ER27-25-000 · 2026-11-19 · Southern Minnesota Municipal Power Agency, WPPI Energy

Motion for Leave to Answer and Answer of Southern Minnesota Municipal Power Agency et al. to the 11/09/2026 Motion for Leave to Answer filed by the…

Text extracted from the eLibrary original (SHA-256 a0d14fe34419594a…). Download the original from the official source.

Contents · 5 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 2
  2. II. ANSWER p. 3
  3. A. MISO’s Answer fails to justify its proposed geographic scope for p. 3
  4. B. MISO fails to show that the Commission can simply ignore cost p. 7
  5. CONCLUSION p. 11

Read topic-matched comments in ER27-25

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

MISO’s argument rests of the false premise that the Commission must choose between timely implementation of LARS or consideration of cost shifting in the context of LARS.
Read this passage Filed comments: Connecting load and generation

I. MOTION FOR LEAVE TO ANSWER

printed heading · Topic match: Cost allocation

Operator, Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause Order”). 7 18 C.F.R. § 385.213(a)(2). - 3 - authority to waive this prohibition for good cause,8 and it has found good cause to waive the general prohibition on answers to answers where, among other things, the answer would assist the Commission…
Read this passage Filed comments: Cost allocation

II. ANSWER

printed heading

II.
Read this passage

A. MISO’s Answer fails to justify its proposed geographic scope for

printed heading · Topic match: Connecting load and generation

MISO also fails to explain how its proposed zonal scope will produce the optimized results MISO claims, particularly given the numerous elements of LARS that broaden its scope and require additional studies.22 20 Id. at 13. 21 See Midwest TDUs Limited Protest at 5-6. 22 See id. at 6-7 (explaining…
Read this passage Filed comments: Connecting load and generation

B. MISO fails to show that the Commission can simply ignore cost

printed heading · Topic match: Connecting load and generation

Even assuming this cost shifting risk is not new to LARS, that is little comfort to ratepayers that face cost shifting risks under 29 Id. at 5. 30 Id. at 16. 31 16 U.S.C. § 824d(e). 32 Show Cause Order P 113. - 10 - unjust and unreasonable Tariff provisions applied to costs incurred to serve…
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading · Topic match: Connecting load and generation

CONCLUSION For the reasons discussed above and in Midwest TDUs’ Limited Protest, the Commission should (1) reject MISO’s proposed geographic scope for paired generation and load eligible for LARS and direct MISO to revise its Tariff language consistent with the Show Cause Order; and (2) condition…
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated on this 19th day of November, 2026. /s/ Jeffrey M.