawals from the study process.”30  But MISO has not demonstrated that transmission owners should have any

27 See Xcel Energy Servs. v. FERC, 41 F.4th 548, 559-60 (D.C. Cir. 2022) (quoting Pub. Serv. Co. of Colo., 172 FERC ¶ 61,297, at P 13 (2020)).
28 PacifiCorp, 171 FERC ¶ 61,112, at PP 68-69 (2020).
29 Id. at P 101.  Although the Commission ultimately accepted PacifiCorp’s proposed commercial readiness criteria, it did so only after the criteria were modified to allow IPPs to provide similar evidence as LSEs that they were developing a project.  Id. at P 102.
30 LARS Filing, Transmittal Letter at 8-9.

PDF page 13

13

role in pre-approving a customer’s point of interconnection or that doing so will achieve any of MISO’s stated objectives.  A transmission owner’s agreement to a point of interconnection is hardly evidence that a proposed point of interconnection is viable.  MISO’s proposed framework contemplates that the parties will reach agreement on the proposed point of interconnection in a matter of weeks immediately prior to the LARS application deadline.  It is unclear what analysis— if any—the relevant transmission owner would conduct during this period or the criteria that it would use to evaluate whether to agree to a proposed point of interconnection.  And any assessment that a transmission owner can make during this period is likely to be preliminary and provide no assurance that other unforeseen issues will not arise later in the process that render the point of interconnection non-viable.31

There can be little question that the design of LARS will favor incumbent utilities and their generation resources over third-party developers.  MISO’s proposal does not merely establish eligibility criteria or commercial readiness requirements that will apply equally to all market participants.  Rather, it grants incumbent utilities the unilateral ability to determine whether competing generation projects gain access to an expedited interconnection pathway and when those projects may enter that process.  In practical terms, an incumbent utility can ensure that its own generation resources are positioned to receive priority consideration while delaying or limiting access for competing resources.  Here, the risk of undue discrimination is particularly acute because incumbent utilities are actively competing to serve large loads and the number of projects that can obtain access to interconnection service through LARS is inherently limited.

31 Notably, proposed section 3.12.9 of Attachment X states that any modification made by a transmission owner after submission of the LARS application, including to the point of interconnection, “shall cause the LARS Interconnection Request to be deemed withdrawn.”  Id., Proposed Tariff, Att. X § 3.12.9.  MISO has not demonstrated that it is just and reasonable to withdraw an interconnection customer’s application due to modifications made by the interconnecting transmission owner.

PDF page 14

14

In short, the design of LARS would allow incumbent utilities to play a gatekeeper function that is incompatible with open access and unnecessary to achieve the objectives that LARS seeks to achieve.  Rather than creating opportunities for incumbent utilities to discriminate against competing generation resources, LARS should be designed in a manner that supports the timely entry of new generation capacity that is best positioned to meet the demand of large load customers.  The best way to achieve this objective is to establish a process that is flexible enough to allow large load customers to work with potential suppliers to identify and pursue the generation solutions that most align with their needs.  A process that allows incumbent utilities or any other market participant an opportunity to erect barriers to these arrangements cannot be squared with the stated purpose of the LARS process, the resource adequacy needs of the MISO region, or the objectives of the Show Cause Order.

B. LARS Agreement Eligibility Criteria Are Unnecessarily Restrictive And
Unduly Discriminatory

Under MISO’s proposal, a LARS application would need to be accompanied by “an agreement executed by the Interconnection Customer and either the LARS Associated Transmission Customer or the entity that owns or controls the LARS Associated Load evidencing that the output of the Generating Facility for which LARS processing is sought shall be used to provide energy to the LARS Associated Load.”32  MISO proposes to limit the universe of acceptable agreements to a PPA or similar off-take agreement, a build-own-transfer agreement, and, for LSEs or Alternative Retail Electric Suppliers only, other agreements such as special contracts, large load tariff agreements, or retail service agreements.33

The requirement that a contract evidence that the “output” of a generation facility will be

