Motion to Intervene and Comments of Geronimo Power, LLC concerning the Midcontinent Independent System Operator, Inc.’s Large Load Addition Resource Study…
Text extracted from the eLibrary original (SHA-256 4c6b18680a40bb9d…). Download the original from the official source.
Contents · 7 sections
- I. COMMENTS
- A. MISO’s Proposal To Allow Incumbent Utilities To Determine Access To
- B. LARS Agreement Eligibility Criteria Are Unnecessarily Restrictive And
- C. Co-Located Generation And Load Should Be Permitted To Participate In
- II. MOTION TO INTERVENE
- III. CORRESPONDENCE AND COMMUNICATIONS
- IV. CONCLUSION
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
ER27-25-000 MOTION TO INTERVENE AND COMMENTS OF GERONIMO POWER, LLC Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Rules of Practice and Procedure1 and the Commission’s October 2, 2026 Combined Notice of Filings #1,2 Geronimo Power, LLC…Read this passage Filed comments: Connecting load and generation
I. COMMENTS
printed heading · Topic match: Connecting load and generation
Nevertheless, any proposal that provides certain customers with a separate path to interconnection service must comply with the Federal Power Act’s (“FPA”) prohibition on undue discrimination and preference and open access requirements.7 Historically, the Commission has been skeptical of any…Read this passage Filed comments: Connecting load and generation
A. MISO’s Proposal To Allow Incumbent Utilities To Determine Access To
printed heading · Topic match: Connecting load and generation
The Commission and courts have recognized that utilities that own generation have an incentive to favor their own generation facilities in providing access to the electric grid.18 Indeed, the Commission’s concern that incumbent utilities might favor their own generation over that of competitors in…Read this passage Filed comments: Connecting load and generation
B. LARS Agreement Eligibility Criteria Are Unnecessarily Restrictive And
printed heading · Topic match: Connecting load and generation
LARS Agreement Eligibility Criteria Are Unnecessarily Restrictive And Unduly Discriminatory Under MISO’s proposal, a LARS application would need to be accompanied by “an agreement executed by the Interconnection Customer and either the LARS Associated Transmission Customer or the entity that owns…Read this passage Filed comments: Connecting load and generation
C. Co-Located Generation And Load Should Be Permitted To Participate In
printed heading · Topic match: Connecting load and generation
EL26- 70-000, Informational Report at 1 (July 20, 2026) (“The unique nature of certain new large loads and the need to help ensure speed to power, however, brings new challenges that require MISO to continue to work with its states and broader stakeholder community to develop new tools and…Read this passage Filed comments: Connecting load and generation
II. MOTION TO INTERVENE
printed heading · Topic match: Connecting load and generation
For these reasons, Geronimo Power’s intervention is in the public interest and it respectfully requests that the Commission grant its motion to intervene in this proceeding.Read this passage Filed comments: Connecting load and generation
III. CORRESPONDENCE AND COMMUNICATIONS
printed heading
CORRESPONDENCE AND COMMUNICATIONS Geronimo Power respectfully requests that the following names be placed on the official service list for this proceeding by the Commission and that all correspondence and communications with respect to this proceeding be addressed to the following:42 Matthew Morais…Read this passage
IV. CONCLUSION
printed heading
CONCLUSION Geronimo Power respectfully requests that the Commission issue an order consistent with these comments.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 23rd day of October 2026. /s/ Stephen J.Read this passage