32 Id., Att. X § 3.12.2(i).
33 Id., Att. X § 3.12.2(i)(a)-(c).

PDF page 15

15

“used to provide energy to the LARS Associated Load” has the potential to arbitrarily exclude commercial agreements between generation and loads that align with the objectives underlying LARS, support the reliable integration of large loads into the MISO system, and protect ratepayers. Importantly, given the significant financial and commercial risks associated with entering into long-term supply agreements, utilities increasingly are encouraging large loads to take a more proactive role in identifying, and entering into contracts with, the generation resources needed to meet their needs.  Although these agreements may involve a physical sale of electricity to the large load customer, large load customers and generation resources increasingly are turning to virtual PPAs as another option to bring new capacity online.  Under a virtual PPA, a large load enters into a financially settled arrangement with a generation developer that provides the revenue certainty needed to finance and build a new resource, but does not provide for the transfer of title to energy between the parties.  Yet, it is not clear that a virtual PPA would qualify an IPP’s project for LARS given the requirement that the generator’s output “be used to provide energy” to the large load.34 MISO has not demonstrated that excluding customers that into enter virtual PPAs and similar arrangements from LARS is just, reasonable, and not unduly discriminatory or preferential. A virtual PPA does exactly what LARS is meant to encourage: it de-risks a new generation project and supports the entry of new capacity necessary to offset the resource adequacy requirements associated with new large loads.  Additionally, a virtual PPA can protect ratepayers by ensuring that the large load—rather than the LSE—is responsible for the costs of the generation resource, reducing the risk that customers will be assigned costs for stranded assets.  And since a virtual PPA generally calls for the resource to sell its generation into the market, a resource that is constructed based on a virtual PPA will be available to serve the needs of the region as a whole.

34 Id., Att. X § 3.12.2(i).

PDF page 16

16

Using a virtual PPA to support new capacity is therefore consistent with the objectives of the Show Cause Order in which the Commission directed MISO to address resource adequacy

issues associated with integrating new large loads and in the MISO region generally.35  A requirement that excludes arrangements like a virtual PPA that advance the resource adequacy and speed to power objectives the process is designed to advance is not narrowly tailored and should be rejected as unduly discriminatory and preferential.

C. Co-Located Generation And Load Should Be Permitted To Participate In
LARS

In its filing, MISO makes certain statements that could be interpreted as excluding
generation co-located with load from LARS.  For example, MISO states that LARS is intended to serve electrically proximate generation and load but that co-located arrangements will be addressed through MISO’s separate, pending Zero Injection Generator Interconnection Agreement (“ZGIA”) framework.36  MISO states that “the ZGIA process will be utilized to meet the co-located portion of the [Large Load Show Cause] Order and LARS will address the electrically proximate large load portion of the [Large Load Show Cause] Order, by pairing generation with large load in the same [local resource zone (‘LRZ’)],”37 and describes LARS as “differentiated from the co- location requirements of the ZGIA process.”38  At the same time, nothing in the proposed tariff

35 Show Cause Order at PP 120-22, 127.  See also Midcontinent Indep. Sys. Operator, Inc., Docket No. EL26- 70-000, Informational Report at 1 (July 20, 2026) (“The unique nature of certain new large loads and the need to help ensure speed to power, however, brings new challenges that require MISO to continue to work with its states and broader stakeholder community to develop new tools and processes to ensure resource adequacy is maintained going forward.… This concentrated and discontinuous load growth requires new processes to most effectively meet this new demand and maintain resource adequacy.”).
36 LARS Filing, Transmittal Letter at 19 (“While the ZGIA process addresses the generator interconnection service and study framework for generation serving co-located load, LARS will address the distinct study issues presented by new generation and large load that are electrically proximate but are not eligible for ZG Interconnection Service.”).  See also Midcontinent Indep. Sys. Operator, Inc., Docket No. ER26-3552-000, Zero Injection Generator Interconnection Agreement (Aug. 18, 2026). 37 LARS Filing, Transmittal Letter at 20-21.
38 Id. at 22.

PDF page 17

17

language explicitly prohibits co-located load and generation from participating in the LARS process.

Categorically prohibiting co-located generation and load from participating in LARS would be unjust, unreasonable, and unduly discriminatory and preferential.  A co-located generation and load pair is similarly situated to an electrically proximate pair in every respect relevant to LARS: both involve a formal contractual pairing, both are located in the same LRZ, both would be studied together for their combined system impacts, and both are intended to bring new generation online to serve new large load.  The only difference is that the co-located pair is closer together and less likely to trigger network upgrades.  MISO has not identified any material difference between electrically proximate load and co-located load that would justify allowing one to use LARS while excluding the other and it is difficult to see how the greater proximity of co- located load could justify less favorable treatment in a process that uses proximity as its organizing principle.  Excluding co-location arrangements would arbitrarily deny an entire class of large load access to interconnection service through LARS.

Excluding co-location arrangements would also undermine the incentives the Commission directed MISO to pursue in the Show Cause Order and the objectives MISO itself has identified for the LARS process.  Specifically, in the Show Cause Order, the Commission found that co- locating generation with large load or locating it in an electrically proximate area, could reduce “the impacts to the transmission system of interconnecting the generating facility to serve that electrically proximate large load or large co-located load … thereby potentially reducing the need for Network Upgrades, which can accelerate the generator interconnection process.”39 Importantly, the Commission’s findings on this issue made no distinction between electrically

39 Show Cause Order at P 113.

PDF page 18

18

proximate large loads and co-location arrangements.  To the contrary, the Commission preliminarily found “that MISO’s Tariff appears to be unjust and unreasonable because it lacks a generator interconnection study process and/or generator interconnection service to reflect an interconnection customer’s commitment in an interconnection agreement to limit the generating facility’s output to minimize the impact on the transmission system while serving an electrically proximate large load or large co-located load.”40

  MISO similarly explains that its requirement that a generator and paired load be located in the same LRZ is designed to give load “an incentive . . . to bring Generation in a manner that maximizes the positive impact this Generation has on Resource Adequacy.”41  Given that co- located generation is equally capable of addressing resource adequacy needs as electrically proximate load and generation, providing co-located load and generation access to interconnection service through the LARS process would be consistent with the objectives of MISO’s proposal. Excluding co-location arrangements from LARS is arbitrary, unduly discriminatory and preferential, and inconsistent with the objectives underlying LARS.

II. MOTION TO INTERVENE
Geronimo Power respectfully moves to intervene in this proceeding.  Geronimo Power is a leading developer of energy projects in North America focused on meeting the needs of the nation’s electric grids generally and in light of the anticipated significant increase in demand from new large loads.  Geronimo Power has numerous projects in various stages of development, construction, and operation in markets throughout the U.S., including in MISO.  Accordingly, Geronimo Power has a direct and immediate interest in the outcome of this proceeding which

40 Id. (emphasis added).
41 LARS Filing, Transmittal Letter at 10.

PDF page 19

19

cannot be adequately represented by any other party.  For these reasons, Geronimo Power’s intervention is in the public interest and it respectfully requests that the Commission grant its motion to intervene in this proceeding.

III. CORRESPONDENCE AND COMMUNICATIONS
Geronimo Power respectfully requests that the following names be placed on the official service list for this proceeding by the Commission and that all correspondence and communications with respect to this proceeding be addressed to the following:42

Matthew Morais
Senior Director, Policy
Kurt Rempe
Assistant General Counsel
GERONIMO POWER, LLC
8400 Normandale Lake Blvd., Ste. 1200
Bloomington, MN 55437
mmorais@geronimopower.com
krempe@geronimopower.com

Stephen J. Hug
Ben N. Reiter
AKIN GUMP STRAUSS HAUER & FELD LLP
2001 K Street, N.W.
Washington, D.C.  20006
Tel: (202) 887-4084
shug@akingump.com
breiter@akingump.com

42 Geronimo Power respectfully requests waiver of Rule 203(b)(3) of the Commission’s regulations, 18 C.F.R. § 385.203(b)(3), in order to permit designation of more than two persons for service in this proceeding.

PDF page 20

20

IV. CONCLUSION
Geronimo Power respectfully requests that the Commission issue an order consistent with these comments.

Respectfully submitted,

/s/ Stephen J. Hug
Matthew Morais
Senior Director, Policy
Kurt Rempe
Assistant General Counsel
GERONIMO POWER, LLC
8400 Normandale Lake Blvd., Ste. 1200
Bloomington, MN 55437
mmorais@geronimopower.com
krempe@geronimopower.com

Stephen J. Hug
Ben N. Reiter
AKIN GUMP STRAUSS HAUER & FELD LLP
2001 K Street, N.W.
Washington, D.C.  20006
Tel: (202) 887-4084
shug@akingump.com
breiter@akingump.com
On behalf of Geronimo Power
Dated: October 23, 2026

PDF page 21

CERTIFICATE OF SERVICE

I hereby certify that I have caused the foregoing document to be served upon the individuals designated on the Commission’s official service list for this proceeding.

Dated at Washington, D.C., this 23rd day of October 2026.

/s/ Stephen J. Hug